Upload
karan-doshi
View
215
Download
0
Embed Size (px)
Citation preview
8/18/2019 Ormen Lange
1/19
Ormen Lange – CorrosionManagement of Import Pipelines
Grethe Selboe, MainTech AS
8/18/2019 Ormen Lange
2/19
Introduction
• MainTech was awarded a contract
with A/S Norske Shell within
“Inspection &Corrosion Monitoring for
Draugen and Ormen Lange”
•Member of Shell’s start-up team for
Ormen Lange from 2005
• Localised together with the project in
Oslo to prepare for start-up in 2007
This lecture will present the work done from 2005 and how the
corrosion management systems for the import pipelines are managed
today
8/18/2019 Ormen Lange
3/19
Ormen Lange - Facts
• Reservoir is located 120 km north
west of Kristiansund
• Discovered: 1997
• Production start: September 2007
• When Ormen Lange produces atits top, this will cover about 20 %
of Great Britain’s gas needs.
• Norsk Hydro was operator during
design and construction.
• Operator today: Norske Shell
8/18/2019 Ormen Lange
4/19
Ormen Lange - Challenges
• Deepwater project
• Reservoir in landslide area,
steep rise towards land
• Rough seabed
• 120 km to the controlcentre
• Multiphase
• Minus 1.7 degree C,
hydrates can form
8/18/2019 Ormen Lange
5/19
8/18/2019 Ormen Lange
6/19
Corrosion Protection Philosophy
Import pipelines contains:
– 0.3mol% CO2
– 0.5ppmv H2S
– Acetate is present in the produced gas
– Formate is present in drilling fluids
Protection Philosophy by Injection of Chemicals:
– MEG is injected @ wellhead to prevent hydrates – pH-stabilizer (added to MEG)
– scale and corrosion inhibitor (added to MEG)
Based on
extensive testingby Hydro before
start-up
8/18/2019 Ormen Lange
7/19
Import Pipelines – Design Details
• Made of X65 carbon steel
• Design life is 50 years
• Robust Corrosion Allowance
• Nominal wall thickness is 26.8-
35.5mm
• Thick film coating externally
• Sacrificial anodes subsea
• Impressed Current in buried
landfall area
8/18/2019 Ormen Lange
8/19
Main Internal Threats
1. Bottom of line
– pH stabiliser + corrosion inhibitor
– Control CO2 concentration
2. Top of line – Inspection of external coating (avoid
condensation)
– Control CO2 concentration
– Control formate and acetateconcentration
– Alkalinity in MEG
8/18/2019 Ormen Lange
9/19
Sampling & Monitoring
•Concentration of:pH stabiliser
Corrosion Inhib
•pH + Fe
•Acetate + Formate
•Water/MEG content
•Fe
•Concentration of:
pH stabiliser
Corrosion Inhib
•pH + Fe
•Acetate + Formate
•Water/MEG content
•Oxygen
Kp 0
ER probes + WLC
•Erosion probes
•Sand detectors
•Temp
•Pressure
CO2 + H2S
sampling in gas
from SC (+ in
export gas)
Wells
8/18/2019 Ormen Lange
10/19
Inspection
Kp 0
Inspected internallyby NDT externally
Inspected externallyfor coating damage
+ Internal pigging if found necessary
Wells
8/18/2019 Ormen Lange
11/19
Intergrity Operating Window (IOW)
What is IOW?
A selection of sample data, process data, corrosion data to control that we
are operating within defined limits. For example:
0
50
100
150
200
250
300
1 0 - m a r
1 7 - m a r
2 4 - m a r
3 1 - m a r
7 - a p
r
1 4 - a p r
2 1 - a p r
2 8 - a p r
5 - m a i
1 2 - m a i
1 9 - m a i
2 6 - m a i
2 - j u
n 9 - j u
n
C o
n c e n t r a t i o n
0
2
4
6
8
10
12
p H
Lean - pHStab (mg/l)
Rich - pHStab (mg/l)
Lean - Alk (mg/l)
Rich - Alk (mg/l)
Lean - pH
Rich - pH
pH in MEGFormate concentration
8/18/2019 Ormen Lange
12/19
Example of IOW Parameters C
o r r o s i o n l o o p
M
o n i t o r i n g p o i n t
S y s t e m
P r i o r i t y
(
X = R e m o v e d )
F r e q u e n c y
( R
= O n R e q u e s t )
Tag # Type Parameter
T h r e a t
U n i t Limit
P h y s i c a l L o c a t i o n
C o m m e n t s
D a t aL o c a t i o n
Time
interval:01.06.09-
31.08.09
Sign: GS
Reviewed
Time
interval:01.09.09-
30.11.09
Sign: GS
Reviewed
Time
interval:01.12.09-
28.02.10
Sign: GS
Reviewed
Time
interval:01.03.10-
31.05.10
Sign: GS
Reviewed
Time
interval:01.06.10-
31.08.10
Sign:
GS/KB
Time
interval:31.08.10-
30.11.10
Sign: KB
Reviewed
01
CE-16-1025
ER probe /
Corrosion rate
LOCATION:
Import pipeline
16 1 3m CE-16-1025 ER probeCorrosion
rate
CO2corrosion
mm/yr
max 0,33
mm/yr (CA
10 mm)
Import
pipeline A
before pig
receiver/slu
g catcher
PCAD/
Livelink
0,000 mm/y
(Q3 2009)
(not
reviewed in
corrosion
0,001 mm/y
(Q4 2009)
(not
reviewed in
corrosion
0,000 mm/y
(Q1 2010)
(not
reviewed in
corrosion
0,000 mm/y
(Q2 2010)
(not
reviewed in
corrosion
0,000 mm/y
(Q3 2010)
(not
reviewed in
corrosion
0,0012
mm/y (Q4
2010) (not
reviewed in
corrosion
01
CE-16-1024
WLC / Corrosion
rateLOCATION:
Import pipeline
16 1 1yr CE-16-1024 WLC
Corrosion
rate
CO2
corrosion mm/yr
max 0,33
mm/yr (CA10 mm)
Import
pipeline A
before pigreceiver/slu
g catcher
Not online,
manual
measureme
nts yearly
Livelink
0,001 mm/y
(Q4 2009)
(notreviewed in
corrosion
0,001
/mm/y (Q4
2010) (notreviewed in
corrosion
01
EC-89-0050
ICCP / Potential
on pipelines PL-
A/B, Kp 0 to HAT
LOCATION:
89 1 1w EC-89-0050 ICCP
Potential on
pipelines PL-
A/B, Kp 0 to
HAT
External
corrosion
-0.85 to -
1.20 V vs.
Cu/CuSO4-
Landfall,
L56
Send report
to Gassco
monthly
Livelink
ICCP area
Potentials
outside
acceptable
levels from
10th of
Problem
fixed,
system is
working
satisfactory
OK OK
OK - still
current
leakage for
Pl-B
OK - still
current
leakage for
Pl-B
01
QN-16-1084
Sampling / Iron
content (total
iron)
LOCATION: After
16 1 3m QN-16-1084 SamplingIron content
(total iron)
CO2corrosion
mg/lNo limit
defined
After slug
catcher
Sample
Manager
Incrasing
trend, (6, 6
and 32
mg/l)
~ max 10
mg/l
Max 14.8
mg/l (3
samples)
Max 6.3
mg/l (3
samples)
Max 17 mg/l
(2 samples)
Max 26 mg/l
(2 samples)
01
QN-16-1084Sampling / Iron
content
(dissolved iron)
LOCATION: After
16 2 3m QN-16-1084 Sampling
Iron content
(dissolved
iron)
CO2corrosion
mg/lNo limit
defined
After slug
catcher
Sample
Manager
Incrasing
trend, (12, 7
and 36
mg/l)
~ 5 mg/l
(only 1
sampling)
No
sampling
performed
No
sampling
performed
No
sampling
performed
No
sampling
performed
01
QT-18-0638
Erosion probe /
Erosion
LOCATION:
Template A, well
18 2 3m QT-18-0638Erosion
probeEros ion Erosi on mi cron
No limit
defined.
Template A,
well 6PI Max. 47 Max. 46 Max. 46 Max. 39 Max. 38 Max. 37
8/18/2019 Ormen Lange
13/19
Expert Group Meeting
Typical members of the group:
• Material & Corrosion Engineer (head of the group)
• Area Inspection Engineer
• Operations Representative
• Process Engineer• Production Chemist
• Pipeline Engineer
• Maintenance Engineer
• Technical Safety Engineer
Meeting frequency: Every 2nd month
8/18/2019 Ormen Lange
14/19
Modifications to CorrMngt System
• Tests performed before start-
up showed that the CI was
effective after regeneration.
• Concentration of CI was
included as an IOW paramter
to follow
• Corrosion tests of field MEG
show that the CI partly looses
its effect after regeneration
• IOW was then revised toinclude corrosion tests, in
addition to CI concentration
sampling
Rich MEG
Lean MEG
8/18/2019 Ormen Lange
15/19
Modifications to CorrMngt System
Original CI limits:
Lean MEG: 200 ppm Rich MEG: 100 ppm
8/18/2019 Ormen Lange
16/19
Monthly/Bi-monthly Evaluation
QN-38-0686
LabA -
rotating1
LabA -
rotating2
LabA -
stationary1
LabA -
stationary2LabB rich lean rich lean rich lean rich lean rich lean
End March 2008 MG exp group 0 300 390 60 70 100 110 80 92
August 2008 MG exp group 5 0.11 0.14 0.06 0.1 230 290 80 100 90 100 80 92
January 2009 MG exp group 9 0.12 0.16 0.06 130 170 110 130 200 240 77 92
April 2009 MG exp group 12 0.08 110 150 80 95 180 210 6 6 6.9 75 92
June 2009 MG exp group 1 0.04 0.02 0.03 200 250 95 110 190 210 6.1 6.4 6.9 76 92
July 2009 MG exp group 2 0.03 230 330 95 120 210 210 6.2 6.4 6.4 76 91
August 2009 MG exp group 3 0.04 230 330 120 140 200 230 6.3 6.7 6.3 70 90
November 2009 MG exp group 2 0.06 270 330 no analysi o analysi o analysisno analysi 6 6.2 6.2 76 92
December 2009 MG exp group 3 0.06 220 330 220 250 350 400 6.3 6.4 6.3 77 92
March 2010 MG exp group 1 0.05 280 370 220 240 320 350 6.1 6.4 6.0 77 92
April 2010 MG exp group 2 0.07 270 370 200 250 280 330 6 6.5 6.0 77 92
July 2010 MG exp group 1 0.03 400 500 200 250 280 330 6.3 6.4 6.0 80 92
September 2010 MG exp group 3 0.06 330 430 200 290 330 400 6.1 6.5 6.1 77 92
October 2010 MG exp group 1 0.06 350 530 200 310 320 450 6.1 6.4 6.0 75 92
November 2010 MG exp group 1 0.05 350 460 200 270 320 440 6 6.4 6.1 73 92December 2010 MG exp group 2 0.06 310 430 200 300 320 460 6.1 6.3 6.1 75 92
April 2011 MG exp group 3 0.07 410 560 250 340 350 450 6.2 6.4 6.0 75 92
April 2011 MG exp group 0 0.02 410 760 250 340 350 450 6.2 6.4 6.0 75 92
Date Sign Review by
No of
months
w ithout
CI
Rate (mm/year)
QN-20-0121/QN-38-0686 QN-20-0121/QN-38-0686 QN-20-0121/QN-38-0686 QN-20-0121/QN-38-0686
CI concentration (mg/l) Acetate
concentration(mg/l)
Formate concentration
(mg/l)
pH @1bar CO2 rich
(lean) MEG
pH @1bar
CO2 rich
MEG
MEG concentration (%)
QN-20-0121/QN-38-0686
8/18/2019 Ormen Lange
17/19
Yearly Review• Review of all parametres collected last year
• Review of all inspection results
• HydroCor calculations
– Result is compared to corrosion tests of sampled MEG and rates found during
qualification of chemicals
• PipeRBA assessment gives pipeline remaining life and inspection due date
8/18/2019 Ormen Lange
18/19
Follow-up of IOW
1. Monthly to 3-Monthly review of most important parameters
in IOW
2. Yearly review of entire IOW + inspection results + experience
from operation + HydroCor calculations + PipeRBA
MIGHT LEAD TO A CHANGE IN PROTECTION PHILOSOPHY, PIGGING
INTERVAL, CHANGES IN SAMPLING/MONITORING PROGRAM
8/18/2019 Ormen Lange
19/19
Summary
• By establishing a Corrosion Management system from day 1,
this will be the tool to document any life extension in the
future, if necessary
• Early involvement in project phase (approx. 2 years before
start-up) allowed us to have:
– Good understanding of challenges
– Good transfer from project (NH) to operation (Shell/MainTech)
– Good communication between disciplines, when in operation
• Systemising useful information allows you to optimise yourrisk based decision, away from conservatism