New Jersey Clean Air CouncilPublic HearingApril 1, 2009
Jeff HalfingerBabcock & Wilcox
2Proprietary and Confidential
A Shifting Landscape
• Increasing construction cost and scheduleSkilled field craft laborNSSS component supply chain
• Tightening capital marketsGovernment loan-guaranteesCapital cost and funding access
• Changing geo-political environmentCarbon-constrained regulatory frameworkFossil-fueled power generation costsEnergy independence and security
Modular reactors are NOT:
Modular Reactors are NOT:
.4
5Proprietary and Confidential
MWe
10
125
1000
ImprovedConstruction
Schedule
ProjectFinancing
Design & Licensing
Risk
Base LoadImpact
The Drivers Behind a Modular Reactor
NSSSsupply chain
Cost Efficiency
Real-world issues are shaping the optimal size.
6Proprietary and Confidential
Solution: B&W’s mPowerTM Reactor Modular Approach
• Flexible and scalable to customer requirements Integrated reactor modules Multi-unit (1-10+) plant 100 percent shop manufactured Rail-shippable
• Reduced licensing risk, construction cost, & schedule Evolved PWR-type concepts Passive safety No on-site NSSS construction Three years to start-up
• Integrated and simplified NSSS with fewer components Internal helical coil SG No need for safety-grade backup power No external pressurizer Conventional core and standard fuel
• Simplified operations and maintenance Four plus-year core design Sequential partial-plant outages Standardized BOP
Lower risk and cost solution…
7Proprietary and Confidential
• 125 Mwe integral reactor
• Internal steam generator
• Standard PWR fuel
• Large primary coolant inventory
• SA508 RPV with SS clad
• Small penetrations into Primary Coolant System at TOP of RPV
• Diverse, redundant internal CRDMs
• No boron in primary coolant
B&W’s mPower Reactor
Steam Generator
Reactor Primary Circulation
Nuclear Core
Feedwater Inlet
Steam Outlet
Circulators
Internal CRDM
8Proprietary and Confidential
Decay heat removal heat sink
Pressure Suppression
Spent fuel pool
Module
B&W’s mPower Reactor Features
• Underground containment
• Used fuel stored in spent fuel pool for life
• Natural circulation decay heat removal system for emergency/refueling cooling
• Primary coolant treatment system within containment
• Steam generator inspection within containment
Independent, self contained modules
9Proprietary and Confidential
The B&W mPower Plant Design Features•Prefabricated components, Streamlined construction
NSSSSteam turbineControl room containment
•Limited Module Interaction Independent controls“Local” responses minimizes interaction
•Underground reactor building, Enhanced safetyMissile penetrationsSeismic advantagesNon-proliferation support
•ReliableSequential outages
•Minimize options, Cost effectiveCondenser cooling (air or water)Seismic design (2 zones?)Number of modules
500 MWe Plant Using 125 MWe Modules
10
• Compact footprint• Self-contained• Location flexibility
1900 Ft1550 Ft
Adaptability to Government Installations
•Small compact standardized design•Passively safe•Scalable•Long refueling cycle 5+ years at <5% enriched U235
~10 years at <10% enriched U235
•Built in the USAHeavy forgings from Lehigh Heavy ForgeComponent fabrication at B&W’s Mt. Vernon, Indiana facilityFuel fabrication at B&W’s Lynchburg, VA facilityModular construction techniquesTransportable size
.12
•Potential for Co-Generation SteamDesalinationElectrolysis for hydrogen and oxygen production
•Fischer-Tropsch?
•Sell Excess Electricity to Secondary Market
Adaptability to Government Installations
.13
Public-Private Partnerships•To be Successful Program Must:Select appropriate sites for reactor deployments•Critical missions•Strategic offensive and defensive capabilities•High energy costs and usage
−Production tax credits and loan guarantees could make nuclear power more competitive at more sites
Develop a long-term land lease agreement (EUL?)•Win-Win arrangement for Air Force and
commercial developerDevelop a long-term power purchase agreement •Mechanism for third-party financing•Minimizes market risks for initial units
14Proprietary and Confidential
Mt. Vernon, IN
Lynchburg, VAMt. Vernon, IN
B&W Supply Chain of Proven Technology
• Domestic Forgings or Rolled Plate • Component fabrication
B&W’s Mt. Vernon, Indiana facility
• Fuel fabrication B&W’s Lynchburg, VA facility
• Control rod drive fabrication B&W’s Euclid facility
• Modular construction capabilities McDermott’s Morgan City
Vertical Integration within B&W
15Proprietary and Confidential
First Plant Deployment
2008 2009 2010 2011 2012 2013 2014 2015 2016
Define Functional Requirements
Concept Definition
Preliminary Design
Prepare DCDLatest submittal
NRC Review
Final Design
Prepare COL Application
NRC Review
Long-Lead Procurement
Construction
ITAAC
2017 2018
NRC review paces project implementation
16Proprietary and Confidential
B&W mPower Benefits•Sized to customer requirements
•Competitive cost
•Reduced risk – minimum site work and supply chain
•Shorter schedule – three-year construction
•Proven approach – evolved PWR technology
•Optimized O&M – four plus-year refuel cycle with partial outages