OR42: County Line
Slide Repair, Phase 4
Key # 21182
Presentation to the Mobility Advisory Committee
Jan 10, 2019
CamasValley
Remote
Winston
PROJECT LOCATIONOR 42, mile point 44.6 – 45.9
PROJECT SCHEDULE
• Bid Opening: May 15, 2019
• PS&E Due: February 19, 2019
• Construction: Summer – fall 2019
• Nearing completion of OR42:
County Line Curves project
• Excavation completed and new
alignment base constructed
• Worked stopped for the winter
• Paving planned for following
spring
PROJECT BACKGROUND AND SCOPE
• A December 2015
landslide covered the new
highway alignment
• Phases 1-3: Remove slide
material and reopen the
highway; install drains; and
retaining walls
• Phase 4: Complete the
retaining walls; complete
the realignment and
paving; replace a
damaged culvert; and
haul remaining slide
material
PROJECT BACKGROUND AND SCOPE
ROADWAY CHACTERISTICS
• The highway is
constrained by the river
and steep, unstable slopes
• Two 12-foot lanes with 6-
foot shoulders
• 2017 ADT: 2,500
• Percent trucks: 23.4%
PROJECT STAGING & MOBILTY IMPACTS
• Excavation and
retaining wall: Work is off
the shoulder
• Roadway realignment
and paving: Single lane
under flaggers. Width
varies, but all wide loads
can be accommodated
• Culvert replacement:
Three construction
stages
PROJECT STAGING & MOBILTY IMPACTS
• County Line Slide Culvert, Stages 1 and 3:
• 19’ of pavement with barrier on one side; at least 3
feet of shoulder will be clear outside of pavement
PROJECT STAGING & MOBILTY IMPACTS
• County Line Slide Culvert, Stage 2:
• 19’ of pavement between hard barrier on slight curve
• Contractor will have 14 consecutive days to complete
Stage 2 once in place
CRITICAL ROUTE PAIR – OR 38
• OR38: Hoagland Cr and Unnamed Cr Culverts -
Potential conflict.
• Replace two large culverts on OR 38. Part of the
OR38/US101 Culvert Pilot Project
• Both culverts require one stage of 19’ between hard
barrier. Contractor will have 14 consecutive days to
complete each Stage 2 once in place
• This may result in a paired route conflict of up to 14 days
for loads wider than 16 feet.