21
MP Power Supply 1 Nuclear Power Nuclear Power Update Update for for The Society of American The Society of American Military Engineers Military Engineers September 15, 2010

Nuclear Power Update for The Society of American Military Engineers

  • Upload
    hertz

  • View
    33

  • Download
    0

Embed Size (px)

DESCRIPTION

Nuclear Power Update for The Society of American Military Engineers. September 15, 2010. 45 inch steel-reinforced concrete. 1/4 inch steel liner. 36 inch concrete shielding. 8 inch steel reactor vessel. nuclear fuel assemblies. Nuclear Power Facilities- Safety is Key. - PowerPoint PPT Presentation

Citation preview

Page 1: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

1

Nuclear Power UpdateNuclear Power Updateforfor

The Society of American Military The Society of American Military EngineersEngineers

September 15, 2010

Page 2: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

2

Nuclear Power Facilities-Nuclear Power Facilities-Safety is KeySafety is Key

45 inch steel-reinforced concrete

1/4 inch steel liner

36 inch concrete shielding

8 inch steel reactor vessel

nuclear fuel assemblies

Multiple Layers of SafetyMultiple Layers of Safety

Page 3: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

3

Industry ActivitiesIndustry Activities

Licensing risk is a key issue for the industry to move forward with actual plant orders

Previously separate construction and operating licenses were required

– No certainty provided by this process

– Many physical changes were required prior to receipt of operating licenses

– Costs increased due to schedule delays and rework required

Industry has adopted new process which results in combined construction and operating license

Page 4: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

4

New Licensing Process provides New Licensing Process provides regulatory certaintyregulatory certainty

• Licensing decisions finalized before major construction begins• Inspections to verify construction• Limited work may be authorized before license is issued

Pre-ConstructionConstruction Verification

Early Site Permit

Standard Design Certification

Combined License Review, Hearing,

and Decision

Verification of Regulations with ITAAC

ReactorOperationDecision

OptionalPre-Application

Review

New page 23

Page 5: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

5

Industry ActivitiesIndustry Activities

Industry has adopted several standard designs

Westinghouse AP 1000 (design certified 1/2006)

General Electric ESBWR

General Electric ABWR (design certified 5/1997)

Areva US EPR

Mitsubishi US APWR

Page 6: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

6

New Technology - Advanced New Technology - Advanced Reactor Reactor

CharacteristicsCharacteristics Safety

– Use of passive safety systems

– Gravity flow and natural circulation designs for cooling

Design

– Reduced number of components and bulk commodities

– Eliminate pumps and valves previously needed

– Use digital controls and fiber optic cables

Procurement

– Standardization of components based on NRC approved design

Page 7: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

7

Fewer Components Reduce Fewer Components Reduce Plant CostsPlant Costs

Confidential and Proprietary

70% Less Cable

45% Less Seismic Building Volume

80% Less Pipe

35% Fewer Pumps

50% Fewer Valves

Page 8: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

8

New Technology - Advanced Reactor New Technology - Advanced Reactor

CharacteristicsCharacteristics Construction

– Extensive use of modular construction improves quality and reduces on-site construction requirements

– Digital controls reduce size and complexity of systems

– Shorter construction schedule

Operation and Maintenance

– Use of proven systems and components

– Man-machine interface advancements

– Fewer systems to maintain and test reduces staff

Page 9: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

9

Smaller and Simpler than Smaller and Simpler than Current PlantsCurrent Plants

74147A

Sizewell B AP1000

Page 10: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

10

What makes Nuclear attractive?–Fuel volatility, both gas and coal, is a major concern

–Fuel transport and supplies are showing signs of capacity constraints

–Environmental compliance measures are increasing cost of coal base load resources

–Regulation of carbon dioxide (CO2) emissions is gaining traction

–New licensing process expected to allow cost control

–New design units are smaller and less costly to construct

Economics

Page 11: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

11

Costs of Competing FuelsCosts of Competing Fuels

Page 12: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

12

Plant Vogtle

Reactor Containment Bldg. Cooling Towers

Turbine Bldg. Electrical Switchyard

Page 13: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

13

Plant Vogtle ExpansionPlant Vogtle Expansion

Page 14: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

14

Schedule OverviewSchedule Overview

S/U

S/U

ConstructionLWA ActivitiesPre-Construction

NRC COL Review

3-31-08

COLA Preparation

4-8-08EPC Contract Signed

PSC Certification Process (complete)

ESP Preparation ESP and LWA Review

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 20172005

08-15-06

ESP and LWA Received8-26-09

PSC Certification received 3-17-09

COL ReceivedFall 2011

COD U34-1-2016

COLA Submitted

Commercial operation date is April 2016 & 2017 for Units 3&4

As of 6/30/2010

Page 15: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

15

Permit and License ActivitiesPermit and License Activities Early Site Permit Submitted to NRC in 2006

Issued by NRC August 2009

First to include Limited Work Authority

Combined License Application COL Application Filed in March 2008

Application Under Review at NRC

Anticipate License in Fall 2011

Vogtle Named Reference Plant

Page 16: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

16

0

1000

2000

3000

2009 2010 2011 2012PSC

Certification LWA COL

Pre Certification

Pre Construction

LWA COL

•Surveying

•Subsurface Exploration

•Environmental Protection

•Site-clearing

•Demolition & Relocation of existing facilities

•Construction of training & storage buildings

•Excavation of the nuclear island

•Back Fill

•Waterproof Membrane

•Rebar

•Basemat Concrete

•Safety Related Construction

On

site

Wo

rker

sVogtle 3 & 4 Construction Phases

Page 17: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

17

Construction Activities –Construction Activities – Module Assembly BuildingModule Assembly Building

Page 18: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

18

Construction ActivitiesConstruction ActivitiesSteam Generator Head Circulating Water Pipe

Reactor Vessel Head

Page 19: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

19

Construction Activities –Construction Activities – Foundation Excavation and BackfillFoundation Excavation and Backfill

Page 20: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

20

Chinese Construction AP1000Chinese Construction AP1000Sanmen U1 Nuclear Island

Page 21: Nuclear Power Update for The Society of American Military Engineers

MPPower Supply

21

QuestionsQuestions