NEW ELEMENTARY SCHOOLREED SITE, ARLINGTON PUBLIC SCHOOLS CONCEPT DESIGNSCHOOL BOARD INFORMATION ITEM MARCH 22, 2018
03.22.2018
School Board Info 2
PROJECT PARAMETERS
1. Create a new neighborhood elementary school with an attendance zone
2. Support APS Strategic Plan Goals, specifically Goal #4 – Provide Optimal
Learning Environments
3. Address capacity by providing at least 725 seats
4. Open by start of school 2021
5. Designate a maximum project cost of $49 million, with options for less
Core Mission
03.22.2018
School Board Info 3
BIDDING
Overall Project Timeline
Apr 2018
Concept Design SB Approval
CONCEPT DESIGN SCHEMATIC DESIGN
DESIGN DEVELOPMENT
tbd 2018
Schematic Design SB Approval
Nov2018
Design Development Submission
Jun 2019
Final Design SBApproval
CONSTRUCTION DOCUMENTATION
Sep 2021
SchoolOpens
CONSTRUCTION
BuildingPermit
Approval
UsePermit
Approval
NOV 2018 MAY 2019
Mar2019
ConstructionDocumentSubmission
03.22.2018
School Board Info 4 Concept / Schematic Design Timeline
21Mar
29Nov
Concept Design
ApprovalCommunity
Forum
24Jan
JointPFRCBLPC
25Oct
JointPFRCBLPC
15Nov
JointPFRCBLPC
13Dec
10Jan
JointPFRCBLPC
SBInfo
22Mar
tbdMay
JointPFRCBLPC
tbdApr
tbdMay
JointPFRCBLPC
tbdJun
Jan 17
Schematic Design
Approval
Community Forum
tbd
CONCEPT DESIGN SCHEMATIC DESIGN
SiteTour
Dec 10
JointPFRCBLPC
JointPFRCBLPC
21Feb
JointPFRCBLPC
JointPFRCBLPC
JointPFRCBLPC
Apr 5
SBInfo
tbd
Building & Site Design MeetingsTransportation
Meetings
JointPFRCBLPC
Mar 14Cost Meeting
03.22.2018
School Board Info 5 What is being approved at this stage?
Choice of a Design Option and
Corresponding Total Project Estimate
In choosing a design option, the School Board is
conceptually approving:
Building Location:
Specific location and orientation on the site
Building Massing:
General building shape, size, and height
Existing Building:
The amount of reuse, renovation and/or renovation
of existing Reed School building
The School Board is NOT approving the location and
quantity of on-site parking spaces. Building location is
primarily independent of parking.
CONCEPT DESIGNAPPROVAL
Approval of a Specific Design Proposal for
the Building and Site
In accepting the schematic design, the School Board is
approving:
Building Program/Educational Specifications:
Final list of spaces inside the building
Locations of spaces
Building Appearance:
Final shape, size, and height
Exterior elevations and materials
Vehicular:
Quantity and layout of parking
Arrangement of bus and parent drop off / pick up
Service entrance and yard
Use Permit issues to be negotiated with County:
Preliminary suggestions for off-site improvements
Proposed ACG/APS jointly funded items
SCHEMATIC DESIGNAPPROVAL
03.22.2018
School Board Info 6 Existing Conditions
EXISTINGCONDITION
18th St N
Parking Lot (26)
Pee Wee
Softball field
Informal
Playfield
Informal
Playfield
Play-
ground
Upper
Playground
84” diameter
storm sewer
Utility key
Easement
Storm Sewer
Overhead
Powerline
Topography
Vast majority of site drains to a
single low point
30’ drop in elevation from high to
low (equivalent to 2 story bldg.)
Permeability
65% permeable
(246,750 sf of 381,000 sf)
Parking
72 on-site spots
03.22.2018
School Board Info 7
1. 725 Students
2. 100 Stalls Needed
Existing Amenities
Parking
County Open Space
Corner Park
Play Field
Westover Library
Parking Lot
Farmers Market
Commercial Property
Sledding Hill
Playground
Parking Lot
Basketball Courts
Recreation Space
Bank
US Post Office
03.22.2018
School Board Info 8 Issues with existing building & Challenges with building up
Existing Building: 2nd Floor
Existing Building: 1st Floor
Existing building, designed in 2007, was built for a very specific program.
Layout Concerns
Middle portion of the building contains mixed programming in physically separated areas
Circulation to level 2 is remote & elevator is on a public corridor
Teaching and Learning Concerns
Appropriate for early childhood programs, but…
Inefficient layout
Space constrained for older students
Visibility / security (narrow, curved corridors)
Circuitous routes between program spaces
No extended learning or small group instruction areas
Design and Construction Concerns
Only curved section designed to take second floor
4 columns and 13 footings would need to be reinforced
Most interior finishes would be lost due to weather exposure
Even with second floor added, 63K-65K additional square feet needed
03.22.2018
School Board Info 9 Design Process
03.22.2018
School Board Info 10
CONCEPT PHASE COST ESTIMATES
• To ensure that School Board action is based on the most complete and up-
to-date information, final total project cost estimates are prepared at the
end of each project phase by both the Architect / Engineering team (A/E)
and Construction Manager at-Risk (CMR).
• Final concept phase estimates for all six Reed options were higher than
preliminary estimates.
• BLPC and PFRC reviewed cost estimates at March 14 joint meeting.
• At that meeting nearly all BLPC, PFRC, and community members continued
to prefer the Integrated option to the others.
• Final concept phase reconciled total project cost estimate for the Integrated
option is $55.1 million.
03.22.2018
School Board Info 11 Integrated Scheme, site plan
RECOMMENDEDSCHEME
Pros
• Lowest loss of open / permeable
space
• Low transition time between classes
• Lowest total energy use per SF
• Lowest required parking
• Builds up on small footprint
• Keeps the most site amenities
• Preferred by BLPC, PFRC, and
community members
Cons
• Minor utility relocation
• Four-story building next to two-story
building and homes
• Demolishes a portion of an existing
asset that is only 9 years old
03.22.2018
School Board Info 12
PROJECT FUNDING
FY 2017-26CIP1
Concept Design
Major Construction Bonds $ 38,250,000 $ 38,250,000
Capital Reserve $ 4,000,000 $ 4,000,000
Other (Operating)2 $ 1,250,000 $ 1,250,000
ACG/APS Jointly Funded Items $ 5,500,000 $ 5,500,000
TBD3 $ - $ 6,000,000
Total $ 49,000,000 $ 55,000,000
Notes:
1. Approved by the School Board on June 16, 2016.
2. Furniture and equipment that cannot be bond funded.
3. Specific source of funding has not yet been determined.
03.22.2018
School Board Info 13
PROJECT FUNDING
Funding for the construction of the Reed project must still be approved by the voters in the November 2018 referendum.
03.22.2018
School Board Info 14
RECOMMENDATIONS
• Approve the Integrated concept design option including general building
location, massing, and extent of reuse/renovation of the existing building.
• Approve a maximum total project funding of $55 million.
• Reaffirm project criteria for a new neighborhood elementary school with
an attendance zone, a minimum capacity of 725 seats, and a project
completion in time for start of school September 2021.
• Direct staff to proceed to the schematic design phase and charge staff and
BLPC members to complete the project as close to the original $49 million
available funding as possible.