2
Novozymes has previously spent a lot of time deciding when a new production should be started and how large a volume that was needed to be produced. Was the start-a-new-production-signal from the SAP system caused by a new big order; the need to keep up with the forecast; or because some items in stock were too close to expiry date? “We were challenged by low accuracy on our forecasts, and we had a relatively high stock level. Management asked if we in some way could do it differently. We tried a num- ber of things, but it didn’t create the preferred increase in accuracy”, says Peter Christian Graae, Strategic Project Manager in Novozymes. Thus, Novozymes and Syncronic decided to develop a pilot project based on the Demand Driven Material Re- quirement Planning (DDMRP) principles to clarify, if this would bring more accuracy into the production planning. Easy-to-understand concept DDMRP fascinated Peter Christian Graae because the concept is simple and easy to understand compared to a traditional MRP method. After all, as he expresses it, the question is whether you would rather start a production when you think there is an order or when you know there is an order. “DDMRP is a hybrid between producing to order and produc- ing to stock and has a good fit into our supply chain. And we have a clear decoupling point in our chain, which is why it makes sense to make a decision based on the DDMRP principle”, says Peter Christian Graae. In the pilot project, which involved selected item num- bers, Novozymes built its DDMRP-concept from scratch within a week in Excel. In addition, one week was spent on high-level simulation. Data originated from daily data extractions from SAP. Novozymes CASE: DDMRP managing production & inventory After a successful pilot project Novozymes is ready to implement DDMRP in a broader part of its planning During the pilot project a number of fine tuning of the Excel model were carried out to optimize parameters and various types of stock levels. “DDMRP gives us the best from two worlds and an unequivocal signal of when to start a new production. Today, we only produce to order and have recalculated our safety stock”, Peter Christian Graae concludes.

Novozymes CASE: DDMRP managing production & inventoryDDMRP principle”, says Peter Christian Graae. In the pilot project, which involved selected item num-bers, Novozymes built its

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

  • Novozymes has previously spent a lot of time deciding when a new production should be started and how large a volume that was needed to be produced.

    Was the start-a-new-production-signal from the SAP system caused by a new big order; the need to keep up with the forecast; or because some items in stock were too close to expiry date?

    “We were challenged by low accuracy on our forecasts, and we had a relatively high stock level. Management asked if we in some way could do it differently. We tried a num-ber of things, but it didn’t create the preferred increase in accuracy”, says Peter Christian Graae, Strategic Project Manager in Novozymes.

    Thus, Novozymes and Syncronic decided to develop a pilot project based on the Demand Driven Material Re-quirement Planning (DDMRP) principles to clarify, if this would bring more accuracy into the production planning.

    Easy-to-understand conceptDDMRP fascinated Peter Christian Graae because the concept is simple and easy to understand compared to a traditional MRP method.

    After all, as he expresses it, the question is whether you would rather start a production when you think there is an order or when you know there is an order.

    “DDMRP is a hybrid between producing to order and produc-ing to stock and has a good fit into our supply chain. And we have a clear decoupling point in our chain, which is why it makes sense to make a decision based on the DDMRP principle”, says Peter Christian Graae.

    In the pilot project, which involved selected item num-bers, Novozymes built its DDMRP-concept from scratch within a week in Excel. In addition, one week was spent on high-level simulation. Data originated from daily data extractions from SAP.

    Novozymes CASE:

    DDMRP managing

    production & inventory

    After a successful pilot project Novozymes is ready to implement DDMRP in a broader part of its planning

    During the pilot project a number of fine tuning of the Excel model were carried out to optimize parameters and various types of stock levels.

    “DDMRP gives us the best from two worlds and an unequivocal signal of when to start a new production. Today, we only produce to order and have recalculated our safety stock”, Peter Christian Graae concludes.

  • Many BenefitsThe DDMRP pilot project is still running and provides Novozymes with many benefits, according to Peter Christian Graae:

    The inventory for item numbers covered by the pilot project has been significantly reduced.

    The inventory is more balanced regarding days-on-hand.

    Planning lead time is short-ened, and the production will

    only begin if an order arrives. The signal that comes through our channel is understandable because the model is so clear. And because the signal

    is easy to understand, we can continuously focus on

    improving the signal. Every day we have scheduled

    a short meeting – however, this is often cancelled because we have

    not had a signal to initiate production. The concept is based on an alert setup

    based on red, yellow and green colours. We only need to respond if something is critical. DDMRP connects tactical planning level with

    operational execution.

    “It is an exciting project. I have introduced it to various parts of our organization, who also finds the project rather excit-

    ing. And I think it is fantastic that our management has dared to allow us to try a completely new concept”, Peter Christian Graae tells.

    Based on the success of the pilot project, DDMRP will be rolled into SAP. From there it will control the production planning for a wide range of Novozymes finished items.

    Initially, the DDMRP model is introduced into Novozyme’s SAP system for those item numbers that have been a part of the pilot project. Once it is running, the remaining item numbers will follow.

    Collaboration with SyncronicThe implementation of DDMRP has been realized in a close collaboration with Syncronic. From the start, Syncronic was a key part of the development of the overall concept and identification of potential benefits.

    Together, both parties have continuously reflected on experiences from the pilot project and the achieved results. And throughout the process, Syncronic has been a sparring partner for Novozymes.

    Going forward, Novozymes has chosen Syncronic to be responsible for the implementation of a fully integrated DDMRP solution in their SAP APO and SAP IBP planning modules. The implementation is expected to run for three months, followed by a roll-out of the solution to several other product areas and locations.

    SyncronicContact us:

    www.syncronic.com

    Novozymes CASE:

    DDMRP managing

    production & inventory

    Start with a manageable projectIf you consider implementing DDMRP into your own organization, Peter Christian Graae recommend beginning with a limited-scope pilot project, that is easy to under stand and straightforward. He finds it very important not to overcomplicate the task. According

    to Peter Christian Graae, DDMRP is particularly suitable for items with a relatively short lead time and that has a decoupling point, where a clear signal can be delivered. Before DDMRP is implemented into e.g. SAP it would be appropriate to make some experiences by building up the pilot project in Excel.

    The purpose of the pilot project is to gain some experiences and results, which makes it easier to explain the concept and achieve support from the rest of the orga-nization. Furthermore, the project participants will become project ambassadors and help drive the change management agenda.

    SYNCRONIC APS, KIRKEBJERG ALLÉ 84, 2.TH., 2605 BRONDBY, DENMARK | +45 7020 2103 | WWW.SYNCRONIC.COM