WEEKLY PRESENTATIONMr.WilsonMr.Wilson Contreras.SITEContreras.SITE MANAGERMANAGER
OAG PROJECT.OAG PROJECT.
OFFSHORE ASSOCIATED GASES PACKAGE 1
DAS ISLAND FACILITIES
INDEXINDEX1.1. ACTIVITIES OF THE WEEKACTIVITIES OF THE WEEK
2.2. MANPOWER STATUSMANPOWER STATUS
3.3. CONCRETE STATUS (PIE / LINE GRAPH)CONCRETE STATUS (PIE / LINE GRAPH)
4.4. WEEKLY PROGRESSIVE QUANTITY REPORT WEEKLY PROGRESSIVE QUANTITY REPORT (CONCRETE)(CONCRETE)
5.5. WEEKLY CONCRETE QUANTITIES WEEKLY CONCRETE QUANTITIES FORECASTFORECAST
6.6. MONTHLY MANPOWER FORECASTMONTHLY MANPOWER FORECAST
7.7. STATUS OF STATUS OF PARPAR’’ss & & PAUPAU’’ss FOUNDATIONFOUNDATION
8.8. WEEKLY HSE STATISTICSWEEKLY HSE STATISTICS
9.9. HSE PLANHSE PLAN
10.10. HSE NEAR MISS TRENDHSE NEAR MISS TREND
11.11. WEEKLY EXECUTIVE SUMMARYWEEKLY EXECUTIVE SUMMARY
12.12. AREA OF CONCERNAREA OF CONCERN
13.13. BLACK SOILBLACK SOIL
14.14. GEND IMPELLERSGEND IMPELLERS
ACTIVITIES OF THE WEEKPODIUM AREA:
Retaining Wall / Pipe Supports Valve Pits / VSD BuildingBooster Compressors (26-K-0401 & 26-K-0451) and Pipe Rack # PAR 101 to 106 & PAR 108 to 109Booster Compressor: 26-K-0401 Booster Compressor: 26-K-0451Pipe Rack:Cable Trench (Podium/ Interconnecting / Offsite)ZAKUM / UMM SHAIF/ LNG MANIFOLD AREA :Reclamation Area /ADMA Flare Area: Road A1 – Bridge B – 7: CulvertAmenities Building
PROCESS AREA:
Outstation Building # 14Substation Building # 11Feed Gas Compressor (I-K-401)Feed Gas Compressor (I-K-451) Train I & Train II: Pipe Rack Train 1 & 2:Manholes / Catch basin / Valve PitsCable Trench / Duct Banks (Process/ Common Facilities)
ACTIVITIES OF THE WEEK
COMMON FACILITIES:
PIPING:Process AreaInterconnecting & Offsite Area:Podium Area:Fabrication Yard
TARGET Yard:
Temporary Office & Lay down Area:Cathodic Protection for RC Foundations
MANPOWER STATUS AS OF 11.07.2008
S. No. Company Manpower
Manhours(this week)
Cum. Manhours
1. MEPI 36 2,095 85,520
2. Target 804 52,490 1,676,438
3. Descon 271 15,775 90,280
Total on Site 1,111 70,360 1,852,238
CONCRETE CASTING
Total Poured 28.78%
Progress this week 2.39%
Remaining 68.83%
Total Poured Progress this week Remaining
Total8086.18 m3
Total671.50 m3
Total Concrete Poured 8757.68 m3
Total19335.32 m3
98.7
3
100
31.1
7
28.7
8
17.2
4
18.3
4
20.0
2
21.6
2
22.1
1
23.6
8
24.1
0
24.3
4
26.0
8
36.8
0
47.5
0
58.1
5
69.5
4
83.7
8
95.1
7
0
10
20
30
40
50
60
70
80
90
100
18 19 20 21 22 23 24 25 26 27 28 31 36 40 44 49 53 58 62
Actual Scheduled
CONCRETE CHART BASELINE SCHEDULEPE
RC
ENTA
GE
WEEK NUMBER13/06/08 20/06/08
6771.43 m3
6837.43 m3
27/06/08
7327.68 m3
04/07/08
8086.18 m3
8757.68 m3
11/07/08
WEEKLY PROGRESS QUANTITY REPORT(CONCRETE)
Discipline : Civil/ Structural Date : July 04, 2008
Progress in Quantity Progress Percentage
Daily ProgressWeekly Cum.
Progress
Rem. Balan
ceDaily
Progress %Weekly Cum. Progress %
R Balance % Remarks
Sch Actl Sch Actl Actl Sch Actl Sch Actl Actl
18th 28,093 M3 969.78 419.58 6499.95 4842.33 23,251 3.45 1.49 23.14 17.24 82.76
Sr. No. Weeks
ACTIVITY DESCRIPTION
EST. QTY
Unit
76.3223.6821,4406652.68441.5028,093Weekly Total =
Week (31/05/08-05/06/08)23rd
77.8922.1121,8826211.1828,093
138.00Week (24/05/08-30/05/08)22nd
78.3821.6222,0206073.1828,093
448.75Week (17/05/08-23/05/08)21st
79.9820.0222,4695624.4328,093
472.60Week (10/05/08-16/05/08)20th
81.6618.3422,9415151.8328,093
309.50Week (03/05/08-09/05/08)19th
24th Week (06/06/08- 12/06/08)
Weekly Total = 28,093 118.75 6771.43 21,322 24.10 75.90
25th Week (13/06/08- 19/06/08)
Weekly Total = 28,093 66.00 6837.43 21,256 24.34 75.66
ActlActlSchActlSchActlActlSchActlSch
Remarks
R Balance
%Weekly Cum. Progress %
Daily Progress %
Rem. Balan
ceWeekly Cum.
ProgressDaily
ProgressUnit
EST. QTY
ACTIVITY DESCRIPTIONWeek
Sr. No.
Progress PercentageProgress in Quantity
Date : July 04, 2008Discipline : Civil/ Structural
73.9226.0820,7657327.68490.2528,093Weekly Total =
Week (20/06/08- 26/06/08)26th
71.2228.7820,0068086.18758.5028,093Weekly Total =
Week (27/06/08- 03/07/08)27th
68.8331.1719,3358757.68671.5028,093Weekly Total =
Week (04/07/08- 10/07/08)28th
WEEKLY CONCRETE QUANTITIES FORECAST
Updated as of : 11-July-08
Date of Delivery of Modules at Das
IslandFoundation Modules
Baseline Forecast Baseline Forecast On Harbour On Site
PAR's1 PAR-012 31/12/2008 17/12/2008 30/4/2008 11/4/2008
2 PAR-013 31/12/2008 17/12/2008 14/6/2008 24/4/2008
3 PAR-014 31/12/2008 17/12/2008 5/8/2008 5/6/2008
4 PAR-016 31/12/2008 17/11/2008 24/6/2008
5 PAR-017 3/11/2008 17/11/2008 20/7/2008
6 PAR-018 3/11/2008 17/12/2008 29/6/2008
7 PAR-019 2/12/2008 17/12/2008 28/7/2008
8 PAR-001 2/12/2008 18/10/2008 27/3/2008 7/5/2008
9 PAR-002 2/12/2008 18/10/2008 21/5/2008 22/5/2008
10 PAR-003 2/12/2008 18/10/2008 10/4/2008 21/5/2008
11 PAR-009 31/12/2008 17/11/2008 27/3/2008 14/3/2008
12 PAR-010 31/12/2008 17/11/2008 6/4/2008 13/3/2008
13 PAR-011 31/12/2008 17/11/2008 31/3/2008 24/5/2008
14 PAR-004 2/12/2008 17/11/2008 7/5/2008
15 PAR-005 2/12/2008 18/10/2008 23/6/2008
16 PAR-006 2/12/2008 19/10/2008 18/5/2008
17 PAR-007 2/12/2008 17/11/2008 26/3/2008 14/3/2008
18 PAR-008 2/12/2008 17/11/2008 8/4/2008 30/4/2008
Process Area, Train-
2
10/6/2008
Process Area, Train-
1
28/7/2008Common Facilities
RemarksFoundation Completed
Sl. No.
Description Location
Updated as of : 11-Jul-08
Date of Delivery of Modules at Das
IslandFoundation Modules
Baseline Forecast Baseline Forecast On Harbour
On Site
PAR's
RemarksFoundation Completed
Sl. No.
Description Location
6/5/200827/3/200817/9/2008PAR-10926
5/3/20088/3/200817/9/200823/8/2008PAR-10325
6/5/200826/3/200817/9/200823/8/2008Booster
Compressor-South
PAR-10224
27/3/200817/9/2008PAR-10823
27/3/200818/10/200823/8/2008PAR-10622
5/3/200812/3/200818/10/200823/8/2008PAR-10521
15/3/200813/3/200817/9/200823/8/2008PAR-10420
11/5/2008
9/4/2008
17/9/200823/8/2008
Booster Compressor
-North
PAR-10119
27 PAR-107 18/10/2008 6/5/2008 24/4/2008
28 PAR-201 3/9/2008 17/7/2008 16/3/2008 26/4/2008
29 PAR-211 3/11/2008 17/8/2008 22/4/2008
30 PAR-212 3/11/2008 17/8/2008 18/3/2008 14/6/2008
31 PAR-216 3/9/2008 17/7/2008 27/4/2008 21/4/2008 20/06/08
32 PAR-217 3/9/2008 17/7/2008 19/4/2008 8/6/2008 20/06/08
33 PAR-221 17/8/2008 8/5/2008
34 PAR-213 3/11/2008 17/8/2008 10/4/2008
35 PAR-214 3/11/2008 17/8/2008 10/4/2008 14/6/2008
36 PAR-215 3/11/2008 17/8/2008 10/4/2008
37 PAR-202 3/9/2008 17/7/2008 22/3/2008 9/4/2008
38 PAR-203 2/10/2008 17/7/2008 14/4/2008 28/4/2008
39 PAR-205 2/10/2008 17/7/2008 2/4/2008 14/5/2008 20/06/08
40 PAR-206 2/10/2008 17/7/2008 2/4/2008 14/6/2008 20/06/08
41 PAR-207 2/10/2008 17/8/2008 27/3/2008 21/5/2008
42 PAR-208 2/10/2008 17/12/2008 27/3/2008 17/5/2008
43 PAR-209 2/10/2008 17/12/2008 27/3/2008 17/5/2008
44 PAR-210 2/10/2008 17/08/2008 2/4/2008 21/5/2008
45 PAR-015
Interconnecting
Piperack-West
31/12/2008 17/12/2008 10/4/2008 5/6/2008
45 TOTAL
Interconnecting
Piperack-Centre
Interconnecting
Piperack-West
9/7/2008
Interconnecting
Piperack-East
Updated as of : 11-Jul-08
Date of Delivery of Modules at Das
IslandFoundation Modules
Baseline Forecast Baseline Forecast On Harbour
On Site
RemarksFoundation Completed
Sl. No.
Description Location
TOTAL8
1/7/200813/11/200818/11/2008PAU-0088
28/7/200813/11/200818/11/2008PAU-0077
19/7/200816/2/200916/2/2009PAU-0066
19/7/200821/1/20092/2/2009
Process area, Train-
2
PAU-0055
30/3/200813/11/200818/11/2008PAU-0044
12/6/200814/10/200814/10/2008Process area, Train-
1
PAU-0033
20/5/200821/1/200914/2/2009PAU-0022
14/5/2008
10/6/2008
21/1/200921/1/2009Process area-West
PAU-0011
PAU's
Updated as of: 11-Jul-08
Date of Delivery of Modules at Das
IslandFoundation Modules
Baseline Forecast Baseline Forecast On Harbour
On Site
RemarksFoundation Completed
Sl. No.
Description Location
TOTAL12
2/10/200822/11/2008PAU-152B12
2/10/200822/11/2008PAU-152A11
2/10/200822/11/2008PAU-151B1010/6/200827/4/2008
2/10/200822/11/2008
Booster compressor
area
PAU-151A9
20/11/20085/2/2009PAU-0588
22/1/20095/2/2009PAU-0577
22/1/20095/2/2009PAU-0566
22/1/20095/2/2009PAU-0555
20/11/20085/1/2009PAU-0544
22/12/20085/1/2009PAU-0533
22/12/20085/1/2009PAU-0522
14/8/200810/6/2008
22/12/20085/1/2009
Process area
PAU-0511
PAU AIRCOOLERS
: Foundations already due to be completed as of report date as per recovery plan submitted by MEPI vide
letter no. L-1364 dated 26 March 2008
: Foundations completed
WEEKLY HSE STATISTICS FROM 05.07.08 TO 11.07.08
LTI MTC RTWD First Aid Near miss Inspections ASA Drill TBM
0 0 1 0 6 6 3 0 77
SAFETY TRAININGS CONDUCTED
No. Title of Training Conducted by
No. of Attendees
1 General HSE Training DESCON 05
2 Heat Stress TARGET 21
3 Defensive Driving TARGET 09
4 Working at Heights TARGET 04
1,852,238Cumulative
70,360Man Hours for the week
OAG PROJECT / HSE PLAN 05/07/08 to 11/07/08
Activities Performed This Week
Activities Planned Next Week
Review and closures of unsafe observations stated in weekly walk thru inspection.
41 new employees have been inducted for safety.Weekly safety walk thru at Process, Interconnecting Pipe
Rack and Podium area Monitoring of Site inspections reports.Weekly HSE Coordination Meeting.Supervisor’s Weekly HSE Meeting.Daily tool box meetings TRA MeetingOpening and close out Meeting with TUV & ADGAS Auditors.Conducted 4 ASA at site.The following inspections/verifications were conducted:
•Working at Heights•Excavation Access•Material Stacking
Training Conducted•Defensive Driving - 09•Heat Stress – 21•Work at Height – 04•Emergency Response - 20•General HSE Training – 05•PTW - 02
HSE Induction for new employees.Daily and weekly Site Inspection Upadte Action Tracking system Weekly supervisors meeting for Target and DesconTRA Meeting for Descon and Target.HSEMS and EMS Awareness Training for StaffManagement safety weekly walk-thruWeekly HSE Coordination MeetingConduct ASA as per scheduleDaily tool box meetings are attended by MEPI/Target/Descon staff as
per scheduleStart month long HEAT STRESS campaignAction Plan :- On going Scheduled Inspections :
•Waste Management•Housekeeping•Power Tools•Full Body Harness•Camp Inspection•Descon Yard
Training•Heat Stress Management•Working at height•H2S Awareness•HSEMS and EMS Awareness
OAG PROJECT / HSE ACTIVITIESNear Miss Trend
05/07/08 to 11/07/08
Description StatusSub standard Practice– One MEPI supervisor climbed from the first stage of the scaffold to the second stage passing through handrail.
Sub standard Practice – DESCON trailer entered C-30 road, blocking the traffic for 30 minutes.
Near Miss – Welding machine was found ON condition at podium at 08.30 PM.
Sub standard practice – No safety latch on the hook of 150 T crane at reclamation area.
Sub standard practice – Wire rope and spring of TRIPOD GRAB not working properly.
Near miss – TOYOTA HIACE, ADGAS vehicle found over speeding near plant-26.
Near miss- Rear door of the tipper truck was not locked while carrying pre-cast manhole.
Unsafe act
Unsafe act
Unsafe condition
Unsafe condition
Unsafe condition
Unsafe act
Unsafe condition
* We have 03 unsafe condition and 06 unsafe act.
WEEKLY EXECUTIVE SUMMARY
Wt Weekly Progress % Cumulative Progress %
L2 L3
Contract /
Baseline
Early Plan
Recovery
Plan
Actual Delta
Delta (Rec.Plan)
Contract /
Baseline Early
Plan
Recovery Plan Actual Delta
(Plan)
Delta (Rec.Pl
an)
Temporary Facilities 2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 98.00% 100.00
% 100.00% 2.00% 0.00%
Construction & Pre-commission-ing
95.20% 1.15% 2.12% 0.65% -0.50% -1.47% 58.13% 44.43% 31.78% -26.35% -12.66%
Civil Works: 64.94% 1.17% 3.09% 0.70% -0.46% -2.39% 82.13% 67.29% 48.12% -34.01% -19.17%
M.E.I. Works: 35.06% 1.12% 0.32% 0.54% -0.57% 0.22% 13.66% 2.09% 1.50% -12.16% -0.59%
Commission-ing 2.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
As Built Document 0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Total 100% 1.09% 2.02% 0.62% -0.48% -1.40% 57.30% 44.30% 32.25% -25.04% -12.05%
Breakdown
ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERNCONCERN
1. Construction & Commissioning Progress Site :Actual : 31.78 %, Delta : - 12.65 %
Before Delta : - 9.27 %Recovery Plant : 44.43 %
The Delta was increase and Need for Recovery Pour Concrete 1 200 M3 every week for minimum during next 12 weeks.
Delays by Aggregate / Bad Weather /Capacity of Harbour for UnLoad/Load .Planning and Coordination.
2. Concrete poured last Thursday 10 July 2008 ------------ 84.0 M3Total concrete poured This Week -------------- 671.5 M3Total Qty Concrete Poured until this Week ---------------- 8757.68 M3
3. ADGAS is looking for Additional Area for storage more Qty of Aggregates. On initial Area requested by MEPI is on process for approval
ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERNCONCERN
4. Radios provided by MEPI have now 3 to 6 New channels and Target/MEPI will be contact Safeer for give to him all information that we request and test for direct communications with CCB / CCR. Ongoing.
5. QHSE & QA / QC Audit was closed 10 July 2008 . Inform with conclusion and Actions will be sending after close Meeting in Abu Dhabi.QA/QC Engineer at Das expect on July 2008. Action by Ed - Livingston / C Foster.ADGAS is requesting MEPI for Filling remaining positions on Site, special on QA/QC, Planning and Piping Areas
ACTIVITIES FOR THE WEEK 11.07.2008AREA OF CONCERNCONCERN
6. Construction Jetty.Sea chart : Done. We have from Furgo / Constain. Survey was done in Dec 2005. TRA & MS. DoneIntegrity & Safety of Construction : 2 core drills was performed. DoneClean Debris : Started with Priority on Area that will be used by OAG-1. Ongoing.Temporary light : ADGAS Maintenance Stores have all parts for re - establish service. Ongoing.Mooring Anchor Blocks : Noble Denton Study provide another Mooring Anchor Concrete Block positions and coordinates. Some of there are the same ofExisting Anchor Blocks on sea bed.Defenders : According with Noble Denton, we need take off old defenders and put New ones or if PPA accept, we can use old big Tired that we have and we used time before on Harbour ? Ongoing.Buoys : Purchasing. Ongoing.
7. Area Plant 19 :a. Reclamation / shore protection: ADGAS requested to MEPI Qty and Prices
Drawing and scope of work was sent to MEPI.b. Area close to liquid Flare need level using excavated material. ADGAS will
request ADMA permission for start to work.
ACTIVITIES FOR THE WEEK 11.07.2008AREA OF CONCERNCONCERN
8. Flare Area: MEPI start the job. The area was demark with bonders for radiation.
9. Modules : PAR 217 was Transported to Podium.PAR 216 will be Transported to Podium Today.205 & 206, are storage on Harbour Area from 27 June 2008 until after install of Modules 201/202/203 that arrived to Harbour.Gatching: Done. SPMT: Is OK.Foundations for Modules 217 & 216 are ready for receive Modules. DESCON 500t crane was assembled in Podium Area. Functional and Load Test were performed.A1 Route is ready for Transport of Modules.Permissions are ready for Transport of Modules PAR 217 / 216.
10. ADGAS Requesting to MEPI for re-start the welding work and back filling on Pipes Process Area sides East & West, there are two Lines 12 inches diameter Fresh Water and Fire Water are on open trenches from time ago. ONGOING.
11. ADGAS is requesting, better protection for compact material on route, close to PAR 217. ONGOING.
12. ADGAS is requesting, What is the detail Plan for Install the Modules PAR 216 & 217. DONE.
13. ADGAS is requesting, When will be start of construction assembling for PAR 220/219/218.
14. ADGAS is very concern with Planning Activities for future Next Weeks and also very concern with Activities that were stopped long time ago and No re started again without any Technical Issue, example Open Trenches for Fire Water / Fresh Water Lines, Flare are dumped, Excavated Material, Erection Modules PAR 220/219/218. ONGOING.
15. ADGAS require MS for interconnection Piping & Modules.
ACTIVITIES FOR THE WEEK 11.07.2008AREA OF CONCERNCONCERN