Upload
bubblyblu2
View
221
Download
2
Embed Size (px)
Citation preview
8/9/2019 Offshore Load Out Day 2
1/103
•1| PAGE
www.bimv.com
LOAD OUT TRAINING - DAY 2:OFFSHORE MARITIME RISK ANALYSIS
Capt. Noël Haegeman
Kuala Lumpur, June 2011
8/9/2019 Offshore Load Out Day 2
2/103
•2| PAGE
www.bimv.com
8/9/2019 Offshore Load Out Day 2
3/103
•3| PAGE
www.bimv.com
MOTIONS TO ACCELERATIONS
MOVEMENTS ON 3 AXES
8/9/2019 Offshore Load Out Day 2
4/103
•4| PAGE
www.bimv.com
MOVEMENTS OF A FLOATING UNIT
8/9/2019 Offshore Load Out Day 2
5/103
•5| PAGE
www.bimv.com
PITCHING
PITCHING/ LONGITUDENAL FORCES ARE
EQUAL TO THE TOTAL WEIGHT OF THE LOAD
8/9/2019 Offshore Load Out Day 2
6/103
•6| PAGE
www.bimv.com
ROLLING
LATERAL FORCES ARE 50% OF THE TOTAL
WEIGHT OF THE LOAD
8/9/2019 Offshore Load Out Day 2
7/103
•7| PAGE
www.bimv.com
SURGE
BACKWARDS FORCES EQUAL AS LATERAL O,5
TIMES THE WEIGHT
8/9/2019 Offshore Load Out Day 2
8/103
•8| PAGE
www.bimv.com
HEAVE
HEAVING CAN REPRESENT 4 TIMES THE
LOAD WEIGHT
8/9/2019 Offshore Load Out Day 2
9/103
•9| PAGE
www.bimv.com
ACCELARATIONS & STABILITY
8/9/2019 Offshore Load Out Day 2
10/103
•10| PAGE
www.bimv.com
FORCES/MOMENTS & HEIGHT
8/9/2019 Offshore Load Out Day 2
11/103
8/9/2019 Offshore Load Out Day 2
12/103
•12| PAGE
www.bimv.com
Static & Dynamic friction
Static/dynamic forces
8/9/2019 Offshore Load Out Day 2
13/103
•13| PAGE
www.bimv.com
Static Friction coefficient
The static friction coefficient (μ) between two solid surfacesis defined as the ratio of the tangential force (F) required toproduce sliding divided by the normal force between thesurfaces (N)
μ = F /N For a horizontal surface the horizontal force (F) to move a
solid resting on a flat surface
F= μ x mass of solid x g.
If a body rests on an incline plane the body is prevented from
sliding down because of the frictional resistance. If the angleof the plane is increased there will be an angle at which thebody begins to slide down the plane. This is the angle ofrepose and the tangent of this angle is the same as thecoefficient of friction.
8/9/2019 Offshore Load Out Day 2
14/103
•14| PAGE
www.bimv.com
Static Friction coefficient
Material 2Coefficient Of FrictionTest
methodDRYGreasyStaticSlidingStaticSlidingAluminumAluminum1,05-
1,351,40,3 AluminumMild Steel0,610,47 Brake MaterialCast
Iron0,4 Brake MaterialCast Iron (Wet)0,2 BrassCast
Iron 0,3 BrickWood0,6 BronzeCastIron 0,22 BronzeSteel 0,16 Cadmium Cadmium0,5 0,05 Cadmium Mild
Steel 0,46 Cast IronCast Iron1,10,15 0,07 Cast
IronOak 0,49 0,075 ChromiumChromium0,41 0,34 CopperCast
Iron1,050,29 CopperCopper1,0 0,08 CopperMild
Steel0,530,36 0,18 CopperSteel 0,8 SPOFCopperSteel (304
stainless)0,230,21 FOFCopper-Lead AlloySteel0,22 -DiamondDiamond0,1 0,05 - 0,1 DiamondMetal0,1 -0,15 0,1 GlassGlass0,9
- 1,00,40,1 - 0,60,09-0,12 GlassMetal0,5 - 0,7 0,2
8/9/2019 Offshore Load Out Day 2
15/103
•15| PAGE
www.bimv.com
Static Friction coefficient
0,3 GlassNickel0,780,56 GraphiteGraphite0,1 0,1 GraphiteSteel0,1 0,1 Gr
aphite (In vacuum)Graphite (In vacuum)0,5 - 0,8 Hard CarbonHard
Carbon0,16 0,12 - 0,14 Hard CarbonSteel0,14 0,11 - 0,14 IronIron1,0 0,15 -
0,2 LeadCast Iron 0,43 LeadSteel 1,4 SPOFLeatherWood0,3 -
0,4 LeatherMetal(Clean)0,6 0,2 LeatherMetal(Wet)0,4 Leather Oak(Parallel grain)0,610,52 MagnesiumMagnesium0,6 0,08 NickelNickel0,7-
1,10,530,280,12 NickelMild Steel 0,64; 0,178 NylonNylon0,15 - 0,25 Oak
Oak (parallel grain)0,620,48 Oak Oak (cross
grain)0,540,32 0,072 PlatinumPlatinum1,2 0,25 PlexiglasPlexiglas0,8 0,8 Pl
exiglasSteel0,4 - 0,5 0,4 -
0,5 PolystyrenePolystyrene0,5 0,5 PolystyreneSteel0,3-0,35 0,3-0,35 PolytheneSteel0,2 0,2
8/9/2019 Offshore Load Out Day 2
16/103
•16| PAGE
www.bimv.com
Static Friction coefficient
RubberAsphalt (Dry) 0,5-0,8 RubberAsphalt (Wet) 0,25-0,75 RubberConcrete
(Dry) 0,6-0,85 RubberConcrete (Wet) 0,45-
0,75 SaphireSaphire0,2 0,2 SilverSilver1,4 0,55 Sintered BronzeSteel-
0,13 SolidsRubber1,0 - 4,0 -- Steel Aluminium Bros0,45 Steel
Brass0,350,19 Steel(Mild) Brass0,510,44 Steel (Mild)Cast Iron 0,230,1830,133 Steel
Cast Iron0,4 0,21 Steel Copper Lead Alloy0,22 0,160,145 Steel (Hard)Graphite
0,21 0,09 Steel Graphite0,1 0,1 Steel (Mild) Lead0,950,95 0,50,3 Steel (Mild)Phos.
Bros 0,34 0,173 Steel Phos
Bros0,35 Steel(Hard)Polythened0,2 0,2 Steel(Hard)Polystyrene0,3-0,35 0,3-
0,35 Steel (Mild)Steel (Mild)0,740,57 0,09-0,19 Steel (Mild)Steel (Mild)-
0,62 FORSteel(Hard)Steel (Hard)0,780,42 0,05 -0,110,029-,12 SteelZinc (Plated on
steel)0,50,45-- TeflonSteel0,04 0,040,04 TeflonTeflon0,04 0,040,04 TinCast
8/9/2019 Offshore Load Out Day 2
17/103
•17| PAGE
www.bimv.com
Static Friction coefficient
Iron ,32 Titanium Alloy Ti-6Al-4V(Grade 5)Aluminium Alloy 6061-
T60,410,38 FOFTitanium Alloy Ti-6Al-4V(Grade 5)Titanium Alloy Ti-6Al-4V(Grade
5)0,360,30 FOFTitanium Alloy Ti-6Al-4V(Grade 5)Bronze0,360,27 FOFTungsten
CarbideTungsten Carbide0,2-0,25 0,12 Tungsten CarbideSteel0,4 - 0,6 0,08 -
0,2 Tungsten CarbideCopper0,35 Tungsten
CarbideIron0,8 WoodWood(clean)0,25 - 0,5 WoodWood
(Wet)0,2 WoodMetals(Clean)0,2-0,6 WoodMetals
(Wet)0,2 WoodBrick0,6 WoodConcrete0,62 ZincZinc0,6 0,04 ZincCast
Iron0,850,21 Material 1Material 2Coefficient Of FrictionTest
methodDRYLUBRICATEDStaticSlidingStaticSlidingFOR = Flat against rotating Cylinder,
FOF = Flat against flat, POF = Pin on flat, IS = inclined surface,SPOF Spherical end pin
on flat.
8/9/2019 Offshore Load Out Day 2
18/103
•18| PAGE
www.bimv.com
SPECIFIC WEIGHTS - KG/CU.M
BARITE 2883
BENTONITE 593
CEMENT PL 1506
CEMENT M 2162
GARBAGE AV 481
ICE 593
LEAD 11389
MUD PACKED 1908
MUD FLUID 1730
NITROGEN 1,26
PETROL 881
CAOUTCHOUC 945
RUBBER MAN. 1522
WATER FRESH 1000
SEAWATER 1002
8/9/2019 Offshore Load Out Day 2
19/103
•19| PAGE
www.bimv.com
Deck cargo securing principles
For deck cargo chain or wire lashings are to bepreferred to web lashings due to less elasticity.Connecting elements and tightening devices
should be used in the correct way.Consideration should be given to any reductionof the strength of the lashings throughcorrosion, fatigue or mechanical deterioration.
It is necessary to apply transverse lashings onthe cargo and to timber uprights alongside theblocks of cargo.
8/9/2019 Offshore Load Out Day 2
20/103
•20| PAGE
www.bimv.com
Deck cargo securing principles
Heavy single pieces of cargo on deck should preferablybe stowed near the centre of the ship and in the fore-and-aft direction. Suitable beams of timber or steel ofadequate strength should be used to transfer the weightof the item onto the ship’s structure. Principles forlashing and securing of such cargo securing calculationsare essential in order to find the correct number andstrength of suggested lashings and shorings in the
arrangement. Cargo on deck can never be completelyprotected from sea water, but cargo details easilydamaged by salt can, to some extent, be protected bygrease oil and covering by tarpaulins.
8/9/2019 Offshore Load Out Day 2
21/103
•21| PAGE
www.bimv.com
S.W.L B.L
For securing use the according
ropes/wires/chains/textile slings in order to
compensate the max load as calculated forthe total weight and friction force.
S.W.L = safe working load
B.L = breaking load
8/9/2019 Offshore Load Out Day 2
22/103
8/9/2019 Offshore Load Out Day 2
23/103
•23| PAGE
www.bimv.com
USE OF BULLDOG GRIPS
DIAMETRE
CABLE mm
# BULLDOG
GRIPS
5 -12 3
13-16 4
17-25 5
26-35 6
36-50 7
8/9/2019 Offshore Load Out Day 2
24/103
•24| PAGE
www.bimv.com
Distance Bulldog grips (B.D)
MAX DISTANCE BETWEEN 2 B.D’S
Dist = max 3 x diam BD ( between bolds)
Wrong way ………
8/9/2019 Offshore Load Out Day 2
25/103
•25| PAGE
www.bimv.com
Colour code textile swl
8/9/2019 Offshore Load Out Day 2
26/103
•26| PAGE
www.bimv.com
BE AWARE OF DANGERS
8/9/2019 Offshore Load Out Day 2
27/103
•27| PAGE
www.bimv.com
DANGEROUS CARGO IMDG
8/9/2019 Offshore Load Out Day 2
28/103
8/9/2019 Offshore Load Out Day 2
29/103
•29| PAGE
www.bimv.com
IMDG CLASSIFICATION
1 EXPLOSIVES
2 GASES (compress.liquified,pressured) inflamm.
3 INFLAMMABLE LIQUIDS
4 INFLAMMABLE SOLIDS
5 OXIDIZING AGENTS & ORGANIC PEROXIDES
6 TOXICS
7 RADIOACTIVE MATERIALS 8 CORROSIVE & INFECTIOUS SUBSTANCES
9 MISCELLANEOUS
8/9/2019 Offshore Load Out Day 2
30/103
•30| PAGE
www.bimv.com
JACK-UP barges
Rowan Gorilla 2
8/9/2019 Offshore Load Out Day 2
31/103
•31| PAGE
www.bimv.com
8/9/2019 Offshore Load Out Day 2
32/103
•32| PAGE
www.bimv.com
8/9/2019 Offshore Load Out Day 2
33/103
•33| PAGE
www.bimv.com
Jack up barge under transit
8/9/2019 Offshore Load Out Day 2
34/103
•34| PAGE
www.bimv.com
JACK-UP barges
When airborne, the weight is taken by
the leg feet:
8/9/2019 Offshore Load Out Day 2
35/103
•35| PAGE
www.bimv.com
JACK-UP barges
When CG is not above CB, a moment is
created
W
R
W
R R R
8/9/2019 Offshore Load Out Day 2
36/103
•36| PAGE
www.bimv.com
JACK-UP barges
Bending moments i.w.o. leg guides !!
8/9/2019 Offshore Load Out Day 2
37/103
•37| PAGE
www.bimv.com
Pt.4: Jack-ups -inclination calc.&measures
Calculation and adjustments to be made PRIOR to jackingdown and getting afloat. Draft permitted maximum load line draft
GM & KG within prescribed limits
• depends on type of passage taken (Ocean Moves/InFieldMoves)
• after adjustment and removal of both liquid and dry cargo
• with legs fully elevated
• content of spud cans (leg footings can sometimes be pumpedout)
if excessive trim/list (>0,25º) exists during lowering,bending moments are imposed on the legs i.w.o. theJackhouses and leg guides, potential damage !
8/9/2019 Offshore Load Out Day 2
38/103
•38| PAGE
www.bimv.com
JACK-UP barges
Also bending moments under motions afloat
8/9/2019 Offshore Load Out Day 2
39/103
•39| PAGE
www.bimv.com
JACK UP BARGE SPUD CANS
Spud cans can “sink”into soft seabed,
causing retractionproblems.
8/9/2019 Offshore Load Out Day 2
40/103
•40| PAGE
www.bimv.com
PUNCH TROUGH
Jack-up under salvage after punch through
8/9/2019 Offshore Load Out Day 2
41/103
•41| PAGE
www.bimv.com
PUNCH TROUGH DANGER
Punch through is an imminent danger - therefore an overloadtest is required by means of: preload tanks -- hydraulic jacking (e.g. PB5,
Energy Explorer) much faster !
8/9/2019 Offshore Load Out Day 2
42/103
•42| PAGE
www.bimv.com
BEFORE JACKING DOWN OR UP
From Operations Manual, procedures to work out weight shift tocorrect trim/list, basic steps:
1) distribute fuel, potable water and drilling water uniformlyand minimise free surface
2) distribute bulk chemical, cement, Baritet etc. uniformlyabout the centre line fore-aft amidships
3) remove all excess deck cargo and distribute tubulars, drillpipe, collars, etc. to box stows
4) unless you are very familiar with the vessel, calculate afloatcondition without any trimming ballast and from thiscalculation derive a trimming/heeling moment and lever.
5) with results of 4), choose tanks to (partly) fill in order tocounteract the moments derived from 4)
8/9/2019 Offshore Load Out Day 2
43/103
•43| PAGE
www.bimv.com
AFLOAT ON EVEN KEEL
Jack-ups in the afloat condition adhere to all the
normal stability regulations governing any other
floating vessel - Intact & Damage Stability.
despite apparently top heavy appearance
elevated legs, quite adequate intact stability.
but due to elevated legs, extremely vulnerable
to damage caused by excessive wave/swellinduced motion. (bending moments, cracking,
some losses in history)
8/9/2019 Offshore Load Out Day 2
44/103
•44| PAGE
www.bimv.com
Cont. jacking even keel
Operations Manual should contain appropriate data on how to calculate the afloat conditions
sample calculations of the vessel afloat
afloat condition calculation sheet
when going afloat, following parameters should be met: list/trim must be nearly zero
at the Tip of Can (TOC) position (legs raised to transitheight), draft should be lower than permitted maximumload line draft
afloat barge must have allowable VCG and KM bothlongitudinally and transversely.
8/9/2019 Offshore Load Out Day 2
45/103
•45| PAGE
www.bimv.com
Jack-up stability jack down example
A jack-up is about to go afloat;
From the daily stability calculations we read:
• Centre of Gravity: LCG = 24,6m TCG = -0,15m VCG = 8,0m
• Total weight: W = 5000 ton
From the hydrostatic tables we read:• For a displacement = total weight:
o mean draft: d = 5,2m
o Centre of buoyancy: LCB = 25,0m TCB = 0,0m VCB = 2,6m
o Metacentre position: KMT = 12,2m KML = 23,7m
o Moment to change heel/trim: MCH1degr = 1600 tonm/degr
o MCT1degr = 4100 tonm/degr
8/9/2019 Offshore Load Out Day 2
46/103
•46| PAGE
www.bimv.com
Jack-up stability jack down example
From the Operation Manual we read the stability limits:
• Centre of gravity envelope:
o Operation: TCG {-1,5m ; +1,5m} LCG {23,0m ; 27,0m}
o Survival: TCG {-0,5m ; +0,5m} LCG {24,5m ; 25,5m}
• Plimsol mark (load line mark) at 5,5m above keel
• Minimum Metacentric height: GMmin = 0,7m
Is it OK to jack down in this condition ?
What list and trim do you expect in the afloat condition ?
8/9/2019 Offshore Load Out Day 2
47/103
•47| PAGE
www.bimv.com
Cont. example
Summary of given data:
o LCG = 24,6m TCG = -0,15m VCG = 8,0m
o W = D = 5000 ton
o mean draft: d = 5,2m
o Centre of buoyancy: LCB = 25,0m TCB = 0,0m VCB = 2,6mo Metacentre position: KMT = 12,2m KML = 23,7m
o Moment to change heel/trim: MCH1degr = 1600 tonm/degr
o MCT1degr = 4100 tonm/degr
8/9/2019 Offshore Load Out Day 2
48/103
•48| PAGE
www.bimv.com
Cont. example
Summary of given data:
stability limits:
• CG inside Operation envelope : TCG = -0,15m inside {-1,5m ; +1,5m}, OKLCG = 24,6m inside {23,0m ;
27,0m}, OK
• CG not inside Survival envelope: TCG = -0,15m inside {-0,5m ; +0,5m}, OKLCG = 24,6m inside {24,5m ;
25,5m}, OK
• Draft 5,2m is below Plimsol mark at 5,5m, OK
• GMT = KMT-KG = 12,2m – 8,0m = 4,2m, this is greater than GMmin = 0,7m,OK
• GML = KML-KG = 23,7m – 8,0m = 15,7m, this is greater than GMmin = 0,7m,OK
Conclusion:
It is safe to jack-down according to Operation Manual
8/9/2019 Offshore Load Out Day 2
49/103
•49| PAGE
www.bimv.com
Cont.example
Summary of given data:
o LCG = 24,6m TCG = -0,15m VCG = 8,0m
o W = D = 5000 ton
o mean draft: d = 5,2m
o Centre of buoyancy: LCB = 25,0m TCB = 0,0m VCB = 2,6mo Metacentre position: KMT = 12,2m KML = 23,7m
o Moment to change heel/trim: MCH1degr = 1600 tonm/degr
o MCT1degr = 4100 tonm/degr
8/9/2019 Offshore Load Out Day 2
50/103
•50| PAGE
www.bimv.com
Cont.example
Summary of given data:
Heel:
• Weight: 5000 ton ; arm = difference TCB-TCG = -0,15m
• Heeling moment = -750 tonm
• Angle of heel = Heeling moment/MCH1degr = 750/1600 = 0,47 degr downto PS
Trim:
• Weight: 5000 ton ; arm = difference LCB-LCG = 0,4m
• Trimming moment = 2000 tonm
• Angle of heel = Trimming moment/MCT1degr = 2000 / 4100 = 0,49 degr
down to aft
8/9/2019 Offshore Load Out Day 2
51/103
•51| PAGE
www.bimv.com
BENDING MOMENTS ANS SHEAR FORCES
8/9/2019 Offshore Load Out Day 2
52/103
8/9/2019 Offshore Load Out Day 2
53/103
•53| PAGE
www.bimv.com
Structural Integrity
Primary
Secondary
There is a maximum
deck load (ton/m²)prescribed, to be
obeyed to !!
‘point’-loads to be
deviated to thestiffeners
8/9/2019 Offshore Load Out Day 2
54/103
8/9/2019 Offshore Load Out Day 2
55/103
•55| PAGE
www.bimv.com
Structural Integrity - imperfections
Structural imperfection - MACRO versus MICRO
>>
stress concentration
>>
stress concentration
8/9/2019 Offshore Load Out Day 2
56/103
•56| PAGE
www.bimv.com
Structural Integrity - micro imperfections
Typical micro failure is undercut:
More welding defects:
slag inclusions lack of fusion
incomplete penetration
8/9/2019 Offshore Load Out Day 2
57/103
•57| PAGE
www.bimv.com
Structural Integrity - micro imperfections
A connection of structures is to have at least thestrength of the members connected connections e.g. welding, riveting, bolting, …
Disadvantage of welding monolite structure
Heat Affected Zone (HAZ) results in brittlestructure (less elasticity, more liable for cracking)
8/9/2019 Offshore Load Out Day 2
58/103
•58| PAGE
www.bimv.com
Structural Integrity - collapse
There are mainly two (2) types of structural collapse: BUCKLING
• occurs mostly
• under pressure
• condition
CRACKING• occurs mostly
• under tension
• condition i.w.o.• stress
• concentrations
Kw.Kg.Kw.
Kg.K
w.
8/9/2019 Offshore Load Out Day 2
59/103
•59| PAGE
www.bimv.com
Cracks
How do they look like ?
8/9/2019 Offshore Load Out Day 2
60/103
•60| PAGE
www.bimv.com
Structural Integrity - stress concentrations
cut-out
doubler
misalignment
Deck repair/maintenance and sea-fastening of deck
equipment shows often poor workmanship:
8/9/2019 Offshore Load Out Day 2
61/103
•61| PAGE
www.bimv.com
Structural Integrity - elasticity
Elasticity creates
deflections
moments shear forces
8/9/2019 Offshore Load Out Day 2
62/103
8/9/2019 Offshore Load Out Day 2
63/103
•63| PAGE
www.bimv.com
Structural Integrity - problems
Problem 1:
steel is elastic, loads create deformations
deformation creates local moments in the structure
SOLUTION: stiffening of the structure
Problem 2: highly stiff structures “attract” stresses and concentrate them
increased risk of micro failures
Problem 3:
when loads become dynamic, the fatigue phenomenon resultsin a decreased resistance against loads
Problem 4:
corrosion is causing diminution of the dimensions and capabilityof acceptance
8/9/2019 Offshore Load Out Day 2
64/103
8/9/2019 Offshore Load Out Day 2
65/103
•65| PAGE
www.bimv.com
SHEAR FORCES & BENDING MOMENTS
8/9/2019 Offshore Load Out Day 2
66/103
•66| PAGE
www.bimv.com
LOADS
TENSILE OR COMPRESSIVE LOADS
8/9/2019 Offshore Load Out Day 2
67/103
•67| PAGE
www.bimv.com
SHEARING STRESSES
VERTICAL SHEAR
8/9/2019 Offshore Load Out Day 2
68/103
•68| PAGE
www.bimv.com
COMPLEMENTARY STRESS
By direct load created in material & in
equilibrium as strenght can resist load
Stress (f) = Load (W) / Area (A)
8/9/2019 Offshore Load Out Day 2
69/103
70| PAGE
8/9/2019 Offshore Load Out Day 2
70/103
•70| PAGE
www.bimv.com
SHEAR Force & Bending moments
diagrams BM = O at the ends & max in the middle
•71| PAGE
8/9/2019 Offshore Load Out Day 2
71/103
•71| PAGE
www.bimv.com
Forces on Cross Section Areas
On Cross Beams linear force up to the max
•72| PAGE
8/9/2019 Offshore Load Out Day 2
72/103
•72| PAGE
www.bimv.com
Construction supported on edges
Construction vertical supported
•73| PAGE
8/9/2019 Offshore Load Out Day 2
73/103
•73| PAGE
www.bimv.com
Longitudenal Stresses in still water
Weight & Buoyancy reactions
8/9/2019 Offshore Load Out Day 2
74/103
•75| PAGE
8/9/2019 Offshore Load Out Day 2
75/103
75| PAGE
www.bimv.com
Cont Stresses in waves
Hogging & sagging
•76| PAGE
8/9/2019 Offshore Load Out Day 2
76/103
76| PAGE
www.bimv.com
Cont Stresses in waves
Consider hogging a sagging as point stress &
ballast to avoid fatigue of construction
•77| PAGE
8/9/2019 Offshore Load Out Day 2
77/103
|
www.bimv.com
WEIGHT DIAGRAM
Counteracting weight stress
•78| PAGE
8/9/2019 Offshore Load Out Day 2
78/103
|
www.bimv.com
Stresses on additional immersion
Water Line ( WL) Additional sectional stress by immersion
Bonjean Curve
•79| PAGE
8/9/2019 Offshore Load Out Day 2
79/103
www.bimv.com
BUOYANCY CURVES
By Bonjean Curve the buoyancy output for
each draft an wave impact .
•80| PAGE
8/9/2019 Offshore Load Out Day 2
80/103
www.bimv.com
Sectional Bending moments & Shear
Force diagram
8/9/2019 Offshore Load Out Day 2
81/103
8/9/2019 Offshore Load Out Day 2
82/103
•83| PAGE
8/9/2019 Offshore Load Out Day 2
83/103
www.bimv.com
TIDAL TIME SCHEDULE
Air pressured B.C according boarding & tidal
schedule
•84| PAGE
8/9/2019 Offshore Load Out Day 2
84/103
www.bimv.com
MARINE LOAD OUT
Preparing downballasting to board jack up
•85| PAGE
8/9/2019 Offshore Load Out Day 2
85/103
www.bimv.com
POSITIONING OPEN WATER
CURRENT & METEO INFLUENCE
•86| PAGE
8/9/2019 Offshore Load Out Day 2
86/103
www.bimv.com
METEROLOGICAL CONDITIONS
Beaufort scale max 3 bft / no tidal or stream currents
Beaufort Force 3
Gentle breeze
Wind speed (knots): 7 - 10 Wave height (feet): 2 - 3
Sea state: Large wavelets; crests begin to break;
scattered whitecaps
•87| PAGE
8/9/2019 Offshore Load Out Day 2
87/103
www.bimv.com
CRITICAL STABILITY POINT
Lost of bouyancy & max weight stresses
8/9/2019 Offshore Load Out Day 2
88/103
•89| PAGE
8/9/2019 Offshore Load Out Day 2
89/103
www.bimv.com
8/9/2019 Offshore Load Out Day 2
90/103
•91| PAGE
8/9/2019 Offshore Load Out Day 2
91/103
www.bimv.com
•92| PAGE
8/9/2019 Offshore Load Out Day 2
92/103
www.bimv.com
HYDRAULIC SKIDDING DEVICES
•93| PAGE
8/9/2019 Offshore Load Out Day 2
93/103
www.bimv.com
Hydraulic Skidding
•94| PAGE
8/9/2019 Offshore Load Out Day 2
94/103
www.bimv.com
VERTICAL JACKS
600 T VERTICAL JACKS
•95| PAGE
8/9/2019 Offshore Load Out Day 2
95/103
www.bimv.com
17800 T JACKET
•96| PAGE
8/9/2019 Offshore Load Out Day 2
96/103
www.bimv.com
•97| PAGE
8/9/2019 Offshore Load Out Day 2
97/103
www.bimv.com
USE OF SKID BEAMS
Number of skidbeams depending on weight
& moments
•98| PAGE
8/9/2019 Offshore Load Out Day 2
98/103
www.bimv.com
SKIDDED TLP TRANSPORT
8/9/2019 Offshore Load Out Day 2
99/103
8/9/2019 Offshore Load Out Day 2
100/103
•101| PAGE
8/9/2019 Offshore Load Out Day 2
101/103
www.bimv.com
SKIDDING TO BARGE
•102| PAGE
8/9/2019 Offshore Load Out Day 2
102/103
www.bimv.com
LOAD OUT BY GANTRY
•103| PAGE
8/9/2019 Offshore Load Out Day 2
103/103
Thank you for your attention and have a nice
evening!