45
North Paintbrush Corridor Meeting Thursday, February 20, 2014 6:30 – 8:30 PM

North Paintbrush Corridor Meeting

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: North Paintbrush Corridor Meeting

North Paintbrush

Corridor Meeting

Thursday, February 20, 2014

6:30 – 8:30 PM

Page 2: North Paintbrush Corridor Meeting

2

Welcome and Introductions

Supervisor Liz Archuleta

District 2

Coconino County

Page 3: North Paintbrush Corridor Meeting

3

Opening Remarks

Lucinda Andreani

Coconino County

Page 4: North Paintbrush Corridor Meeting

4

Tonight’s Goals

Review and Discuss Proposed 60% Plans

Review FLO2D Analysis Results

Review Next Steps

Opening Remarks

Page 5: North Paintbrush Corridor Meeting

5

60% Designs

Reminder - Integrated Design Critical

Watershed Restoration on Forest and Off

Forest Conveyance Through the Neighborhood

to Lower Campbell Avenue Ditch

Forest Measures Contingent on Neighborhood

Measures and Vice-Versa

Project Delivers Important Flood Mitigation to

the Highly Impacted North Paintbrush

Corridor

Page 6: North Paintbrush Corridor Meeting

6

Design Assumptions

5 Year, 6 Hour Design Storm Accounting for ~2 Years of Soil and Vegetative Recovery

Design Peak Flow Rate is 258 Cubic Feet Per Second

Create No Adverse Impacts

Stay Within Existing Right-Of-Way and New Easements on Private Property

Re-Vegetate Measures On and Off Forest

Provide Fencing Along Easements

60% Designs

Page 7: North Paintbrush Corridor Meeting

7

60% Designs

Design Through Neighborhood Reflects Feedback

from Initial Corridor Meeting & Individual Meetings

All Easements Secured From Private Property

Owners & Now Securing Mortgage Releases

Engineering Identified Need for Additional Sediment

Reduction

Less Alluvial Fan Area On Forest

South to North Conveyances Occur on Flat Grades

Reduce Future Maintenance Need & Cost

Page 8: North Paintbrush Corridor Meeting

8

Basis of Design – Two Sections

On-Forest Measures

Natural Channel Design, Inc.

Forest Boundary to Lower Campbell

Ditch

Civiltec Engineering, Inc.

60% Designs

Page 9: North Paintbrush Corridor Meeting

9

60% Design:

On-Forest Measures

Allen Haden

Natural Channel Design, Inc.

Page 10: North Paintbrush Corridor Meeting

10

On-Forest Measures -

Key Considerations

Retain as Many Trees as Possible but Ensure Full

Value of Alluvial Fan Restoration

All Disturbed Areas will be Ripped, Seeded and

Mulched

Flows in Excess of Design Storm Will Flow in Historic

Flow Corridor

Private Properties Will See Flood Water from Storms

Greater than Design Storm; However, First 260+/-

CFS is in the Conveyance and NOT on Private

Property

Page 11: North Paintbrush Corridor Meeting

Paintbrush On–Forest Measures

11

Page 12: North Paintbrush Corridor Meeting

12

Page 13: North Paintbrush Corridor Meeting

13

Page 14: North Paintbrush Corridor Meeting

Middle Fan in Thames, Spreading Water During Flows

Page 15: North Paintbrush Corridor Meeting

Log rundown and fan in Lenox.

Log rundown and fan in Lenox15

Page 16: North Paintbrush Corridor Meeting

16

Log Sill Across Fan

Page 17: North Paintbrush Corridor Meeting

17

Log Run-Down Structure:

Brandis/Thames Watershed

Page 18: North Paintbrush Corridor Meeting

18

Terminal Trench:

Brandis/Thames Watershed

Page 19: North Paintbrush Corridor Meeting

19

Transition Channel Connects

to Neighborhood Conveyance

19

Page 20: North Paintbrush Corridor Meeting

20

60% Design:

Off-Forest Measures

Chris Dusza, P.E.

Civiltec Engineering, Inc.

Page 21: North Paintbrush Corridor Meeting

21

Off Forest Flood Mitigation –

Key Considerations

Limited Right of Way Available for Improvements

Multiple Road and Driveway Crossings

Utility Considerations and Conflicts

Easements Needed from Multiple Property

Owners

Need for Additional Sediment Reduction and

Storage

Coordination of Corridor Improvements with ILM

Page 22: North Paintbrush Corridor Meeting

22

60% Design: Forest Boundary to

Lower Campbell Ditch

Page 23: North Paintbrush Corridor Meeting

23

TRM Channel

60% Design: TRM Channel

Page 24: North Paintbrush Corridor Meeting

24

TRM Channel

Wupatki Trails

24

Page 25: North Paintbrush Corridor Meeting

25

60% Design: Gabion-Concrete

Channel

Page 26: North Paintbrush Corridor Meeting

26

Gabion-Concrete Channel

Lower Campbell Avenue

26

Page 27: North Paintbrush Corridor Meeting

27

60% Design: Pipe

Page 28: North Paintbrush Corridor Meeting

28

60% Design: Sediment Reduction Site

Page 29: North Paintbrush Corridor Meeting

29

FLO2D Analysis

Chris Dusza

Civiltec Engineering, Inc.

Page 30: North Paintbrush Corridor Meeting

FLO2D

Results

Any Frequency

5-Year, 100-Year, Etc.

Any Location

USFS

Private

Downstream

Every Grid Cell

Maximum Depth

30

Page 31: North Paintbrush Corridor Meeting

No Adverse Impact Criteria

(NAI)

“An Approach by which the Action of Any Community

or Property Owner, Public or Private, will Not

Adversely Affect the Property Rights of Others”

Floodplain Management Initiative Developed by

the Association of State Flood Plain Managers

Does Not Mean No Development

Means that Any Adverse Impact that is or would be

Caused by a Project – or the Cumulative Impact of

Projects – Must be Mitigated31

Page 32: North Paintbrush Corridor Meeting

No Adverse Impact Criteria

(NAI)

Board of Supervisors Adopted NAI Criteria for

County Projects in the Schultz Flood Area Only, on

April 2, 2013

Does Not Apply to Private Property Owners or

Work in Other Parts of the County, Only County

Mitigation Projects in the Schultz Area

Criteria Based on FLO-2D Modeling of

Differences Between Pre- and Post-Mitigation

Water Depths and Velocities

32

Page 33: North Paintbrush Corridor Meeting

No Adverse Impact Criteria

(NAI)

Water Depth

No More than .1 Foot increase at 5 Year Storm

No More than .5 Foot Increase at 10 Year Storm

No More than 1 Foot Increase at 100 Year Storm

Water Velocity

No Increase Less than 1 Foot/Second or 10% of

the Pre-Project Condition

33

Page 34: North Paintbrush Corridor Meeting

345 yr./6 hr. Storm - Existing Condition

Page 35: North Paintbrush Corridor Meeting

355 yr./6 hr. Storm – Post Measures

Page 36: North Paintbrush Corridor Meeting

3610 yr./6 hr. Storm - Existing Condition

Page 37: North Paintbrush Corridor Meeting

3710 yr./6 hr. Storm – Post Measures

Page 38: North Paintbrush Corridor Meeting

38

FLO2D Results –

Five Year Storm Existing Condition100 yr./6 hr. Storm - Existing Condition

Page 39: North Paintbrush Corridor Meeting

39100 yr./6 hr. Storm – Post Measures

Page 40: North Paintbrush Corridor Meeting

Adverse Impact Conclusions

No Adverse Impacts at the 5, 10 or 100 Year

Storms

Important Reduction in Flood Impacts Resulting

from Five Year Design Storm Measures from

Forest Boundary and Downstream

Reduced Impact to the Paintbrush Corridor and

Therefore Provides Opportunity to Construct Flood

Mitigation for this Highly Impacted Corridor

Excess Flows Go Where They Go Now

40

Page 41: North Paintbrush Corridor Meeting

41

Moving Forward…

Lucinda Andreani

Coconino County

Page 42: North Paintbrush Corridor Meeting

42

Total Preliminary Costs: $2.9 Million to $3.2 Million

Benefits Entire Corridor

No Adverse Impacts

Secured Easements

Project Meets Feasibility Criteria

Page 43: North Paintbrush Corridor Meeting

43

Secure Cost Share Approval from NRCS

Secure Final Approvals from Utilities

Complete Engineering Plans

Secure Any Necessary Temporary Construction

Easements

Approvals – FCD Board of Directors, NRCS & USFS

Target - April 1, 2014

Preliminary Construction Timeline – Weather

Permitting, Begin Construction On and Off Forest in

Early April and Complete Construction by June 30th

Next Steps . . .

Page 44: North Paintbrush Corridor Meeting

44

Resources

Please Direct All Questions and

Comments To:

Schultz Flood Hotline: (928) 679-8390

Schultz Flood Email:

[email protected]

Schultz Flood Website:

www.coconino.az.gov/schultzfloodinform

ation

Page 45: North Paintbrush Corridor Meeting

45

Thank You!

Breakout Sessions

to Review Preliminary Plan Sets