Upload
gertruna3
View
13
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Paper about petroleum plataforms
Citation preview
SELECTION OF AN OFFSHORE PETROLEUM PRODUCTION SYSTEM BY EVALUATING AN ENVIRONMENTAL IMPACT INDEX
Maiara Moreira Gonalves Graduate Program
Petroleum Science & Engineering University of Campinas
Campinas-SP, Brazil
Celso Kazuyuki Morooka Faculty of Mechanical Engineering & Center for
Petroleum Studies, LabRiser University of Campinas
Campinas-SP, Brazil
Ivan Rizzo Guilherme Statistics, Applied Mathematics and
Computation Dept., Paulista State University
Rio Claro-SP, Brazil
ABSTRACT The development of an offshore petroleum production
system corresponds to define a set of equipment to make
possible oil and gas extraction from an underwater petroleum
reservoir. To better comprehension of the process, definition of
this production system can be divided into phases. Phase I
corresponds to the selection of number of wells and type of the
well. Then, following the previous work (Franco, 2003), in the
Phase II, the layout arrangement of wells and the set of the
stationary Floating Production Unit (FPU) are selected. And, in
the Phase III, storage and offloading alternatives for the
produced oil and gas are selected.
The present paper aims to identify environmental impacts
associated with the each component of an offshore system for
oil and gas production, and quantify each of them through
indexes. It is expected to support the decision makers to select
the best fitted system for a given offshore petroleum field. The
increasing needs of petroleum to fulfill the energy matrix
demanded in Brazil, the growing concern of the society for
keeping the environment clean and the inclusion of an index
related to the environment besides the technical and
technological indexes usually taken makes it an important
contribution to improve the process for selection and decision
about the offshore production system. Particularly, it will be
fundamental in the adverse condition of the Pre-salt scenario of
petroleum production, in ultra-deep water depth and oil and gas
with more aggressive contaminants to the system.
The proposed methodology follows a similar procedure for
the assessment of environmental impacts through the use of environmental sensitivity index (ESI) and the use of impact
matrix (NOOA, 1997; Patin, 1999; Mariano and La Rovere,
2006). For the estimation of environmental impacts, it was
defined the ESI of the area to be developed, and it was
constructed an impact matrix based on the activities involved in
the installation of platform, operational phase and
decommissioning of a FPU and the elements from environment.
Therefore, this systematic and structured approach allowed
incorporating to the process of selection of the offshore
production system for an oil and gas field the selection of
alternative which combines the best technical and technological
characteristics with better aspects from the environment.
INTRODUCTION Nowadays, the petroleum performs an important role in the
context of Brazilian economy, and it also plays a fundamental
role in terms of the energy matrix of consumption in the
country. On the other hand, to maintain the petroleum
production overcoming the demand requirements, it is
mandatory to increase petroleum exploitation to reach large
accumulations such as those of the pre-salt, usually placed in a
more severe environmental condition.
Figure 1 shows typical configuration for an offshore
petroleum production system for deep and shallow waters
which usually incorporates technical and technological indexes
in the selection process.
In previous works, the development of an offshore
petroleum production system considered mainly economical
aspects (Morooka and Galeano, 1999; Morooka and Castro,
2002; Dezen and Morooka, 2003; Morooka and Carvalho,
2011). Franco (2003) describes an approach for the
Proceedings of the ASME 2014 33rd International Conference on Ocean, Offshore and Arctic Engineering OMAE2014
June 8-13, 2014, San Francisco, California, USA
OMAE2014-23461
1 Copyright 2014 by ASME
development of an offshore petroleum production system based
on technical aspects, and uses Fuzzy Logic tools to support an
intelligent system to select and decide the best alternative.
Figure 1: Typical Offshore Petroleum Production System
composed by different components of system.
Taking into account the increasing adverse conditions of
production scenario, an index related to environment impact of
the each systems component is proposed to be added in the selection and decision process.
NOMENCLATURE EIA - Environmental Impact Assessment
ESI - Environmental Sensitivity Index
FPSO - Floating Production Storage and Offloading
FPU - Floating Production Unit
FSO - Floating Storage and Offloading
MODU - Mobile Offshore Drilling Unit
SS - Semisubmersible
TLP - Tension Leg Platform
OFFSHORE PETROLEUM PRODUCTION SYSTEM The field discovery occurs in the Exploration Phase, which
consists to search entrapped hydrocarbon formation in the
underwater subsurface. In this manner, initially, a geophysical
survey usually done and the data acquired interpreted. Then, a
wildcat well is drilled, and with the evidence of a hydrocarbon
accumulation, the volume of oil in place is estimated. If
exploitation of the petroleum reservoir is economically viable,
the field development plan is decided and the design of the
production system is started.
Among initial steps of the field development, the wellbore
is built to reach the reservoir. Rotary drilling is the usual
process for the well construction, when the steel casing is
cemented into the bore to isolate it from the formation. Then,
the production equipment is set into the well, and commonly
artificial lifting devices or pumps are applied. Finally, each
subsea well is connected to a stationary FPU at the sea surface,
through pipes and risers.
Sometimes manifolds are used to organize petroleum flow
from the wells, and to minimize numbers of risers connected to
the FPU.
More details for offshore petroleum production systems
can be obtained from the literature (Chakrabarti, 1987; Jah et
al, 1998)
ENVIRONMENTAL SENSITIVITY INDEX ESI index allows an integrated view of the environmental
condition for a given region. Its main feature is the ability to
relate the sensitivity of an area in relation to a kind of impact.
ESI provides means to identify any changes of the
environmental scenario in an area or region coming from the
usage of each systems component. ESI is comprised with three general types of information: 1) shoreline classifications,
which are ranked according to a scale relating to sensitivity,
natural persistence of oil and ease of cleanup; 2) biological
resources, which include oil-sensitive animals and rare plants;
habitats, which are used by oil-sensitive species or are
themselves sensitive to oil spills, such as submersed aquatic
vegetation and coral reefs; and 3) human-use resources, which
are specific areas that have added sensitivity and value because
of their use, such as beaches parks and marine sanctuaries,
water intakes and archaeological sites (NOOA, 1997).
The concept of ESI is divided into three types: low,
medium and high. The environment with low ESI is decrypted
with high energy waves, substrate impermeable, intertidal zone
slope with 30 degrees or greater, biota with low density and the
shoreline type with rocks shores exposed and beaches with fine
to medium grained sand. Medium ESI is an area with high to
medium wave energy, substrate impermeable or semi
permeable, slope medium, the density of marine biota low, and
type of shoreline composed with mixed sand and gravel
beaches. And, sensitive areas with high ESIs are characterized
with low wave energy, flat substrate containing mud, the
complex ecosystem, and the shoreline consisting of salt
marshes and mangroves (NOOA, 1997).
ENVIRONMENTAL IMPACT IN THE PETROLEUM PRODUCTION
Drilling fluids are used in the wellbore building process to
lubricate and cool down the drill bit and to transport rock
cuttings from the well bottom up to the surface. Two types of
drilling fluid are the most common: the water based fluid and
oil based one.
The oil-based fluids are widely used and commonly
applied for offshore well drilling. The drilling of horizontal
2 Copyright 2014 by ASME
wells traditionally uses oil-based drilling fluids and, water
based ones in the vertical wells drilling.
An important issue is related to the use and disposal of
drilling wastes into the ocean. Water based drilling fluids
usually have lower costs when compared with other types.
They are biodegradable and easily disperse in water (Mariano
and La Rovere, 2006). From the other hand, oil-based muds are
harmful to the environment if discarded into the ocean due to
its toxicity and slow biodegradation.
Besides of the type of well, in the drilling process there are
decisions related to the number of wells and the layout
arrangement of wells. In areas with high environmental
sensitivity, the seafloor has a rich biodiversity of marine biota.
If many wells are drilled within those areas, the impact over
the biota would be large. Moreover, if the layout arrangement
of wells is satellite, the length of flowlines connecting each
well to FPU will be larger. And, the environmental impact
would be larger again, due to increase of the possibility of oil
spills.
Installation and commissioning of the FPU cause
environmental impact due to physical presence, pre-sweep
dredging activity, seabed disturbance and, finally, atmospheric
emissions resulting from power generation.
Storage and offloading of the produced petroleum affect
the environment because the existing probability of collision of
ships, and high environmental impact in the pipeline
construction. Thus, in areas with high ESI it is necessary a
careful environmental impact analysis regarding offloading
alternatives.
METHODOLOGY The proposed methodology follows a similar procedure for
the Environmental Impact Assessment (EIA) through the use of ESI (Patin, 1999; NOOA, 1997).
Therefore, the impact matrix is used to select the best FPU
alternative, and the ESI to define all the offshore production
system for the petroleum field.
In this process, the ESI is initially classified for the area of
the given petroleum field, as shown in Figure 2. Then, phases
for designing the offshore petroleum production system are
initiated.
Figure 2: ESI classification for the area of the given petroleum
field.
For the development of the production system, number of
wells, type of wells, layout arrangement of wells, type of the
FPU and, finally, oil storage and offloading process are defined.
The sequence and dependency among phases are schematically
shown in Figure 3.
Figure 3: Phases of Development of a Production System
for an Offshore Petroleum Field.
PHASE I
Phase I begins with the selection of number of wells. It is
decided based on the oil and gas reserves, flow rate per well
and the ESI index of the area (Figure 4). In areas with high ESI,
the number of wells must be low, because the vulnerability of
the area, independently the volume of reserve and the flow rate
per well. When the ESI is medium, the number of wells must be
medium if the volume of reserve and the flow rate per well are
low. And, the number of wells must be low, if the volume of
reserve is small and the flow rate per well is low. Finally, for
the low ESI, the number of wells will be high if the volume of
reserve is large and flow rate per well is high, and the number
of wells will be medium if the volume of reserve is medium
and flow rate per well is medium, and so on.
Figure 4: Determination of the Number of Wells and Type
of Well (Phase I).
Phase I
Number of Wells
Reserves Flow Rate per Well ESI
Area of the
Reservoir
Depth of the
Reservoir
Number
of Wells ESI
Type of Well
Development of an Offshore Petroleum Production System
Number
of Wells
Type of
Well
Arrangement
of Wells
FPU
Oil Storage
and
Offloading
Phase I Phase II Phase III
ESI
Low Medium High
3 Copyright 2014 by ASME
Following in the Phase I, the type of wells is vertical or
horizontal, and it is determined by the number of wells, the area
of reservoir, the depth of the reservoir and ESI (Figure 4). If
the ESI of the area is: (a) high, the type of well will not be
horizontal because the well drilling trajectory requires a large
inclination angle being necessary the oil based drilling fluid
with possibility to cause impact into the environment; (b)
medium, and the number of wells is medium the type of well is
vertical, or if the number of wells is low the type of well could
horizontal or vertical. When the ESI is low, alternatives pointed
out by the technical and technological index can be followed.
PHASE II
As scheme in Figure 5, Phase II begins with the layout
arrangement of wells. In the satellite arrangement, the wells are
spread out over the area of the reservoir. It is deployed
especially on large acreage fields. In clustered arrangement, the
wells heads are clustered close each other. It is necessary the
use of directional drilling to reach different positions of the
reservoir. Thus the clustered arrangement is used in small
acreage fields.
In a reservoir with large thickness, horizontal well is
usually applied to increase productivity, and the layout
arrangement of wells will be clustered. If the area of reservoir
is small, the number of wells is low and the arrangement of
wells will be also clustered.
And finally, if the ESI of the field is high, the layout
arrangement of wells will be clustered in order to minimize
environmental impacts due to reduction of the area with
disturbance.
Figure 5: Determination of the Layout Arrangement of Wells
and of the FPU (Phase II).
In the next section, the impact matrix based on the
installation of platform, operational phase and
decommissioning of a FPU and elements from the environment
is constructed to select the FPU.
IMPACT MATRICES ASSESSMENT
For estimation of environmental impacts, impact matrices
for the each component was elaborated (Figure 6) in order to
support a systematic and structured approach of decision for the
selection of the FPU.
Considering the main parameters for the development of an
offshore petroleum production system, activities in below will
be evaluated:
- Installation of Platform: vessel traffic, soil preparation,
positioning platform and mooring system;
- Operational Phase: physical presence platform, seawater
uptake, atmospheric emissions, disposal of sewage, disposal of
solid waste, disposal of water production, oil spills and vessel
traffic support;
- Decommissioning: removal of structure, abandonment of
wells and conditioning, disposal of sewage, oil leaks,
atmospheric emissions and disposal of solid waste.
Observing activities as enumerated in above, a list of
elements from the environment that can suffer impact (Patin,
1999) was obtained: air, water, sediments, plankton, benthic
communities, fish, fisheries, birds, marine mammals and
tourism.
Possible impacts to the environment from an offshore
petroleum production system are: anthropogenic interference,
navigation, fishing and tourism; degradation of water quality,
landscape and air quality; potential emergencies such as
environmental risk of accidents; and interference with biota as
light pollution and noise pollution.
The impact matrix for the each type FPU was developed
based on types of activities involved in the development of
offshore petroleum production system, and the elements from
the environment. In the Figure 6, activities as mentioned in
before will be enumerated in each line of the first column, and
elements from the environment are placed in the each column,
as in Figure 6.
Air
Wat
er
Sed
imen
ts
Pla
nct
on
Ben
thic
Com
munit
ies
Fis
h
Fis
her
ies
Bir
ds
Mam
mal
s
Touri
sm
Installation of Platform +
Operational Phase +
Descomissioning +
Total
Index :
Impact Matrix for each FPU
Kind of Activity
Elements from the Enviroment
Partial
Index
Figure 6: Generic Impact Matrix for a FPU.
Phase II
Area of the
Reservoir
Depth of the
Reservoir
Number of
Wells
Arrangements of Wells
Type of
Wells
Arrangement
of Wells
Water
Depth
Number
of Wells ESI
FPU
Environmental
Conditions
ESI
Flow Rate
per Well
4 Copyright 2014 by ASME
The estimation of probability of occurrence of the
environmental impact is obtained as the scheme in Figure 7.
The consequence and frequency of occurrence of the impact
can be classified into different ranges from low to extreme
ones.
Figure 7: Estimation Procedure for the Probability of
Environmental Impact.
The calculation of the probability of occurrence of impact
is made for all activities related with each of the elements of the
environment, and finally by summing up each probability of
occurrence to obtain the partial index for the activity.
OFFSHORE PRODUCTION PLATFORMS
Each FPU has a particular characteristic which influences
the construction of its impact matrix. There are fixed platforms
which are supported on the seabed, and floating ones which are
compliant structures positioned by a mooring system.
The Jacket Platform is a metallic structure fixed with piles
driven into the seabed. It indicates possible changes of the
seabed conditions due to the use of dredging. This operation of
installation requires special care and must be a very precise
work because the structure can not be removed. In the
decommissioning, the platform will be cut into several parts
with the use of explosives which can cause environmental
impacts, such as elimination of artificial habitat appeared
around the base of the structure.
The Compliant Tower is a structure supported by a truss
structure and kept stationary by a spread guided cable guides
fixed at the sea bottom by gravity anchors. This type of
platform can cause environmental impact due to dredging and
mooring system. The decommissioning has similar impact of
the jacket platform.
A Jack-up Platform or a Self-elevating Unit is a Mobile
Offshore Drilling Unit (MODU) with a buoyant hull fitted with
a number of movable up and down legs which can be supported
on the seabed. Sometimes, this platform is modified for
production, particularly for marginal oil fields (Bunce &
George, 2000). These platforms generate low impact on the
seabed if compared to other types of platform, and there is no
difficulty for decommissioning being a mobile unit.
The Gravity Tower is a fixed platform and its foundation is
built by increasing weight of the ballast. The installation
process needs support of a large number of barges for
transportation to the field, and its decommissioning also
requires the use of explosives and ships with high capacity.
The Spar units are designed with a huge submerged buoy
that can be used to storage the produced petroleum. Once
positioned in the field, ballast tanks are used to upright the hull
into the position, and mooring system is set. The operation of
installation of the mooring system increases the environmental
impact. For decommissioning, the removal of the platform
usually is very complex due to the underwater hull size
The SS floating platforms have small motions, then the
safety of this type of platform will be high, with less number of
recorded accidents than other type of mobile platforms. From
the other hand, the FPSO has a large storage capacity, and the
number of mooring lines are larger than that for the SS
platform, due to larger motions. FPSO has larger number of
recorded accidents, especially accidents and incidents in
adverse weather conditions (HSE, 2003). Installation and
decommissioning, for both, SS and FPSO are similar. The
station keeping is done by a mooring system. The main
difficulty in the process of decommissioning of the vessel is the
disconnection of all moorings, flowlines and risers, once the
FPU are usually used in deeper waters.
The TLP has a similar hull of the SS. However, TLP
tendons are anchored into a foundation at the seabed by
concrete or steel piles. Leg tendons are pulled by the buoyancy
of the platform which reduces platform heave motions.
Although the TLP is a floating platform, it has a different
process for decommissioning, because the tensioned mooring
systems which will make more difficulty uninstall procedure.
Figure 8: Total Environmental Impact Index for the each FPU.
The summation of all partial indexes for activities in the
impact matrix will give the total environmental impact index. It
represents how far the each offshore production platform will
X
= Probability of the Occurrence of Impact
Frequency of the Occurrence of Impact
Consequence of the Occurrence of Impact
Insignificant
1
Less
2
Catastrophic
5
Moderate
3
Larger
4
Low
1-4
Moderate
5-8
High
9-14
Extreme
15-25
Rare
1
Improbable
2
Certain
5
Possible
3
Probable
4
800
900
1000
1100
FPU
Total Environmental Impact Index
5 Copyright 2014 by ASME
affect the environment, as can be seen in Figure 8. The Table 1
shows the total environmental impact index according to the
water depth, where the FPU with low total environmental
should be applied for area of high ESI.
In the second part of Phase II, several parameters are
considered for selection of the FPU.: water depth, layout
arrangement of wells, environmental conditions, number of
wells, flow rate per well and ESI. In this work, the water depth
is classified as: shallow, medium, deep, and ultra-deep (Table
1). The classification differs from the standard water depth
ranges (API, 2006), in order to improve classification of the
FPU type according to the ESI.
This parameter is important because each type of FPU has
application restrictions according to the water depth. For
instance, fixed type platform as the Jacket, Jackup, Gravity
Platform and Compliant Tower, are fixed directly into the
seabed, and they usually are feasible up to around 100 meters
water depths. The floating platform such as the Spar, TLP,
FPSO and SS can be operated up to around 2500 meters with
the use of new technologies for mooring system. Each type of
FPU has a particular layout arrangement of wells, for example,
the TLP and the jacket just work with the clustered layout
arrangement.
Table 1. Distribution of the FPUs according to the ESI and the
water depth, respectively.
ESI
Water Depth
Shallow (0-150m)
Medium (150-500m)
Deep (500-900m)
Ultra-Deep
(> 900m)
Low
Jackup,
Jacket, SS,
FPSO,
Gravity.
Jackup,
Jacket, SS,
FPSO,
Tower-
Guide, TLP.
SS, FPSO,
Tower-
Guide, TLP,
Spar.
SS, FPSO,
Tower-
Guide, TLP,
Spar.
Medium
Jackup,
Jacket, SS,
FPSO.
Jackup,
Jacket, SS,
FPSO, TLP.
SS, FPSO,
TLP, Spar.
SS, FPSO,
TLP, Spar.
High Jackup, SS. Jackup, SS,
TLP. SS, TLP. SS, TLP.
Environmental conditions will be determined by the
amplitude of the waves and the wind speed, which produce the
vertical and horizontal motions in the platforms. The
environmental conditions are divided according to the Beaufort
scale: calm, moderate, or severe. In such cases the
environmental conditions will influence in the selection,
because in severe conditions as in the North Sea is common the
use of fixed platforms that support that conditions, in contrast
of Brazil which has the environmental conditions from calm up
to moderate. Each type of platform has a limited capacity to
process oil, which will limit the number of wells. The rate flow
per well from the reservoir will determine the select of the
capacity oil processing FPU.
PHASE III
Phase III is the last phase of the process of selection an
offshore petroleum production system, it involves the decision
of the storage and the type of flow the oil and gas produced,
which will depend on factors such as distance from the coast,
the FPU storage capacity, the type of FPU and existence or not
of infrastructure (Figure 9).
There are three types of storage and flow of oil and gas
produced: pipeline, FPU with storage capacity and with relief
vessel to flow, and FPU without storage capacity with a
permanent storage vessel and more a relief vessel to flow. The
existence of an infrastructure near the FPU facilitates the flow
by pipeline or when the production of a field is high may be
feasible to build a pipeline, if the ESI of the area isnt high. If the distance from the coast to the field is very large, the flow by
relief vessel could be the best option.
Figure 9: Determination of Oil Storage and Offloading (Phase
III).
RESULTS
In order to evaluate the present approach, it is used the
database composed of 33 fields, which their actual system are
constituted by number of wells, type of wells, arrangement of
wells, FPU and oil storage and offloading, as in Franco (2003).
The ESI of each petroleum field is present in Table 2.
Fields have ESI selected, through the methodology
presented in this work the configuration the each petroleum
field is selected and compared with the results in work of
Franco (2003), which it is used the technical and technological
indexes to select an offshore petroleum production system, the
different between theses methodologies and real configuration
of fields are presented in Figure 10.
Figure 10 presents 33 petroleum fields, among which 17
fields presented ESI low, 6 fields with medium ESI and 10 with
high ESI. The present approach obtained a result with large
difference in fields with high and medium ESI in relation the
actual system, whilst Franco (2003) obtained similar results of
actual system for all kinds of ESI. The agreement of present
approach between the actual fields is 49% and 60 % for fields
with high and medium ESI, respectively. The results of all
phases of the system are presented in Annex A.
Phase III
Existence of
Infrastructure
Flow Rate
per Well
Distance
from the
Coast
Oil Storage and Offloading
FPU Number
of Wells ESI
6 Copyright 2014 by ASME
Table 2. ESI of Petroleum Fields (Franco, 2003).
Location
ESI
Low Medium High
North Sea
Glamis Veslefrikk Gullfaks
Telford Oseberg Ekofisk
Argyll Troll East Oseberg
Captain West Troll Siri
Forties - -
Alba - -
Andrew - -
Britannia - -
Gulf of Mexico
- - Baldpate
- - Brutus
- - Mars
- - Cognac
Canada - - Hibernia
Grand Banks Campos Basin Barracuda Marlim -
Roncador Albacora -
East Albacora - -
Mediterranean Sea Aquila - -
Australia Stag - -
Gulf of
Guinea/Nigeria
Ceiba - -
Luanda/Angola - Girassol -
West Africa Kuito - -
Figure 10: Results of Comparison of the Database of Petroleum
Fields.
Figure 11 and 12 illustrates the comparison between
present approach and Franco (2003) in relation actual system. It
can be noted in present approach that around of 20% of
numbers of wells there is a disagreement, which consequently
changed the result of the following phases. In works of Franco
(2003), the number of wells and type of wells has 100% of
agreement because these parameters are an input necessary to
run the respective system.
Figure 11 shows the mainly difference is present in the
number of wells, type of wells and FPU. And Figure 12 shows
the agreement approximately 50% of the arrangement of wells
and 60% of FPU, in relation to actual cases.
The difference of the results indicates the lack of
indicators from the environment in development of petroleum
fields, as Gullfaks (Sintef, 2010) Snorre (Sintef, 2010) and
Hibernia (Shrimpton, 1985). Another difference of the results is
attributed the lack of technologies of platform, which make
impossible the selection the best FPU for the field, as Girassol.
In Gulf of Mexico, petroleum fields are present in high
sensitivity area, the environmental conditions and geology
difficult dispersion of oil in case of accident, moreover the
historic of accidents in this region is large due to presence the
many fields (NOOA, 1997).
Presumably the fields with high or medium ESI not used
the environmental impact index in its development; therefore
some accidents occurred probably they would not have
generated a large environmental impact.
Figure 11: Results of Comparison of the Database of Petroleum
Fields (ESI Medium).
0%
20%
40%
60%
80%
100%
Low Medium High Co
nco
rdan
ce o
f A
ctu
al S
yste
m
ESI
Agreement with Actual Systems
Present Approach Franco (2003)
0%
20%
40%
60%
80%
100%
Number of Wells
Type of Well Arrangements of Wells
FPU Oil Storage and
Offloading
Co
nco
rdan
ce w
ith
Act
ual
Sys
tem
Agreement with Actual System (ESI Medium)
Franco (2003) Present Approach
7 Copyright 2014 by ASME
Figure 12: Results of Comparison of the Database of Petroleum
Fields (ESI High)
CONCLUSION
Indexes related to the environment have been included in
the process of selection of each component of an offshore oil
and gas production system. A case study was performed by
following the proposed approach that combines the best
technical and technological characteristics with environmental
aspects, through the consideration of ESI index in the selection
of the offshore production system from alternatives.
The inclusion of ESI and the total index environmental
impact index modified parameters for the selection of offshore
petroleum production system. The selected alternative from the
present approach demonstrates being less sensitive for
environmental accident and less impact from the petroleum
activity.
ACKNOWLEDGMENTS
The authors would like to thank PRH/ANP and CNPq for
the support in the present research.
REFERENCES
[1] Morooka, C. K., Galeano, Y. D., 1999, Systematic Design for Offshore Oilfield Development, International Society of Offshore and Polar Engineers, ISOPE, Brest, France.
[2] Morooka, C.K.; Castro, G.T., 2002, A Methodology for the Selection of an Alternative for a Floating Production
System, 21th International Conference on Offshore Mechanics and Arctic Engineering (OMAE), Oslo,
Norway.
[3] Dezen, F., Morooka, C.K., 2003, Alternatives for Deepwater Field Developments: A Real Option
Approach, Offshore Technology Conference (OTC), Dallas, Texas, USA.
[4] Morooka, C.K, Carvalho, D., B., M., C., 2011, Evaluation of Alternatives for Offshore Petroleum Production System
in Deep and Ultradeep Waterdepth, 30th International Conference on Offshore Mechanics and Arctic
Engineering (OMAE), Rotterdam, Netherland.
[5] Franco, K.P.M., 2003, An Intelligent System to Assist the Selection of Offshore Production System, M.Sc. Thesis, University of Campinas, Campinas, (In Portuguese).
[6] CHAKRABARTI S.K. 1987, Hydrodynamics of Offshore
Structures. Southampton Boston:Computational
Mechanics Publications, Southampton, Boston.
[7] Jahn, F., Cook, M., Graham, M., 1998, Hydrocarbon Exploration and Production, Vol. 1, Elsevier, Netherlands.
[8] NOAA, 1997, Environmental Sensitivity Index Guidelines, Version 2.0, National Oceanic and Atmospheric Administration (NOAA), Technical Memorandum NOS
ORCA 115, Hazardous Materials Response and
Assessment Division, Seattle.
[9] Mariano, B. J., La Rovere, L. E., 2006, Methodology for Impact Assessment and Environmental Risks Studies of
Strategic Environmental Assessment of Offshore Areas, Rio Oil & Gas Expo and Conference, Rio de Janeiro,
Brazil, (In Portuguese).
[10] Patin, S., 1999, Environmental Impact of the Offshore Oil and Gas Industry, Vol. 1., EcoMonitor Publishing, New York.
[11] Bunce, J.W., George, P.J., 2000, A Jackup-Installed Platform for Marginal Fields, Offshore Technology Conference (OTC), Dallas, Texas, USA.
[12] API American Petroleum Institute, 2006, Petroleum and natural gas industries -- Design and operation of subsea
production systems -- Part 1: General requirements and
recommendations, ISO 13628-1:2005.
[13] HSE - Health and Safety Executive, 2003, Analysis of Accident Statistics for Floating Monohull and Fixed
Installations. Research Report 047, United Kingdom.
[14] SINTEF Technology and Society, 2010, Organizational Accidents and Resilient Organizations: Six Perspectives, Revision 2, Sintef A17034, Norway.
[15] Shrimpton, M. Osberg, L., Sinclair, P., Steele, D., 1985,
The Impact of Hibernia, Hibernia Development Project: Report of the Hibernia Environmental Assessment Panel,
Government of Canada, Minister of Supply and Services,
Ottawa, Canada.
0%
20%
40%
60%
80%
100%
Number of Wells
Type of Well Arrangements of Wells
FPU Oil Storage and
Offloading
Co
nco
rdan
ce w
ith
Act
ual
Sys
tem
Agreement with Actual System (ESI High)
Franco (2003) Present Approach
8 Copyright 2014 by ASME
ANNEX A
Table A1. Results of the system compared with Actual Cases and Franco (2003).
Aqu
ila
Gla
mis
Telfo
rd
Ceib
a
Gira
ssol
Bald
pate
Hib
erni
a
Gul
lfaks
Siri
Ekof
isk
Stag
Brut
us
Mar
s
Mar
lim
Ves
lefr
ikk
Snor
re
Arg
yll
Area of the Reservoir (m) 13 15 11 41 180 43 68 50 66 19 100 53 59 132 25 62 24
Depth of the Reservoir (m) 3500 3094 2750 2811 1200 4145 3700 2000 2070 3197 3500 4500 4267 2300 2925 2500 3500
Flow per Well (m/d) 2900 22000 9300 2000 1000 400 2900 250 100 12000 1000 5000 2000 100 1300 1400 800
Water Depth (m) 850 145 135 800 1350 500 80 140 60 70 47 910 760 850 174 158 80
Environmental Conditions Calm Severe Severe Calm Calm Calm Mod. Severe Severe Severe Calm Calm Calm Calm Severe Severe Severe
Distance of the Coast (Km) 50 204 170 41 210 222 315 175 220 300 65 306 241 110 145 210 320
Infra. No Yes Yes No No No No Yes No No Yes Yes Yes Yes Yes Yes No
Reserves (m) 3E+06 4E+08 7E+06 4E+07 1E+08 2E+07 8E+07 3E+08 1E+07 1E+08 9E+06 4E+07 8E+07 3E+08 5E+09 1E+08 5E+06
ESI Low Low Low Low Med. High High High High High Low High High Med. High High Low
Number of Wells 2 3 6 4 40 18 18 106 42 4 8 8 10 135 24 46 8
Type of Well horiz. vert. horiz. vert. vert. horiz. horiz. vert. horiz. horiz. horiz. horiz. horiz. vert. horiz. horiz. horiz.
Arrangements of Wells satel. satel. clust. satel. satel. satel. satel. satel. satel. satel. clust. clust. clust. satel. clust.satel.,
clust.satel.
FPU FPSO SS Jacket FPSO FPSO Tower Gravity Gravity Jackup Jackup Jacket TLP TLPSS &
FPSOSS
TLP &
SSSS
Oil Storage and Offloading vessel pipe. pipe. vessel vessel vessel vessel pipe. vessel pipe. pipe. pipe. pipe. pipe. pipe. pipe. vessel
Number of Wells 2 3 6 4 40 18 18 106 42 4 8 8 10 135 24 46 8
Type of Well horiz. vert. horiz. vert. vert. horiz. horiz. vert. horiz. horiz. horiz. horiz. horiz. vert. horiz. horiz. horiz.
Arrangements of Wells satel. satel. clust. satel. satel. satel. satel. satel. satel. satel. clust. clust. clust. satel. clust. satel. satel.
FPU FPSO FPSO Jacket FPSO FPSO Tower Gravity Jacket Jackup FPSO Jacket TLP TLP FPSO Jacket Gravity SS
Oil Storage and Offloading vessel pipe. pipe. vessel vessel vessel vessel pipe. vessel pipe. pipe. pipe. pipe. pipe. pipe. pipe. vessel
Number of Wells 2 3 6 4 33 7 10 15 8 4 8 8 10 35 15 15 8
Type of Well horiz. vert. horiz. vert. vert. vert. vert. vert. vert. vert. horiz. vert. vert. vert. vert. vert. horiz.
Arrangements of Wells satel. satel. clust. satel. satel. clust. clust. clust. clust. clust. clust. clust. clust. satel. clust. clust. satel.
FPU FPSO FPSO Jacket FPSO Spar SS Jackup Jackup Jackup Jackup Jacket TLP TLP FPSO SS SS SS
Oil Storage and Offloading vessel pipe. pipe. vessel storage vessel vessel pipe. vessel vessel pipe. pipe. pipe. pipe. pipe. pipe. vesselRes
ult o
f Sys
tem
Case
Para
met
ers
of th
e Sy
stem
Resu
lt of
Act
ual
Case
s
Resu
lt of
Fra
nco
(200
3)
9 Copyright 2014 by ASME
Table A.2 (Continuation): Results of the system compared with Actual Cases and Franco (2003).
Alb
aco
ra
Co
gnac
Ose
ber
g
Bal
der
Cap
tain
Fort
ies
Alb
a
An
dre
w
Bri
tan
nia
Trit
on
Tro
ll Ea
st
Wes
t Tr
oll
Ku
ito
Bar
racu
da
Ro
nca
do
r
East
Alb
aco
ra
Area of the Reservoir (m) 235 94 80 80 40 93 56 27 112 61 70 95 290 157 111 215
Depth of the Reservoir (m) 2805 2180 2700 1760 914 2135 1830 2430 4000 3400 1300 1547 1000 1500 1500 1500
Flow per Well (m/d) 300 40 1200 1400 800 1000 700 3000 4000 1900 2000 1000 1000 23000 2000 1400
Water Depth (m) 1900 487 101 125 104 128 138 117 140 90 303 345 384 785 1700 1400
Environmental Conditions Calm Calm Severe Severe Severe Severe Severe Severe Severe Severe Severe Severe Calm Calm Calm Calm
Distance of the Coast (Km) 100 22 115 165 134 170 210 230 210 195 50 80 93 160 125 120
Infra. Yes Yes Yes Yes No No Yes No Yes No Yes Yes No No Yes Yes
Reserves (m) 7E+08 5E+07 1E+11 1E+07 6E+07 4E+08 2E+08 2E+07 2E+07 8E+09 1E+12 3E+08 8E+07 4E+08 1E+09 8E+07
ESI Med. High Med. Low Low Low Low Low Low Low Med. Med. Low Low Low Low
Number of Wells 221 61 30 13 21 104 20 5 14 11 40 71 12 59 57 36
Type of Well horiz. horiz. horiz. horiz. horiz. horiz. horiz. horiz. horiz. vert. horiz. horiz. vert. horiz. horiz. horiz.
Arrangements of Wells satel. clust. clust. satel. satel. clust. clust. clust. clust. satel. satel. satel. satel. satel. satel. satel.
FPUSS &
FPSOJacket Jacket FPSO
Jacket &
FPSOJacket Jacket Jacket Jacket FPSO Gravity SS FPSO FPSO
SS &
FPSOFPSO
Oil Storage and Offloading pipe. pipe. pipe. pipe. storage pipe. vessel pipe. pipe. vessel pipe. pipe. vessel storage pipe. pipe.
Number of Wells 221 61 30 13 21 104 20 5 14 11 40 71 12 59 57 36
Type of Well horiz. horiz. horiz. horiz. horiz. horiz. horiz. horiz. horiz. vert. horiz. horiz. vert. horiz. horiz. horiz.
Arrangements of Wells satel. clust. clust. satel. satel. clust. clust. clust. clust. satel. satel. satel. satel. satel. satel. satel.
FPU FPSO Jacket Jacket FPSO FPSO Jacket Jacket Jacket Jacket FPSO Gravity SS FPSO FPSO FPSO FPSO
Oil Storage and Offloading pipe. pipe. pipe. pipe. storage pipe. vessel pipe. pipe. vessel pipe. pipe. vessel storage pipe. pipe.
Number of Wells 35 15 30 13 21 104 20 5 14 11 35 35 12 59 57 36
Type of Well vert. vert. horiz. horiz. horiz. horiz. horiz. horiz. horiz. vert. vert. vert. vert. horiz. horiz. horiz.
Arrangements of Wells satel. clust. clust. satel. satel. clust. clust. clust. clust. satel. satel. satel. satel. satel. satel. satel.
FPU FPSO SS Jacket FPSO FPSO Jacket Jacket Jacket Jacket FPSO SS Jackup FPSO FPSO FPSO FPSO
Oil Storage and Offloading pipe. pipe. pipe. pipe. storage pipe. vessel pipe. pipe. vessel pipe. pipe. vessel storage pipe. pipe.
CaseP
aram
eter
s o
f th
e Sy
stem
Res
ult
of
Act
ual
Cas
es
Res
ult
of
Fran
co
(20
03
)R
esu
lt o
f Sy
stem
Where: horiz. = horizontal, vert. = vertical, mod. = moderate, med. = medium, clust. = cluster, pipe. = pipeline, Tower = Compliant-Tower.
10 Copyright 2014 by ASME