Offshore Valves for FPU

  • Upload
    lazk

  • View
    221

  • Download
    1

Embed Size (px)

Citation preview

  • 8/10/2019 Offshore Valves for FPU

    1/21

    Shtokman Development AG

    Offshore

    Floating Production Unit (FPU): Valves

    Technical meeting with Russian valve manufacturers

    Moscow 24th June 2010

  • 8/10/2019 Offshore Valves for FPU

    2/21

    2

    Summary

    Offshore Project Description

    FPU presentation

    Valves main characteristics

    General design requirements

  • 8/10/2019 Offshore Valves for FPU

    3/21

    3

    650 km650 km

    Shtokman Field Mourmansk : 650 kM

    280 km280 km

  • 8/10/2019 Offshore Valves for FPU

    4/21

    4

    340 water depth reservoir 2 000 m below mud line

    Reserves estimated to 3 700 GSm3 Covers an area of 1 400 km2

    2 subsea templates per drill center 3 Drill centers - 20 wells 16 flow-lines & 14 flexible risers

    Floating Platform:

    Ice resistant & disconnectable floater

    Design capacit y: 71.2 MSM3/d Winterization

    Subsea trunkline to shore 2 x 36 x 550 km Dry 2 phasetransport

    Drilling rigs

    Logistics (vessels & helicopters) Ice and Iceberg Management

  • 8/10/2019 Offshore Valves for FPU

    5/21

    5

    FPU Main Characteristics presentation

    Ice resistant & turret disconectable floater

    Self propulsion (3 aft / 2 bow thrusters)

    Gas treatment Design capacity: 71.2 MSm3

    /d 3 separation & dehydration trains in parallel (3x33%)

    2 condensate treatment trains (2x100%)

    Compression: 85 MW compression duty 160 barg discharge

    Gas and Condensate metering before biphasic export

    Power Generation Normal 3 dual fuel TGs - 3 x 40MWe (n+1)

    Essential 4 diesel generator 4 x 10MWe (n)

    Emergency 1 EDG approx 2MWe

    Cold start 1 Cold start generator approx 120kW

    Fully winterized FPU

    FPU POB capacity (300 / 350 for maintenance period in summer)

  • 8/10/2019 Offshore Valves for FPU

    6/21

    6

    FPU Process presentation

    TEG

    Regen.

    Package

    Gas

    Metering

    To 36"

    trunkline 1

    MEG pretreatment,

    reclamation and

    regeneration

    To Produced

    water treatmentOverboard

    Swi

    vel

    MP Compression

    (2x 75 %)

    Gas dehydration train

    (3 x 33%)

    Gas Compression (4 x 33 %)

    To Users (HP

    and LP)

    Fuel gas system (1 x 100%)

    CONDENSATE TRAIN (2 x 100%)

    Production

    manifold

    (3 x 33%)

    Gas

    Metering

    To 36"

    trunkline 2

    De-sanding

    Inlet

    Separator(3 x 33%)

    EXPORT

    GAS PROCESS

    INFIELD

    RISERS

    INLET

    SEPARATION

  • 8/10/2019 Offshore Valves for FPU

    7/21

    7

    Technological Development

    Shtokman FPU Main technological challenges

    Topsides Winterization)

    Disconnectable through

    MRB/Turret/swivel

    First FPU development

    of its kind paving the

    way for future Arctic

    development

    EER

    Daily production (70MSm3/d)

    Ice-resistant hull design for sea ice

    and iceberg

  • 8/10/2019 Offshore Valves for FPU

    8/21

    8

    FPU CLASSIFICATION

    Dual CLASS Russian Maritime Register of Shipping / BV

    Class notation as follows:

    I HULL MACH

    Offshore Service Barge Production

    Unrestricted navigation - Shtokman Field

    AUTO POSA IG VeriSTAR-HULL HEL

    ARC DYNAPOS ALM LSA COLD STI

    COMF

  • 8/10/2019 Offshore Valves for FPU

    9/21

    9

    FPU Layout Design Principles (1/2) Topsides arrangement is optimized considering Shtokman challenges including:

    Safety and Environmental requirements

    Cold weather, harsh sea and remote location conditions

    Huge gas inventory onboard50 years life time requiring stringent IMR

    Layout is strictly organized in order to keep the hull as a safe space

    Segregate risks from topsides process to hull

    Great care on hull penetrations for interfaces between hull and topsidesAchieve adequate safe haven in hull

    Marine systems are able to run independently from process topsides (i.e. as a

    ship)

    And .FPU Hull space has been used to locate some utilities equipment/systems

    FPU Hull deck has been used in order to optimize layout and limit

    winterization impacts.

  • 8/10/2019 Offshore Valves for FPU

    10/21

    10

    FPU Layout Design Principles (2/2)

    Process functionsLQ & Utilities functions

    Storage of

    MEG, Diesel, slop etc

    & utili ties equipment

    Storage of

    Water etc

    & util ities equipment

    No gas

    Below main

    deck

    Safer

    Safer

    (& warmer)

    Low Pressureand Liquid

    High PressureGas

    Flare stack &KO drums

    TR

  • 8/10/2019 Offshore Valves for FPU

    11/21

    11

    FPU Living Quarter Design Principles

    The Temporary refuge is a key element of EER Strategy and FPU Safety

    Concept.

    The TR is a protected and independent cocoon inside the LQ designed

    for:

    Direct connection with the Safety Escape tunnel

    Withstanding all major accidental hazards

    Increasing the survival period on the FPUGetting most of the Evacuation Equipment (Primary/Secondary)

    immediately adjacent to the Living Quarters

    Allowing personnel to stay onboard during/after an accident until the

    last moment (i.e. no capsizing of Hull)Allowing personnel to wait safely for best moment to evacuate.

    TR is located at aft to benefit from the Ice-Free Channel created by the

    FPU.

    With the TR, the FPU Hull is, at first, our Life Buoy

  • 8/10/2019 Offshore Valves for FPU

    12/21

    12

    Valves main characteristics

    2 to XX

    1 to 24

    2 to 42

    2 to 42

    Size

    365

    360

    3000

    750

    Topsides

    approx Qty

    300# to 2500#75Relief valves

    300# to 2500#90Automatic and Manual

    control valves

    150# to 2500#Manual On/Off Valves

    150# to 2500#145Actuated On/Off Valves

    RatingHull approx

    Qty

    Categories

    All valves will be supplied by main contractor or packages vendors fromapproved vendor list

    Main ON/OFF valves types used:

    Ball valves for practically all process applications

    Gate valves for utilities

    Butterfly valves for utilities

    Special Butterfly Valves (2 or 3 off sets) for process applications

  • 8/10/2019 Offshore Valves for FPU

    13/21

    13

    Valves main characteristics

    Main valves materials used:

    Low Temperature Carbon Steel (LTCS)

    Stainless Steel (SS)

    Duplex, Super Duplex

    LTCS + Inconel 625 WO on all wetted areas

    For critical functions: M/M seating, double sealing barriers (dynamic & static),fire safe, antistatic, interchangeability;

    Due to tight layout onboard Mono-block Double Block & Bleed (DBB) valvesare considered, mostly in Turret;

    To address long design life of the plant (50 Years) following featuresobserved:

    High level of integrity, reliability and availability;

    Enhanced design and robust materials selection;

    Proof sealing systems;

    Enhanced FAT;

  • 8/10/2019 Offshore Valves for FPU

    14/21

    14

    Mono-block DB&B Valves typical design

  • 8/10/2019 Offshore Valves for FPU

    15/21

    15

    Valves main characteristics

    Typical application for

    monobloc DBB inside

    Turret area (QCDC

    System)

  • 8/10/2019 Offshore Valves for FPU

    16/21

    16

    Valves main characteristics: side entry, forged

    body, flange ends

  • 8/10/2019 Offshore Valves for FPU

    17/21

    17

    Valves main characteristics: full welded body

  • 8/10/2019 Offshore Valves for FPU

    18/21

    18

    Valves main characteristics; side entry, forged

    body, hub ends

  • 8/10/2019 Offshore Valves for FPU

    19/21

    19

    Ball valve with DP seat design

  • 8/10/2019 Offshore Valves for FPU

    20/21

    20

    Main general requirements

    All valves to be design, fabrication and testing in full compliance with

    applicable SDAG bases of design specifications (GS-EP-PVV-112 &

    142, GS-EP-INS-101 & 137 and other project specifications);

    For Marine applications, Dual class requirements (BV & RS) shall be

    applied;

    Interchangeability;

    Applicable Codes & Standards:

    ASME B 31.3, ASME B16.34,

    API 6D, API 598, API 6FA/607

    BS 6755xx

  • 8/10/2019 Offshore Valves for FPU

    21/21

    21

    THANK YOU