28
 Lloyd George Acoustics PO Box 717 Hillarys  WA  6923 T: 9300 4188  F:9300 4199 W: www.lgacoustics.com.au   Noise & Vibration Management Plan METRONET -Yanchep Rail Extension Reference: 17074053-02   Prepared for: Public Transport Authority                

Noise & Vibration Management Plan

  • Upload
    others

  • View
    12

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Noise & Vibration Management Plan

 

Lloyd George Acoustics PO Box 717

Hillarys  WA  6923

T: 9300 4188  F:9300 4199

W: www.lgacoustics.com.au 

 

 

Noise & Vibration Management Plan

METRONET -Yanchep Rail Extension Reference: 17074053-02

 

 

Prepared for: Public Transport Authority 

            

   

Page 2: Noise & Vibration Management Plan

Report:17074053-02

LloydGeorgeAcousticsPtyLtdABN:79125812544

POBox717HillarysWA6923

Contacts DanielLloyd TerryGeorge MattMoyle OlivierMallié

E:

M:

[email protected]

0439032844

[email protected]

0400414197

[email protected]

0412611330

[email protected]

0439987455

Date: Rev Description PreparedBy Verified

30/05/2018 - Finalissuedtoclient DanielLloyd TerryGeorge

Thisreporthasbeenpreparedinaccordancewiththescopeofservicesdescribedinthecontractor

agreementbetweenLloydGeorgeAcousticsPtyLtdandtheClient.Thereportreliesupondata,surveys,

measurementsandresultstakenatorundertheparticulartimesandconditionsspecifiedherein.Any

findings,conclusionsorrecommendationsonlyapplytotheaforementionedcircumstancesandnogreater

relianceshouldbeassumedordrawnbytheClient.Furthermore,thereporthasbeenpreparedsolelyfor

usebytheClient,andLloydGeorgeAcousticsPtyLtdacceptsnoresponsibilityforitsusebyotherparties.

Page 3: Noise & Vibration Management Plan

Lloyd George Acoustics

Table of Contents 1 SUMMARY______________________________________________________________________________1

2 CONTEXT,SCOPEANDRATIONALE___________________________________________________________2

2.1 DescriptionoftheProposal _____________________________________________________________2

2.2 KeyEnvironmentalFactors______________________________________________________________3

2.3 RequirementsoftheRequestforAdditionalInformation______________________________________4

2.4 RationaleandApproachinMeetingtheEnvironmentalObjective_______________________________4

2.4.1 NoiseandVibrationModellingandAssessment__________________________________________4

2.4.2 NoiseandVibrationModellingandAssessmentResults ___________________________________6

2.4.3 ManagementApproach____________________________________________________________13

2.4.4 RationaleforChoiceofManagementTargets __________________________________________13

3 NVMPPROVISIONS ______________________________________________________________________14

3.1 EnvironmentalObjectives______________________________________________________________14

3.2 ManagementActionsandTargets_______________________________________________________14

3.3 DesignandConstructionofNoiseMitigationMeasures______________________________________15

3.4 Monitoring _________________________________________________________________________16

3.5 NoiseandVibrationComplaintProcedure_________________________________________________18

3.6 ReviewandRevisionofManagementActions______________________________________________18

3.7 Reporting __________________________________________________________________________19

3.7.1 MonitoringReports_______________________________________________________________19

4 ADAPTIVEMANAGEMENTANDREVIEWOFTHENVMP__________________________________________20

4.1 AdaptiveManagement________________________________________________________________20

4.2 ReviewofPlan_______________________________________________________________________20

5 STAKEHOLDERCONSULTATION_____________________________________________________________21

5.1 ConsultationandCommunityEngagement________________________________________________21

6 GLOSSARY______________________________________________________________________________23

7 REFERENCES____________________________________________________________________________24

Page 4: Noise & Vibration Management Plan

Lloyd George Acoustics

List of Tables Table1-1NoiseandVibrationManagementPlanSummary___________________________________1

Table2-1EnvironmentalFactorsoftheProposalforAmenity(NoiseandVibration) _______________3

Table3-1ManagementActions&TargetstobeImplementedtoAchieveObjectives______________14

Table3-2NoiseandVibrationRecommendedMonitoringLocations___________________________17

Table5-1StakeholderConsultation_____________________________________________________21

Table6-1GlossaryofTerms___________________________________________________________23

List of Figures Figure2-1RailProjectExtent___________________________________________________________2

Figure2-2ExtentofProposedNoiseWalls(1of6)__________________________________________7

Figure2-3ExtentofProposedNoiseWalls(2of6)__________________________________________8

Figure2-4ExtentofProposedNoiseWalls(3of6)__________________________________________9

Figure2-5ExtentofProposedNoiseWalls(4of6)_________________________________________10

Figure2-6ExtentofProposedNoiseWalls(5of6)_________________________________________11

Figure2-7ExtentofProposedNoiseWalls(6of6)_________________________________________12

Figure3-1RecommendedMonitoringLocations___________________________________________17

Figure5-1UrbanDevelopmentLocations________________________________________________22

Page 5: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page1

1 SUMMARY Thisdocumentpresentstheenvironmentalmanagementactionstomanagethepotentialimpactsoftheproposalonamenity(noiseandvibration).

The required extent, location and height of noise mitigation measures will be progressivelyreassessedbyasuitablyqualifiedpersonasdetaileddesignforlevelsandlayoutfortherailwayandfuturesurroundingdevelopmentsbecomeavailable. Table1-1 summarisesthegeneralcontentofthisNoiseandVibrationManagementPlan(NVMP).

Table 1-1 Noise and Vibration Management Plan Summary

Item Details

TitleofProposal YanchepRailExtension

ProponentName PublicTransportAuthority

KeyEnvironmentalFactorsandObjective Noise and vibrations - EPA’s objective for SocialSurroundings is to protect social surroundings fromsignificantharm.

NVMPObjectives To minimise noise and vibration emissions from theoperation of the proposal to as low as reasonablypracticable.

NoiseManagementTargets StatePlanningPolicy5.4targetLAeq(Day)55dBandLAeq(Night)50dBunlesshigherlevelsarepermittedduetotheincorporationofspecifiedhousefacadeprotection.

VibrationManagementTargets Criterion 1: vibration isolation measures will beprovidedwherethepredictedoractualvibrationisCurve2orgreater,asdefinedinAS2670.2.

Criterion2:theproposalwillbedesignedtomeetCurve1.4asdefinedinAS2670.2.

Criterion3:Vibrationwillbemanagedtobeaslowasreasonablypracticable.

NVMPReview Changestotheoperationoftheproposal,suchasincreased train speeds, number of trainmovements, length of rail car sets or extendedhoursofoperation.

Where significant complaints are received fromsensitivereceptors.

Neworrevisedinformationbecomingavailable.

Annually.

Page 6: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page2

2 CONTEXT, SCOPE AND RATIONALE 2.1 Description of the Proposal

ThePublicTransportAuthority(PTA)isproposingtoimplementstageoneoftheWesternAustralianGovernment’s METRONET vision, which includes the Yanchep Rail Extension (YRE) project (theproposal).Theproposalisa14.5kilometre(km)extensionoftheJoondaluprailwaylinefromButlertoYanchep,whichincludestheconstructionofthreenewstationsatAlkimos,EglintonandYanchep.

Thenewrailwaylinewillbeconstructedinacuttingthatisapproximately5mbelowexistingand/orfuture surroundingground levels. The railway corridor is surroundedbyexistingand futureurbandevelopmentsasshowninFigure5-1.

Figure 2-1 Rail Project Extent

Page 7: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page3

ThescopeoftheNVMPistooutlinethemanagementandmitigationofpotentialnoiseandvibrationimpactsduringtheoperationoftheproposal.TheNVMPhasbeenpreparedinaccordancewiththeEnvironmentalProtectionAuthority(EPA)InstructionsonhowtoprepareEnvironmentalProtectionAct1986PartIVEnvironmentalManagementPlans.

ManagementofconstructionrelatednoiseandvibrationimpactswillbeaddressedwithinseparateprojectspecificConstructionEnvironmentalManagementPlans(CEMPs)and isnot includedintheNVMPscope.TwoCEMPswillbepreparedfortheproject,toalignwiththestagedconstructionofthe rail lineoverParts 1 and2. Part 1of the proposal is the constructionof the alignment fromButler Station to Eglinton Station and construction environmental impacts will be managed inaccordancewiththePart1CEMP(EcoLogical,2018). Part2oftheproposal istheconstructionofthealignmentfromEglintonStationtoYanchepStationandconstructionenvironmentalimpactswillbemanagedinaccordancewiththePart2CEMP.

2.2 Key Environmental Factors

Amenity (noiseandvibration),classifiedundertheSocialSurroundingsenvironmental factor is thekeyenvironmentalfactorapplicabletothisNVMP.FurtherinformationisprovidedinTable2-1.

Table 2-1 Environmental Factors of the Proposal for Amenity (Noise and Vibration)

EnvironmentalFactoroftheProposal

Activity SensitiveReceptors PotentialImpact

TrainNoise Trainmovementsduringtheoperationoftheproposal

Existingandfutureresidentialpremisesadjacenttotheproposal.

Othersensitivepremisessuchasschools.

Noisedisturbanceleadingtoannoyance.

Sleepdisturbanceduetohighnoiselevelwhentrainspassing.

TrainVibration Trainmovementsduringtheoperationoftheproposal

Feltvibrationorregeneratednoiseleadingtoannoyance.

Vibrationlevelsresultingindamagetobuildingstructures

StationNoise OperationoftheStation

NoisefromStationoperationssuchasthepublicaddresssystem,mechanicalplantandcleaningrequirements

Page 8: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page4

2.3 Requirements of the Request for Additional Information

FollowingreferraloftheproposaltotheEPAunderSection38oftheEnvironmentalProtectionAct1986,theEPAissuedanotice(EPA,2018)requestingPTAprovideadditionalinformationforreferralassessment.Thisincludedthepreparationofa:

Noise and vibration management plan (NVMP) to detail proposed noise and vibrationmanagementmeasures.

Constructionenvironmentalmanagementplan(CEMP)todetailproposedmanagementandmitigationactionsforeachofthePreliminaryKeyEnvironmentalFactors.

The CEMP is a separate document and includes the management and mitigation of noise andvibrationsgeneratedbytheproposalconstructionworks.

ThisNVMPissubmittedinaccordancewiththefollowingcriteria:

Railway operation (noise) - State Planning Policy 5.4 Road and Rail Transport Noise andFreightConsiderationsinLandUsePlanning(thepolicy).

Railwayoperation(vibration)-MinisterialStatement629,whichrelatedtotherailwaysouthofButlerStation(MinisterialStatement629).

Railway station operation - The Environmental Protection (Noise) Regulations 1997 (theregulations).

2.4 Rationale and Approach in Meeting the Environmental Objective

2.4.1 Noise and Vibration Modelling and Assessment

The resultsof thenoisemodellingandassessment informthemanagementapproach formeetingthe NVMP requirements stated in Section 2.3. The identified management actions, managementtargets and proposed review and revision of management actions are aligned with the overallproposedmanagementapproach.

Anoiseandvibrationassessmentwasundertaken, inaccordancewith thepolicy,byLloydGeorgeAcoustics(January2018),toassessthelikelytransportationnoiseandvibrationlevels,resultingfromtheproposal,onsensitivereceptors.

Whilethepolicystatesthat“transportinfrastructureprovidersshoulddesignmitigationmeasurestoachievethenoiselimit”(60dBLAeq(Day)atgroundfloorlevel,basedonthepredictedfuture(15to20years) scenarios, the noise assessment designed mitigation to achieve the policy target of 55 dBLAeq(Day)wherever practicable using noise barriers up to a height of 4metres, unless the sensitivereceptorincorporatesspecificnoisemitigationwithintheconstructionofthebuildingfacade.

NoisemodellingfortheoperationoftheproposalwasundertakenusingthecomputerprogrammeSoundPLAN8.0andincorporatingtheNordicRailPredictionMethod(KildeRep.130)algorithm.ThealgorithmhadbeenmodifiedtoreflectlocalconditionsandtrainsusingtheMETRONETrailnetwork.The3-dimensionalcomputermodelling includedexistingtopography integratedwiththeproposed

Page 9: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page5

designoftherailway,whichhasbeendesignedtobeinacutting,between4-7mbelowgroundlevel,forthemajorityofthealignment. Variables includedexpectedtrain lengthsandspeeds,expectednumberoftrainmovements,existingnoisesensitivepremises,futureresidentialdevelopmentsandexistingnoisebarriers.

Thetrainconfigurationusedinthemodellingassumedalltrainswere6-carsets,havingalengthof150metres. Itwas assumed that 75 trainmovements occurred in each direction during the dayperiod(6:00a.m.to10:00p.m.)and22trainmovementsoccurredineachdirectionduringthenightperiod(10:00p.m.to6:00a.m.)

Thetrainspeedsused inthemodellingwasbasedonsimulationplotsundertakenbyAustralisRailConsulting.Thespeedsrangedfrom55km/hcomingintostationsto130km/honstraightsections.

Forthepurposesofmodelling,allbuildingswereassumedtobesinglestoreyandhaveaheightof4.0 metres. Considering the type of buildings constructed in the area and the fact that theassessmentisundertakenatgroundfloorlevel,thisapproachwasconsideredtobereasonable.

Existing noise walls were considered in the model; however, noise mitigation that has beenincorporated intoasubdivisiondesignaspartoftheDevelopmentApplicationprocess,whichmayincludenoisebarriers,specifiedfacadeprotectiononcertainlots,oracombinationofbothwerenotincludedinthisassessment.

Calibrationofthenoisemodelwasundertakenassumingapassingnoiselevelfromatraintravellingat130km/hof87dBLAmax.ThismeasurementdatawasobtainedduringthecommissioningofnewtrainsoperatingontheJoondalupline.

Thekeyassumptionsanduncertaintiesassociatedwiththenoisemodellinginclude:

Numberoftrainmovementiscorrect.

Trainspeedsareasmodelled.

Daytimenoiselevelswillbemorethan5dBabovethenighttimelevels.

Groundlevelsatexistingandproposedsensitivereceiversareassurveyedordesigned.

Noise control measures assigned to existing residential development along the alignmentareconstructedasspecified.

Noisewallsforfutureresidentialdevelopmentsareconstructedasspecified.

The assessment of noise from the railway stations will be undertaken during the detailed designstageofthestations.

ThevibrationassessmentwasbasedonmeasuredvibrationlevelsadjacenttotheNorthernSuburbsRailwayundertakenbyHerringStorerAcoustics.Theassessmentconsideredtheprofileofthetrack(straight,bend,etc)anddistancefromthetracktothesensitivereceptor.

Theattenuationofvibrationlevelsoccurswithdistancefromthesourceandthedampingpropertiesofthegroundmaterial. Basedonthemeasuredvibrationlevels,thedistancesrequiredtoachieve

Page 10: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page6

the criterion of Curve 1.4 in Australian Standard 2670.2-1990 “Evaluation of human exposure towhole-bodyvibration;Part2:Continuousandshock-inducedvibrationinbuildings(1to80Hz)are:

NearStation-50metres

Insidebend-55metres

Outsidebend-40metres

StraightTrack-40metres

Thesedistancesassumethetrainwillbetravellingathighspeeds.

Thekeyassumptionsanduncertaintiesassociatedwiththevibrationpredictionsinclude:

Vibrationmeasurementresults fromtheexistingrailwaytranslate to theproposedrailwaydesignandgroundconditions.

2.4.2 Noise and Vibration Modelling and Assessment Results

TheresultsofthenoisemodellingshowedthatthePolicynoisetargetwasexceededatanumberofreceiverlocationsandassuch,noisemitigationisrequiredtobeincorporatedintothedesignoftherailwaytoachievethiscriterion,wherepracticable.

ForthePTA,theonlypracticablenoisemitigationmeasureavailableistoinstallnoisebarriersalongtherailreserveboundary,wherepracticable,atallidentifiednoisesensitivepremises.Forreasonsofpracticability,noisewallshavebeenlimitedtoaheightof4metresabovegroundlevel.

The recommendednoisewalls are presented inFigures 2-2 to 2-7. While these noisewalls havebeen designed to achieve the Policy noise target, wherever practicable, they do not take intoconsideration other mitigation measures, such as house facade protection, which are permittedunder the Policy. For example, where urban development includes the requirement for facadeprotectiononcertain lots,higherexternalnoise levelsarepermittedand thereforea reduction intheheightofthenoisewall,ortheeliminationofthewall,wouldbeconsideredacceptable.

Theresultsofthevibrationassessmentshowthecriterionof103dBVispredictedtobemarginallyexceededatanumberof locationsalongtherailwayalignment. Whilevibrationcriteriaforabovegroundrailwaysaregenerallysettoaddressannoyance(i.e.Curve1.4AS2670.2-1990),thegroundconditionssouthofButlerStationresulted inanumberofpropertiesexperiencingstructure-borneregeneratednoiseissues(rumbling)astrainspassedby.Asaresultofthis,PTAhavecommittedtoinstallingballastmattingadjacent toallexistingandapproved future residentialdevelopments. Areductionofbetween10to15dBVcanbeexpectedwhichwouldsignificantlyreducevibrationlevelstowellbelowthevibrationcriterion.

Page 11: Noise & Vibration Management Plan

Butler Station

2.4m

2.4m

2.4m

2.4m

2.2m

3.5m

2.4m

2.4m

2.4m

2.4m

2.2m

3.5m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-2Scale

0 50 100 200 300 400m

Page 12: Noise & Vibration Management Plan

Alkimos Station

4.0m4.0m

4.0m

2.2m

3.5m

3.5m

2.6m

2.6m

2.8m

4.0m4.0m

4.0m

2.2m

3.5m

3.5m

2.6m

2.6m

2.8m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-3Scale

0 50 100 200 300 400m

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

Page 13: Noise & Vibration Management Plan

4.0m4.0m

4.0m

4.0m

2.6m

2.4m

3.5m

3.0m

3.0m

3.0m

4.0m4.0m

4.0m

4.0m

2.6m

2.4m

3.5m

3.0m

3.0m

3.0m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-4Scale

0 50 100 200 300 400m

Page 14: Noise & Vibration Management Plan

Eglinton Station

2.4m2.2m

3.0m

4.0m

4.0m4.0m

2.4m2.2m

3.0m

4.0m

4.0m4.0m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-5Scale

0 50 100 200 300 400m

Page 15: Noise & Vibration Management Plan

3.5m

3.0m

m3.0m

4.0m3.5m

3.0m

m3.0m

4.0m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-6Scale

0 50 100 200 300 400m

Page 16: Noise & Vibration Management Plan

Yanchep Station

3.5m

3.0m

3.0m

4.0m

3.0m

4.0m

3.0m2.4m

3.0m

3.5m

2.4m

GEORGE

LLOYD

A c o u s t i c s

Lloyd George Acoustics [email protected](08) 9300 4188

KeyExisting Barriers

Proposed Barriers

Buildings

Railway axis

METRONET - Yanchep Rail ExtensionProposed Noise Barriers Figure 2-7Scale

0 50 100 200 300 400m

Page 17: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page13

2.4.3 Management Approach

Themanagementapproachfornoisehasbeeninformedbythepolicyandindustrybestpractice.

ForvibrationtheapproachisidenticaltoMinisterialStatement629(relatingtotherailwaysouthofButler Station), which references Australian Standard AS2670.2-1990: Evaluation of humanexposuretowholebodyvibration-Part2:Continuousandshockinducedvibrationinbuildings(1to80Hz). ThisStandardcharacterisessources (ofvibration)whichoperate intermittently,butwhichwouldproducecontinuousvibrationifoperatedcontinuously,suchasrailwaytrains.

2.4.4 Rationale for Choice of Management Targets

The rationale for the choice of management targets to achieve the environmental objectives foramenityisdetailedbelow:

Themanagement target foroutdoornoisehasbeendevelopedby theWesternAustralianPlanning Commission in the policy based on emissions of road or rail transport noise asreceivedatanoise-sensitivelanduse,namely:

o for new road or rail infrastructure proposals, at 1 m from the most exposed,habitablefaçadeofthebuildingreceivingthenoise,atgroundfloorlevelonly;and

o for new noise-sensitive development proposals, at 1 m from the most exposed,habitable façade of the proposed building, at each floor level, andwithin at leastoneoutdoorlivingareaoneachresidentiallot.

In the application of these outdoor noise criteria to new major transport projects, theobjectivesofthePolicy isthatthenewinfrastructurebedesignedandconstructedsothatnoiseemissionsareatalevelthat-

o Provides an acceptable level of acoustic amenity for existing noise-sensitive landusesandfortheplanningofnoise-sensitivedevelopments;

o Isconsistentwithotherplanningpoliciesandcommunityexpectations;and

o Ispracticablyachievable.

Themanagement targets forground-bornevibration resulting fromthe trainpass-byswasgiven in theMinisterialStatement629for theexistingrailwaysouthofButlerStation.TheMinisterial Conditions required that the proponent meet specific vibration criteria withreference to the Australian Standard AS 2670.2-1990: Evaluation of human exposure towholebodyvibration-Part2:Continuousandshockinducedvibrationinbuildings(1to80Hz). This Standard characterises sources (of vibration) which operate intermittently, butwhichwouldproducecontinuousvibrationifoperatedcontinuously,suchasrailwaytrains.The preferredmethod of assessing the influence of continuous vibrations is to assess therootmeansquare(RMS)valueoftheweightedparticleacceleration.Intermsofvibrationalenergy,bothparticleaccelerationandvelocityareidentical.

Themanagementtarget fornoiseresultingfromoperationoftherailwaystations isbasedon the requirements and assigned levels contained within the Environmental Protection(Noise)Regulations1997.

Page 18: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page14

3 NVMP PROVISIONS 3.1 Environmental Objectives

The environmental objective of this NVMP is tominimise noise and vibration emissions from theoperationof theproposal toas lowas reasonablypracticable. This alignswithEPA’sobjective forSocialSurroundingswhichistoprotectsocialsurroundingsfromsignificantharm.

3.2 Management Actions and Targets

Risk-basedmanagementactionshavebeen identifiedandprioritisedtoachievetheenvironmentalobjective.Thesemanagementactionsfocusthegreatestmanagementeffortonreducingthenoiseandvibrationlevelsatsensitivereceptorsalongthealignment.

Table 3-1 Management Actions & Targets to be Implemented to Achieve Objectives

RiskandKeyImpact ManagementTargets ManagementActions

Noisedisruptiontoexistingandfuturesensitivereceptorsalongthealignmentandreductioninamenityvaluesduetorailoperations.

OperationalNoiseManagementTarget

ThetargetforoutdoornoiseistomaintainoperationalnoisetobelowLAeq(Day)55dB(6.00a.m.to10.00p.m.)andbelowLAeq(Night)50dB(10.00p.m.to6.00a.m.)(WAPC,2009)

Designoftherailwaytobeincutasfaraspracticable.

Noiseattenuationbarriers(noisewalls)willbedesignedandconstructedduringtheconstructionphaseoftheProject,asdetailedinSection3.3.

Anoisemonitoringprogramwillbeimplementedwithinthreemonthsoftheopeningoftheproposal,andagainat18months,toassesstheeffectivenessofnoisemitigation.Specificallytheprogramwill:

Confirmtheas-builtandoperatingrailwayachievesthePolicytargetLAeq(Day)55dBandLAeq(Night)50dBunlesshigherlevelsarepermittedduetotheincorporationofspecifiedhousefacadeprotection.

Assesstheaccuracyofthepre-constructionnoisemodellingpredictionsthatwereusedtodeterminenoisereductiontreatments.

FurtherdetailsareprovidedinSection3.4.

ThePTAwillundertakerailmaintenancetoreasonablymaintaintheoperationalperformanceoftherelevantrailwayinfrastructureandreduceweartotrains.Thiswillinvolveregularinspectionoftherailconditionandrailrectification/grindingtoremoveexcessiveroughnessorcorrugationwhichmaydevelopovertime.

Page 19: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page15

RiskandKeyImpact ManagementTargets ManagementActions

StationnoiseStationNoiseManagementTargets

ThetargetfornoiseresultingfromoperationoftherailwaystationsistoensurenoiselevelscomplywiththeassignedlevelsundertheEnvironmentalProtection(Noise)Regulations1997.

Designandconstructrailstationstomeetstationnoisemanagementtargets.

Vibrationdisruptiontoexistingandfuturesensitivereceptorsalongthealignmentandreductioninamenityvaluesduetorailoperations.

OperationalVibrationManagementTarget

Thetargetforground-bornevibration,fromMinisterialStatement629isdetailedbelow:

Criterion1:vibrationisolationmeasureswillbeprovidedwherethepredictedoractualvibrationisCurve2orgreater,asdefinedinAS2670.2.

Criterion2:theproposalwillbedesignedtomeetCurve1.4asdefinedinAS2670.2.

Criterion3:Vibrationwillbemanagedtobeaslowasreasonablypracticable.

Vibrationmitigationintheformofballastmattingwillbeinstalledadjacenttoallexistingandfutureresidentialdevelopmentsduringtheconstructionphaseoftheproject.

Complaintsregardinglevelsofnoiseandvibration

Nocomplaintsregardingnoiseand/orvibrationsduringoperationoftherailway.

NoiseandvibrationcomplaintsduringoperationwillbemanagedbyPTAthroughaspecificprocedureasdetailedinSection3.5.

3.3 Design and Construction of Noise Mitigation Measures

Therequiredextent,locationandheightofnoisewallswillbeprogressivelyreassessedbyasuitablyqualifiedperson/consultant/engineerasthefollowingdetailbecomesavailable:

Detaileddesignlevelsoftherailway;

Detaileddesignlevelsandlayoutofthesurroundingfuturedevelopments;and

Confirmation of noise wall and building facade noise control packages implemented bysurroundingdevelopmentswhererequiredaspartofthesubdivisionapprovalconditions.

Under thepolicy, building facadenoise control packages allowhigher noise levels external to thebuilding by maintaining acceptable internal noise levels. While custom facade packages can be

Page 20: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page16

designedbyanacousticalconsultant,thepolicyguidelineshavethree“deemedtocomply”facadepackages,beingPackageA,BandC.PackageAisrequiredforexternalnoiselevelsbetween55and60dBLAeq(Day),PackageBisrequiredforexternalnoiselevelsupto63dBLAeq(Day)andPackageC is s required forexternalnoise levels up to65dBLAeq(Day). Theuseof facadeprotectioncanresultinlowernoisewallswhereconsideredappropriate.

TheresponsibilityforconstructionofnoisewallswillalsoneedtobedeterminedinaccordancewithPolicyrecommendations.Whereanewrailinfrastructureprojectistobeconstructedinthevicinityofafuturenoise-sensitivelanduse,theinfrastructureprovideranddeveloperarebothresponsiblefor ensuring that the objectives of the policy are achieved, and a mutually-beneficial noisemanagementplan,includingindividualresponsibilities,shouldbenegotiatedbetweentheparties.

NoisewallswillbedesignedtothefollowingspecificationsandconstructedduringtheconstructionphaseoftheProject:

Heightwillvarybasedonlocationtoamaximumheightof4m;and

Constructedofamaterialwithasurfacedensityexceeding15kg/m2.

3.4 Monitoring

Thepurposeofmonitoringistoinform,throughthemanagementtargets,iftheenvironmentalnoiseandvibrationcriteriaarebeingachievedandwhenmanagementactionsneedtobereviewedandrevised.

A noise and vibration monitoring program aimed at measuring the noise and vibration levels atexisting sensitive premiseswill be developed. Themonitoring resultswill provide information toassesshoweffectivethemanagementactionshavebeeninachievingthemanagementtargets.

Noise and vibration monitoring will be undertaken by a suitably qualifiedperson/consultant/engineerwithin threemonthsof theopeningof theproposal, overaperiodofseven(7)daysatsensitivepremiseswithinthe localityaspresented inTable3-2and illustrated inFigure 3-1. Additional monitoring locations will be added where residential areas are developedadjacenttotheproposalpriortothecommencementofoperations.

The monitoring will be undertaken in accordance with the policy guidelines using un-mannedstatisticalnoiseorvibrationmonitorsplacedonemetrefromthefacadeofthesensitivepremises.AllequipmentusedwillhavebeenNATAlaboratorycertifiedwithintheprevioustwoyears.

The results of the monitoring will be used to assess the effectiveness of noise and vibrationmitigationmeasuresbycomparingtheresultsagainstthemanagementtargets.

Thissuiteofmeasurementswillberepeatedatthesamelocations18monthsaftercommencementof the normal train service to establish that compliance with the management targets is beingmaintained.

Monitoringmayalsobeconductedatsensitivereceptorswherecomplaintshavebeenreceived.

Page 21: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page17

Table 3-2 Noise and Vibration Recommended Monitoring Locations

MeasurementID Localityofmeasurement

ReceiverPoint1 CharlburyDrive,Alkimos

ReceiverPoint2 CheshamRise,Alkimos

ReceiverPoint3 DuerdenStreet,Alkimos

ReceiverPoint4 MaroonAvenue,Alkimos

ReceiverPoint5 BulburinParade,Yanchep

Figure 3-1 Recommended Monitoring Locations

1

23

4

5

Page 22: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page18

3.5 Noise and Vibration Complaint Procedure

NoiseandvibrationcomplaintsduringoperationwillbemanagedbyPTAthroughaspecificprocedurethatincludes:

DirectingcomplaintstocontactthePTAviatheirInfoline136213orviathecommentssectiononthePTA’swebsitewww.pta.wa.gov.au/about-us/complaints-and-comments

Allcallsandemailswillbeloggedandrespondedtowithinfivedaysofreceipt.

ThePTAwillinvestigateallnoiseand/orvibrationcomplaintsreceivedby:

o Investigatingtheoperationsatthetimeofthecomplaint

o Substantiatedorwidespreadcomplaintswillbeinvestigatedasfollows:

§ Anappropriatenumberofshort-termmeasures/measurementswillbeundertakentoassessthecauseofsubstantiatedcomplaint/incidentsandtoassesshowtorectifythesituation.

§ Unattended (logged)noise levels relevant to thecomplaintor incidentwillbereviewed.

§ Where appropriate, immediate measures that could be implemented toaddressthenatureofthecomplaintwillalsobereviewed/assessed.

o Filinganincidentreport.

o Whereappropriate,provideawrittenresponsewithin10workingdaysfromreceiptofthecomplaint.

3.6 Review and Revision of Management Actions

Wherethemanagementtargetisnotmetorwhereamanagementactionisnotimplemented,PTAwillinvestigatethereasonsforthemanagementtargetnotbeingmetorthemanagementactionnotbeingimplemented,reviewandrevisethemanagementactionsasrequired,anddevelopadditionalmanagementactionswherenecessary.

Asaminimum,managementactionswillbereviewedandrevisedannually.

Additionalmanagement/remedialactionslikelytobeconsideredinclude:

Investigatethecauseoftheactionnotbeingmet.

Undertakeadditional/moredetailedmonitoringtoidentifythecause.

Investigateadditionalmitigationmeasures/managementactions.

Review of noise and vibration complaint procedure including the response times andapproachtoinvestigations.

Page 23: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page19

3.7 Reporting

3.7.1 Monitoring Reports

Two monitoring reports will be prepared following completion of the two specified monitoringevents(i.e.withinthreemonthsoftheopeningoftheproposalandwithin18monthsoftheopeningoftheproposal).Themonitoringreportswill:

Includeandsummarisemonitoringresults

Comparemonitoringresultstomanagementtargets

AssessoperationalcompliancewithandsuccessofthemanagementactionsdetailedinTable3-1inrelationtomonitoringresults

Wheremanagementtargetshavenotbeenachievedduringthereportingperiod,includeadescriptionofrevisedand/oradditionalmanagementactionstobeimplementedtoachievethetargets.

Page 24: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page20

4 ADAPTIVE MANAGEMENT AND REVIEW OF THE NVMP

4.1 Adaptive Management

ThePTAwillimplementadaptivemanagementtorespondtoissuesidentifiedintheimplementationof management actions, monitoring and evaluation against the management targets, to moreeffectivelymeettheenvironmentalobjective.

Potentialadaptivemanagementactionsmayinclude:

Where modelling indicates that noise sensitive premises will be in excess of themanagement targets, assess additional noisemitigationmeasures (provided this does notincludenoisewallsinexcessof4m).

Where monitoring suggests certain locations exceed the vibration management target,undertakeinvestigationstoassessthecauseoftheexceedance.

Where complaints are received resulting from operation of the proposal, undertakemeasurementsatthecomplainantspremisestocompareagainstthemanagementtargets.

Wheremanagementtargetsareexceededatcomplainant’spremises,investigatecauseandassessadditionalmitigationasrequired.

4.2 Review of Plan

This plan will be reviewed annually to assess if management actions require revision. Potentialreasonsortriggersforrevisingmanagementactionsinclude:

Changesto theoperationof theproposal, suchas increasedtrainspeeds,numberof trainmovements,lengthofrailcarsetsorextendedhoursofoperation.

Wheresignificantcomplaintsarereceivedfromsensitivereceptors.

Neworrevisedinformationbecomingavailable.

TheimplementationofthisplanwillbeauditedbyPTA.

Page 25: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page21

5 STAKEHOLDER CONSULTATION 5.1 Consultation and Community Engagement

The PTA has consulted extensively with key stakeholders including the proponents/developersresponsiblefortheurbandevelopmentprojectsinproximitytotherailalignmentto:

Informpreliminaryplanningfortheproposal.

Understandtheurbandevelopmentlocation,extentandprogresstodate.

Understandtheexistingnoiseandvibrationmanagementandmitigationmeasures.

Table5-1identifiesthekeygovernmentandcommunitystakeholdersconsultedfortheYREprojectinrelationtonoiseandvibrationimpactsand/ormanagementmeasuresatthetimethisNVMPwasprepared.

ThePTAhasalsoinitiatedanextensivecommunityengagementprogram,includingtheprovisionofinformationontheprojectviatheMETRONETwebsitewww.metronet.wa.gov.au.

As required, information will be routinely updated to inform the community as the projectcommencesconstructionandastherailwayiscommissioned.

Table 5-1 Stakeholder Consultation

Timeframe Keystakeholder Summaryofconsultation

September2017topresent.Consultationisongoing.

EPAandDWEREPAservicesunit.

EnvironmentaladviceundertheEPAct(asrequired).

Jan2018topresent.Consultationisongoing.

DepartmentofWaterandEnvironmentalRegulation(DWER)

Environmentaladvice(asrequired).

ProvisionofdraftNoiseandVibrationAssessmentreporttoDWERNoiseBranchfortechnicalexpertreviewandcomment.

DWERNoiseBranchprovidedreportfeedbackandadviceandguidancetobeimplementedinProjectplanninganddesign.

Asrequired,ongoing.

DepartmentofPlanning,LandsandHeritage(DPLH)/WesternAustralianPlanningCommission

Obtainingandverifyingplanningapprovalsforurbandevelopments.

Feb2018topresent.Consultationisongoing.

PropertydevelopersfortheadjacenturbandevelopmentprojectsillustratedinFigure5-1.

Noiseandvibrationimpactsandmanagementconditions(existingandproposed).

Projectdefinitionanddelivery.

Page 26: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page22

Figure 5-1 Urban Development Locations

AlkimosCentral

Eden BeachEstate

Yanchep Sun City

Lot 6 TarongaPlace

Vertex Estates

AllaraEstates

Amberton

Jindowie

AlkimosVista

AlkimosBeach

Shorehaven

Jindee

SouthYanchep

Eglinton West

St Andrew'sEstate

TrinityEstates

Eglinton Town Centre

Eglinton Hill

Eglinton Service/CommercialEglinton Future

Development

BrightonJindalee

Beachside Estate

Lot101

LegendYanchep Rail Extension Footprint

Yanchep Rail Extension - Urban Development Areas

Document Path: Y:\ENVIRONMENTAL\Sam\06_Yanchep\02_MXDs\Urban Development\20180510_UrbanDevelopment.mxd

Date Printed: 10/05/2018Created By: David Fotheringham ¯

Base Data: Nearmap 2018, Sources: Esri, HERE, Garmin, USGS, Intermap, INCREMENT P, NRCan, Esri Japan, METI, Esri China (Hong Kong), Esri Korea, Esri (Thailand), NGCC, © OpenStreetMap contributors, and the GIS User Community

1:75,000Scale

0 1,100 2,200550 m

Page 27: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page23

6 GLOSSARY Table 6-1 Glossary of Terms

Abbreviation Definition

PTA PublicTransportAuthority

YRE YanchepRailExtension

NVMP NoiseandVibrationManagementPlan

EPA EnvironmentalProtectionAuthority

CEMP ConstructionEnvironmentalManagementPlans

NATA NationalAssociationofTestingAuthorities,Australia

dB Decibel

dB(A) A-weighteddecibellevel

LAeq AverageA-weightednoiseenergyduringameasurementperiod

LAeq(Day) LogarithmicaverageofthehourlyLAeqlevelsfrom6.00amto10.00pmonthesameday.

LAeq(Night) LogarithmicaverageofthehourlyLAeqlevelsfrom10.00p.m.to6.00a.m.thesameday.

Hz Hertz

Kg/m2 Kilogramspermetresquared

CAR ComplianceAssessmentReport

CEO ChiefExecutiveOfficer

EMP EnvironmentalManagementPlan

OEPA OfficeoftheEnvironmentalProtectionAuthority

Page 28: Noise & Vibration Management Plan

Lloyd George Acoustics

Reference:17074053-02.docx Page24

7 REFERENCES Lloyd George Acoustics. 2018. Ref:17074053-01. Transportation Noise & Vibration Assessment:METRONET-YanchepRailExtension

Herring Storer Acoustics. 2012. Ref: 15438-1-12160. Northern Rail Extension: Romeo Road toYanchep-GroundVibrationAssessment

AustralianStandardAS2670.2-1990:Evaluationofhumanexposuretowholebodyvibration-Part2:Continuousandshockinducedvibrationinbuildings(1to80Hz)

State Planning Policy 5.4: Road and Rail Transport Noise and Freight Considerations in Land UsePlanning

EnvironmentalProtection(Noise)Regulations1997.