NTKWG - Membership

HACC

LA Officers

HACAN

AIRLINES

NATS

BAA

NTKWG

Page 3: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

Early Observations

• 5 years since my last NTKWG and what I noticed was :– low attendance levels

– discussion dominated by one or two specific issues

– short meetings with little discussion

– 6 meetings per annum

– no focused workplan

– limited agenda

– little industry participation in the meetings

• needed to review the terms of reference, especially in light of the anticipated END Noise Action Plan

Page 4: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

New TORS

• The purpose of the Group is to:– receive and consider technical data from the NTK system and related reports

concerning the management of aircraft noise

– seek to identify and encourage areas of improved performance in relation to established noise management policy

– help facilitate the dissemination of information in relation to noise issues between the HACC and FLOPC

– to consider trends in complaint statistics

– track and comment upon the delivery of the Heathrow END action plan

– at the discretion of the Chairman, to consider such other aspects of Heathrow aircraft noise as may arise from time to time, and where appropriate to refer issues to other bodies such as for example the DfT, CAA, HACC and FLOPC.

Page 5: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

2010 Workplan

Activity Description

Quarterly FEU Reports

The aim of this piece of work is to develop a standard reporting template and content to enable quality debate at the meetings and for regular publication on our website.

END Noise Action Plan Updates

The final action plan will include a number of actions for delivery in 2010. The purpose of this activity is to track progress against those actions with an appropriate level of support and challenge.

Community Noise & Track Monitoring Program

The aim of this piece of work is to establish a structured approach to conducting noise and track studies with agreed outputs, site selection criteria and reporting. This could involve a smaller group developing up the approach for endorsement by the main group.

Annual Contour Review

As part of the draft action plan we are committed to commissioning a range of contours. It is anticipated that the results of this work will be annually reported on and tracked by the group.

CDA height study

The purpose of this would be to answer whether the promotion of CDA (as defined) has resulted in aircraft being generally higher.

Activity Description

A380 Study This would be an informative action where we could understand the noise performance of the A380 relative to other large aircraft.

Supplementary Metrics Study

There has been much debate about the use of contours to describe noise impacts. A pilot study was conducted by OMEGA in this area. This would be a piece of work to establish a suite of metrics that could be used and understood by a variety of stakeholders. The role of the group would be to review the methodology and findings.

Industry/

Community Presentations

This could be an open slot which could be used for “learning” by the group. It could (subject to availability) include updates from industry representatives, regulators, local authority community and pressure groups

2011 Workplan As part of the ongoing work and in order top be clear about our objectives we would need to set time in the meeting to review 2010 successes and plan for 2011.

Page 6: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

Deliverables

• Standing items review FEU Performance data and progress of the noise action plan.• May 2010

– commence supplementary metrics study– agree Community Noise and Track Monitoring Program methodology

• September 2010 – first web publication of quarterly FEU report.– complete CDA height study– review 2009 Lden contours– A380 noise comparison report

• November 2010– complete supplementary metrics study– agree 2011 work plan– agree 2011 community noise and track monitoring study areas for 2011

Page 7: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

Supplementary Metrics

Page 8: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

Community Noise & Track Program

Page 9: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010

Any questions?

Page 10: NTKWG Workplan 2010 Richard Norman, Head of Noise and Air Quality March 2010