37
PACE Technical Standards Eddy Trevino, P.E., Program Manager State Energy Conservation Office August 2015

PACE Technical Standards Eddy Trevino, P.E., Program Manager State Energy Conservation Office August 2015

Embed Size (px)

Citation preview

PACE Technical Standards

Eddy Trevino, P.E., Program ManagerState Energy Conservation Office

August 2015

Agenda

Overview

Project Process

Exhibits and Reference Materials

Overview

Local Government CodeSec. 399.002. DEFINITIONS. • Qualified Improvement – Permanent improvement fixed to property

– Customer side of the meter

– Decrease water or energy consumption or demand

– Energy technology to generate electricity, provide thermal energy, or regulate temperature

Overview

Local Government CodeSec. 399.011. REVIEW REQUIRED. • Independent third party• Before construction activities– Review of water or energy baseline conditions

– Review of projected water or energy savings

• After project is completed– Verification that the qualified project was properly

completed and is operating as intended

Overview

ParticipantsProperty Owner– Separate contracts

Independent Third Party Review (ITPR) Engineer– At beginning and through PACE contract

Engineer of Record– At beginning and through construction phase

Contractor– At beginning, construction and M+V

Overview

Technical StandardsInvestor Confidence Project (ICP) Energy Performance Protocols (EPP) for Standard and Large Commercial Facilities

Standardize the technical review of energy efficiency projects to bring uniformity and reliability on a national scale

Overview

Technical RequirementsStep 1: Establish BaselineWater and energy use must be measured

Step 2: Project SavingsWater and energy conserving measures must be quantified

Step 3: Independent Third Party ReviewProject must be reviewed by the ITPR Engineer

Step 4: Annual ReportingProperty Owner reports savings to PACE Administrator

Project ProcessPre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Project Process

• Is there a potential project?

• Engage an Engineer and/or Architect for Preliminary Assessment Purposes

• Conduct Preliminary Utility Audit– Identify energy and water

retrofit opportunities

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Project Process

• Engage Independent Third Party Reviewer (ITPR)

• Engage Engineer of Record– Full Assessment– FAST TRACK Assessment

• Engage Contractor if Design Build Contract

• Measurement and Verification (M&V)– Plan (decide at beginning)– Implementation

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Project Process

• Engage Independent Third Party Reviewer (ITPR)

• Engage Engineer of Record– Full Assessment– FAST TRACK Assessment

• Engage Contractor if Design Build Contract

• Measurement and Verification (M&V)– Plan (decide at beginning)– Implementation

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Independent Third Party Review

The ITPR EngineerTechnical Standards Manual – Section II

• Selected by the property owner• Validates projected future energy or water

savings (not an original review) • Verifies that project was properly completed

and is operating as intended• Reviews and validates of post-construction

M&V reports• Ideally, the same ITPR should follow a project

from initial review to project completion

Independent Third Party Review

ITPR Engineer QualificationsTechnical Standards Manual – Section II

• Licensed Professional Engineer with energy/water efficiency experience

• Without conflict or relationship to the project • One of the following certifications:

– American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE)

– Building Energy Assessment Professional (BEAP)– Building Energy Modeling Professional– Association of Energy Engineers (AEE)– Certified Energy Manager (CEM)– Certified Measurement and Verification Professional (CMVP)– Certified Energy Auditor (CEA)– Building Commissioning Association– Certified Commissioning Professional– Investor Confidence Project (ICP) Credentialed Quality Assurance Provider

Independent Third Party Review

ITPR Engineer CertificationsTechnical Standards Manual – Section II

• Reviewer’s Certification• Statement of Compliance

Independent Third Party Review (ITPR)

ITPR Engineer Site VisitsTechnical Standards Manual – Section II

Site Visit 1: Reviewer’s Certification

• Reviews completed Energy/Water Assessment Report

• Visits site

• Project Verification Certificate

– No conflict of interest– Certification that project complies with PACE guidelines– Sealed by Texas Professional Engineer

Independent Third Party Review (ITPR)

ITPR Site Visits (cont.)Technical Standards Manual – Section II

Site Visit 2: Statement of Compliance

• Post Construction

• Revisit the site to confirm that the improvements were properly installed, meet EPP guidelines, and are operating as intended

• Statement of Compliance– No conflict of interest– Certification that project complies with PACE guidelines– Sealed by Texas Professional Engineer

Project Process

• Engage Independent Third Party Reviewer (ITPR)

• Engage Engineer of Record– Full Assessment– FAST TRACK Assessment

• Engage Contractor if Design Build Contract

• Measurement and Verification (M&V)– Plan (decide at beginning)– Implementation

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Full Assessment / Fast Track ProtocolEngineer of Record ResponsibilitiesTechnical Standards Manual – Section III

• Multiple Energy and/or Water Efficiency Measure Projects

Fast Track• Type 1 – Like-for-Like

Replacement – Example: Lighting retrofit or A/C

unit upgrade

• Type 2 – Single-Measure Efficiency Projects – Example: Window film,

additional insulation, or reflective roof coating

• Type 3 - Distributed Generation – Examples: CHP, micro turbines,

solar photovoltaic (PV)

Full Assessment

Full Assessment / Fast Track ProtocolEngineer of Record ResponsibilitiesTechnical Standards Manual – Section III

Fast Track• Projects do not qualify for

the FAST TRACK approach if:– Project requires energy

modeling – Project requires IPMVP

(Option C or D) measurement and verification

– Project value to building appraisal ratio exceeds 0.10 (10%)

Full Assessment

ProtocolEngineer of Record ResponsibilitiesTechnical Standards Manual – Section III

1. Establishes energy and water baseline conditions 2. Prepares the Energy/Water Assessment Report3. Provides oversight during construction activities4. Evaluates project performance (M&V)

ProtocolApproaches for Different Project TypesTechnical Standards Manual – Section III1. Commercial Projects– ASHRAE standards based

2. Industrial and Agricultural Projects– Facility, process or equipment

3. Distributed Generation (DG)– Metering of delivered energy without a baseline

is often recommended in the M&V approach– Delivers energy on customer side of meter

Protocol

Using Prior AuditsTechnical Standards Manual – Section III

Engineer of Record:• Prior ASHRAE Level II or Level III energy/water

audit may be used provided that it was completed within the last three (3) years – see conditions

• Update baseline utility data

Protocol

Projected Savings CalculationsTechnical Standards Manual – Section III

Engineer of Record

• “Open book” methodology – Savings calculations are transparent – Results are readily verifiable

• “Closed book” methodology (proprietary software is prohibited) – Exception – If it meets open book methodology

standards

Project Process

• Engage Independent Third Party Reviewer (ITPR)

• Engage Engineer of Record– Full Assessment– FAST TRACK Assessment

• Engage Contractor if Design Build Contract

• Measurement and Verification (M&V)– Plan (decide at beginning)– Implementation

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Texas PACE law: “After a qualified project is completed, the local government shall obtain verification that the qualified project was properly completed and is operating as intended.”

• ITPR Engineer Validation– ASHRAE Guideline 14, Whole Building Performance Path and

the International Performance Measurement and Verification Protocol (IPMVP)

– IPMVP Options (Decided when Full Assessment is Developed)

• Owner’s Contractor– May continue M&V throughout the term of the assessment or

as contractually specified

Protocol

Verifying Completion and OperationTechnical Standards Manual – Section III

Project Process

• Contractor implements retrofit project

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Project Process

• Contractor completes retrofit project

• Verifying Completion and Operation

Pre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Texas PACE law: “After a qualified project is completed, the local government shall obtain verification that the qualified project was properly completed and is operating as intended.”

• ITPR Engineer Validation– ASHRAE Guideline 14, Whole Building Performance Path and

the International Performance Measurement and Verification Protocol (IPMVP)

– IPMVP Options (Decided when Full Assessment is Developed)

• Owner’s Contractor– May continue M&V throughout the term of the assessment or

as contractually specified

Protocol

Verifying Completion and OperationTechnical Standards Manual – Section III

Independent Third Party Review (ITPR)

ITPR Site VisitTechnical Standards Manual – Section II

Site Visit 2: Statement of Compliance

• Post Construction

• Revisit the site to confirm that the improvements were properly installed, meet EPP guidelines, and are operating as intended

• Statement of Compliance– No conflict of interest– Certification that project complies with PACE guidelines– Sealed by Texas Professional Engineer

Project Process

• Owner ReportingPre Application

Application and Review

Financing and Contractor Engagement

Construction Retrofits

Final Review

Repayment / Reporting

Owner is required to provide a post-construction Annual Savings Report to the PACE administrator. – Submitted during the term of the assessment or throughout

the term of the M&V– Shall be reviewed and validated by the ITPR

Full Assessment Protocol

Owner Reporting RecapTechnical Standards Manual – Section III

EXHIBITS

Exhibit A: INDUSTRIAL PROTOCOL

Exhibit B: AGRICULTURAL PROTOCOL

Exhibit C: INDEPENDENT THIRD PARTY CERTIFICATION

Technical Standards

Exhibits

Reference Materials• Accepted methods for data collection, measurement, and savings calculations should be used on proposed

projects. • Technical methodology relies primarily upon the Investor Confidence Project (ICP) - Energy Performance

Protocols (EPP) for Standard and Large Commercial Facilities.– Contains processes that form a framework for bringing together all aspects of project implementation from

establishing a baseline and audit, through M&V. • American Society for Testing and Materials (ASTM) E2797-11, Building Energy Performance Assessment

(BEPA) Standard (data collection and baseline calculations for the energy audit, building asset data);• International Performance Measurement and Verification Protocol (IPMVP) (latest edition);• American National Standards Institute/Building Owners and Managers Association (ANSI/BOMA) Z65.3- 2009

(gross floor area measurement);• ASHRAE Guideline 14-2002 (measurement of energy and demand savings);• ASHRAE Procedures for Commercial Building Energy Audits (latest edition);• National Institute of Standards and Technology (NIST) Life-Cycle Costing Manual, NIST Handbook 135 (latest

edition);• ASHRAE Standard 202, Commissioning Process for Buildings and Systems (latest edition);• ASHRAE Guideline 4, Preparation of Operating and Maintenance Documentation for Building Systems (latest

edition);• ASHRAE Guideline 1.4, The Systems Manual for Facilities; (latest edition);• ASHRAE Handbook-2011, Fundamentals, Chapter 39 (Codes and Standards); and• ASHRAE Guideline 14, Whole Building Performance Path (2002 edition);• The Alliance for Water Efficiency (AWE) Conservation Tracking Tool; and• EPA WaterSense Product Guide.

QUESTIONS?

Dub Taylor, DirectorEddy Trevino, Program ManagerState Energy Conservation [email protected]