Upload
argentinoar01
View
216
Download
0
Embed Size (px)
Citation preview
7/27/2019 Nigerian pipeline completed through swamp, rock and forest
1/2
3 PiPelines international digest | deCeMBer 2011
key ProjeCts
The project involves construction of an 18 inch diameter
pipeline, which will transport 172 MMcf/d of natural gas
at a pressure of 70 bar from the existing Obigbo ALSCON
Pipeline at Ukanafun, Akwa Ibom state, to Mfamosing, near
Calabar in Cross River state.
A local inuenceEHGC ensured that local companies were involved in the
project, creating jobs in the local community.
The pipeline was designed and engineered by Zishan
Engineering Nigeria Ltd with indigenous rm Oilserv Nigeria Ltd
appointed as main construction contractor.
Major aspects of the project were subcontracted to local
operators, such as horizontal directional drilling awarded to
Enikkom and swamp pipeline construction awarded to MJD
Oil Services.
EHGC also engaged the services of Solewant/Kema Coating
Nigeria Ltd a NACE-certied indigenous rm to execute the
application of corrosion coating of the bends and their girth welds.
Host communities were educated on the environmental, health
and safety impact assessment of the project through several
enlightenment sessions that EHGC held.
Saety frstOando Gas and Power which is ISO 9001:2000 certied
ensured that the design and construction of the pipeline
project was compliant with the American Society of Mechanical
Engineers 31.8 standard.
Oando Gas and Power is committed to world-class operations
with strict adherence to safety, quality, health and environment
standards, said Oando Head of Upstream, Gas and Power
Projects John Alamu.
Nigerian pipeline completed
through swamp, rock and forestOando Gas and Power's subsidiary East Horizon Gas Company (EHGC) recently completed a 128 km pipeline to supplynatural gas to industrial areas operating heavy-duty power engines and equipment in southeast Nigeria, overcomingvarious terrain challenges along the way.
The gas pipeline under construction.
http://-/?-7/27/2019 Nigerian pipeline completed through swamp, rock and forest
2/2
4 PiPelines international digest | deCeMBer 2011
key ProjeCts
To mitigate the social and environmental impact of
conventional, open-cut river crossing construction, all seven river
crossings were constructed using horizontal directional drilling.
Procedures and job hazard analyses were developed for all
activities with barriers, controls and recovery measures clearly
identied.
The end facilities were also tted with pressure relief valves set
at 10 per cent below the pipelines maximum allowable operating
pressure.
A challenging pipeline routeThe pipeline route traversed various challenging terrains
through swamp, forest and built-up areas, as well as throughundulating and extremely rocky topography.
The swampy nature of the right-ofway (RoW), and the
seasonal and reoccurring ooding of the land area presented
some civil engineering and logistic challenges, said Mr Alamu.
Mr Alamu described some of the initiatives which were
deployed to overcome these challenges.
In the extended swamp segment, the swamp constructions
were executed using anchor blocks in order to provide negative
buoyancy on the welded pipeline and to avoid oating.
The soil cover after pipe burial was also increased from 1.2 m to
2 m from the top of the pipe, said Mr Alamu.
In the forest and built-up areas, the pipeline network was
categorised at Class 2 HD, which necessitated the installation of
line break valves at intervals as prescribed by applicable codes.
The pipeline was located at the centre of a 15 m wide RoW.
Thrust-bore technology was also used to pull welded spools
across major roads. This innovation allowed for the preservation
of the roads integrity and structure.
Mr Alamu said that community shrines and sacred lands were
avoided; however, some cultural heritage sites were unavoidably
located in the pipeline RoW.
Relevant parties were adequately compensated for these sitesprior to their relocation. Landowners were also compensated as
required by the State Government for all farmlands and trees that
were aected.
In September 2011 just under three years after Oilserv Nigeria
rst mobilised to site in November 2008 the pipeline reached
technical completion.
Pre-commissioning was completed in October 2011, gas was
introduced into the pipeline by the end of October, and the
system was nally stabilised on the 3 November 2011.
Oando Gas and Powers city gate facility for its recently completed gas pipeline.
http://-/?-