Upload
lamdieu
View
216
Download
0
Embed Size (px)
Citation preview
ORANGE WATER AND SEWER AUTHORITY
A public, non-profit agency providing water, sewer and reclaimed water services
to the Carrboro-Chapel Hill community.
400 Jones Ferry Road Carrboro, NC 27510-2001
Equal Opportunity Employer Printed on Recycled Paper
Voice (919) 968-4421 www.owasa.org
Final Report
February 2017 Water Emergency
June 2, 2017
(Amended August 4, 2017)
Purpose
Provide a summary of the events and actions for improvements regarding the Orange Water and
Sewer Authority (OWASA) February 2017 Water Emergency.
Executive Summary
The water emergency in February 2017 resulted from the combination of: 1) an accidental
overfeed of fluoride which was contained at the Jones Ferry Road Water Treatment Plant (WTP),
but made it necessary to shut down the plant and obtain drinking water from the City of Durham;
and 2) a major water main break which occurred about 19 hours after the WTP had been shut
down. The major water main break caused the storage of drinking water for the Carrboro-Chapel
Hill community to drop to very low levels which resulted in a “Do Not Use, Do Not Drink”
directive by the Orange County Health Department for OWASA customers for about 25 hours.
Water with elevated levels of fluoride was fully contained within the WTP and OWASA’s
drinking water remained in full compliance with all quality standards throughout the event.
OWASA customers reduced water use by about 37% during the “Do Not Use, Do Not Drink”
directive. The supply of water was not exhausted and was available for fire protection.
The Board of Directors approved three Action Plans for improvements related to the emergency:
• Improvements related to the water main break at Foxcroft Drive (approved on March
23rd);
• Improvements for the reliability and safety of the fluoride feed system at the WTP
(approved on April 13th); and
• Improvements for strategic communications in OWASA-related emergencies (approved
on April 27th).
Fluoridation of drinking water is expected to resume this fall upon completion of fluoride feed
system improvements at the WTP.
OWASA deeply appreciates the cooperation and understanding of our customers, who
experienced disruption and hardship. We sincerely thank the City of Durham, Chatham County
and Town of Hillsborough for their water supply support. We are very grateful to Orange
County, the Towns of Chapel Hill and Carrboro, the University of North Carolina at Chapel Hill
and other agencies for partnering with us to inform and otherwise serve the community during
the emergency.
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 2
1. Summary of Events – Thursday, February 2, 2017
At 3:22 p.m. on Thursday, February 2nd, the WTP was shut down due to an accidental overfeed
of fluoride in the treated drinking water. Testing confirmed that water with elevated levels of
fluoride was contained in the 1.5 million gallon (MG) clearwell located at the WTP and did not
enter the public drinking water distribution system.
The decision to shut down the WTP was made by OWASA’s Water Supply and Treatment
Manager to avoid pumping drinking water to OWASA customers that wasn’t in full compliance
with all applicable drinking water standards. In making this decision, it was understood that
OWASA would follow standard protocol by immediately initiating actions to bring drinking
water into OWASA’s distribution system through emergency interconnection(s) with the City of
Durham (and Chatham County and/or Town of Hillsborough, if necessary). In doing so, the
expectation at the time was that a sufficient amount of water would be available from the City of
Durham (Durham) to maintain an adequate supply of drinking water for the estimated 48 hours
needed to return the WTP to service. It was also understood at the time that depending solely
upon the water made available through the interconnects increased the risk of a drinking water
shortage. A drinking water shortage could occur if there was an unanticipated increase in water
demand (such as a large water main break or major fire) and/or an unexpected loss of sufficient
supply through the emergency interconnection(s). Staff decided to accept that risk in order not to
send any overfluoridated water into the distribution system.
At 5:09 p.m., the primary emergency interconnection with Durham was activated at a rate of
approximately 6 million gallons per day (MGD) by running a booster station to pump the water
from Durham into OWASA’s water distribution system.
OWASA issued a news release at 6:00 p.m. to inform the public of the accidental overfeed of
fluoride that was contained within the WTP. The release noted that OWASA expected to
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 3
continue to receive drinking water from Durham for a few days and requested that customers use
water wisely.
At 9:10 p.m., OWASA staff began pumping the water with elevated fluoride out of the WTP’s
clearwell into OWASA’s wastewater collection and treatment system. The treatment process at
OWASA’s Mason Farm Wastewater Treatment Plant (WWTP) does not remove fluoride so the
rate of pumping was controlled to avoid a water quality violation in the WWTP’s treated water.
OWASA issued a second news release at 11:00 p.m. to renew the request for conservation.
By the end of the day on Thursday, February 2nd, drinking water storage in OWASA’s system
(solid blue in graphic below) had dropped to about 2.8 MG, which was significantly below
normal minimum storage of 5.0 MG (yellow line below), but still above the emergency storage
minimum of 2.0 MG (red line below).
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 4
Summary of Events – Friday, February 3, 2017
Through the early morning hours of Friday, February
3rd, the quantity of drinking water stored in OWASA’s
system increased as expected to about 3.4 MG, but
was still well below the normal minimum storage
level. At the time, staff expected that the continued
use of the primary Durham interconnection would
keep water storage sufficiently above the 2.0 MG
emergency storage minimum for another 36 hours or
so until the WTP was projected to return to service.
At 8:00 a.m., OWASA issued a news release
requesting continued conservation.
At 10:13 a.m., water storage levels suddenly began
dropping at a very high rate. As a result, OWASA
field staff were notified of a suspected water main
break(s).
At 10:36 a.m., a customer called to report the location of the water main break was Foxcroft
Drive in Chapel Hill. OWASA crews were dispatched to that location to isolate the leak and
stop the loss of water.
At 11:00 a.m., OWASA staff requested immediate
activation of the Orange County Emergency Operations
Center (EOC) because water storage was expected to
drop below the 2.0 MG emergency storage level.
OWASA issued a news release at 11:30 a.m. declaring a
Water Emergency to include a “Do Not Use Water”
directive until further notice because the water supply
was running out. Water storage dropped to 1.8 MG,
well below the emergency minimum supply level.
Water main break at Foxcroft Drive
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 5
At 11:30 a.m., OWASA crews isolated the 12-inch water main break at Foxcroft Drive which
resulted in loss of water service to about 250 people in the Foxcroft Drive area. About 1.3 MG
of water was lost from storage as a result of the water main break. The water main break
damaged Foxcroft Drive and flooded some residences at The Apartments at Midtown 501.
Working closely with partners at the EOC, at 2:00 p.m. the Orange County Health Department
issued a “Do Not Use, Do Not Drink” directive because drinking water storage had dropped to
1.8 MG. At that very low storage level, the community had very limited buffer should another
water main break occur and/or a major fire take place which could have resulted in a total loss of
water supply for the Carrboro-Chapel Hill community. Had OWASA’s water storage been
totally depleted, the time to refill, sample and test the water storage and distribution system to
ensure its safety would have taken at least two to three days, or perhaps more depending on the
circumstances.
The EOC held a media briefing at 4:00 p.m.
Summary of Events – Saturday, February 4, 2017
The pumping of water with elevated fluoride from the WTP clearwell to the wastewater system
continued as planned. OWASA staff began restarting the WTP at 7:30 a.m. on Saturday,
February 4th.
During the previous 20 hours, the water stored in OWASA’s system had increased to about 3.8
MG.
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 6
At 12:34 p.m., bacterial testing of 10 sites in the OWASA service area confirmed that the water
was safe. When distribution system pressures drop below 20 pounds per square inch, the risk of
bacterial contamination increases. A backsiphonage event can occur when water from outside
the pipe seeps into the pipe through cracks, breaks, or joints in the water system. Such a system
failure carries with it the potential for bacterial contamination. Samples had been taken to ensure
that no bacteriological contamination had occurred.
At 2:30 p.m., working closely with partners at the EOC, the Orange County Health Department
rescinded the “Do Not Use, Do Not Drink” directive because water supply had returned to a near
normal minimum storage level and bacterial testing in the distribution system indicated that the
water was safe to drink. It was also clear at this time that the WTP was on schedule to be back in
service within the next four to six hours.
The EOC held a media briefing at 3:00 p.m.
At 3:30 p.m., the contractor working for OWASA completed repairs to the broken water main
and service was restored for about 250 people in the Foxcroft Drive area. However, those
affected in this area were issued a “Boil Water Advisory” until testing confirmed that the water
was safe to drink.
The WTP was returned to service at 6:37 p.m.
By 9:04 p.m., OWASA stopped receiving drinking water from Durham.
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 7
Summary of Events – Sunday, February 5, 2017
At 7:00 a.m. on Sunday, February 5th, the “Boil Water Advisory” was lifted for the Foxcroft
Drive area after testing indicated that the water was safe to drink.
OWASA staff issued a news release at 9:00 a.m. lifting the request for conservation for all
customers.
2. Remediation of the WTP
The treated water with elevated levels of fluoride was contained at the WTP in the 1.5 MG
clearwell and associated piping and channels. The primary task to return the WTP to service was
to pump the water containing elevated fluoride out of the clearwell into OWASA’s wastewater
collection and treatment system at a rate which wouldn’t result in a water quality violation for
the treated water leaving the WWTP. The WWTP does not remove fluoride, so the rate of
pumping had to be controlled to ensure adequate dilution with the wastewater being collected
and treated. Additionally, pumping from the clearwell had to be carefully monitored and
controlled so the capacity of the wastewater collection system wasn’t exceeded (or a sewer
overflow would have occurred). Ultimately, three diesel powered pumps were used to pump the
water from the clearwell to the WWTP beginning on Thursday, February 2nd at 9:10 p.m. and
ending on Saturday, February 4th at 6:30 p.m.
OWASA staff began the process of restarting the WTP at 7:30 a.m. on February 4th by beginning
to treat a small amount of raw water and returning the water filters to service one by one in a safe
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 8
and orderly manner. This process was completed and the WTP was returned to service at 6:37
p.m. on Saturday, February 4th.
During the shutdown, remediation and restarting of the WTP, OWASA staff remained in close
communication with NC Department of Environmental Quality staff in the Public Water Supply
Section.
3. Decision to shut down the WTP
The decision to shut down the WTP was made by OWASA’s Water Supply and Treatment
Manager to avoid pumping drinking water to OWASA customers that wasn’t in full compliance
with all applicable drinking water standards. In making this decision, it was understood that
OWASA would follow standard protocol by immediately initiating actions to bring drinking
water into OWASA’s distribution system through emergency interconnections with Durham (and
Chatham County and/or Town of Hillsborough, if necessary). In doing so, the expectation at the
time was that a sufficient amount of water would be available from Durham to maintain an
adequate supply of drinking water for the estimated 48 hours needed to return the WTP to
service.
It was also understood at the time that shutting down the WTP increased the risk of a drinking
water shortage should there be an unanticipated increase in water demand (such as a large water
main break or major fire) and/or an unexpected loss of sufficient supply from the emergency
interconnection(s) to meet demand. At the time, OWASA staff decided that the avoidance of a
violation of the drinking water quality standard for fluoride was the best course of action for the
community when weighed against what was believed to be a low risk of a large water main break
or loss of supply from Durham. Since September 2010, when staff began recording volume of
water lost from main breaks, there had been no main breaks which resulted in the loss of 1 MG
or more of water (1.3 MG was lost on February 3rd). Additionally, the Durham interconnection
booster pumping station is in excellent condition (only 10 years old) and is routinely tested to
ensure its readiness.
Alternatively, to reduce the risk of a water shortage, OWASA staff could have decided to keep
the WTP in service knowing that a water quality violation would occur. However, taking action
to knowingly violate drinking water standards could have resulted in civil and/or criminal
penalties. Such action could also have resulted in a review by the State Certification Board of
the license(s) of certified operator(s) who knowingly violated a drinking water standard. It is
important to note that there is no known regulatory guidance that supports intentionally
distributing water to the community that does not meet drinking water standards, to reduce the
risk of a water supply shortage. Furthermore, OWASA staff did not and still does not have
detailed information about possible short and long-term health risks of drinking water containing
elevated levels of fluoride. Had this “pump anyway” option been selected, staff would likely
have issued a “Do Not Drink” directive at the same time.
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 9
4. The “Do Not Use, Do Not Drink” Directive
The “Do Not Use, Do Not Drink” directive was issued in consultation with EOC partners
because storage of drinking water in OWASA’s system had dropped to 1.8 MG, which was
below the emergency storage level of 2.0 MG. At that very low storage level, the community
had a very limited buffer should another water main break occur and/or a major fire take place,
either of which could have resulted in a total loss of water supply for the Carrboro-Chapel Hill
community. Had OWASA’s water storage been totally depleted, the time to refill, sample and
test the water storage and distribution system to ensure its safety would have taken at least two to
three days, or perhaps more depending on the circumstances.
When the decision was made, no options other than the “Do Not Use, Do Not Drink” directive
were seriously considered.
Had the supply of drinking water continued to drop below 1.8 MG, an option to keep the system
from running out of water would have been to quickly restart the WTP and pump water with
elevated levels of fluoride into OWASA’s storage and water distribution system. Had this been
done, the EOC would have developed the appropriate messages for the community to ensure
their safety. Keeping the water supply from running out completely is critically important for
fire protection and high-priority sanitation needs.
5. Conservation by OWASA Customers
OWASA customers were directed not to use OWASA drinking water from 11:30 a.m. on Friday,
February 3rd, to 2:30 p.m. on Saturday, February 4th. During that time, it is estimated that
OWASA customers reduced demand by 3.1 MG (a 37% decrease).
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 10
During the “Do Not Use, Do Not Drink” period, all OWASA customers except about 250 people
in the Foxcroft Drive area (where water was shut off to isolate the water main break) had water
service available for their use.
Also of note, OWASA didn’t observe any reduction in demand in response to OWASA’s initial
requests on Thursday, February 2nd, and Friday, February 3rd, to use water for essential purposes
only.
6. Public Communications
With activation of the EOC including representatives of the Towns of Chapel Hill and Carrboro,
Orange County including the Health Department, UNC and UNC Health Care, the American
Red Cross, and others, OWASA participated in the Joint Information Center to coordinate public
communications including news conferences, news releases, text messages and web information.
Orange County also set up a phone bank at the EOC to respond to the numerous inquiries and
developed Spanish translations for distribution through its contact network.
OWASA staff used the following communication platforms and methods during the water
emergency:
• Constant Contact: distribution of news releases to more than 13,800 e-mail addresses,
primarily from the Customer Service database.
• OC Alerts: distribution of notices by telephone, e-mail and text to more than 22,000
people and including additional e-mail addresses which may be used under State law for
health and safety reasons.
• Website: Information posted and updated on the homepage and the Updates on Water
Event page created on February 7th.
• Twitter: the number of Twitter followers grew from about 300 before the emergency to
about 1,100. We sent 14 tweets during the emergency.
• Responding to individual inquiries received by e-mail and telephone. On Friday,
February 3rd, we set up an informal phone bank due to the large number of calls. E-mails
sent to [email protected] were recorded and tracked in our software to maintain a list of
pending requests and log when they were resolved. Our Spanish line was maintained by
bilingual Customer Service staff.
• News media coverage: We provided information as noted above and responded to
interview and information requests from print and broadcast media. There was extensive
news coverage including a national news item on CBS.
7. Investigating the fluoride overfeed and water main break
On Monday, February 6, 2017, OWASA staff contracted with CH2M Hill North Carolina, Inc.
(CH2M) to conduct an independent evaluation of the cause of fluoride overfeed. CH2M was
selected for this work because of their expertise in water treatment and problem solving and their
prior lack of involvement in the design and operation of the WTP. For the water main break,
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 11
OWASA staff contracted with AECOM Technical Services of North Carolina, Inc. (AECOM)
because of their familiarity with OWASA’s water distribution system. Each consultant was
requested to provide their findings to OWASA staff by noon, February 10, 2017.
OWASA staff issued a news release at 12:17 p.m. on Friday, February 10, 2017, notifying the
public that the consultant reports below had been posted to the OWASA website:
• Onsite Fluoride overfeed at Jones Ferry Road Water Treatment Plant on February 2, 2017
(Report by CH2M)
• Water main break in Northeast Chapel Hill (Report by AECOM)
o Letter from AECOM Summarizing the Report on Water Main Break
CH2M determined that the primary cause of the accidental fluoride overfeed was an
unintentional operator keystroke that increased the pump feed rate to higher than the desired
level. Twelve seconds later, the operator entered the corrected command that should have
resulted in the correct pump feed rate. However, according to the control system and logs, the
pump acknowledged the command but failed to respond appropriately. The pump has been sent
to the manufacturer for examination to determine why it failed to respond appropriately. The
secondary cause was that during subsequent routine WTP inspection, the operator failed to take
timely corrective action.
AECOM determined that the water main located on Foxcroft Drive failed due to improper
installation in 1972.
8. Opportunities for Improvement
In addition to the independent consultants’ reports, OWASA staff conducted After Action
Reviews (AARs) on various elements of the water emergency. The purposes of the AARs were
to determine what went well in response to the Water Emergency (that should be repeated in the
future) and to determine opportunities for improvement. The information from the AARs, the
consultant reports, feedback from the public and guidance by the OWASA Board of Directors
resulted in staff preparing Action Plans for improvement regarding: 1) Foxcroft Drive Water
Main Break; 2) the Fluoride Feed System; and 3) Strategic Communications During OWASA-
Related Emergencies. These Action Plans were shared with the public and the Board of
Directors invited public feedback at Board meetings prior to approving the plans.
Foxcroft Drive Water Main Break
This Action Plan was discussed and approved by the Board at the March 23, 2017
meeting. Key actions for improvement are:
• Additional staff training;
• Updates to Standard Operating Procedures; and
• Updates to the list of contractors available for emergency repair of infrastructure.
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 12
Fluoride Feed System
This Action Plan was discussed by the Board at the March 23rd Board meeting and discussed
further and approved at the April 13, 2017 Board meeting. Key actions for improvement are:
• Replacement of feed pumps;
• Installation of new automated monitoring and control system with alarms and
safeguards;
• Additional staff training; and
• Updates to Standard Operating Procedures.
Strategic Communications During OWASA-Related Emergencies
This Action Plan was discussed and approved by the Board at the April 27, 2017
meeting. Key actions for improvement are:
• Continuing to work with local partners on public communications for emergency
preparedness and response;
• Active and responsive relationships with the media and other stakeholders;
• Improving internal procedures and resources;
• Communicating with public about emergency preparedness in homes and businesses; and
• Additional staff training.
Other Opportunities for Improvement
In addition to the specific improvements covered in the three Action Plans, OWASA staff will:
• Continue to participate with staff from Orange County, the Towns of Carrboro and
Chapel Hill, the University and other stakeholders in an AAR process being facilitated by
Orange County Emergency Services;
• Work closely with water utilities in the region to further explore opportunities to further
enhance the region’s water supply reliability and resiliency;
• Work with customers and other stakeholders on matters of insurance, preparedness and
communications during periods of service interruption; and
• Proactively share its “lessons learned” from the February 2017 Water Emergency with
utility peers and other stakeholders.
9. What worked well?
As noted in section 8, staff identified actions and activities in response to the water emergency
that worked well, as summarized below:
• OWASA drinking water in the distribution system remained in full compliance with all
quality standards (water with elevated fluoride was safely contained at the WTP and did
not enter the public drinking water system);
• The supply of safe drinking water was not exhausted;
Final Report on the February 2017 Water Emergency
June 2, 2017 (Amended August 4, 2017)
Page 13
• The Orange County EOC, working cooperatively with the Towns of Chapel Hill and
Carrboro, the University, OWASA and other stakeholders, performed effectively to keep
the community safe and informed;
• There was extensive media coverage of the event;
• The interlocal mutual aid assistance of drinking water supplied by City of Durham,
Chatham County and (although not necessary) the Town of Hillsborough was excellent;
• OWASA customers and stakeholders were understanding and responded to the “Do Not
Use, Do Not Drink” directive by reducing water use by about 37%;
• Remediation of the WTP by OWASA staff went according to plan and without a
violation of any water quality standards for the wastewater collection and treatment
system;
• OWASA worked hard to be fully transparent and forthcoming with all communications
with the public and other stakeholders; and
• No OWASA accidents or injuries occurred.
10. OWASA’s Incurred Costs
As of April 30, 2017, the operating costs incurred by OWASA (not including staff time) in
response to the water emergency is about $126,000, as summarized below:
Item Cost
WTP fluoride overfeed $71,000
Water main break $55,000
The cost to upgrade the fluoride feed system at the WTP is estimated to be between $123,500
and $175,500. These improvements are expected to be completed by the fall of 2017.
11. Closing
OWASA deeply appreciates the cooperation and understanding of our customers, who
experienced disruption and hardship. We sincerely thank the City of Durham, Chatham County
and Town of Hillsborough for their water supply support. We are very grateful to Orange
County, the Towns of Chapel Hill and Carrboro, the University and other agencies for partnering
with us to inform and otherwise serve the community so well during the emergency.
The OWASA team will work hard to implement the many improvements noted in this report to
further improve the reliability and resiliency of our services.
Submitted by:
Ed Kerwin
Executive Director