86
Pacific University Architecture Katie Kozarek Engineering Christian Heimple Construction Debbie Sit Apprentice Christina Cho Owner Peter Demian School of Engineering – New Construction Design Alternatives

Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Embed Size (px)

Citation preview

Page 1: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Pacific University

Architecture Katie Kozarek

Engineering Christian Heimple

Construction Debbie Sit

Apprentice Christina Cho

Owner Peter Demian

School of Engineering – New Construction Design Alternatives

Page 2: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Presentation Outline:

General Project Information & Introduction Discipline Constraints & Goals Alternative 1-4 by Discipline Decision Matrix (Pros/Cons of each Alternative) Team Process – Iteration Examples Team Dynamics Conclusion

CCAA

EE

Page 3: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Pacific Team & Project Information

Engineering School of Pacific University in Oregon

Location: Beautiful valley site near Pacific Ocean “Sunny Pond” of about 3000 sq.ft.

Preservation of existing footprint10,000 sq.ft. per story (3)

60% assignable CCAA

EE

Page 4: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Project Constraints

Total Budget: PV = $4.1 millionStructural System Budget: $330,000Completion Time: 1 year, by September

30, 2012Occupancy for Lab Facility: May 1, 2012Soil Condition: Rippable Rock

Page 5: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Design Considerations:

Rebuild a 3-story building for classroom, lab, office, and auditorium

Design a facility for innovative courses taking a team approach to engineering design

Put forth creative ideas considering: Architectural sense of place Functional use by occupants

Listen to team members knowledge-based notifications to design issues

Page 6: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Topography map Topography map

Oregon coast Site considerations:

•Small community

•Steep topography

•Cliffs

•Sparse highway system

Page 7: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Site map Site map

Small campus

Nearby pond

Overlooking cliff

Page 8: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Site photographsSite photographs

Considerations:

Cliff & Pond

Page 9: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Campus buildingsCampus buildingsNote:

Brick skin & Rectilinear forms

Page 10: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Structural Engineering – Requirements & Conditions

System Requirements Steel or concrete frame Cast-in-place, post-tensioned, or precast concrete

slab

Geometric Requirements Height of structure limited to 30’ Footprint of structure limited to existing

footprints

Pacific University – School of Engineering

Page 11: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Structural Engineering – Load Considerations Live Loads

Terrace, Atrium, Storage, & Stairwells – 100 psf Corridors – 80 psf Auditorium & Lobby – 60 psf Classrooms & Offices – 50 psf Roof – 20 psf

Dead Loads Lightweight concrete floor – 60 psf Metal deck – 5 psf Flooring, ceiling, lights – 12 psf Ductwork – 5 psf Partitions – 20 psf Exterior Cladding – 30 psf

Pacific University – School of Engineering

Page 12: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Structural Engineering – Load Considerations

Seismic Considerations Moderate to high seismic activity; Zone 3 Occupancy category, I = 1.0 Rock subsurface

Wind Considerations Design wind speed, V33 = 85 mph (38m/s)

Pacific University – School of Engineering

Page 13: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Equipment

Track-type Tractor

Ripper

Hydraulic Crane

Page 14: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Site Plan: L-shape

Material LaydownMaterial Storage

Office Trailer

Crane

Temporary Road Access

Main Road Access

Site Main Entrance

Optional Site Entrance

Site Boundary

Page 15: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Site Plan: Double Square

Material LaydownMaterial StorageOffice Trailer

CraneMain Site Entrance

Site Boundary

Optional Site Entrance

Page 16: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 - ArchitectureAlternative 1 - Architecture

Previous drawings restructured by engineer: Architectural redesign in Alternative 2

Page 17: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1Alternative 1Previous Section & Elevation

Page 18: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 1 Structural Proposal

Pacific University – School of Engineering

Steel moment resisting frame Composite concrete/steel deck (t = 4.5”)

Page 19: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 1 Structural Proposal

First Floor Plan

Pacific University – School of Engineering

Third Floor Plan

Outdoor TerraceLaboratory

Page 20: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 1 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

W12x45

W14x61

6x6 tube

Third Floor Structural Plan

Page 21: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Roof StructurePacific University – School of Engineering

Alternative 1 – Option 1 Structural Proposal

Page 22: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 1 Structural Proposal

Roof Structure

Pacific University – School of Engineering

Page 23: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 1 Structural Proposal

Roof Structure

Pacific University – School of Engineering

Page 24: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 2 Structural Proposal

Pacific University – School of Engineering

Cast-in-place concrete frame and two-way concrete slab (t = 6”) Shear walls (t = 10”) Goal: To address cost cost concerns of CM regarding rotunda

Page 25: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 2 Structural Proposal

Second Floor Plan

Pacific University – School of Engineering

Third Floor Plan

Outdoor TerraceStorage

Page 26: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 2 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

Foundation Plan Main columns have 5’x5’ spread

footings Rotunda has 10” drilled piles

10”x15”

10”x10”

Complex connection

Page 27: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 3 Structural Proposal

Eccentrically braced steel frame Composite steel/concrete deck (t = 4.5”) Goal: To address cost and constructability concerns of previous two

options

Pacific University – School of Engineering

Page 28: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 3 Structural Proposal

First Floor Plan

Pacific University – School of Engineering

Second Floor Plan

No conflicts with architecture

Page 29: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 3 Structural Proposal

Third Floor Structural Plan

Pacific University – School of Engineering

W12x45

W14x61

Second Floor Structural Plan

W14x61

Fewer columns than with original concept (A/E/C)

W12x45

Page 30: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1 – Option 3 Structural Proposal

Gravity load distribution

Pacific University – School of Engineering

Lateral load distribution

Page 31: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Space frame: Construction Method Excavated cost for sunken auditorium (20,000 cy)

at about $400,000, ~10% of Total Cost Steel SMRF more labor-intensive then braced

frame; Concrete requires CIP

Alternative 1 – Construction Issues

Page 32: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 1: Option 3 Schedule & Estimate

Total: $3.8 Million

Structural: $420,000

Page 33: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 - PartiAlternative 2 - Parti

Parti:Redevelopment of last year’s idea

How can the design pattern laid above the space be incorporated and brought into the building?

Can circulation systems become the pattern?

Can the pattern be highlighted with structure?

Can the structure reflect the pattern’s form and in turn cause sunshadows to develop in the interior spaces?

Page 34: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 - PlansAlternative 2 - Plans

Initial plans

More Finalized plans

Page 35: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Model ViewsAlternative 2 – Model Views

Auditorium space underground

Pattern defined by structure and pathways

Structure filters and captures sunlight

Page 36: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2Alternative 2

SectionSection through building bringing truss down through building above stairwells

Question to engineer? Can you make this a load bearing element in your structural considerations?

Page 37: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 1 Structural Proposal

Eccentrically braced steel frame Composite steel/concrete deck (t = 4.5”) Basement auditorium (steel space frame or concrete dome roof) Goal: To meet architect’s challenge of a radial layout with the structure

integrated into the north building’s radial hallways

Pacific University – School of Engineering

Page 38: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 1 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

W12x45

W14x61

First Floor Plan

Laboratory

Page 39: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 2 Structural Proposal

Special moment resisting steel frame Composite steel/concrete deck (t = 4.5”) Basement auditorium (steel space frame or concrete dome roof

with compression ring) Goal: To eliminate structural conflicts with architecture

Pacific University – School of Engineering

Page 40: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 2 Structural Proposal

First Floor Plan

Pacific University – School of Engineering

W12x45

W14x61

Second Floor Structural Plan

No conflicts w/architecture

Page 41: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 3 Structural Proposal

Steel frame with shear walls Composite steel/concrete deck (t = 4.5”) Basement auditorium (steel space frame or concrete dome roof

with compression ring) Goal: To explore a shear wall alternative

Pacific University – School of Engineering

Page 42: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 3 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

First Floor Plan

No conflicts w/architecture

Page 43: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 4 Structural Proposal

North Building – visible braced frames along main corridors South Building – eccentrically braced frames on exterior walls Composite steel/concrete deck (t = 4.5”) Basement auditorium (steel space frame or concrete dome roof) Goal: To integrate functional braced frames into the north building’s

hallways

Pacific University – School of Engineering

Page 44: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Option 4 Structural Proposal

Pacific University – School of Engineering

First Floor Plan

W12x45

W14x61

Page 45: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2 – Construction Issues

Building is separated into two parts:Cost Consideration for duplication of MEP systems

Connecting the two parts by 3rd floor skywalk: Potential savings: ~20% of total cost

Enclosed or Open Radial hallways: Life-cycle Costs

Constructability issues: Curved Walls & Angled Connections

Page 46: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Milestone 1:Structural System Erected

Milestone 2:Building enclosed

Milestone 3:Project completion

Total: $6.0 Million

Structural: $590,000

MEP: $.2.2 Million

Alternative 2: Schedule & Estimate

Page 47: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 2: Revised Estimate

MEP: $1.1Million

Structural:$400,000

Total: $4.2 Million

Page 48: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

parti sketches

Alternative 3Alternative 3

Organically growing plans and elevations moving out from footprint: representing natural growth of coastal habitat ; provisions for experimental growth

Page 49: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3: Puzzle ConceptAlternative 3: Puzzle Concept

Option 1 – First set of plans

Page 50: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3: Option 1Alternative 3: Option 1

Second set of plans: Changes include moving auditorium to first and second floor instead of excavation – consequential redesign of some interior spaces

Page 51: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3: Elevation

Page 52: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Option 2 involves the L-shaped plan for the site

It is still working with the puzzle concept – showing its versatility

Alternative 3: Option 2

Page 53: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Material selectionMaterial selection3 materials

5 blocksEach block has own material skin

Considered in construction and structural process

Computer block: brick to match surrounding buildings

Administration block : wood

Student block: wood

Auditorium: concrete

Classroom block: concrete

Page 54: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3: ModelAlternative 3: ModelSuggestions made to construction manager and engineer: think about how can we think of this design as being constructed in separate functional blocks? Can prefabrication be an option? Classroom block

Computer blockStudent blockFaculty blockAuditorium

PUZZLE PIECE AS INTERCONNECTING BLOCKS

Page 55: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 - Interior examplesAlternative 3 - Interior examples

Isozaki/

Kurokawa

how can elements from puzzle concept enter into interior spaces?

Page 56: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 - Exterior examples

Isozaki/

Kurokawa How can elements of form

create interesting spaces? Can structure be pushed into

stipulating form? Can functional blocks merge

to create a whole?

Page 57: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 1 Structural Proposal

Pacific University – School of Engineering

Steel frame w/ shear walls (t = 8”) Composite steel/concrete deck (t = 4.5”)

Page 58: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 1 Structural Proposal

First Floor Plan

Pacific University – School of Engineering

W14x90

W12x65

Second Floor Structural Plan

Instructional Laboratory

Page 59: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 1 Structural Proposal

Cantilever Details

Pacific University – School of Engineering

Tube Section (6x6)

Tube Section (6x6)

Page 60: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 2 Structural Proposal

Concrete frame w/ shear walls (t = 8”) C-I-P two-way beam supported slab (t = 5”) Post-tensioned cantilever beams and slab Goal: To explore concrete alternatives

Pacific University – School of Engineering

Page 61: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 2 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

Cantilever Details

Page 62: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 3 Structural Proposal

Eccentrically braced steel frame Composite steel/concrete deck (t = 4.5”) Preferred option for Alternative 2 Goal: A cost and time efficient, constructible alternative

Pacific University – School of Engineering

Page 63: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 – Option 3 Structural Proposal

First Floor Plan

Pacific University – School of Engineering

Moment frames used to integrate structure with architecture

Page 64: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

W12x45

W14x61

Alternative 3 – Option 3 Structural Proposal

Second Floor Structural Plan

Pacific University – School of Engineering

Page 65: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3

Computer Room & Instructional Lab located on different floors: Construction Sequence

Trailer rental costs $10,000 vs Late move-in penalty $37,500

Pre-cast concrete allows fast erection, yet relatively expensive for small-scale projects

Page 66: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 3 - Option 3 Schedule & Estimate

Total: $4.0 Million

Structural: $460,000

Page 67: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 - Architecture

CAD model sent by structural engineer…

Page 68: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4Breaking down massing to make for more usable interior spaces outside of auditorium

Working on unfolding building to consider spatial issues

Page 69: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4

Potential

for new

spaces

Creating circulation

Page 70: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4How can “floating column” be replaced to show load transfer?

• Conceptual plan – how can this form fit into the site? – needs to be broken down

Page 71: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 1 Structural Proposal

60’ Cable-stayed cantilever over ocean-side cliff Composite steel/concrete deck with eccentrically

braced frame

Pacific University – School of Engineering

Page 72: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 1 Structural Proposal

Structural Concept based on TWA hangar in Philadelphia and American hangar at San Francisco International

Design started with engineer to break out of A > E > C pattern and to overcome prior structural difficulties with previous alternatives

Pacific University – School of Engineering

Page 73: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 1 Structural Proposal

Cantilevered portion of structure

Pacific University – School of Engineering

Page 74: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 1 Structural Proposal

Pacific University – School of Engineering

Eccentrically braced steel frame Composite steel/concrete deck (t = 4.5”)

8x8 tube steel hanging columns

Page 75: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 1 Structural Proposal

Third Floor Plan

Pacific University – School of Engineering

Page 76: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 2 Structural Proposal

60’ Cable-stayed cantilever over ocean-side cliff Shear walls and post-tensioned slab (t = 5”) Cantilevered portions remain steel Goal: Reduce mast height and reflect architect’s

revisions

Pacific University – School of Engineering

Page 77: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4 – Option 3 Structural Proposal

Pacific University – School of Engineering

Northeast shoulder removed to accommodate footprint constraint

Page 78: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Pacific University – School of Engineering

Footprint

2nd Floor Structural Plan

Alternative 4 – Option 3 Structural Proposal

Page 79: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4

Structurally very dynamic, yet repetition aids in cutting construction costs

Cable-stayed system requires deep pile foundation 2nd and 3rd floor cantilever hanging over cliff:

require temporary platform for efficient construction of the exterior wall

Design still young; construction input in structure/materials/method can possibly drive cost and schedule down

Page 80: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Alternative 4: Schedule & Estimate

Total: $4.6 Million

Structural: $560,000

Page 81: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Cost Comparisons

Page 82: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Decision Matrix AEC

1

2

3

4

PROS CONS

•Dynamic, radial, curvilinear, sun pattern•Semi-regular bays sizes and layout•Easier to construct (regular layout, little welding)

•Most flexible puzzle piece parti•material-functional block relationships•Braced frames have dual purpose of “backing” cantilevers & lateral load support

•Most dynamic interior spaces (auditorium), sunpatterns, shadowplay•Structure integrated with architecture

•Design speaks to engineering and structure•Extremely interesting structural system•Regular structural patterns – many common components throughout

•Cantilevered walkway over atrium susceptible to vibration and imposes large moments in connecting column•Costly atrium space

•May not challenge engineer•Long cantilevers may be susceptible to vibration problems•No economies of scale with so many materials

•Circulation undeveloped•Very irregular layout resulting in a large number of angled connections •Expensive to construct (curved walls, angled connections)

•No relationship to site or context, lack of spatial variation creating architectural limitations•Exceeds height limit and footprint (under review)•Deep piles require lots of time & money, large overhanging portion

Page 83: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Team Process – Iteration Examples Alternative 1 A->E->C->A->E->C

Predetermined, old architectural drawings redesigned

Alternative 2 A->E->C Developed architecturally but needs more structural and construction advice due to issues of

constructability

Alternative 3 A->E->C->E->A->C Redesign of Alternative 1 E&C advised architect against irregular, oblique layout

Expensive, angled connections A challenges E&C to integrate their systems into the architecture (e.g. exposed structural

system)

Alternative 4 E->A->C->A->E->C Design started with engineer

Page 84: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Team Dynamics INTERACTION WITH OWNER:

Very understanding, sensitive, & informative b/c has engineering

Encouraging of ideas outside original scope

INTERACTION WITH TEAM: Initial lack of conceptual understanding of each

others’ fields and roles Challenge to meet new expectations for next semester

by being informative and understanding of different expectations and considerations in the design process

Challenge to be more communicative and outspoken during the design process

Page 85: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

Consideration of Alternative 4 Redesign as Final Solution:

CCAA

EE

Challenging Structural Design Feasible in Time and Cost for

Construction without current considerations for material

Architecturally lacks spatial concept and connection to context

Page 86: Pacific University Architecture Katie Kozarek EngineeringChristian Heimple ConstructionDebbie Sit ApprenticeChristina Cho OwnerPeter Demian School of Engineering

CONCLUSION

Considering a fifth alternative

that can challenge all fields equally

CCAA

EE