View
17
Download
0
Tags:
Embed Size (px)
Citation preview
UNDERSTANDING THE RELATIONSHIP BETWEEN PLANNING RELIABILITY
AND SCHEDULE PERFORMANCE
RICARDO OLANOProject Superintendent at Freeport McMoran Americas. Perú.
LUIS F. ALARCÓNProfessor of Civil Engineering, School of Engineeri ng ,Pontificia Universidad Católica de Chile, Santiago, C hile.
CARLOS RAZURIM.Sc. School of Engineering, Pontificia Universidad C atólica de Chile, Santiago, Chile.
17th International Conference of theInternational Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
IGLC
17 T
AIP
EI
IGLC
17 T
AIP
EI
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Introduction
• Is the Earned-Value Method an Enemy of Work Flow? (Yong-Woo and Ballard, 2000)
• What can Learned from Studies on Delay in Construction? (AlSehaimi and Koskela, 2008)
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
3
Project Feature: New HighwayProject Feature: New Highway
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Project Feature: New Highway
• 7.1 Km of highway
• Budget about on the US$ 7 million • Execution schedule of up to 44 weeks.
• The main volumes of work are:– an structure of asphaltic pavement of 7,500
m3 ;
– 2,000 m3 of concrete works;– 494,875 m3 of earthworks, which included
330,627 m3 of rock excavation with explosives.
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
5
Project Feature: Leaching PadProject Feature: Leaching Pad
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Project Feature: Leaching Pad
• 48 million m3 of capacity• budget about US$ 20 million • schedule of construction of up to 60 weeks • The main volumes of work are:
– 1´980,556 m3 of earthworks;– 600,986 m2 of geosynthetic;
– 22,6 Km of HDPE pipe installation;
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Projects Features
• Both projects were developed in Peru, in middle of: – adverse weather conditions, – strikes,
– possibility to find archaeological remains, – strict governmental control for the use of
explosives,
– uncertain soil conditions, and – changing market conditions.
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Project Control Methodology
• Weekly measurement of performance throughout the project execution.
Use of methodologies and tools recommended by:
• The Project Management Institute (PMI): Earned Value Analysis (EVA)
• Lean Construction Institute (LCI): Last Planner System (LPS).
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Earned Value Analysis (EVA)
• SPI: Earned Hours / Planned Hours• Earned Hours = QTYToDate (MHRSBDG / QTYBDG)
Where: – QTYToDate = quantity executed to date. – QTYBDG = quantity budgeted. – MHRSBDG = man-hours budgeted.
Man
Hou
rs
Time
Planned hours (baseline)
earned hours
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Last Planner System (LPS)
• PPC = ∑ nº of completed activities / ∑ nºof planned activities
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Data Collection: Highway Construction
0%
20%
40%
60%
80%
100%
120%
140%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43
Number of Week
PPC
SPI (
%)
PPC
SPI
Figure 1: Highway Construction - Time Evolution of the PPC and SPI
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Data Collection: Leaching Pad
0%
20%
40%
60%
80%
100%
120%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43
Number of Week
PPC
SPI (
%)
PPC
SPI
Figure 2: Leaching Pad - Time Evolution of the PPC and SPI
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Data Analysis: Highway Construction
.434 .113 .529 3.842 .000
.619 .063 9.818 .000
PPC
(Constant)
B Std. Error
UnstandardizedCoefficients
Beta
StandardizedCoefficients
t Sig.
Table 1: Regression Analysis Results
Scatter Plot for SPI and PPC
SPI= 0.434xPPC + 0.619R2 = 0.28
0.20
0.40
0.60
0.80
1.00
1.20
1.40
0.10 0.30 0.50 0.70 0.90PPC
SPI
Figure 3: Highway Construction – Scatter Plot for SPI and PPC
R = 0.529
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Data Analysis: Leaching Pad
.156 .061 .397 2.562 .015
.844 .042 20.332 .000
PPC
(Constant)
B Std. Error
UnstandardizedCoefficients
Beta
StandardizedCoefficients
t Sig.
Scatter Plot for SPI and PPC
SPI = 0.156xPPC + 0.844R2 = 0.158
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
1.05
1.10
0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00PPC
SPI
Figure 3: Leaching Pad – Scatter Plot for SPI and PPC
Table 2: Regression Analysis Results
R = 0.397
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
Relationship Between PPC and Overall Schedule
Project SPI (av)
PPC (av) R Comment
Leaching Pad 0.95 66% 0.397 Project completed on time
Highway 0.84 51% 0.529 Increased time in 16%
Table 2: Relationship between SPI, PPC and R
17th International Conference of the International Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
CONCLUSIONS
• It has been confirmed, that workflow reliability and schedule performance were statistically significantly correlated.
• The methodologies of project management such as the EVA and production management as the LPS can be complemented and managed together to ensure project success.
• Like the findings of Liu and Ballard (2008), the understanding of this relation can help the contracts administrators to demonstrate responsibilities at the time to support a claim for extension of time.
UNDERSTANDING THE RELATIONSHIP BETWEEN PLANNING RELIABILITY
AND SCHEDULE PERFORMANCE: A CASE
STUDY
RICARDO OLANOProject Superintendent at Freeport McMoran Americas. Perú.
LUIS F. ALARCÓNProfessor of Civil Engineering, School of Engineeri ng ,Pontificia Universidad Católica de Chile, Santiago, C hile.
CARLOS RAZURIM.Sc. School of Engineering, Pontificia Universidad C atólica de Chile, Santiago, Chile.
17th International Conference of theInternational Group for Lean ConstructionJuly 15th -17th 2009,Taipei, Taiwan
IGLC
17 T
AIP
EI
IGLC
17 T
AIP
EI