Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup I added a section on simulation needs – should be vetted. I have generated a strawman schedule with milestones A preliminary funding request has been submitted to Daniela Will probably not be fully funded by CMS and we will be asked for priorities It would be worthwhile exploring additional “generic” funding. A second proposal which will explore more conventional interconnect technology has been submitted to CMS Some overlap in proponents Considerable overlap in R&D subjects – simulation, circuit design, overall architecture I expect (and hope) that there will be some 1

Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Embed Size (px)

DESCRIPTION

Schedule 3

Citation preview

Page 1: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Organization, Proposal and Funding

• We hope to finish the revised proposal this week• Need some cleanup• I added a section on simulation needs – should be vetted.

• I have generated a strawman schedule with milestones• A preliminary funding request has been submitted to Daniela

• Will probably not be fully funded by CMS and we will be asked for priorities

• It would be worthwhile exploring additional “generic” funding.• A second proposal which will explore more conventional interconnect

technology has been submitted to CMS• Some overlap in proponents• Considerable overlap in R&D subjects – simulation, circuit design,

overall architecture• I expect (and hope) that there will be some rational combination of

these efforts (more later)

1

Page 2: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Goals

• Demonstrate 3D interconnect concept• Demonstrate Interposer technology

• Interposer material• Via density, interposer thickness• mass

• Study overall architecture• Begin electrical simulation• Understand connectivity and power consumption

• Begin mechanical design• Module design and mechanical properties• Rod design and properties

• Simulation of interaction between physics and track trigger design• Thresholds• Rates

2

Page 3: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Schedule

3

Page 4: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

4

Page 5: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

5

Page 6: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Milestones

6

Task listMilestone End

Submit VICTR * 08/14/09

Measure silicon interposer charactoristics * 11/11/09

Receive VICTR * 11/12/09

Design demonstration architecture * 11/12/09

Receive sensor * 11/29/09

Measure PC interposer * 12/14/09

Bench Test VICTR * 12/27/09

Mate VICTR chips to sensors * 02/10/10

Thermal modelling * 02/12/10

Bench test chip+sensor assembly * 04/03/10

Bottom stack interconnection * 05/18/10

Bottom stack interconnection tests * 07/17/10

Full stack Interconnect * 08/31/10

Full stack interconnect tests * 09/30/10

Page 7: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

First Pass FY09 Costs

7

Institution M&S eng Tech COLA Travel Total CommentsBrown $8,000 $45,360 $6,000 $0 $10,000 $69,360Cornell $0 $0 $0 $0 $0 $0request in progress

Fermilab $23,000 $16,667 $43,750 $0 $1,200 $84,617generic R&D funding is~ $320k

UC Davis $44,100 $17,640 $15,120 $0 $12,096 $88,956$28000*1.26 for grad student removed

Rochester $0 $35,000 $7,500 $0 $2,000 $44,500RL estimate of $/month

Texas A&M   $0no submitted costsVanderbilt   $0no submitted costsUCSB   $0no submitted costsUC Riverside           $0no submitted costs

Total FY10

$287,432.

67

Page 8: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

8

Who does what?

Page 9: Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup…

Pt Module Proposal

• There is a recent proposal to CMS by Goeff and Anders to prototype “Pt modules” using more conventional technology. Although the module design would be different, there is overlap in much of the work, including circuit design, architecture, simulation, off-detector components, communication …

• I think two parallel, overlapping efforts would be at best, counterproductive and some level of coordination is needed as soon as possible

• In discussions with Goeff we discussed a model where there would be one person assigned to coordinate efforts among the groups in the short term until a structure is formed by the tracker group.

• I would hope that the efforts would be coordinated and ultimately diagonalized by CMS.