Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
California Statewide Utility Codes and Standards Program
1
Nonresidential HVAC
Stakeholder Meeting – Space
and Water Heating CASE Study
Heschong Mahone Group, Inc.
Energy Solutions
April 8, 2011
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
ACM Update-Water & Space Heating, VRF
● Summary of current code requirements
● Summary of code change proposals
● Typical practice
● Data/findings
● Specifics of code change proposals
● Remaining data collection and analysis
2 2
by topic
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Current Code Requirements ● DHW Performance Algorithms
● ACM algorithms based on PIER MF central DHW study
● Distribution system pipe heat loss – with controls & branch
● Standard and default plumbing designs
● Hydronic Space Heating Algorithms
● Consistent with DHW pipe heat loss model
● ACM Standard Designs
● Wall furnace and space heating boiler
● Air duct assumption
● Pipe Insulation
● Improvement - Table 123-a update
● Include pipes in unconditioned buildings (Table 100)
● VRF – not addressed in 2008 Title 24
3
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Typical Practice
● Performance calculation method reflecting common
design practice
● Central DHW distribution with recirculation loop
● Hydronic heating distribution system is similar to DHW
distribution pipe heat loss
● Standard Designs
● Fan type wall furnace is as common as gravity type wall furnace
● Hot water boilers are used for hydronic heating in most buildings
● Air ducts are in conditioned spaces in most MF buildings
● Pipe Insulation
● Cost effectiveness is the barrier for more insulation
● VRF – market penetration is low
4
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Summary of code change proposals
● DHW Performance Algorithms
● Distribution system pipe heat loss – controls, plumbing, branch
● Hydronic Space Heating Algorithms
● Follow DHW pipe loss algorithms, optional capability required
● ACM Standard Designs
● Heating equipment efficiency
● Res ACM: Wall-furnace standard design – fan type
● Boiler – hot water boiler, not steam boiler
● Air duct in MF building – standard design same as proposed (no credit)
● Pipe Insulation
● Update mandatory insulation thickness - Table 123–a
● Cover pipes in unconditioned buildings
● VRF – 2008 Title 24 Optional Capability
5
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Data / Findings – PIER DHW Research
● Field performance study of 30+ MF buildings
● Energy flow analysis
● Performance Modeling
6
Water Heater
Losses Distribution Losses
End-Use
Energy 30%
30%
Branch
Losses* Recirculation
Loop Losses Include pipe inside and
outside of dwelling units
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Data / Findings – Pipe Heat Loss Model
● System model includes two heat transfer modes
with consideration of transition
● Pipe heat transfer with HW flow
● UA, water temp & flow, ambient temp
● Pipe without HW flow - cool down
● UA and pipe/water thermal capacity
7
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Data / Findings –Model Validation
● Based on actual building DHW recirculation loop
configurations
● Compare modeled vs. measured HWR Temp, and
energy losses
8
2
3
4
9
5
6
7
1 10 11 12
8
1 2
3
4
10
5
7
8
9
11
12 13
6
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
9
Data / Findings – Model Validation Result
SFDMeasured
(Btu/day)
Modeled
(Btu/day)
Measured
reduction
(%)
Modeled
reduction
(%)
Measured
(Btu/day)
Modeled
(Btu/day)
Measured
reduction
(%)
Modeled
reduction
(%)
Measured
(Btu/day)
Modeled
(Btu/day)
Measured
reduction
(%)
Modeled
reduction
(%)
CONT Pump 608,711 608,711 - - 639,732 643,487 - - 1,875,663 1,879,417 - -
Temp Mod 600,697 582,695 1.3% 4.3% 633,433 616,266 1.0% 4.2% 1,958,764 1,941,597 -4.4% -3.3%
Timer 507,048 461,656 17% 24% 600,803 562,822 6.1% 13% 1,732,428 1,694,446 7.6% 10%
Demand 215,483 191,328 65% 69% 411,903 453,556 36% 30% 1,423,628 1,465,281 24% 22%
Total Hot Water EnergyRecirculation Flow Heat Loss Recirculation Loop Heat Loss
HW Draw
SFD
Hot Water
Energy
(Btu/day)
Modeled
savings
(%)
Measured
(Btu/day)
CONT Pump 1,879,417 - 1,235,931
Temp Mod 1,871,511 0.4% 1,325,331
Timer 1,816,132 3.4% 1,131,625
Demand 1,749,959 6.9% 1,011,725
w/o Flow Variation
Recirculation loop loss represent 34% Total hot water energy
Total hot water energy = Hot water draw + recirculation loop loss
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
10
DHW ACM – Proposal Overview
● Recirculation Loop Pipe Heat Loss
● Flow and temperature dependent
● Recirculation system controls
● Hydronic system pipe heat loss
● Standard and Default Distribution
Plumbing Layout
● Branch Pipe Heat Loss
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
DHW ACM – Hourly Heating Load
Distribution pipe heat loss – Existing DHW ACM
11
● Recirculation Loop ● Plumbing layout based on
building geometry
● HW Draw patterns; or HW flow
rates for hydronic heating
● HW temp: 135F for HW; vary
for hydronic heating & Control
Hourly
Standard
End Use
Hourly
Adjusted
Recovery Load
Distribution
Loss
Multiplier
Solar
Savings
Multiplier
Hourly
Recirculation
Distri. Loss
Hourly
Jacket
Loss
Implement monthly variation
Inside dwelling unit:
DLMk =1 + (SDLMk-1)*DSMk
DSMk =1 for MF
SSMk should be applied to HRDLk
as well; however, it depends on
how SSF is rated
● Branch ● Depend on HSEUk
should be a multiplier
to HSEUk
● Modify DLMk to include
heat loss from
branches outside of
dwelling unit
Proposed Improvement
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
DHW ACM – Pipe Heat Loss
Proposed Recirculation Distribution Pipe Heat Loss
12
Hourly ambient temperature
for pipe section, n
Hourly average water
temperature for pipe section, n
Average water temperature
during pump-off period
Average water temperature
during pump-on period
● Assess hourly average pipe temperature to calculate heat loss
- Replace the table of UL with explicit calculation
● Average pipe temperature is weighted between two modes, which
depend on control schedule
Weighting factor depending
on control schedule
● Each control strategy has a 24-hour schedule
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
13
DHW ACM – Hourly Control Schedule
TEMPERATURE MODULATION
p Pump
off
Time
TS TS
With cont.
monitoring
0 0 120 115
0 0 120 115
0 0 120 115
0 0 120 115
0 0 125 120
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 135 130
0 0 125 120
DEMAND CONTROL
p Pump
off
Time
TS
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
t 1-t 135
Continuous Pumping
Hour p Pump
off
Time
TS TS
With cont.
monitoring
1 0 0 135 130
2 0 0 135 130
3 0 0 135 130
4 0 0 135 130
5 0 0 135 130
6 0 0 135 130
7 0 0 135 130
8 0 0 135 130
9 0 0 135 130
10 0 0 135 130
11 0 0 135 130
12 0 0 135 130
13 0 0 135 130
14 0 0 135 130
15 0 0 135 130
16 0 0 135 130
17 0 0 135 130
18 0 0 135 130
19 0 0 135 130
20 0 0 135 130
21 0 0 135 130
22 0 0 135 130
23 0 0 135 130
24 0 0 135 130
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes 4/11/2011
14
DHW ACM – Plumbing Design
Hydronics heating and Central DHW ACM update
Supply
Return
Boiler
Room
n=1 n=2 n=3
n=6 n=5 n=4
● Current ACM requires user input of pipe length for three
pipe sections
● Proposed changes
● Supply and return each has three sections –
● Unconditioned, conditioned, underground,
● Return pipes behave dramatically different from supply pipes under controls
● ACM generate default system layout to check/adjust user input
(details to be discussed after ACM algorithms)
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
DHW ACM – Default Plumbing Design
Existing ACM algorithms – only rely on user input
15
• Building Story, floor area
• Number of apartment/guest room
• Boiler room Location
• Number of Loops
• Supply and Return Loop section
locations and length
USER INPUT
• Recirculation loop path
• Branch length and number
• Pipe diameters (Follow UPC)
• Pipe insulation thickness
ACM Generate Standard &
Default Loop Configuration
User
Input
Design
Default
Design
Compare
Standard
Design
Proposed
Design
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
16
User Inputs
Return Recirculation Pipe
Section #1
30
Section #2 Section #3
10
Supply Recirculation Pipe
Section #1
10
Section #2 Section #3
30
Uncondition
ed Space
2”
Conditione
d Space
2”
4 stories / 2 loops
Conditioned
Space
1”
Uncondition
ed Space
3/4”
Supply Return
Loop 1 80 ft 80 ft
Loop 2 80 ft 80 ft
Total 320 ft
Generate ACM
Default
Total Length <
90% ACM
Default?
Yes No
Keep
user
input
Default Design
Adjust
user
input
Increase total length
to ACM default
DHW ACM – Default Plumbing Design
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
DHW ACM – Standard Recirc. Design
17
● Dual loop design
● Boiler room near the middle of the building
● Any floor - 1st floor, garage, roof, middle floor
● Smaller pipe diameters less surface area
● Smaller temp drop (not included in savings calc.)
● Verification
● Res: HERS
● NR: follow Appendix NA2
● NR Field Verification & Diagnostic
Test Procedures
Standard Design
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
18
● Existing – pressure drop and pump power
● Based on IAPMO Uniform Plumbing Code
# of Dwelling Units Line Size
1 0.75
2 1
3 – 4 1.25
5 – 7 1.5
8 – 20 2
21 – 42 2.5
43 – 67 3
68 – 100 3.5
101 – 144 4
DHW ACM – Pipe Sizing
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
19
DHW ACM – Branch Heat Loss
● Pipe Heat Loss
● Pipe heat loss during usage = (GPHk/Numbranch)∙ ∙Cp∙ Tbranch
● tbranch: follow recirculation loop formula
● Water Waste
● Water waste = NumWait∙Cp ∙ ∙(1.4∙Volbranch) ∙(Tsupply,branch-Tcoldwater)
1.4∙Volbranch : 40% more – pipe heat capacity, non-mixing, waiting
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
20
DHW ACM – Branch NumWait
● NREL HW draw event tool
● Random hot water draw patterns
●
Number of unit
on branch
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
21
DHW ACM – Hydronic Heating
● Move from Optional Capability to required
● Hydronic system fuel consumption calculation
PL:
Hourly pipe loss rate
RI:
Rated input of the gas
water heater
Exis
tin
g
Pro
po
sed
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
22
● Only consider pipe loss in unconditioned space
● Return temperature is lower than supply temp
Conditioned
Space
HourlyLoad Supply Return
TS,end TR,start
DHW ACM – Hydronic Heating Heat Loss
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Wall Furnace – Current Standard Designs
● Fan types are more efficient than gravity type
● Federal efficiency standards
23
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Wall Furnace – LCC Analysis
● Fan type only cost effective in the climate zone 16 - No change
24
Climate Zone PV Saving/Unit Incremental Cost LCC
1 $212 $514 $302
2 $227 $514 $287
3 $102 $514 $412
4 $120 $514 $394
5 $53 $514 $461
6 $9 $514 $505
7 $4 $514 $510
8 $17 $514 $497
9 $9 $514 $505
10 $44 $514 $470
11 $257 $514 $257
12 $241 $514 $273
13 $189 $514 $325
14 $254 $514 $260
15 $16 $514 $498
16 $576 $514 -$62
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Boiler – Current Standard Designs
● EnergyPro use steam boiler efficiency as
standard design heating equipment
● Federal boiler efficiency standards (AFUE)
25
Effective
January 1,
1992
Effective
Septemper 1,
2012
Gas steam boilers
with single phase
electrical supply
75% 80%
Gas hot water
boilers with single
phase electrical
supply
80% 82%
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Boiler – Proposed Code Language
● Specify hot water boiler as the standard design
heating equipment
● NR ACM
● Table N2-15 – System #3 Description
Heating System: Gas hot water boiler
● Table N2-16 – System #4 Description
Heating System: Gas hot water boiler
● Table N2-17 – System #5 Description
Heating System: Gas hot water boiler
26
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● MF buildings have similar duct assumption as
single-family buildings
Air Ducts – Current Standard Design (Res)
27
Air Dis Table R3-1 – Summary of Standard Design HVAC System
Proposed Design Standard Design
Heating System Cooling System Heating System Cooling System Detailed Specifications
Through-the-wall heat pump Same equipment as proposed design with no air distribution ducts
Equipment efficiency determined by CEC Appliance Efficiency Regulations
Gas wall furnace with our without ducts and/or circulation fan
Any Same equipment as proposed design with no air distribution ducts
Split system AC with air distribution ducts
Any other electric heat including electric resistance, water source heat pump, etc.
Any Split system heat pump with air distribution ducts
SEER per Package D
Verified refrigerant charge (prescriptive requirement)
No credit for sizing
No credit for cooling coil airflow
No credit for reduced fan power
All other gas heating Any Split system air conditioner with gas furnace and air distribution ducts.
Note: The standard design cooling system is also used for the proposed design if the proposed design has no air conditioning
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
Air Ducts – Proposed Code Language (Res)
● Update Table R3-30 in Res ACM
28
Propose Design Standard Design
Heating Cooling Heating Cooling Detailed Specifications
Through-the-wall heat pump Same equipment as proposed design with no air
distribution ducts
Equipment efficiency
determined by CEC
Appliance Efficiency
Regulations Gas wall furnace
with or without ducts
and/or circulation fan
Any Same equipment as
proposed design with no
air distribution ducts
Same equipment as
proposed design
with no air
distribution ducts
Any other electric
heat including
electric resistance,
water source heat
pump, etc.
Any Split system heat pump with air distribution ducts;
For multi-family buildings, air distribution duct
length in unconditioned space is the same as the
proposed design
SEER per Package D
Verified refrigerant
charge (prescriptive
requirement)
No credit for sizing
No credit for cooling
coil airflow
No credit for reduced
fan power
All other gas heating Any Split system air conditioner with gas furnace and
air distribution ducts.
For multi-family buildings, air distribution duct
length in unconditioned space is the same as the
proposed design
Note: The standard design cooling system is also used for the proposed design if the proposed design has no air
conditioning
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Hydronic heating system may be compared to split system
with central furnace with duct loss
● The “Other” category compared to ducted systems
Air Ducts – Current Standard Design (NR)
29
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Table N2-14 – System #1 and System #2
Descriptions
Ducts: For ducts installed in unconditioned buffer spaces or outdoors
as specified in § 144(k), the duct system efficiency shall be as
described in Section 2.5.3.18. For All residential including
hotel/motel guest room, duct configurations shall be the same
as proposed.
Air Ducts – Proposed Code Language (NR)
30
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Not required for unconditioned building
● Res Mandatory follows the same requirements
Pipe Insulation – Current Requirements
31
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Increase insulation by 0.5 inch for all cases
● Cost effective (negative LCC) in all climate zones
Pipe Insulation – LCC (100% duty)
32
Fluid
Temperature
Range (°F)
Conductivity
Range
(Btu-inch/hr/
sqft/ °F)
Nominal Pipe Diameter (inches)
0.5 0.75 1 1.25 2 2.5 4 5 6 8
LCC ($/ft) – 30 year gas TDV
Above 350 0.32-0.34 -$9.0 -$13 -$0.26 -$1.0 -$3.0 -$1.5 -$4.2 $0.00
251-350 0.29-0.31 -$4.23 -$6.5 -$1.19 $0.33 -$1.2 -$2.2 -$4.9 $0.00
201-250 0.27-0.30 -$7.76 -$11 -$0.88 -$1.5 -$3.3 -$2.2 -$4.8 -$3.6
141-200 0.25-0.29 -$9.82 -$14 $0.02 -$0.4 -$1.8 -$2.6 -$5.2 $4.7
105-140 0.24-0.28 -$3.42 -$5.2 -$0.39 -$0.8 -$2.0 -$2.8 -$5.2 $4.7
DHW >105 0.24-0.28 -$4.19 -$6.2 -$0.76 -$0.2 -$2.3 -$0.1 -$1.3 $4.7
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Increase insulation by 0.5 inch for all cases
● Not cost effective (positive LCC) in all climate zones
Pipe Insulation – LCC (50% duty)
33
Fluid
Temperature
Range (°F)
Conductivity
Range
(Btu-inch/hr/
sqft/ °F)
Nominal Pipe Diameter (inches)
0.5 0.75 1 1.25 2 2.5 4 5 6 8
LCC ($/ft) – 30 year gas TDV
Above 350 0.32-0.34 -$2.3 -$4.2 $2.1 $1.7 $0.8 $2.0 $0.9 $0.00
251-350 0.29-0.31 -$0.3 -$1.4 $1.3 $2.4 $1.7 $1.3 $0.2 $0.00
201-250 0.27-0.30 -$2.4 -$4.0 $1.1 $0.8 $0.0 $1.0 $0.0 -$3.6
141-200 0.25-0.29 -$3.4 -$5.4 $1.5 $1.3 $0.8 $0.5 -$0.5 $4.7
105-140 0.24-0.28 -$0.6 -$1.5 $1.0 $0.8 $0.4 $0.1 -$0.7 $4.7
DHW >105 0.24-0.28 -$1.0 -$2.0 $0.8 $2.7 $1.9 $1.8 $1.5 $4.7
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Table 123-A DHW Pipes
● “Service water-heating systems (recirculating
sections, all piping in electric trace tape systems,
and the first 8 feet of piping from the storage tank for
nonrecirculating systems, and the first 8 feet of
branch piping from recirculation loops)”
● Increase pipe insulation by 0.5 inch for DHW pipes
● Space Heating – only for selected climate
zones
Pipe Insulation – Proposed Change
34
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● DHW pipe in unconditioned buildings
Pipe Insulation – Proposed Change
35
CALIFORNIA STATEWIDE UTILITIES CODES AND STANDARDS PROGRAM
Water & Spacing Heating
4/8/2011 CA Utilities 2013 Title 24 Stakeholder Meeting for Proposed Code Changes
● Statewide energy savings analysis
● Finalize insulation requirements for space
heating pipes
Remaining Analysis
36