201
AUBURN UNIVERSITY STUDENT LAUNCH Project Nova 211 Davis Hall AUBURN, AL 36849 PRELIMINARY DESIGN REVIEW NOVEMBER 3, 2017

New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

AUBURN UNIVERSITY STUDENT LAUNCH

Project Nova

211 Davis Hall

AUBURN, AL 36849

PRELIMINARY DESIGN REVIEW

NOVEMBER 3, 2017

Page 2: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

2

Table of Contents

Table of Contents ...........................................................................................................................2

List of Figures .................................................................................................................................7

List of Tables ................................................................................................................................10

Section 1: General Information ..............................................................................................14

Section 1.1: Team Information .............................................................................................14

Section 1.2: Adult Educators ................................................................................................14

Section 1.3: Safety Officer ...................................................................................................15

Section 1.4: Team Leader .....................................................................................................16

Section 1.5: Project Organization .........................................................................................16

Section 1.6: NAR/TRA Sections ..........................................................................................19

Section 2: Summary of CDR Report ......................................................................................19

Section 2.1: Team Summary.................................................................................................19

Section 2.2: Launch Vehicle Summary ................................................................................20

Section 2.3: Payload Summary .............................................................................................21

Section 3: Changes Made Since PDR .....................................................................................21

Section 3.1: Vehicle Changes ...............................................................................................21

Section 3.2: Payload Changes...............................................................................................21

Section 3.3: Project Plan Changes ........................................................................................23

Section 4: Launch Vehicle .......................................................................................................23

Section 4.1: Mission Statement ............................................................................................24

Section 4.2: System Level Design Review ...........................................................................24

Page 3: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

3

Section 4.2.1: Structure ..........................................................................................................25

Section 4.2.2: Propulsion .......................................................................................................28

Section 4.2.3: Aerodynamics .................................................................................................31

Section 4.3: Dimensional Drawings .....................................................................................34

Section 4.4: Design Integrity ................................................................................................40

Section 4.4.1: Fin Shape and Style ........................................................................................40

Section 4.4.2: Materials .........................................................................................................41

Section 4.4.3: Assembly Procedures ......................................................................................43

Section 4.5: Mass Statement .................................................................................................44

Section 5: Subscale Flight Results ..........................................................................................45

Section 5.1: Flight Data ........................................................................................................45

Section 5.2: Scaling Factors .................................................................................................46

Section 5.3: Subscale Analysis .............................................................................................46

Section 5.4: Impact on Full-Scale Design ............................................................................48

Section 6: Recovery System Design ........................................................................................49

Section 6.1: Structural Elements...........................................................................................49

Section 6.2: Materials ...........................................................................................................51

Section 6.3: Ejection .............................................................................................................54

Section 6.4: Parachutes .........................................................................................................58

Section 6.5: Altimeters .........................................................................................................62

Section 7: Mission Performance Predictions .........................................................................65

Section 7.1: Simulations .......................................................................................................65

Page 4: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

4

Section 7.1.1: Motor Thrust Curve ........................................................................................69

Section 7.1.2: Component Weights .......................................................................................70

Section 7.1.3: Stability ...........................................................................................................71

Section 7.1.4: Computational Fluid Dynamics ......................................................................72

Section 7.2: Kinetic Energy ..................................................................................................75

Section 7.3: Drift ..................................................................................................................76

Section 7.4: Simulation Verification ....................................................................................79

Section 8: Safety .......................................................................................................................79

Section 8.1: Pre-Launch Day Items Checklist ......................................................................79

Section 8.2: Preassembly Checklists ....................................................................................81

Section 8.2.1: Recovery .........................................................................................................81

Section 8.2.2: Altitude Control ..............................................................................................82

Section 8.2.3: Body ................................................................................................................82

Section 8.2.4: Rover ...............................................................................................................83

Section 8.2.5: Engine .............................................................................................................84

Section 8.3: Launch Vehicle Assembly and Check ..............................................................84

Section 8.4: Launcher Setup and Launch Procedure ............................................................86

Section 8.4.1: Launcher Setup ...............................................................................................86

Section 8.4.2: Launch Procedure ...........................................................................................87

Section 8.5: Post-flight Inspection ........................................................................................88

Section 8.6: Personnel Safety Hazards .................................................................................89

Section 8.7: Environmental Effects ......................................................................................93

Page 5: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

5

Section 8.7.1: Effects on Environment ..................................................................................93

Section 8.7.2: Effects of Environment ...................................................................................94

Section 8.8: Failure Modes ...................................................................................................95

Section 9: Rover .....................................................................................................................114

Section 9.1: Mechanical Design .........................................................................................114

Section 9.1.1: Body ..............................................................................................................115

Section 9.1.2: Movement .....................................................................................................118

Section 9.1.3: Solar Panel Deployment System (SPDS) .....................................................120

Section 9.2: Electrical Design .............................................................................................123

Section 9.2.1: Microcontroller .............................................................................................124

Section 9.2.2: Communication Method ...............................................................................124

Section 9.2.3: Orientation ....................................................................................................126

Section 9.2.4: Power ............................................................................................................127

Section 10: Altitude Control Module .....................................................................................128

Section 10.1: Drag Plates ......................................................................................................129

Section 10.1.1: Internal Plate Drag System (IPDS) .............................................................129

Section 10.1.2: Wall Armed Fin-Lattice Elevator (WAFLE) ..............................................131

Section 10.1.3: Spherical Joint Actuator (SJA) ...................................................................133

Section 10.1.4: System Comparison ....................................................................................134

Section 10.2: Drag Plate Deployment ..................................................................................135

Section 10.3: Components ....................................................................................................136

Section 10.3.1: Controller ....................................................................................................136

Page 6: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

6

Section 10.3.2: Motor ..........................................................................................................141

Section 10.3.3: Electronics ..................................................................................................142

Section 10.3.4: Interfaces .....................................................................................................143

Section 10.3.5: Precision of Instrumentation .......................................................................143

Section 10.4: Dimensional Drawings ...................................................................................144

Section 11: Project Plan ..........................................................................................................144

Section 11.1: Testing ............................................................................................................144

Section 11.1.1: Rover Battery and Motor Test (AU 4.4, 4.5) ..............................................145

Section 11.1.2: Recovery and Altitude Control Battery Tests (AU 3.1, 6.9) ......................147

Section 11.1.3: Full-Scale and Subscale Separation Test (AU 3.2) .....................................148

Section 11.1.4: Tension Testing of Composite and 3D Printed Material (AU 2.1, 2.2) ......151

Section 11.1.5: 3-Point Bend Testing of Composite and 3D Printed Material (AU 2.1, 2.2,

6.7) .......................................................................................................................................154

Section 11.1.6: Compression Testing of Composite and 3D Printed Material (AU 2.1, 2.2,

6.7) .......................................................................................................................................158

Section 11.1.7: Rover Maneuverability (AU 4.2, 4.3, 4.6, 4.7) ...........................................160

Section 11.1.8: Altitude Control System (AU 6.4 – 6.8) .....................................................161

Section 11.2: Requirements Verification ..............................................................................163

Section 11.2.1: General Requirements .................................................................................163

Section 11.2.2: Vehicle Requirements .................................................................................169

Section 11.2.3: Recovery Requirements ..............................................................................179

Section 11.2.4: Deployable Rover Requirements ................................................................185

Page 7: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

7

Section 11.2.5: Safety Requirements ...................................................................................186

Section 11.3: Team Requirements ........................................................................................188

Section 11.3.1: General Requirements .................................................................................188

Section 11.3.2: Vehicle Requirements .................................................................................189

Section 11.3.3: Recovery Requirements ..............................................................................190

Section 11.3.4: Deployable Rover Requirements ................................................................190

Section 11.3.5: Safety Requirements ...................................................................................192

Section 11.3.6: Altitude Control Requirements ...................................................................193

Section 11.4: Budget .............................................................................................................195

Section 11.5: Funding Plan ...................................................................................................199

Section 11.6: Timeline ..........................................................................................................200

List of Figures

Figure 1.1: Team Organization Chart ........................................................................................... 17

Figure 3.1: Rover Body Comparison ............................................................................................ 22

Figure 3.2: Rover Domes vs Without ........................................................................................... 22

Figure 3.3: Rover Bay Comparison .............................................................................................. 23

Figure 4.1: Vehicle Rendering ...................................................................................................... 23

Figure 4.2: Motor Tube Rendering ............................................................................................... 28

Figure 4.3: Motor Thrust Curve .................................................................................................... 29

Figure 4.4: Motor Retention ......................................................................................................... 31

Page 8: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

8

Figure 4.5: Fin Rendering ............................................................................................................. 32

Figure 4.6: Booster Tube Dimensional Drawing .......................................................................... 34

Figure 4.7: Engine Block Dimensional Drawing .......................................................................... 35

Figure 4.8: Lower Booster Section Dimensional Drawing ........................................................... 36

Figure 4.9: Upper Body Tube Dimensional Drawing ................................................................... 37

Figure 4.10: Upper Section Assembly Dimensional Drawing...................................................... 38

Figure 4.11: Centering Ring Dimensional Drawing ..................................................................... 39

Figure 4.12: Bulkhead Dimensional Drawing .............................................................................. 39

Figure 4.13: Fin Dimensional Drawing ........................................................................................ 40

Figure 4.14: Fin Shapes ................................................................................................................ 41

Figure 5.1: Subscale Flight Data ................................................................................................... 45

Figure 5.2: Initial Subscale Design ............................................................................................... 46

Figure 6.1: Redundant Jolly Logic System ................................................................................... 56

Figure 6.2: Jolly Logic Chute Release .......................................................................................... 57

Figure 6.3: Gore Template ............................................................................................................ 60

Figure 6.4: Parachute Template .................................................................................................... 60

Figure 6.5: Altus Metrum TeleMega Altimeter ............................................................................ 63

Figure 6.6: Altus Metrum TeleMetrum Altimeter ........................................................................ 63

Figure 6.7: Altimeter Block Diagram ........................................................................................... 64

Figure 7.1: OpenRocket Model..................................................................................................... 65

Figure 7.2: Altitude Vs. Time ....................................................................................................... 67

Figure 7.3: Velocity Vs. Time ...................................................................................................... 68

Page 9: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

9

Figure 7.4: Acceleration Vs. Time ................................................................................................ 69

Figure 7.5: Motor Thrust Curve .................................................................................................... 70

Figure 7.6: Stability Vs. Time....................................................................................................... 72

Figure 7.7: Nosecone Meshing ..................................................................................................... 74

Figure 7.8: Tail-fin Meshing ......................................................................................................... 74

Figure 9.1: Rover Overview “top side” ...................................................................................... 115

Figure 9.2: Rover Overview “bottom side” ................................................................................ 115

Figure 9.3: First Iteration of the Rover Body “top side” ............................................................ 116

Figure 9.4: First Iteration of the Rover Body “bottom side” ...................................................... 116

Figure 9.5: Rover Body Dimensions .......................................................................................... 118

Figure 9.6: Rover Wheels and Tread .......................................................................................... 118

Figure 9.7: MATLAB Script....................................................................................................... 119

Figure 9.8: Rover Motor Inset .................................................................................................... 120

Figure 9.9: SPDS Stowed vs Deployed ...................................................................................... 121

Figure 9.10: SPDS Deployed Position Overview ....................................................................... 121

Figure 9.11: Solar Panel Tray, Motor, and Gear......................................................................... 123

Figure 9.12: Rover Electrical Layout.......................................................................................... 124

Figure 9.13: X-Bee Module ........................................................................................................ 125

Figure 9.14: X-Bee Shield Module on Arduino .......................................................................... 125

Figure 9.15: X-Bee Setup ........................................................................................................... 126

Figure 9.16: Rover Battery Setup ............................................................................................... 128

Figure 10.1: IPDS System Concept ............................................................................................ 130

Page 10: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

10

Figure 10.2: IPDS Bottom-Up View .......................................................................................... 130

Figure 10.3: WAFLE .................................................................................................................. 132

Figure 10.4: Spherical Joint Actuator ......................................................................................... 133

Figure 10.5: SJA External Fairing .............................................................................................. 134

Figure 10.6: Arduino Uno Microcontroller ................................................................................ 137

Figure 10.7: IMU Breakout......................................................................................................... 137

Figure 10.8: AndyMark NeveRest 40 DC Motor ....................................................................... 141

Figure 11.1: Subscale Separation Test ........................................................................................ 150

Figure 11.2: Epoxy - Carbon Fiber Tension Test Results .......................................................... 152

Figure 11.3: Epoxy - Fiberglass Tension Test Results ............................................................... 153

Figure 11.4: Onyx Tension Test Results..................................................................................... 154

Figure 11.5: Epoxy - Carbon Fiber Bend Test Results ............................................................... 156

Figure 11.6: Epoxy - Fiberglass Bend Test Results .................................................................... 157

Figure 11.7: Onyx Bend Test Results ......................................................................................... 157

Figure 11.8: Spending Comparison ............................................................................................ 198

Figure 11.9: Fall Timeline .......................................................................................................... 200

Figure 11.10: Spring Timeline .................................................................................................... 201

List of Tables

Table 1.1: Team Members ............................................................................................................ 17

Table 2.1: Team Information ........................................................................................................ 19

Table 2.2: Mentor Information ..................................................................................................... 20

Page 11: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

11

Table 2.3: Launch Vehicle Information ........................................................................................ 20

Table 4.1: Section Lengths ........................................................................................................... 25

Table 4.2: Motor Specifications .................................................................................................... 29

Table 4.3: Fin Dimensions ............................................................................................................ 32

Table 4.4: Manufacturing Schedule .............................................................................................. 43

Table 4.5: Mass Estimations ......................................................................................................... 44

Table 5.1: Subscale Launch Data vs Simulation .......................................................................... 47

Table 6.1: Pugh Chart of Carbon Fiber vs. Fiberglass Material for the BAE............................... 50

Table 6.2: Parachute Materials Pugh Chart .................................................................................. 51

Table 6.3: Comparison of Paracord, Tubular Nylon, Kevlar ........................................................ 53

Table 6.4: Comparison of U-bolts and Eye-bolts ......................................................................... 54

Table 6.5: Comparison of Black Powder and CO2 ....................................................................... 54

Table 6.6: Parachute Shape Pugh Chart ........................................................................................ 59

Table 6.7: Parachute Dimensions ................................................................................................. 61

Table 7.1: Flight Simulation Data (Wind = 0 mph) ...................................................................... 66

Table 7.2: Component Weights .................................................................................................... 70

Table 7.3: CFD Drag Coefficient Results ..................................................................................... 75

Table 7.4: Drift Calculations for Upper Section ........................................................................... 78

Table 7.5: Drift Calculations for Lower Section .......................................................................... 78

Table 10.1: Drag System Comparison ........................................................................................ 134

Table 10.2: Arduino Options ...................................................................................................... 136

Table 10.3: Microcontroller Data ............................................................................................... 138

Page 12: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

12

Table 10.4: Normalization of Data ............................................................................................. 138

Table 10.5: Trade Study Weighting Factors ............................................................................... 139

Table 10.6: Sensor Trade Study (Normalized Values) ............................................................... 140

Table 10.7: Sensor Trade Study (Weighted Values) .................................................................. 140

Table 10.8: AndyMark NeveRest 40 .......................................................................................... 141

Table 10.9: Uxcell 40 RPM 24V Motor (Alternative) ................................................................ 142

Table 10.10: New Guanlian RE 40 (Alternative) ....................................................................... 142

Table 11.1: General Requirements Verification ......................................................................... 163

Table 11.2: Vehicle Requirements Verification ......................................................................... 169

Table 11.3: Recovery Requirements Verification ...................................................................... 179

Table 11.4: Deployable Rover Requirements Verification ......................................................... 185

Table 11.5: AU General Requirements ....................................................................................... 188

Table 11.6: AU Vehicle Requirements ....................................................................................... 189

Table 11.7: AU Recovery Requirements .................................................................................... 190

Table 11.8: AU Rover Requirements.......................................................................................... 190

Table 11.9: AU Altitude Control Requirements ......................................................................... 193

Table 11.10: Vehicle Costs ......................................................................................................... 195

Table 11.11: Recovery Costs ...................................................................................................... 196

Table 11.12: Rover Costs ............................................................................................................ 197

Table 11.13: Budget Allocation .................................................................................................. 198

Table 11.14: Funding Sources .................................................................................................... 199

Page 13: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

13

Page 14: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

14

Section 1: General Information

Section 1.1: Team Information

General Team Information

Team Affiliation Auburn University

Mailing Address 211 Engineering Drive

Auburn, AL 36849

Title of Project Project Nova

Date of CDR January 12th, 2018

Experiment Option 2: Deployable Rover

Section 1.2: Adult Educators

Contact Information

Name Dr. Brian Thurow

Title Aerospace Engineering Department Chair, Faculty

Advisor

Email [email protected]

Phone 334-844-4874

Address 211 Davis Hall

Auburn, AL 36849

Page 15: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

15

Contact Information

Name Dr. Eldon Triggs

Title Lecturer, Aerospace Engineering, Mentor

Email [email protected]

Phone 334-844-6809

Address 211 Davis Hall

Auburn, AL 36849

Section 1.3: Safety Officer

Safety Officer – Contact Information

Name Corey Ratchick

Title Senior in Aerospace Engineering

Auburn University

Email [email protected]

Corey Ratchick will be the Safety Officer for the Auburn Student Launch team this year. It is his

third year on the team. His goal for the year is to provide more exhaustive checklists than the team

has had access to in the past in an attempt to minimize human error.

Page 16: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

16

Section 1.4: Team Leader

Student Team Lead – Contact Information

Name Tanner Straker

Title Senior in Aerospace Engineering

Auburn University

Email [email protected]

Phone 847-507-1193

Address 211 Engineering Dr.

Auburn, AL 36849

Tanner Straker will be the student team leader for this year’s competition team. This is Tanner’s

third year on the team. In the previous year, Tanner served as the Recovery team leader and

oversaw the successful recovery of the team’s rocket throughout the year and during the

competition flight. He enjoys long walks across launch sites and sewing parachutes. Tanner is level

one high power rocket certified through Tripoli Rocketry Association.

Section 1.5: Project Organization

The Auburn Student Launch team is broken into five major sub-teams: vehicle body design,

payload, electronic systems, testing, and recovery. Safety and educational engagement also exist

as sub-teams composed of students from the five primary groups. Each sub-team has at least one

member dedicated to identifying safety concerns and acting as the point of contact (POC) for the

safety officer. In addition, all members of the Auburn Student Launch Team are required to

participate in at least one educational engagement event and each event has its own coordinator,

Page 17: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

17

all of whom are working members of other sub-teams. Figure 1.1: Team Organization Chart shows

the hierarchy of project management with all teams reporting to their team leads, the student

project manager, and the safety officer, who in turn report to the adult educators.

Figure 1.1: Team Organization Chart

Table 1.1: Team Members

Name Role Team

Dr. Eldon Triggs Adult Educator Overall Management

Dr. Brian Thurow Adult Educator Overall Management

Tanner Straker Project Manager Overall Management

Corey Ratchick Safety Officer Overall Management/Safety

Reilly B. Team Lead Vehicle Body

Tanner O. Team Lead Electronic Systems

David T. Team Lead Payload

Page 18: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

18

Ben C. Team Lead Recovery

Bryce G. Team Lead Testing

Kate M. Team Lead Education

Nick R. Team Member Testing

Zac B. Team Member Education

Icis M. Team Member Education

Jaylene A. Team Member Education

Jake R. Team Member Safety

Rhett R. Team Member Safety

Ruth A. Team Member Safety

Sydney F. Team Member Safety

Zach W. Team Member Recovery

Paul L. Team Member Recovery

Omkar M. Team Member Recovery

Jaysal S. Team Member Recovery

Bill M. Team Member Vehicle Body

Adam B. Team Member Vehicle Body

CJ L. Team Member Vehicle Body

Matthew D. Team Member Vehicle Body

Logan J. Team Member Vehicle Body

Anthony G. Team Member Vehicle Body

Victor D. Team Member Vehicle Body

Rhett R. Team Member Payload

Stephen S. Team Member Payload

Zach S. Team Member Payload

Kevin H. Team Member Payload

Page 19: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

19

Matthew W. Team Member Payload

Landon B. Team Member Payload

Salaar K. Team Member Electronic Systems

Andrew R. Team Member Electronic Systems

Ruth A. Team Member Electronic Systems

Michael C. Team Member Electronic Systems

Austen L. Team Member Electronic Systems

Matthew H. Team Member Electronic Systems

Section 1.6: NAR/TRA Sections

The Auburn Student Launch team is planning on attending launches hosted by Southern Area

Rocketry (SoAR) at Phoenix Missile Works (PMW) in Sylacauga Alabama (NAR Section #571).

The team also occasionally attends launches with the Music City Missile Club (MC2) in

Manchester, Tennessee (NAR Section #589) and the South Eastern Alabama Rocket Society

(SEARS) in Samson, Alabama (NAR Section #572/TRA Prefect 38). We will also be partnering

with SEARS through Christopher Short. Chris provides technical experience and serves as a

reliable rocketry vendor for the team.

Section 2: Summary of CDR Report

Section 2.1: Team Summary

Table 2.1: Team Information

Team Information

Team Name Auburn University Student Launch (AUSL)

Page 20: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

20

Mailing Address 211 Engineering Drive

Auburn, AL 36849

Project Name Project Nova

Table 2.2: Mentor Information

Mentor Information

Mentor Name Eldon Triggs

TRA Number 12159

Certification Level 2

Contact Information Email: [email protected]

Phone: 334-844-6809

Section 2.2: Launch Vehicle Summary

Table 2.3: Launch Vehicle Information gives the basic details of the launch vehicle. More

information regarding the launch vehicle can be found in Section 4: Launch Vehicle of this report.

Table 2.3: Launch Vehicle Information

Launch Vehicle Information

Total Length 108 in.

Estimated Mass 40.5 lbm

Motor Selection Aerotech L1420R

Recovery System Double Separation, Dual Deployment

Page 21: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

21

Rail Size 12 ft. 1515

Section 2.3: Payload Summary

Auburn University's Student Launch team will be completing the deployable rover experiment.

After landing under parachute, the rover that will be completely housed inside the rocket will be

remotely deployed from the rocket. It will autonomously travel at least five feet from the rover and

deploy foldable solar panels. A dual-tread design deployed from an orientation-independent

containment bay has been chosen to minimize the possibility of error and risk within the system

Section 3: Changes Made Since PDR

Section 3.1: Vehicle Changes

The vehicle design has not changed substantially since PDR. The team has stopped considering a

grid fin design for the tail fins and will continue with a clipped delta fin planform. This decision

was made due to the performance of clipped delta fins and in favor of focusing efforts on the

isogrid weave body tube structure. Mass estimates have also been adjusted due to experience with

gained from constructing a subscale vehicle.

Section 3.2: Payload Changes

Due to extensive trade studies done during PDR, minimal changes have been made to the overall

design of the rover. However, based on further research, some components have been changed or

removed entirely. The following figures show changes made to the mechanical design of the rover.

The body design was changed to provide more space for electronics, the treads had an external

dome removed that was deemed unnecessary, and the rover bay was modified to account for

Page 22: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

22

different orientations upon landing. Some electronics that had scored comparably in the PDR trade

studies have also been substituted for the team’s initial choices due to experience with them.

Figure 3.1: Rover Body Comparison

Figure 3.2: Rover Domes vs Without

Page 23: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

23

Figure 3.3: Rover Bay Comparison

Section 3.3: Project Plan Changes

The team has secured additional support from Lockheed Martin, so the budget and funding plan

have been updated accordingly. Several tests, including a subscale flight, have also been completed

and this is reflected in the team’s updated timeline.

Section 4: Launch Vehicle

Figure 4.1: Vehicle Rendering

The Auburn University Student Launch team (AUSL) is determined to design and manufacture an

effective and unique launch vehicle. Learning from past experiences and Auburn’s history with

Page 24: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

24

the competition, AUSL has re-examined every component of the launch vehicle. AUSL requires

the highest quality of all components to reach the goals set by NASA in this year’s competition.

Section 4.1: Mission Statement

The mission of the AUSL launch vehicle is to design and construct a lightweight, safe, and reliable

vehicle. These motivators will ensure a vehicle that will allow for successful launches and the

flexibility to adapt the design to various experimental payloads. Three driving requirements from

the NASA Student Launch Handbook have been chosen to guide the success of this mission:

1. The vehicle must have an apogee of 5280 feet AGL

2. The vehicle must be recoverable and reusable.

3. The vehicle will not exceed Mach 1 during flight.

These requirements serve as minimum standards set to achieve mission success. AUSL has also

determined three team-specific requirements to drive the design of the launch vehicle:

1. The vehicle must maintain stability of 2 or more calibers.

2. The vehicle must have a factor of safety of at least 2.

3. Structural components must remain attached to launch vehicle.

These team requirements serve as additional constraints to assure the vehicle design is compatible with

the mission.

Section 4.2: System Level Design Review

The vehicle has been designed to satisfy mission requirements set forth by NASA in the 2017-

2018 NASA Student Launch Handbook, as well as requirements set by the team. The vehicle

design must ensure adequate space for avionics, payload equipment, and electronics. These

Page 25: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

25

systems are crucial to the success of the mission. The vehicle design is also heavily driven by

manipulating weight and length to control altitude and stability. These factors determine the

success of the flight itself. The vehicle design is separated into three major divisions: structure,

propulsion and aerodynamics. These three divisions are all vital to the success of the flight and

recovery of the launch vehicle, as well as the success of the onboard experiments.

Section 4.2.1: Structure

The structure of the launch vehicle has been designed to be able to withstand the forces the rocket

will experience during operation. The launch vehicle body must be strong enough to maintain

stable flights, while accommodating all other subsystems, and ensuring they have adequate space

and protection. The design of the structure requires heavy tradeoffs between strength, space, and

weight.

The total length of the rocket is 108.0 inches. Component lengths are shown in Table 4.1: Section

Lengths.

Table 4.1: Section Lengths

Body Tubes:

Section Length (in.)

Nose Cone 16

Avionics Section 47

Rover Section 16

Airbrake Section 10

Booster Section 19

Total 108

Page 26: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

26

The body tubes house all subsystems of the launch vehicle. These tubes comprise a majority of the

vehicle body surface exposed to the airflow. Therefore, the aerodynamic properties of the body

tubes are directly related to the altitude gained by the vehicle. Additionally, as the largest structure

in the rocket, the body tubes represent the largest collection of mass in the rocket, except for the

motor. To ensure mission success, it is critical to select and design body tubes that can survive the

stresses of high-powered flight while remaining light enough to achieve the mission altitude.

The body tubes will be constructed using carbon fiber braiding, a process that involves taking

individual strands of carbon fiber and stitching them into a tightly-wound braid. The carbon fiber

braids that are produced will be formed into an isogrid structure around a 6-inch mandrel, which

will be pre-wrapped with a layer of carbon fiber already to make bonding the internal systems to

the body tubes easier. Isogrid structures are a lighter alternative to using a solid tube structure. For

aerodynamic purposes, a thin layer of fiber glass will be cured and wrapped around the structure

to allow for a smooth aerodynamic skin. By giving the structure this skin, the result is a lightweight,

aerodynamic body. Using this wrapped isogrid method, the mass of the body tubes will be

decreased by approximately 20 to 30 percent less than if the tubes were constructed using only

filament wound carbon fiber, while also maintaining the same compressive strength properties as

a carbon fiber tube. This mass reduction was confirmed using tube samples constructed by team

members using final production methods.

Couplers:

The couplers serve as a joint between two body tube sections. The couplers must be able to

withstand forces experienced during rocket ascent to keep the structure of the body attached. The

upper body tube will be attached to the booster section with 4 aluminum bolts. The team has

decided to use fiber glass to create the couplers. This choice of material reduces risks which can

lead to separation of the upper body from the booster section in mid-flight. With the trade-off of

an increase in mass and more difficult construction for strength, fiber glass was considered to be a

very safe and reliable option. Fiber glass also has the additional benefit of being non-conductive,

thus it will be ideal for making the coupler which will be holding our electronics, the avionics bay.

Page 27: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

27

This will reduce the issues the team has had in the past when it comes to being able to communicate

to the electronics inside the vehicle, such as GPS systems.

Ballast Tank:

The ballast tank is used to hold additional mass if balance corrections must be made. The design

allows for easy mass addition and reduction as needed to account for variations in mass predictions

and launch day conditions. The tank will be placed forward of the grid fin section, near the CG

location, and is secured to the launch vehicle body by two aluminum pins. As the tank will not be

subjected to a large force, the team is confident that the pins will hold the tank securely without

fear of a shear failure. The tank will be constructed using high impact polystyrene (HIPS) on a

TAZ4 3D printer.

Bulkheads:

Bulkheads are typically flat plates used to increase the structural strength of a rocket. They are also

used to create airtight spaces and to divide the body into separate compartments. In rockets, they

are commonly used to separate payload bays and to mount equipment for avionics and payloads.

For rockets similar in size to the Project Nova rocket, the material used varies from fiberglass to

plywood to carbon fiber. The bulkheads for this rocket will be made from pre-impregnated carbon

fiber. This was chosen due to the simplicity of manufacturing with pre-impregnated carbon fiber.

The interior diameter for the circular cross-sectional rocket will be 6 inches and the bulkheads are

designed to fit perfectly into this size. All bulkheads for this rocket will be 0.25 inches thick.

Centering Rings:

The purpose of the centering rings is to center a smaller cylindrical body or tube inside a tube of a

larger diameter. In the case of high powered model rocketry, centering rings can be used as an

engine block in motor mounts. The Project Nova rocket will be using three centering rings. These

Page 28: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

28

centering rings are located in the engine tube and serve to attach to the fin set and to attach to the

motor retention. The centering rings are made of carbon fiber and manufactured using the

Computer Numerical Control (CNC) machine at Auburn University Aerospace Design Lab due to

the availability and the teams experience with using carbon fiber. The centering rings have an outer

diameter of 6 inches with an inner diameter of 3 inches. The thickness of each ring is approximately

0.25 inch. The centering rings have a mass of 3.65 oz., determined from sample pieces.

Section 4.2.2: Propulsion

Figure 4.2: Motor Tube Rendering

Motor:

The motor selected for the competition is the Aerotech L1420R. This is the same motor that was

used in PDR, and after minor modifications were made to the rocket, it still gave us the needed

altitude for the rocket. The specifications are listed below in Table 4.2: Motor Specifications.

Additionally, the thrust curve for this motor is shown in Figure 4.3: Motor Thrust Curve.

Page 29: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

29

Figure 4.3: Motor Thrust Curve

This motor was chosen based on OpenRocket simulations, as it provides the roughly 8-to-1 thrust-

to-weight ratio desired for stable and predictable flight.

In addition, as shown in the motor thrust curve above, the motor achieves a higher than average

thrust after approximately one-quarter second, thus reaching the required 8-to-1 thrust ratio in

about one-quarter second. Based on OpenRocket simulations, the motor provided an apogee of

5866 feet with a max acceleration of 275 ft/s^2 which delivers a max velocity of 723 ft/s or close

to Mach = 0.65.

Table 4.2: Motor Specifications

Motor Specifications

Manufacturer Aerotech

Motor Designation L1420R

Diameter 2.95 in

Length 17.4 in

Page 30: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

30

Total Impulse 1038 lb·sec

Total Motor Weight 10.1 lbm

Propellant Weight 5.69 lbm

Propellant Type Solid

Average Thrust 326 lbf

Maximum Thrust 374 lbf

Burn Time 3.18 sec

Motor Tube:

To contain the motor on the rocket, a carbon fiber motor tube is being used. The motor tube will

be made by braiding carbon fiber strands and then filament wound around a mandrel that is the

same diameter of the motor. The 3D braided carbon fiber material was chosen for its strength

relative to its weight when compared to a solid tube. Basalt fiber was considered to be used for the

motor tube for its high heat resistance properties, but the team decided the weight of the basalt,

which was approximately 50% heavier when compared with the carbon fiber was not worth the

tradeoff. The tube will be 0.1-inch-thick and is designed to fit around an Aerotech L1420R motor.

With these specifications, the motor tube will be ideal for the rocket.

To mount the motor tube, three centering rings will be epoxied to the outer diameter of the motor

tube and the inner diameter of the lower section tube. The epoxy will be a 24-hour epoxy, which

will create a permanent bond between the components. A bulk plate will be epoxied forward of

the motor tube. This is to provide extra strength to hold the motor in place as well as separate the

motor from the internal components of the rocket.

Motor Retention:

The purpose of the motor retention system is to secure the rocket motor during launch and flight

and to be easily removable for subsequent flights. The team has chosen a commercial bought

Aeropack motor retention system, Figure 4.4: Motor Retention. This is a simple system with two

Page 31: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

31

components. One component will bolt directly into a centering ring, using aluminum bolts. The

other component threads onto the part that is bolted onto the structure. This allows for a fast

replacement of a used motor. The team chose a commercial motor retention system due to past

reliability and to avoid the time requirements of designing and manufacturing a custom system.

Figure 4.4: Motor Retention

Section 4.2.3: Aerodynamics

The aerodynamics system requires the rocket remain stable during flight. The placement and

design of the aerodynamic surfaces determines the center of pressure along the length of the rocket.

Fins:

The stability of the rocket is controlled by the fins. The primary purpose of the fins is to keep the

center of pressure aft of the center of gravity. The greater drag on the fins will keep them behind

the upper segments of the vehicle, thus allowing the rocket to fly straight along the intended flight

path. They are also helpful in minimizing the chances of weather-cocking. Fins serve as an ideal

addition to the vehicle body as they are lightweight and easy to manufacture using the CNC

Page 32: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

32

machine. A clipped delta planform has been selected for the fins. Four fins will be machined from

0.2-inch-thick carbon fiber flat plates. A rendering of the fin design is shown in Figure 4.5: Fin

Rendering.

When attached, the trailing edge of each fin will be located slightly forward of the end of the body

tube. This design feature will theoretically provide some impact protection for the fins when the

rocket hits ground. Carbon fiber of 1.03 oz/in3 density has been selected as the material due to its

stiffness, strength, and light weight. The stiffness and strength of carbon fiber reduces change of

fin flutter which increases the vehicles chance of success during flight. Each fin will have a surface

area of 54 in2 (summing both sides), making the fin surface area total equal to 216 in2. The total

component mass is 13.5 ounces. These dimensions provide the vehicle with a projected stability

of 2.1 calibers. This level of stability is close to ideal, as it is well above stable, yet still below

over-stable. Detailed fin dimensions are provided in Table 4.3: Fin Dimensions.

Table 4.3: Fin Dimensions

Fin Dimensions

Root Chord 6.25 in

Tip Chord 2.5 in

Figure 4.5: Fin Rendering

Page 33: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

33

Height 6 in

Sweep 3.68 in

Sweep Angle 31.5°

Thickness .2 in

Aero-elastic flutter has been considered as a potential failure mode for the rocket structure. At a

particularly high velocity, the air is no longer able to sufficiently dampen the vibrational energy

within the fin. At this flutter velocity, the first neutrally stable oscillations are experienced within

the wings.

The flutter velocity is directly reflective of the aero-elastic conditions of the structure/fin system.

The catastrophic flutter phenomenon results from coupling of aerodynamic forces creating a

positive feedback loop. The increase in either torsion or bending drives an infinitely looped

increase in the other motion. Since it is assumed that the fins are rigidly fixed and cantilevered to

an infinitely stiff rocket body, the fin twist (torsion) and fin plunge (bending) are the only two

degrees of freedom.

Once this flutter velocity is exceeded, the air, inversely, amplifies the oscillations and significantly

increases the energy within the respective fin. As velocity increases, the fin twist and plunge are

no longer damped. At this velocity, known as the divergent speed, one degree of freedom usually

diverges while the other remains neutral. Structural failure usually occurs at or just above this

velocity. Due to certain failure of the structure associated with potential aero-elastic flutter, the

flutter velocity is applied to the design as a “never-to-exceed” parameter.

There are various ways to minimize the chances of experiencing fin flutter. Increasing fin retention

by strengthening the joints between the fins and rocket body is one way to supplement system

stability. Furthermore, additional layers of carbon fiber and epoxy applied to portions of the fins

as well as the joints should provide extra defense against aero-elastic flutter.

Nosecone:

Page 34: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

34

The coefficient of drag affects the overall performance of the rocket in flight. The goal for the team

was to select a nose cone shape with a low drag coefficient to maximize performance. Utilizing

the software OpenRocket, the four cone types were compared using the already chosen dimensions

for the rocket. The team has decided to increase the fineness ratio of the nosecone, increasing to a

near 5-to-1 ratio versus the initially designed near 3-to-1 ratio. This change has been made due to

the increased stability that a 5-to-1 provides, and the team can easily acquire these nose cones by

purchasing them from several vendors. The material for the nose cone has also changed to being

fiber glass, as this is the most common material sold by these vendors.

Section 4.3: Dimensional Drawings

Figure 4.6: Booster Tube Dimensional Drawing

Page 35: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

35

Figure 4.7: Engine Block Dimensional Drawing

Page 36: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

36

Figure 4.8: Lower Booster Section Dimensional Drawing

Page 37: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

37

Figure 4.9: Upper Body Tube Dimensional Drawing

Page 38: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

38

Figure 4.10: Upper Section Assembly Dimensional Drawing

Page 39: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

39

Figure 4.11: Centering Ring Dimensional Drawing

Figure 4.12: Bulkhead Dimensional Drawing

Page 40: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

40

Figure 4.13: Fin Dimensional Drawing

Section 4.4: Design Integrity

Section 4.4.1: Fin Shape and Style

The three most common planforms are clipped delta, trapezoidal and elliptical, as shown in Figure

4.14: Fin Shapes. In most situations, the elliptical fin design is the optimal design choice for model

rockets. This is due to their lower drag and superior lift forces compared to various other fin

designs, allowing for the highest altitudes. The downside, however is a far lower stability, and as

previously mentioned, the drag is needed for better stability and a solid flight path. Most

importantly, there is little room for error when it comes to the construction of an elliptical fin. So,

if all four fins are not identical in shape and weight then this will lead to undesirable flight results.

Another variable the team considered while designing the fins is fin flutter. The excessive amounts

of fin flutter in elliptical shaped fins only causes more instability. So, even with the advantage of

an optimal altitude, it does not justify the several other complications that will arise during the

Page 41: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

41

construction process. The clipped-delta fin, being a variation of the trapezoidal fin, gives excellent

stability, offering a slight stability advantage over the plain trapezoidal due to having more surface

area aft of the chord of the fins midpoint. The simplicity of the clipped-delta fin design also allows

for an easy and accurate construction process. Though elliptical fins do give a slight advantage

when it comes to altitude, the team has decided to implement the clipped-delta fin design due to

its increased stability.

Figure 4.14: Fin Shapes

The fins will be manufactured from the same carbon fiber plates as the bulkheads and centering

rings. The same data used to verify the bulkheads and centering rings will be used to ensure the

fins can withstand any inflight or landing forces.

To verify that the size and shape of the fins allows for stable flight, simulations were conducted.

There have also been two subscale flights which further verified the simulation data. Multiple full

scale test flights will be performed to visually verify no anomalies are present on the fins during

flight.

Section 4.4.2: Materials

Body Tubes:

Page 42: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

42

The structural tubes of the launch vehicle are going to be constructed using a 3D braided carbon

fiber isogrid structure. As this is something the team has not done in past years, structural data will

need to be collected for this structure. To do this, using the same material and manufacturing

method, a test sample will be made consisting of an equal diameter of the tubes that will be used

on the launch vehicle. This sample will then be placed into a load cell to determine the maximum

load of the structure. This will allow us to determine that the structure is capable of safely

completing the mission. The structure will experience a maximum of 300 lbs during flight, to meet

the factor of safety requirements the tube structure must fail at or above 600 lbs of force during

testing.

Bulkheads and Centering Rings:

The bulkheads and centering rings are manufactured by cutting a flat carbon fiber plate with a

CNC machine. To verify these components can handle the expected loads, sample pieces of the

carbon fiber have been made. These samples were manufactured using the same material that the

bulkheads and centering rings will be made of. The samples were placed in a three-point bending

test as well as a tensile stress test.

Coupler:

To verify the coupler functions correctly, ground tests of the separation will be performed. Once

proven on the ground, a subscale flight test using this coupler component will be used.

Ballast Tank:

By running simulations, the team is able to determine where the center of gravity is located. Once

the launch vehicle is manufactured a final simulation will be run using real component weights. If

the center of gravity is not where initially predicted, the ballast tank will be used to correct the

location. Throughout the project, this will be re-examined to ensure stable flight.

Page 43: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

43

Section 4.4.3: Assembly Procedures

Manufacturing of the vehicle generally takes two weeks to produce and assemble the components.

To account for this the team plans to start manufacturing three weeks prior to any scheduled

launches. This allows for one extra week if any problems arise during the manufacturing process.

The typical manufacturing schedule can be seen in Table 4.4: Manufacturing Schedule.

Table 4.4: Manufacturing Schedule

Week Events Percentage of

Completion

1

Manufacturing of Major

Components Such as body

tubes, fins, centering rings,

etc.

50%

2

Begin assembly of

subsystems such as the

booster section and the fin

assembly.

90%

3 Assemble completed

rocket 100%

Manufacturing body tubes using braided structures is a very time-consuming process. The team is

in the process of creating the material required to make these body tubes, and the first four weeks

of January will be used to manufacture the tube structures, both braided and non-braided. These

tubes are the most time-consuming component to manufacture and the event of a crash would have

negative effects on the team’s timeline. To mitigate the effects of a total loss crash, six tube

sections and three motor tube sections will be produced during this time, which will allow for the

construction of three full scale rockets, two with braided body tubes and one with non-braided

body tubes.

Page 44: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

44

Several flat plates of carbon fiber have been produced at various thicknesses. The plates will be

placed in a CNC router to be shaped into flat components. These components include fins, bulk

plates and centering rings.

Section 4.5: Mass Statement

The mass of the rocket and all its subsystems was calculated using optimal mass calculations from

OpenRocket. In addition to using final masses from last year as a basis, a brick sample of carbon

fiber was created to have an accurate density measurement since most of the parts will be

manufactured using carbon fiber. This density test is exceedingly important given the method of

mass estimation. Since construction methods vary drastically from each manufacturer, as well as

different resin and cloth systems varying, it is highly important to get an accurate model of the

density.

Having determined an accurate density for the carbon fiber of the rocket, and the structure of the

rocket being the most significant portion of the weight of the structures of the rocket, the team

used estimates from last year’s rocket to determine the initial size estimate of the rest of the

subsystem components. The team believes that this model presents an estimate that is sufficient.

As the program develops, the model will attain a higher and higher accuracy in its simulation.

Table 4.5: Mass Estimations

Section Mass (lb) Percentage

Structure 15.4 38.02%

Motor 10.1 24.93%

Rover 6 14.81%

Recovery 7 17.28%

Airbrake 2 4.94%

Total 40.5 100%

Page 45: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

45

Section 5: Subscale Flight Results

Section 5.1: Flight Data

Flight data for the subscale launch can be seen below in Figure 5.1: Subscale Flight Data. This

figure represents the launch data of the full rocket and the recovery data of the upper section of the

rocket. The rocket reached an apogee of 2887 feet, had a maximum velocity of 525 feet per second,

and had a landing velocity of 23 feet per second. The data verifies that the vehicle and recovery

designs are safe and within the limits of the competition.

Figure 5.1: Subscale Flight Data

Page 46: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

46

Section 5.2: Scaling Factors

A 2/3 scale was applied to the vehicle diameter and approximately applied to the length of the

vehicle. The diameter of the rocket was the primary scaling factor as the diameter controls the area

of the vehicle perpendicular to the flow and as such has a significant impact on aerodynamic

performance. The length was approximated to a 2/3 scale to ensure integrity of the subscale, but

was not exact due to safety concerns. The team was unwilling to compromise the length of the

recovery sections or the booster section due to the potential hazards that could induce.

The scaling factor of 2/3 was chosen to accurately model the geometry of the vehicle and the forces

the full-scale will experience. The smaller size made the subscale easier to manufacture, but the

team decided that any smaller of a scaling factor could result in risk of the recovery system failing.

Section 5.3: Subscale Analysis

Figure 5.2: Initial Subscale Design

Multiple simulations were run before and after the subscale launch. Initial simulations provided a

predicted apogee of 4090 feet, and a static stability margin of 2.1 calibers. The simulated subscale

weighed 11.94 pounds. Although the motor selected for the flight was simulating a lower apogee

than desired, it was flown because it was readily available to the team and, of the alternatives, it

most closely simulated the maximum velocity the full-scale vehicle is expected to experience.

Page 47: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

47

The team’s subscale launch took place on November 4th 2017 in Samson, AL under SEARS

(Southeast Alabama Rocketry). Upon arrival, the rocket was assembled and the altimeters and

recovery system were tested to verify integrity. Some issues were encountered due to lack of space

inside the recovery section of the rocket. This was due to not accounting for the size of space the

couplers would take up internally, as well as issues with bolts potentially catching the parachutes

and preventing deployment. Additionally, the team found that the rocket was four pounds over-

weight, bringing the total weight to approximately 16 pounds. The recovery issue was resolved by

carefully packing the parachutes. The rocket was flown slightly overweight and was successfully

launched and recovered. The launch data is shown above in Figure 5.1: Subscale Flight Data.

The flight data did not match the simulated data, but the team believes that this is primarily due to

the change in weight of the rocket. When inputting accurate weight values into OpenRocket, values

similar to those achieved in the flight test were outputted. The results for the simulation with 4

pounds added at approximately the CG, as well as changing the surface finish to increase the drag

coefficient values, are shown in Table 5.1: Subscale Launch Data vs Simulation. Changing the

surface type in OpenRocket resulted in the coefficient of dragging changing from .49 to .54. These

simulated values were then slightly below the flight data. The team performed a CFD analysis that

will be discussed later that yielded a coefficient of drag for the full-scale model of .53, and coupled

with the subscale flight data, that is the value used in the team’s most recent full-scale simulations

discussed in Mission Performance Predictions.

Table 5.1: Subscale Launch Data vs Simulation

OpenRocket

Simulation

Recorded Flight

Data Updated Simulation

Apogee (ft) 4090 2887 2867

Max Velocity (ft/s) 620 525 473

Page 48: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

48

Section 5.4: Impact on Full-Scale Design

The subscale flight tests determined that the design is very stable and will perform effectively.

Because of the complex aerodynamic shape of the rocket, simulations were not exactly accurate

at first, but with the subscale data the team is confident the current simulation iteration is far more

accurate than before. More tests will be run to further improve and verify the accuracy of the

simulation model. The design of the rocket will not change because of the latest subscale flight.

The major insight from the subscale launch came from the vast underestimates of the weight of

the different subsystem components. To ensure that this does not happen in the full-scale, each

subsystem will be re-examined to ensure that the proper weight is simulated for each section.

As for recovery, all components of the subsystem worked exactly as designed in the subscale test

of the Auburn Student Launch team’s rocket. The subscale was 2/3 the scale of the full-scale

rocket, giving it a diameter of 4 inches. The subscale used a nosecone of a similar design to the

full-scale rocket, so ejection of the nosecone provided data proving the efficacy of the ejection

system. The subscale, like the full scale, had three parachutes, a drogue deployed at apogee, an

upper main parachute deployed at 1000ft and a lower main parachute deployed at 750 ft. The

drogue parachute was a standard 31-inch diameter circular parachute and both main parachutes

were 17.5-inch diameter hemispherical parachutes. Black powder was used as the ejection system

for both the lower and upper parachutes in the subscale rocket. The avionics bay board was

modified slightly to fit into the approximately 3.75” interior diameter of the avionics bay, and

employed a more compressed assembly of altimeters and batteries than will be used in the full

scale. The board had one altimeter and its corresponding battery mounted on each side of the

carbon fiber avionics bay board. This helped save space and reduce interference between the

altimeters. Charge cups filled with black powder were mounted directly adjacent to the outsides

of both the upper and lower bulk plates of the avionics bay. Electronic matches attached to the

black powder charges were run through holes the bulk plates and inserted to the appropriate ports

in the altimeters. In summary, the recovery design will not change as a result of subscale

experience.

Page 49: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

49

Section 6: Recovery System Design

The Auburn Student Launch team is using an augmented dual-stage recovery system with a drogue

parachute deployed at apogee (target height of 5280 ft.), an upper main parachute being deployed

at 1000 ft. and a lower main parachute deployed at 750 ft. At apogee, the nose cone, drogue

parachute and upper main parachute are all ejected using redundant black powder charges. When

the upper main parachute is ejected though, it is held closed by the Jolly Logic Chute Release

System. At the beginning of the second event (at 1000 ft.), The Jolly Logic System will release

and deploy the upper main parachute with the rocket still in one piece. At the end of the second

event (at 750 ft.), a second set of redundant black powder charges will detonate and separate the

rocket, pushing the lower main parachute from its housing. Using this configuration, the entire

rocket will fall under a single drogue parachute from apogee until the second event occurs where

the rocket separates into two separate pieces and falls under two separate main parachutes. The

nose cone and drogue parachute will remain attached via shock cord to the upper section after

separation. This augmented dual-stage recovery system was chosen to reduce the likelihood of the

upper section drifting into and collapsing the lower main parachute after deployment.

Section 6.1: Structural Elements

The centerpiece of Auburn's recovery system is the Barometric Avionics Enclosure (BAE). Every

recovery subsystem is either attached to or contained inside the BAE. The BAE is formed by a 12-

inch-long cylinder of fiber glass. A comparison showing why fiber glass was chosen over carbon

fiber can be seen in a Pugh chart below in Table 6.1: Pugh Chart of Carbon Fiber vs. Fiberglass

Material for the BAE. As for the design of the BAE, there is one inner bulk plate attached inside

of the BAE that serves as the top cap of the avionics bay. Inside the avionics bay there are two sets

of rails to secure the avionics board. Both altimeters and their batteries are mounted to this board.

The bottom of the BAE is closed off by another bulk plate. The two bulk plates are linked by two

rods and secured by locking nuts on the outside of the BAE. Both bulk plates have a single open

hole to allow the ejection charge wires to run from the altimeters to their proper e-matches. Each

Page 50: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

50

hole has two charge wires that run through it to minimize the chance of the sensitive recovery

electronics being damaged by the pressurization that occurs when the black powder charges are

deployed.

Table 6.1: Pugh Chart of Carbon Fiber vs. Fiberglass Material for the BAE

Weight Fiberglass Carbon Fiber

Altimeter Signal

Disruption

3 3 1

Strength 2 2 3

Ease of

Manufacturing 1 3 2

Total 16 9

The BAE serves as the coupler between the upper and the lower parachute housings. Each section

is secured to the BAE with three machine bolts per section. Neither of these sections separate once

the rocket is assembled. On the outside of the BAE is a ring of the vehicle body tube taken from

the same tube the upper section is constructed from. This is done so the tube connections between

the upper parachute housing, the BAE, and the lower parachute housing are continuous and

smooth, minimizing the impact on the aerodynamic performance of the rocket due. This ring is the

only surface of the BAE that is on the outside of the rocket, so two key switches and two pressure

holes are located along this ring. The key switches located on the ring allow the team to externally

arm the altimeters while the rocket is assembled.

A single U-bolt is mounted to the top bulk plate of the BAE for the upper parachute assembly to

be mounted to. This location was chosen as it is the only point in the upper section where the

parachutes can be tethered to keep the rocket in an upright position and minimize the chance of

the parachute tearing when deployed. The lower main parachute is connected to a second U bolt

Page 51: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

51

mounted to the bottom of the Rover section. This is mounting location was chosen because it is

the only point where the lower parachutes can be mounted while also keeping the charge cups next

to the BAE, thus minimizing the potential for error with the e-matches and decreasing risk.

Section 6.2: Materials

The materials chosen to create the team's recovery system have a direct effect on the success of

the system. Specifically, the parachutes, shock cords, and bulkhead attachments must be strong

enough to withstand the recovery procedures and also be light enough to avoid hindering the

launch. Failure of the recovery system materials to survive the ejection charges would cause an

inadequate landing of the vehicle, and could severely damage the rover payload. The success of

recovery systems materials is essential for proper payload delivery, so they are chosen

appropriately. The chosen materials for the parachute, shock cord, and bulkhead attachment are

rip-stop nylon, paracord, and U-bolts, respectively.

The parachute must withstand ejection charges during the recovery process. Ideally, the chosen

materials for the parachute allow it to be sturdy to be used in multiple tests and launches. The

factors that should be used to assess the suitability of different parachute materials to allow for

recovery system requirement satisfaction are strength, durability, and weight. Rip-stop nylon was

chosen over cotton fabric as our parachute material for several reasons. Rip-stop nylon weights

about 2.75 oz. per square yard while cotton fabric weighs about 4.3 oz. per square yard. It also

has a tensile strength of 1500 psi while cotton fabric has a tensile strength of 400 psi. Additionally,

rip-stop nylon will stretch up to 40 percent of its length before breaking while cotton will stretch

up to 10 percent. The Pugh chart shown below in Table 6.2: Parachute Materials Pugh Chart

confirms the choice of rip-stop nylon for the parachute material.

Table 6.2: Parachute Materials Pugh Chart

Rip-stop Nylon Cotton fabric

Page 52: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

52

Strength 3 1

Durability 3 1

Weight 3 2

Totals 9 4

The shock cord must be able to survive the same events as the parachute. The materials that were

considered for shock cord and shroud lines are Paracord, 1-inch Tubular Nylon, and Kevlar.

Paracord is extremely light, strong for its weight, and does not take up much space. The only

possible problem with paracord is that it can only withstand 550 pounds. However, the other

benefits of paracord make it an ideal material for the drogue shroud lines, since the drogue will

not create much drag force and so will not put as much tension on the shroud lines.

Tubular nylon consists of a nylon tube which is made from exceptionally high strength material

which is both light and strong. Tubular nylon is easy to handle and cost efficient. The wrap around

webbing increases the overall strength per inch. Tubular nylon is highly flexible and pliable. Due

to its pliability, it tends to glide better over rough or jagged surfaces preventing the wear and tear

that occurs more with Kevlar. One inch width of tubular nylon webbing can withstand about 4000

pounds of pressure. For the main parachutes, which create more drag force, the shroud lines will

be made from this material. Nylon has a much high strength and will also allow the team to use a

double seam across either side of the shock cord, ensuring the stitch is stronger as well.

While tubular Kevlar is stronger, the strength of tubular nylon is more than sufficient for the needs

of the mission. In addition, the pliability of nylon will allow the shock cord to better absorb the

shock of ejection and ensure smooth movement of the potentially rough surfaces inside the upper

section. By using a material known to be strong, the team ensures failure is less likely to happen

in this component. The pliability and strength of tubular nylon have led to the team choosing to

use it as our material of choice for shock cords.

Page 53: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

53

The factors that should be used to assess the suitability of different shock cord materials to allow

for recovery system requirement satisfaction are volume, strength, durability, pliability, flexibility,

and weight. The Pugh chart that was used to evaluate which material was chosen for the parachute

is shown in Table 6.3: Comparison of Paracord, Tubular Nylon, Kevlar

Table 6.3: Comparison of Paracord, Tubular Nylon, Kevlar

Paracord 1-inch Tubular Nylon Kevlar

Volume 3 1 2

Weight 3 2 2

Strength 1 2 3

Durability 1 2 1

Pliability 3 3 1

Flexibility 3 3 2

Total 14 13 11

Nylon shear pins will be used to attach the nosecone to the BAE and to prevent drag separation.

In the team’s configuration, #4-40 nylon screws are used to secure the sections. These machine

screws have a double shear strength of 50 lbs. Ground testing was performed on these shear pins

to ensure safety and eliminate the possibility of manufacturing discrepancies.

The materials used to attach the shock cord to the bulk plates should be chosen appropriately. The

team will be using U-bolts to attach the parachutes to the bulk plates, because U-bolts have proven

to be more reliable in the team’s past. Shock cord cannot become easily tangled, and an eye bolt

is more susceptible to failure for this reason, as the shape allows cord to wrap around it. U-bolts

also provide two points of attachment to the bulk plate while eye bolts only provide one. The

factors that should be used to assess the suitability of different bulk plate attachment materials to

Page 54: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

54

allow for recovery system requirement satisfaction are strength and an ability to limit cord tangles.

The Pugh chart that was used to evaluate which material was chosen for the parachute is shown in

Table 6.4: Comparison of U-bolts and Eye-bolts.

Table 6.4: Comparison of U-bolts and Eye-bolts

U-bolt Eye-bolt

Attachment Strength 3 2

Limits cord tangles 3 1

Totals 6 3

Section 6.3: Ejection

4F black powder has been chosen for the ejection of the team's parachutes. Black powder is an

effective, reliable means of pressurization that the team has had success with in the past. Compared

to CO2 ejection, black powder can produce greater pressures per cubic inch required to house the

system. A comparison between CO2 and black powder can be seen in Table 6.5: Comparison of

Black Powder and CO2.

Table 6.5: Comparison of Black Powder and CO2

Criteria Black Powder 𝐂𝐎𝟐

Pressure Produced per

Volume 3 1

Damaging Heat Produced 1 3

Cost 3 2

Ease of Integration 3 1

Page 55: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

55

Reliability 2 1

Total 12 8

For the both events, two charges are placed within 3D printed charge cups and armed with

electronic matches: the first charge is the primary means of ejection, and the other will be a backup

charge for redundancy and to decrease the chances for failure of the recovery system. The

redundant apogee charge is set to fire 3 seconds after the first charge. The charges are not ignited

at the same time as that has the potential to cause damage to the airframe and failure of the system.

Black powder, when ignited, can be approximated as an ideal gas. While further testing will be

performed to guarantee the validity of the team’s calculations, the Ideal Gas Law can be used to

calculate an estimate for the amount of black powder needed for ejection. The Ideal Gas Law is as

follows:

𝑃×𝑉 = 𝑛×𝑅×𝑇

𝑅 = 265.9𝑖𝑛 − 𝑙𝑏𝑓

𝑙𝑏𝑚×𝑅 𝑇 = 3300R°

Ignoring the volume of the parachutes and other recovery systems contained within the upper

section, a conservative volume for the upper section can be calculated with an inner diameter of 6

inches and a length of 24 inches as:

𝑉 = 𝐴×𝐿 =𝜋

4×𝑑2×= 678.6 𝑖𝑛3

Using this equation, the team can calculate the amount of black powder needed to produce

pressures sufficient to shear the nylon screws attaching the nosecone to the upper section.

Assuming 3 nylons screwed each rated for 50 psi of shear, pressure required to shear the screws

is:

𝑃 =3×𝐹

𝜋4 ×𝑑2

= 5.3 𝑝𝑠𝑖

Page 56: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

56

Which, in conjunction with the previous equations, yields a charge size for 4F black powder of:

𝑛 =𝑃×𝑉

𝑅×𝑇×

453.592𝑔

𝑙𝑏𝑚= 1.86 𝑔

1.86 grams of black powder will serve as a starting estimate and will be verified via ground testing.

Both charge sections are filled with fireproof cellulose insulation (colloquially known as “barf”)

to protect the parachutes from the heat of ejection. The first event deploys the drogue parachute

and the rifled upper main parachute, held closed by our Jolly Logic chute release system. The

second event consists of the second set of charges being deployed to separate the rocket and deploy

the lower main parachute as well as a mechanical release of a pin in the Jolly Logic system,

allowing the upper main parachute to deploy.

The AUSL team is utilizing the Jolly Logic system in series for redundancy in the recovery

systems. It is an efficient system that doesn’t need any black powder charges, decreased amount

of wires connected to the altimeter bay, as well as reduced risk of entangled shock cord in the main

body. The only cons of this system would be a Jolly Logic system malfunction.

Figure 6.1: Redundant Jolly Logic System

Page 57: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

57

The Jolly Logic system allows for the deployment of both a drogue and main parachute

simultaneously in a single separation. This system deploys more parachutes with fewer

separations, reducing the chance of failure of the recovery portion of flight. The only parachute

that will utilize the Jolly Logic Chute Release System will be the upper main parachute.

Figure 6.2: Jolly Logic Chute Release

The Jolly Logic system consists of an independent altimeter device which releases a mechanical

pin an altitude that is preset at (target height 1000 ft.). The pin is connected to the Jolly Logic

device via a rubber band which provides tension on the pin so that when it is released, it is pulled

from its socket. Since the Jolly Logic system consists of rubber bands which can easily break if

put under stress, the recovery system is set up so that tension from the shock cord is never

transferred to the Jolly Logic devices. To do this, the main parachute is not folded with the shock

cord inside as is normal. Instead the parachute is located on the shock cord so that the shroud lines

are at full extension and so that the drogue line, which runs through the main parachute spill hole

is able to deploy to its full length during the initial separation. The main parachutes are then

carefully gathered and positioned in the body tubes so that the drogue line will pull it out without

putting any forces on the actual parachutes and Jolly Logic system.

Page 58: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

58

To preserve the redundancy of our recovery system, we are using two Jolly Logic chute releases

in series to gather the main parachutes. If either of the Jolly Logic devices happens to malfunction,

the other will still release, allowing the main parachutes to deploy.

Section 6.4: Parachutes

Auburn’s augmented dual deploy recovery approach will make use of three separate parachutes

designed and constructed in house by the AUSL team. The team has been constructing its own

parachutes in house for five years and has refined its manufacturing process to produce quality,

custom chutes that produce the desired drag and drift for all sections of the rocket.

The drogue parachute will be a small, circular parachute constructed of rip-stop nylon with

paracord shroud lines. Following the first event at apogee, the drogue along with the upper main

parachute bundled with a jolly logic chute release system will be deployed from the top of the

rocket. This will stabilize descent until main deployment at the second event. The drogue parachute

is designed to stabilize the descent of the rocket from apogee to main parachute deployment at a

descent velocity of approximately 100 m/s. This velocity was chosen to minimize the drift of the

rocket while still having a stable descent. A drag coefficient of 0.8 for a fully inflated circular

parachute was determined from research. Further testing will be done later to ensure the validity

of this coefficient.

𝐴 = 2×𝐹

𝜌×𝐶𝐷×𝑉2

Where F is force, ρ is density of the air, CD is the drag coefficient and V is descent velocity. The

team has used this equation to calculate an appropriate area for the drogue parachute.

𝐴 = 2×32𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 ×0.8× (100𝑓𝑡𝑠 )

2 = 3.37 ft2

These calculations yield a circular drogue with a 24.9-inch diameter.

Page 59: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

59

The recovery system will have two main parachutes constructed of rip-stop nylon with 0.5-inch

tubular nylon shroud lines. The main parachutes will be hemispherical. The hemispherical shape

can be more difficult to manufacture, but will produce the most drag, allowing the rocket to have

maximum drag with minimum weight. A Pugh chart can be seen below comparing different

parachute shapes.

Table 6.6: Parachute Shape Pugh Chart

Baseline Square Circular Hemispherical

Drag Produced 3 1 1 2

Ease of

Manufacturing

2 1 2 1

Stability 1 2 1 1

Total 7 8 9

The shape of the main parachutes and their gores can be seen in Figure 6.3: Gore Template and

Figure 6.4: Parachute Template. When the rocket reaches 750 feet in altitude, a second charge will

separate the top section of the rocket to release the lower main chute, and the jolly logic chute

release system will release the bundled upper main chute. A spill hole will be added to the main

parachutes. This spill hole will be necessary with our configuration of dual-deployment from the

same compartment at the top of the rocket body. In accordance with the general rule of thumb, the

spill holes will be close to 20% of the total base diameters of the chutes. The 20% diameters of the

spill holes are chosen because it only reduces the areas of the parachutes by about 4%, allowing

enough air to go through the spill hole to stabilize the rocket without drastically altering the descent

rate.

Page 60: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

60

Figure 6.3: Gore Template

Figure 6.4: Parachute Template

Parachute areas for hemispherical shaped chutes are determined using the following equation:

𝐴 = 2×𝐹

𝜌×𝐶𝐷×𝑉2

Where F is force, ρ is density of the air, CD is the drag coefficient and V is descent velocity. The

team has used this equation to calculate an appropriate area for the main parachutes so that the

kinetic energy of either section of the rocket does not exceed 75 ft-lbs during recovery and remains

within safe limits.

Page 61: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

61

𝐴𝑈𝑝𝑝𝑒𝑟 =2×8𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 ×1.31× (20𝑓𝑡𝑠 )

2= 12.86 𝑓𝑡2

𝐴𝐿𝑜𝑤𝑒𝑟 =2×24𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 ×1.31× (11.5𝑓𝑡𝑠 )

2= 116.66 𝑓𝑡2

Table 6.7: Parachute Dimensions

Upper Chute Lower Chute

Area 12.86 ft2 116.66 ft2

Diameter 34.3 in 103.4 in

Diameter of Spill hole 6.9 in 20.7 in

Number of Gore 6 8

Width of Each Gore at Base 18.0 in 40.7 in

Height of Each Gore 26.9 in 81.15 in

Circumference at Base 107.8 in 27.1 ft.

The team decided to move from 6 gores to 8 gores for the lower main parachute. The main reason

for this change is that the template the team would have to print out for a 6-gore hemispherical

parachute would simply be wider than any printer available to the team would be able to print.

Moving to an 8-gore configuration also increases the accuracy the accuracy of the parachute to a

true hemisphere.

Page 62: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

62

Section 6.5: Altimeters

The avionics bay will house two altimeters to satisfy redundant system requirements. Both

altimeters will fire the apogee charge at the apogee height of 1 mile (5280 feet) to eject the

nosecone and thus the drogue and bundled upper main parachute. Then both altimeters will fire

the main deployment at an altitude of 750 ft. Neither set of charges are fired at the exact same

time. A three second delay has been placed between the firing of each charge to ensure the

structural integrity of the rocket is maintained.

The team will be using one Altus Metrum TeleMega as the primary and one Altus Metrum

TeleMetrum as the secondary altimeters. The other altimeter that was being considered was the

PerfectFlite Stratologger. The TeleMega has 4 additional sets of pyro connectors, allowing for

future expansion if necessary. It can also have a second battery easily installed into dedicated screw

terminals for additional power for pyro ignition purposes. The TeleMega also has a more advanced

accelerometer for more detailed flight data acquisition. The PerfectFlite Stratologger requires a

standard 9V battery, which is larger and heavier than the battery used for the Altus Metrum

altimeters. Additionally, using two Altus Metrum altimeters will make programming quicker and

easier, as they share an interface program. This makes any last minute or on-site adjustments across

both boards simpler. Should one of the Altus Metrum altimeters fail, the PerfectFlite Mawd or

Stratologger can be used as additional backup. All altimeters are capable of tracking in flight data,

apogee and main ignition, GPS tracking, and accurate altitude measurement up to a maximum of

25,000 feet. Figure 6.5: Altus Metrum TeleMega Altimeter and Figure 6.6: Altus Metrum

TeleMetrum Altimeter shown below are pictures of the altimeters the team will be using.

Page 63: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

63

Figure 6.5: Altus Metrum TeleMega Altimeter

Figure 6.6: Altus Metrum TeleMetrum Altimeter

Another reason the Altus Metrum altimeters are preferred are their radio frequency (RF)

communication abilities. Both TeleMega and TeleMetrum are capable of communicating with a

Yagi-Uda antenna operated by the team at a safe distance at any point during the launch. It can be

monitored while idle on the ground or while in flight. While on the ground, referred to as “idle

mode”, the team can use the computer interface to ensure that all ejection charges are making

proper connections. Via the RF link, the main and apogee charges can be fired to verify

functionality, which was used to perform ground testing. The voltage level of the battery can also

be monitored, and should it dip below 3.8V, the launch can be aborted in order to charge the battery

to an acceptable level. Additionally, the apogee delay, main deploy height, and other pyro events

can be configured. The altimeter can even be rebooted. While in flight, referred to as “flight mode”,

the team can be constantly updated on the status of the rocket via the RF transceiver. It will report

altitude, battery voltage, igniter status, and GPS status. However, in flight mode, settings can’t be

Page 64: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

64

configured, and the communication is one way from the altimeter to the RF receiver. Figure 5.11

shown below demonstrates the process the altimeters go through to deploy the charges at each

event.

Figure 6.7: Altimeter Block Diagram

Isolating one altimeter system (altimeter, battery, and wires) from the other helps prevent any form

of coupling or cross-talk of signals. Isolation is realized via distancing the two systems, avoiding

parallel wires, and twisting wires within the same circuit. Additionally, the most apparent form of

radio-frequency interference, the antenna, will resonate on wires any multiple of ¼ λ (1/4 of

Page 65: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

65

~70cm). Avoiding resonant lengths of wire will be done wherever possible. Should a wire happen

to be a resonant length and is unable to be shortened or lengthened, a low-pass filter can be

implemented to block the high frequency noise. Both altimeters and their batteries will be mounted

on a carbon fiber board that slides into a set of rails. The altimeters and batteries will be mounted

on opposing sides of the board, with one battery and altimeter per side. Since carbon fiber is an

effective shielding material (50dB attenuation), this board will act as shielding between the two

altimeters and minimize cross-talk as well as near-field coupling. This board will also be easily

removable for connecting the altimeters to computers for configuration and for charging the

altimeters’ batteries.

Section 7: Mission Performance Predictions

Section 7.1: Simulations

The launch vehicle has been simulated using OpenRocket, an open source rocket simulation

software. The team is confident in this software’s ability to simulate a rockets flight due to past

years success with using OpenRocket. The rocket as it is modeled in OpenRocket is shown in

Figure 7.1: OpenRocket Model.

Figure 7.1: OpenRocket Model

The multiple runs of the simulation were conducted using various calculation methods and

assumptions such as wind speed as well as using different approximations for the earths shape.

Page 66: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

66

Wind speeds were tested up to a maximum of 25 mph, which yielded only nominal changes in the

expected velocity, acceleration, or apogee. The same held for the different earth approximations.

Additionally, simulations were run where the temperature was varied between 50°F to 80° F. These

changes had no major impact on the projected values for velocity, acceleration and apogee.

Between all the different simulations the team ran, the results differed by approximately 1%.

Therefore, the following data is presented from a simulation run with 0 mph winds and standard

sea level conditions.

Table 7.1: Flight Simulation Data (Wind = 0 mph)

Flight Simulation Data (Wind = 0 mph)

Maximum Velocity 708 ft./s

Maximum Acceleration 269 ft./s2

Launch Weight 39.9 lbm

Burnout Weight 34.4 lbm

Length 108 in

Maximum Diameter 6.25 in

Launch Stability 2.4 calibers

Velocity off Rod 78.6 ft/s

Page 67: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

67

Figure 7.2: Altitude Vs. Time

Page 68: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

68

Figure 7.3: Velocity Vs. Time

Page 69: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

69

Figure 7.4: Acceleration Vs. Time

Section 7.1.1: Motor Thrust Curve

The simulated motor thrust curve for the selected motor can be seen below. The team is confident

that this motor selection will provide adequate thrust to propel the launch vehicle to above the

target altitude to enable the altitude control module to adjust the final altitude to 5280 ft.

Page 70: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

70

Figure 7.5: Motor Thrust Curve

Section 7.1.2: Component Weights

Table 7.2: Component Weights

Component Weight (lbm)

Upper Body Tube 4.78

Lower Body Tube 4.64

Nose Cone 2.17

Fins (4) .91

Centering Rings (3) .6

Motor 10.1

Motor Retention .3

Page 71: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

71

Motor Tube 1

Rover and Bay 4.5

Airbrake System 2

Bulkheads .9

Electronics 1.5

Recovery Section 7

Total 40.5

Section 7.1.3: Stability

For the rocket to be stable during flight the center of pressure must be located aft of the center of

gravity. It is recommended for this size of rocket that the stability margin should be 1-2 calibers.

The stability margin for the rocket is predicted to be 2.4 calibers at the point of rail exit which is

comfortably above the minimum requirement of 2 calibers. This number was calculated without

considering the drag plate system, which will move the center of pressure forward. However, the

drag plates will not deploy until after motor burnout. The team feels confident that having a

stability margin of over 2 calibers will allow the rocket to still remain stable with the inclusion of

the drag plates.

Page 72: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

72

Figure 7.6: Stability Vs. Time

Before flight, the center of pressure and the center of gravity are measured to be 84.13 inches and

69.992 inches from the top of the rocket, respectively. In Figure 7.6: Stability Vs. Time, the change

in the locations of the center of pressure and center of gravity can be seen for the entirety of the

flight. After apogee, the data for the stability drops off due to the deployment of the drogue

parachute. The increase in stability is due to the motor losing propellant mass due to motor burnout

as well as the decrease in velocity which moves the center of pressure away from the center of

gravity.

Section 7.1.4: Computational Fluid Dynamics

Computational Fluid Dynamics (CFD) is a branch of fluid mechanics that utilizes numerical

analysis methods and high-performance parallel computing to best analyze the flow properties and

fluid dynamic interactions of aerospace systems. Through CFD, the Navier-Stokes equations are

Page 73: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

73

solved numerically across a finite volume that encompasses the boundary conditions that comprise

the tested system. The finite volume is constructed through a series of successive steps, beginning

with the creation of a surface geometry through computer-aided design (CAD) software. The

surface data is then imported into mesh generation software, where domains are constructed

according to the specific boundary conditions inherent in the desired simulation. The exported grid

is then processed through a CFD software package, where flow parameters and boundary

conditions are specified, and a specific flow solution is chosen to account for various aerodynamic

phenomena (vorticity, viscosity, turbulence, and more), and numerical data approaches

convergence.

A new shell was constructed in SolidWorks to simulate the exterior of the rocket body, comprised

of the revolved nose-cone, uniform cylindrical body, and trapezoidal fin control surfaces. The

SolidWorks geometry was then exported in the form of a .STP file in order to be imported into

Pointwise mesh generation software. A farfield domain, in the form of a cylinder, was constructed

around the rocket body, extending roughly five rocket-body lengths in the aft direction, and two

lengths in the forward direction, while having a diameter many multiples of the rocket-body

diameter in order to maintain a farfield condition. The connection point discontinuities, apparent

after importation into Pointwise, between the nose-cone and the cylindrical body, and between the

trapezoidal fins and the cylindrical body, were resolved and smoothed.

Page 74: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

74

Figure 7.7: Nosecone Meshing

Grid spacing on the fins was also applied more uniformly through the leverage of anisotropic

tetrahedral meshing, and is evidenced in the following figure.

Figure 7.8: Tail-fin Meshing

The entire domain was processed through an anisotropic tetrahedral mesh extrusion, with the

cylindrical farfield as a “farfield” boundary condition, and the entire rocket-body defined as a

Page 75: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

75

“wall” condition, with a ∆s value of roughly 1.0x10^-7 (a value calculated as a function of the

Reynolds number of the simulated transonic flow).

Upon exportation of the grid, the TENASI CFD software package, developed by UT Chattanooga

and used by Auburn University, was utilized to construct separate parameter and boundary

condition files to test the freshly created grid with. Current research efforts are focusing on the

comparison between the use of an arbitrary mach flow regime with the Menter Scale-Adaptive

Simulation (SAS single equation) and the Spalart-Allmaras (SA single equation) flow solution

types. Preliminary analysis of the rocket-body grid flying at roughly Mach 0.65, with a post-

burnout center of gravity occurring roughly 1.25 meters aft of the origin of the coordinate axis

defined at the center of the nose-cone connecting ring produced coefficient of drag values, and are

shown in the following table. These drag coefficients were then inputted into OpenRocket to

ensure the use of accurate drag coefficients in the team’s simulations.

Table 7.3: CFD Drag Coefficient Results

Mach Number (M) Coefficient of Drag (C_d)

0.6 .532

0.725 .5375

0.750 .5425

Section 7.2: Kinetic Energy

The kinetic energy for the rocket upon impact can be calculated using the following formula:

𝐾𝐸 =1

2𝑚×𝑉2

Where m is mass and V is descent velocity. With a mass of 8 lbm and a calculated velocity of 20

ft./s for the upper section, this equation yields:

Page 76: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

76

𝐾𝐸 =1

8𝑙𝑏𝑚

32.2𝑓𝑡𝑠2

× (20𝑓𝑡

𝑠)

2

= 49.7 𝑓𝑡 ∙ 𝑙𝑏

With a mass of 24 lbm and a calculated velocity of 11.5 ft/s for the lower section, this equation

yields:

𝐾𝑒 =1

24𝑙𝑏𝑚

32.2𝑓𝑡𝑠2

× (11.5𝑓𝑡

𝑠)

2

= 49.3 𝑓𝑡 ∙ 𝑙𝑏

Section 7.3: Drift

The distance the rocket will drift during descent can be estimated with the following equation.

𝐷𝑟𝑖𝑓𝑡 = 𝑊𝑖𝑛𝑑 𝑆𝑝𝑒𝑒𝑑×𝐴𝑙𝑡𝑖𝑡𝑢𝑑𝑒 𝐶ℎ𝑎𝑛𝑔𝑒

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦

However, this drift estimation assumes wind speed and descent velocity are constant and does not

account for the horizontal distance the rocket travels during ascent. There will be two stages of

descent. First, the rocket will descend under the drogue parachute from an altitude of 5280 ft. to

750 ft. At 750 ft. a second black powder series will occur separating the rocket into two pieces,

and the Jolly Logic parachute release system will separate and another event will occur releasing

a lower main parachute to safely escort the rover to the ground. The rate of descent under drogue

can be calculated with the following equation:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2×𝐹𝑜𝑟𝑐𝑒

𝐴𝑖𝑟 𝐷𝑒𝑛𝑠𝑖𝑡𝑦×𝐷𝑟𝑎𝑔 𝐶𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡×𝑃𝑎𝑟𝑎𝑐ℎ𝑢𝑡𝑒 𝐴𝑟𝑒𝑎

Since this is a variation on the formula used to calculate the parachute areas, the resulting velocities

are the team’s desired descent velocities. However, as the competition progresses, this formula can

be used to update our predicted velocities with different drag coefficients, weights, or parachute

areas. This descent velocity will then be used to ensure drift is kept to a reasonable amount. An

assumed drag coefficient of 0.8 was estimated from research. Testing will be performed later to

Page 77: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

77

ensure the validity of this coefficient. Assuming a total rocket weight after burnout of 32 lbm and

a drogue diameter of 12.43 inches (3.37 ft2), the descent velocity under drogue is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2×32𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 ×0.8×3.37 𝑓𝑡2= 100

𝑓𝑡

𝑠

Assuming a total rocket weight of 32 lbm and an upper main parachute area of 12.86 ft2, the descent

velocity of the entire rocket before separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2×32𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 ×1.31×12.86 𝑓𝑡2= 39.9

𝑓𝑡

𝑠

Assuming a total upper rocket weight after burnout of 8 lbm and an upper main parachute area of

12.86 ft2, the descent velocity of the upper section after separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2×8𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 ×1.31×12.86 𝑓𝑡2= 20.0

𝑓𝑡

𝑠

Assuming a total lower rocket weight after burnout of 24 lbm and a main parachute area of 116.66

ft2, the descent velocity of the lower section after separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2×24𝑙𝑏𝑚×32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 ×1.31×116.66 𝑓𝑡2= 11.5

𝑓𝑡

𝑠

Estimated drift distances for a variety of wind speeds are shown below in Table 7.4: Drift

Calculations for Upper Section and Table 7.5: Drift Calculations for Lower Section. These tables

contain the total and the broken-down drift at each wind speed. The drift is broken down into three

Page 78: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

78

separate sections: Drift under drogue (5280 – 1000 ft), drift under upper main before separation

(1000 – 750 ft) and drift under each respective main after to separation (750 – 0 ft).

Table 7.4: Drift Calculations for Upper Section

Wind Speed

(mph)

Wind

Speed

(ft./s)

Drift Under

Drogue (ft.)

Drift Before

Separation

(ft.)

Drift Under

Upper (ft.)

Total Drift

of Upper

Rocket (ft.)

5 7.33 313.72 45.93 274.88 634.53

7.5 11.00 470.80 68.92 412.50 952.22

10 14.67 627.88 91.92 550.13 1,269.93

12.5 18.33 784.52 114.84 687.38 1,586.74

15 22.00 941.60 137.84 825.00 1,904.41

17.5 25.67 1,098.68 160.84 962.63 2,222.15

20 29.33 1,255.32 183.77 1,099.88 2,538.97

Table 7.5: Drift Calculations for Lower Section

Wind Speed

(mph)

Wind Speed

(ft./s)

Drift Under

Drogue (ft.)

Drift

Before

Separation

(ft.)

Drift Under

Lower (ft.)

Total Drift of

Lower

Rocket (ft.)

5 7.33 313.72 45.93 478.04 837.69

7.5 11.00 470.80 68.92 717.42 1,257.14

10 14.67 627.88 91.92 956.78 1,676.58

12.5 18.33 784.524 114.84 1,195.48 2,094.84

Page 79: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

79

15 22.00 941.60 137.84 1,434.84 2,514.25

17.5 25.67 1,098.68 160.84 1,674.20 2,933.72

20 29.33 1,255.32 183.77 1,912.90 3,351.99

Section 7.4: Simulation Verification

Multiple instances of the simulation, although not shown, were ran to verify the accuracy of the

simulation. Variables such as ambient temperature and wind speed changed the results by

approximately 1% and so were kept fixed. In addition, the simulation data was compared to the

subscale flight and CFD results to ensure an accurate drag coefficient for the model. The team is

confident that the simulation is reliable currently, but will continue to test and adapt it with full-

scale test flight data.

Section 8: Safety

Section 8.1: Pre-Launch Day Items Checklist

□ All Rocket Components

□ Trailer

□ Generator

□ Tables

□ Insulation Packing (Barf)

□ Power tools

□ Drills

□ Dremels

□ Plug in batteries the night before

□ Recovery Tower

□ Black powder

Page 80: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

80

□ Charge cups

□ Shear pins

□ Spare electrical wire

□ Spare batteries

□ Wire strippers

□ Recovery Laptop

□ With attachment to talk to

altimeters

□ Systems box of extra electronics

□ Spare batteries

□ Systems laptop

□ With attachment to talk to

electronics

□ Rover box of extra electronics

□ Spare batteries

□ Rover laptop

□ With attachments to talk to rover

□ Silver Sharpies

□ Extra launch buttons

□ Snap rings

□ Axle grease

□ Sandpaper

□ Duct tape

□ Extension cord(s)

□ Tents

□ Old toothbrushes

□ Extra launch controller

□ Allen wrenches

□ Scale

□ At least 48 water bottles

□ Trash bags

□ Chairs

□ Paper towels

Page 81: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

81

Section 8.2: Preassembly Checklists

Section 8.2.1: Recovery

Task Completed (Initialed)

Ensure all necessary items are transported

Check primary and back-up batteries

Check both altimeters and jolly logic

systems for functionality

Folded parachutes and pack into sleeves

Attach shock chord for nose cone, drogue

parachute and upper main parachute

Attach key switches

Secure e-match in charge cup

Fill Charge Cups (done or supervised by

authorized personnel):

• Use clear and clean table surface

• Wear provided safety equipment

• Fill cups using clean funnel

• Fill to exact mass (measure with scale)

Attach key switches and e-matches to

altimeter boards

Place system in housing BAE

Page 82: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

82

Section 8.2.2: Altitude Control

Section 8.2.3: Body

Task Completed (Initialed)

Ensure all necessary items are transported

Check primary and back-up batteries

Check altimeters for functionality

Check for any damage on plates or housing

Test system for functionality and smooth

extension

Place system in housing and secure

attachment screws

Task Completed (Initialed)

Ensure all necessary items are transported

Check for damage to nose

Check for damage to upper section

Check for damage to lower section

Check fins for correct alignment and any

damage from transportation

Page 83: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

83

Section 8.2.4: Rover

Task Completed (Initialed)

Ensure all necessary items are transported

Check primary and back-up batteries

Test rover functionality along with engine

response and functionality

Test radio receiver

Place rover on tracks in housing bay

Secure housing bay door

Check engine housing for structural

integrity

Gather all shear pins and attachment

screws

Page 84: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

84

Section 8.2.5: Engine

Safety Officer Signature President Signature

X X

_______________________ __________________________

Section 8.3: Launch Vehicle Assembly and Check

Task Completed (Initialed)

Attach lower main parachute to lower

section attachment ring

Attach upper section to avionics BAE with

screws

Attach upper main parachute assembly to

avionics bulkhead

Task Completed (Initialed)

Use engine transported by team mentor or

purchase engine from authorized range

store

Engine prepared by licensed team mentor

Page 85: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

85

Ensure charge cups are in proper locations

indicated by design

Pack insulation (barf) around lower charge

cups and insert lower main parachute and

shock chord

Attach lower section to avionics BAE with

shear pins

Pack insulation (barf) around upper

charge cups and insert upper main

parachute assembly and shock chord

Attach nose cone to upper section with

shear pins

Check all connections for proper alignment

Place and secure engine in engine housing

Test center of gravity

Check key stitches to ensure functionality

of avionics

Check body for flight readiness

Check engine mount for flight readiness

Check fins for flight readiness

If any steps cannot be completed,

disassemble and correct

Page 86: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

86

Safety Officer Signature President Signature

X X

_______________________ __________________________

Section 8.4: Launcher Setup and Launch Procedure

Section 8.4.1: Launcher Setup

Task Completed (Initialed)

Test to ensure all weather conditions are

within preset limits

With supervision of range safety officer,

place rocket on launch rail

Ensure angle launch rail is within limits

Turn on avionics

Clear surrounding area of flammable

material

Page 87: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

87

Have all viewing personnel move to safe

distance

Place ignitor against engine fuel grain

Attach launch controller to ignitor

Check for proper connection

Section 8.4.2: Launch Procedure

Task Completed (Initialed)

Move setup team to safe launch distance

Initialize mission process with range

officials

Receive all clear from range officials

Initiate motor ignition

Check for proper ignition

Safety Officer Signature President Signature

X X

_______________________ __________________________

Page 88: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

88

Section 8.5: Post-flight Inspection

Task Completed (Initialed)

Locate upper and lower sections

Follow guidelines for proper safe recovery

Check altimeter beeps for launch altitude

Remove any vehicle components

Remove any environmental hazards

Page 89: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

89

Section 8.6: Personnel Safety Hazards

Hazard Cause Result Severity Probability Combined

Risk Mitigation

Improper

use of small

power tools

Lack of

training,

improper

use, and/or

improper

protection

such as a

lack of

gloves or

safety

glasses

Mild to

severe cuts,

scrapes, and

other

injuries.

Additionally,

reactions can

result in

harm to

rocket

components

being worked

upon.

3 3 9

Demonstration

of proper use by

experienced

team members,

easily accessible

safety materials

and protective

wear, and

securely

fastening the

object being

worked upon

Improper

use of large

power tools

Failure to

pay

attention,

aggressive

use of the

tools, lack

of proper

protective

equipment,

or a lack or

training

Severe cuts,

burns, rashes,

bruises, or

other harm to

fingers,

hands, or

arms

4 2 8

Experienced

team members

will instruct

inexperienced

team members

before the newer

team member is

allowed to use

the tools, and

only those that

display

comprehensive

and safe work

may proceed.

Protective

equipment will

also be easily

accessible

Page 90: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

90

Carbon

fiber

particles

Sanding

carbon

fiber or

other

fibrous

material

without

using a

mask or

filter

Mild

coughing and

difficulty

breathing,

irritation in

the eyes and

skin.

2 4 8

When sanding or

cutting tools are

used on carbon

fiber all

members in the

lab, regardless if

they are working

on the carbon

fiber or not, are

required to

utilize a mask to

prevent the

breathing in of

excessive

particles

Improper

use of

soldering

tools

Failure to

pay proper

attention to

the

soldering

tool or lack

of training

Mild to

severe burns

on the fingers

or hands of

the team

member

using it.

Additionally,

could result

in excessive

heat and

damage to

the

component

being worked

on.

3 2 6

Members that

use the soldering

iron are required

to give it their

full attention for

the duration of

their work. They

must turn off

and stow the tool

somewhere

away from the

object being

worked on if

they must attend

to something

else before work

is finished. Only

those who have

been instructed

in the use of the

soldering iron

may work with

the tool

unassisted

Page 91: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

91

Noxious

Fumes

Improper

ventilation

of the

workstation

where

soldering or

curing is

taking

place

Excessive

exposure to

toxic fumes

results in

nausea and

irritation.

Reactions

could

potentially

damage the

component

being worked

upon.

3 2 6

The workstation

will be properly

vented and

members using it

are required to

confirm

ventilation is

functioning

periodically.

Additionally, if

ventilation is

malfunctioning,

team members

will not be

allowed to

continue

soldering for an

extended period

of time and must

take a break to

let any buildup

of fumes

disperses

Insecure

Tools

Tools are

left out in

the lab

workspace

and not

returned to

a storage

space

where they

belong

Cuts, pricks,

or tears when

members sort

through

items or

knock loose

tools around

or off tables.

2 3 6

The storage

spaces for all

tools are clearly

marked and easy

to find.

Members are

instructed to

return tools they

find left out to

their storage

spaces. A

checklist must be

finished before

project members

can leave the lab

or start a

different project.

Page 92: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

92

Electrical

discharge

from

equipment

a)

Improperly

maintained

equipment

b)

Improper

use of

equipment

Electric

shocks could

occur to team

members

handling the

equipment

4 1 4

Electrical

equipment will

be maintained

regularly.

Electrical

equipment will

only be plugged

in when ready

for immediate

use and will be

promptly

unplugged

afterward. All

wires will be

kept out of the

path of other

team members

or any other

equipment.

Improper

use of

nonpowered

tools

Lack of

training or

discipline

with tools

Damage to

sections of

the rocket or

to team

members and

delays to the

project due

to the need

for

replacements

2 2 4

All team

members will be

trained on the

use and proper

educate of the

lab. If they are

not followed,

members will be

reprimanded

before an

incident occurs

New Mitigation Steps Completed or To Be Completed:

• New, clearer labeling of all tools, tool locations, and hazards associated with the use of

said tools

• Work stations dedicated to one specific job at a time to promote accountability within the

work area

Page 93: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

93

Section 8.7: Environmental Effects

Section 8.7.1: Effects on Environment

Hazard Cause Result Severity Probability Combined

Risk Mitigation

Fire on

ignition

Upon

ignition,

the exhaust

from the

rocket may

set fire to

any

vegetation

beneath or

around the

launch site

Fires will

destroy the

vegetation

near launch

and have the

potential to

spread

further from

the site

4 3 12

In accordance

with the NAR

guidelines, the

launch site will

be placed such

that it does not

present the risk

of grass fires.

Cured

epoxy in

landfill

Cups used

to cure

epoxy are

thrown into

normal

trash bins

and taken

to landfills

The epoxy

breaks down

and releases

harmful

chemicals

into the

ground

2 4 8

Epoxy and

epoxy stirring

cups will be

disposed of

separately into a

bin by the work

station. The

contents will be

taken to an

approved

chemical

disposal site

Epoxy gas

and

chemical

release

Epoxy

releases

volatile

chemicals

and gasses

as it cures

This small

release can

be vented

into the

environment

1 5 5

With our rather

small scale of

our construction,

the impact of our

ventilation is

minimal

Page 94: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

94

Section 8.7.2: Effects of Environment

Hazard Cause Result Severity Probability Combined

Risk Mitigation

Exposure to

humidity

(corrosion)

Exposure to

humidity

can cause

metals

within

certain

systems to

corrode

Corroded

metals do not

have the

same

integrity as

their original

states leading

to potential

damage

3 2 6

Our system

components will

be kept in a

dehumidified

space at room

temperature to

avoid and

corrosion

Exposure to

humidity

(electronics)

Exposure to

humidity

can cause

wires or

electronic

boards to

corrode

Corroded

wires can

cause

electrical

signals to not

be

transmitted

leading to a

loss of

avionics or

rover control

3 3 9

Our system

components will

be kept in a

dehumidified

space at room

temperature to

avoid and

corrosion

Page 95: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

95

Cross winds

in flight

Rocket is

launched

when cross

winds are

faster than

allowed

limits

Winds can

cause the

rockets

trajectory to

change or its

flight to

become

unstable.

This can

further cause

the rocket to

land in an

unanticipated

or unsafe

location

3 4 12

In accordance

with NAR

regulations, the

rocket will not

be launched if

wind speeds

exceed 20 miles

per hour. The

safety officer

and range safety

officer will

monitor the wind

speed prior to

launch

Section 8.8: Failure Modes

Hazard Cause Result Severity Probability Combined

Risk Mitigation

Improper

wiring

Faulty

connections or

mistaken

placement of

connections

The electronic

payload does

not behave as

expected or

does not

function at all

4 4 16

Wires will be

color-coded to

communicate

their function

and a specific

checklist will

be used to

correct wiring.

The checklist

will be

doubled

checked by the

systems lead

and recovery

lead.

Page 96: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

96

Parachute

failure after

deployment

(tangled)

The parachute

is not packed

properly

The parachute

becomes

tangled on

descent

resulting in an

erratic and

fastmoving

projectile that

endangers

personnel and

property below

5 3 15

Packing of the

parachute will

be performed

by dedicated

members of the

recovery team

who will have

practiced

previously.

Parachute

deploys early

A faulty

altimeter fails

to detect the

altitude at

which the

parachute

should deploy

The rocket's

ascent will be

compromised

and its descent

will result in

the rocket

drifting for a

very long

distance

4 3 12

The altimeter

will be

thoroughly

tested prior to

its use in a

full-scale

capacity to

confirm that it

will function

as intended.

Safety

procedures will

be followed as

directed by the

USLI

handbook for

the recovery of

the vehicle.

Page 97: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

97

Fire in

recovery

system

Excessive

black powder

and

insufficient

flame retardant

wadding

The descent of

the rocket is

accelerated and

the external

and internal

structure of the

rocket is

jeopardized.

Upon landing,

a flaming

parachute or

chords could

ignite brush.

4 3 12

Testing will be

done to

determine the

exact amount

of black

powder and

wadding

needed to

safely deploy

the parachute.

No more than

is needed will

be used. A fire

extinguisher

will be

available to

combat any

fires that may

occur once the

rocket lands. If

the fire spreads

or is

significantly

large,

authorities will

be contacted.

Safety

procedures

will be

followed as

directed by the

USLI

handbook for

the recovery of

the vehicle.

Page 98: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

98

Rocket

sections poorly

coupled

The use of

weak bolts or

poorly

designed

manufactured

couplers

between

sections

Sections of the

rocket may

wobble and the

trajectory of

the rocket

could be

affected during

ascent or

during

recovery.

5 2 10

Extensive

testing of the

coupler will be

done prior to

sub-scale and

full-scale

launches. The

coupler will be

visually

inspected

before and

after assembly

by the team

leads, safety

officer, and

Range Safety

Officer.

Page 99: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

99

Holes in the

airframe

Insufficient

communication

in addition to

excessive

drilling or

work on

components or

failure to

notice missing

pins or screws

The hole could

result in an

improper

reading of air

pressure by the

altimeter and

result in

premature

activation of

the recovery

system.

5 2 10

All sections of

the rocket will

be visually

inspected

immediately

after

construction,

before

transport to the

launch site,

and on

assembly.

Duplicates of

objects such as

pins, screws,

etc. will be

available to

replace any

missing ones.

Prelaunch

machining will

be kept to an

efficient

minimum with

our preflight

checklists and

assembly plan.

Motor fails on

launch

(explosion)

Manufacturing

defect

The rocket is

destroyed on

the launch pad

or shortly after

launch

5 2 10

Rocket motors

will only be

purchased

from a certified

source and will

be handled

with extreme

care

exclusively by

the team

mentor or by

someone with

permission of

the team

mentor.

Page 100: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

100

Parachute

failure after

deployment

(tear)

Defects in the

parachute or

parachute bay

occurred

during

construction

The rocket's

descent will

not be slowed

as effectively

and could

endanger the

rocket or

personnel

5 2 10

The parachute

will be visually

inspected and

tested prior to

its utilization

in a full-scale

capacity and

upon assembly

on launch day.

The container

holding

parachute will

be smoothed to

not contain any

sharp edges.

All parachutes

will be

reinforced at

any potential

tear location.

Page 101: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

101

Parachute

fails to deploy

a) A faulty

altimeter fails

to detect the

altitude at

which the

parachute

should deploy

b) Not enough

black powder

is used in the

recovery

system

The rocket

descends

chaotically at a

speed that his

extremely

dangerous to

both the rocket

and personnel.

5 2 10

a) A reliable

altimeter will

be selected

during the

PDR phase

and will be

tested prior to

launch in a

full-scale

capacity.

b) The amount

of black

powder that

will be used

will be

calculated by

team members

beforehand.

Calculations

will include

the amount

necessary and

the amount

allowable with

the final

amount used

lying

somewhere

within the

range. Use and

final

preparation of

black powder

charges will be

monitored by

the safety

officer.

Page 102: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

102

Rocket blown

off course on

descent

a) Strong

winds on the

day of the

launch affect

descent more

than expected

b) A premature

parachute

deployment

causes the

rocket to be

subject to

more drift

Rocket could

become lost,

damaged, or

could endanger

observers.

3 3 9

The rocket will

not be

launched if

weather

conditions are

considered

dangerous by

either the team

or the range

safety officer.

All parts of the

rocket will

have a GPS

locater device

securely

attached to

facilitate

tracking during

and after

descent. Safety

procedures will

be followed as

directed by the

USLI

handbook for

the recovery of

the vehicle.

Page 103: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

103

Insecure

aerodynamic

attachments

such as fins or

brakes

a) The epoxy

was mixed or

cured

improperly

b) The epoxy

used was not

strong enough

to withstand

forces

encounter in

flight

Fins may

vibrate and

cause

unexpected or

erratic changes

to the course of

the rocket.

This could

cause mission

failure and

potentially

endanger

personnel

4 2 8

Proper

procedures

regarding the

mixing and

curing of

epoxy will be

strictly

followed

during

construction of

the rocket.

During

assembly, team

members will

apply pressure

to the fins to

confirm they

do not move

and will not

move during

flight. If the

epoxy is not

sufficient,

steps will be

taken to fully

secure the fins

and if they

cannot, the

safety officer

will deem the

rocket unsafe

to launch.

Page 104: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

104

Improper

coding

Improper

coding of the

microcontroller

controlling the

airbrake

system

Airbrakes do

not actuate as

expected

compromising

our maximum

altitude and

overall mission

4 2 8

The code that

will drive the

microcontroller

will be written

and reviewed

by multiple

team members

and tested on

the ground to

ensure that it

reacts in ways

it is meant to.

Improper

soldering or

board

manufacturing

Too much or

too little solder

is used when

constructing

the electrical

equipment

Electrical

malfunctions

and a loss of

system

integrity

leading to a

loss of

whichever

system the

electronics are

used in

4 2 8

The electrical

equipment will

be visually

inspected by

multiple team

members and

tests run to

ensure that it

carries

electrical

signals as

intended.

Page 105: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

105

Rocket

descends to

rapidly

Design

oversight

causes the

rocket to fall

faster than

desired

The body of

the rocket will

be damaged

and potentially

the internal

components

damaged as

well. This

could violate

vehicle

requirement

1.4 and

jeopardize

mission

success.

4 2 8

The exact size

of the

parachute

needed to slow

down the

descent of the

rocket and the

timing of its

release will be

calculated and

sufficient

leeway given

to ensure that

recovery will

not threaten the

rocket or

personnel. All

members and

observers will

remain vigilant

until the rocket

is recovered

after landing.

Page 106: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

106

Payload

(rover)

becomes

unstable

during flight

Payload is not

properly

secured within

its

compartment

With a moving

payload inside

the rocket, the

center of

gravity would

be constantly

changing. This

would cause

the rockets

flight to

become

unstable and

potentially

damage the

payload and

other

components

within the

rocket

4 2 8

The payload

will be housed

within a secure

bay inside the

rocket. It will

be placed

inside this bay

with a bulk

plate door to

hold it in place.

The payload is

also at the

bottom of the

rocket with the

opening facing

upward. If the

payload

dislodges, the

inertial forces

of launch

would keep it

in place inside

the bay.

Page 107: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

107

Structure is

dropped and

damaged

during

construction,

assembly, or

in transport

Distracted or

clumsy

handlers that

are not aware

of their

surroundings

The body of

the rocket or

components in

the rocket may

be damaged by

the impact and

may require

replacement

3 2 6

Great care will

be taken when

working on

components

under all

conditions.

The

transportation

vehicle will

have a stable

carrying

structure for

the launch

vehicle.

During

transportation,

multiple

personnel will

carry the

rocket slowly

and carefully

while an

additional

team member

removes

obstacles or

opens doors as

necessary.

Replaceable

parts such as

pins, screws,

and the nose

cone will have

duplicate parts

available

during

assembly.

Page 108: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

108

Motor fails on

launch (fails to

ignite)

a)

Manufacturing

defect

b) Failure of

the ignition

system

c) Delayed

ignition

a) and b) The

motor will not

fire and the

rocket will not

launch

c) The motor

will fire and

the rocket will

launch at an

unknown

amount of time

after the button

is pressed

3 2 6

In accordance

with the NAR

Safety Code,

the safety

interlock will

be removed or

the battery will

be

disconnected

and no team

member will

approach the

rocket for 60

seconds. After

60 seconds

without

activity the

safety officer

will approach

and check the

ignition

systems. In the

event that the

ignition

systems are not

at fault, the

motor will be

removed and

replaced with a

spare. A

second launch

will be

attempted if

there is time to

do so.

Page 109: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

109

Servos used in

aerodynamic

systems do not

actuate

smoothly

a) Internal

electrical

failure

b) Worn gears

or slide rails

The science

payload may

not respond as

accurately as

expected

3 2 6

The servos that

will be used

for flight will

be purchased at

the beginning

of the project

and will be

stored in a

space away

from any

chemicals or

excessive

humidity. The

servos will be

tested before

transport,

before and

after assembly

to confirm that

they actuate

properly. The

airbrake

system will be

tested before

launch to

ensure the

accurate

response from

our system as a

whole.

Page 110: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

110

Structural

integrity of

rocket

compromised

in flight

Excessive

aerodynamic

loading on the

airframe of the

rocket

Rocket may be

entirely lost

after flight

becomes

unstable and

recovery

systems may

be

compromised

5 1 5

Extensive

testing of the

materials and

structural

architecture of

the rocket body

will be done

before sub-

scale and full-

scale launches

to confirm that

the design will

withstand

forces that it

will encounter.

Cracked

airframe

Excessive

physical or

thermal

loading to the

rocket body

during storage

or transport

The rocket

body fractures

on launch or on

ascent

releasing

debris in the

immediate area

5 1 5

Sections of the

rocket body

will be kept in

a dry location

at room

temperature.

The rocket

body will be

visually

inspected

before and

after transport,

during

assembly, and

immediately

prior to launch

to confirm that

there are no

cracks. If

cracks are

found, the

launch vehicle

will be deemed

unsafe for

launch by the

safety officer.

Page 111: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

111

Center of

gravity or

center of

pressure

misplaced

Rocket

property

calculations

were made

incorrectly or

with improper

data

The rocket's

ascent will be

unstable and

potentially

dangerous to

personnel and

equipment

5 1 5

Calculations

will be

checked

multiple times

prior to launch.

Subscale

launches will

provide an

opportunity to

confirm these

calculations

prior to full

scale launch.

Additionally,

the center of

gravity will be

physically

checked prior

to launch.

Misplaced or

lost

components

A messy or

disorganized

work

environment

leads to poor

tracking and

storage of

pertinent

rocket

components

An incomplete

rocket body is

transported or

ready for

assembly on

launch day.

Segments may

need to be

remanufactured

if they cannot

be located.

4 1 4

Once segments

of the rocket

body are

completed they

will be

immediately

stored in a

location

exclusively for

launch-ready

components.

For subscale

launches, some

components

will be

manufactured

twice so that

one may serve

as a backup.

Page 112: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

112

Rocket

exceeds mach

1 on ascent

The rocket

motor utilized

in the design is

too powerful

for the mass of

the rocket

Vehicle

requirement

1.19.7 is

violated,

compromising

the validity of

the mission

and an

infraction of

our launch

licensing

4 1 4

Team members

will

analytically

evaluate the

expected speed

of the rocket

prior to testing

and will

confirm these

results in sub-

scale and full-

scale testing.

In the event

that the mass

of the rocket is

too low,

additional

mass will be

added to the

inside of the

rocket to

ensure it does

not exceed

Mach 1. If the

mass cannot be

fixed in a safe

manner, the

rocket will be

deemed unsafe

to launch by

the safety

officer.

Page 113: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

113

Motor is

physically

damaged

Motor was

damaged

during

handling or

transport due

to a drop or

insecure

transportation

Motor can

function

improperly or

potentially

explode due to

pressure forces

on damaged

area

3 1 3

The motor will

be primarily

handled by the

team mentor or

another

member

certified to do

so with the

permission of

the mentor or

safety officer.

The motor will

be checked

multiple times

before flight to

ensure no

damage has

been done

Page 114: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

114

Section 9: Rover

The following deployable rover system and component designs have been chosen at this point in

the competition based on trade studies of alternative designs and testing that has proven the validity

of the designs. Most designs for the rover have stayed similar to the designs chosen and laid out in

the PDR.

The design of the rover has been broken down into mechanical and electrical sub-teams. This team

format has allowed those members who are interested in those aspects of design dedicate their time

to those fields. Integration of the mechanical and electrical sub-teams' work has been placed on

the deployable rover team lead.

Section 9.1: Mechanical Design

The rover mechanical design entails any part of the rover that is a structural component. This

design group includes the rover body, rover movement system and the SPDS.

An overview of the rover assembly is shown in figures Figure 9.1: Rover Overview “top side” and

Figure 9.2: Rover Overview “bottom side” below.

Page 115: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

115

Figure 9.1: Rover Overview “top side”

Figure 9.2: Rover Overview “bottom side”

Section 9.1.1: Body

Page 116: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

116

Figure 9.3: First Iteration of the Rover Body “top side”

Figure 9.4: First Iteration of the Rover Body “bottom side”

An I-beam shape has been chosen for the shape of the rover body. The initial design employed a

2-layered sandwich design but did not have enough space for the necessary components. A

comparison of the designs can be seen in Figure 3.1: Rover Body Comparison. The components

Page 117: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

117

that take up the most space on the rover are the electrical components. The I-beam design allows

for the placement of components on both sides of the I-beam web, giving the team more room to

work with to place components. The “top side” (orientation is dependent on how the rocket lands)

will house the Arduino used for control, the communication system, two motors for driving the

rover, and two 9V batteries for powering the Arduino and the motor shield (Figure 9.3: First

Iteration of the Rover Body “top side”). The “bottom side” will house the SPDS (panel tray, motor,

and solar panels) and the motor driver. Wiring from one side of the rover will be routed through a

hole located under the motor shield (Figure 9.4: First Iteration of the Rover Body “bottom side”).

Placement of the components was based on fitting the parts together closely and so that they would

not move around no matter the deployment orientation of the rover. On the top side, the motors

will stick through holes in the side wall of the rover and will be secured with a shell that the motors

will slip into. The Arduino will rest on the body with the communications system on top of that

(communication system is on a shield that attaches to the Arduino). The 9V batteries will be

slipped between two “compression walls” at the back end of the rover. On the bottom side, the

motor driver will rest on racks above the wire hole while the SPDS motor will also rest on a raised

platform housed inside another shell (shells not included on first iteration of rover body). The

SPDS tray will slide under rails seen closest to the motor platform in Figure 9.2: Rover Overview

“bottom side”. Since the body is a carbon fiber composite, the electrical conductivity of the Onyx

was tested. The carbon fiber based composite was determined to not be electrically conductive at

all.

Onyx, a printing material comprised of chopped carbon fiber in a nylon matrix, was chosen as the

material for the rover body as it is stronger than nylon and easier to manufacture than standard

carbon fiber. The team decided that, although weaker than carbon fiber, the strength of this material

is sufficient for the rover as it is not expected to experience large loads.

Dimensions of the rover were constrained by the size of the bay allotted for the rover. The team

decided that the rover needed to be able to deploy either right-side-up or upside-down, so the body

had to fit inside the height of the wheels/treads and be shorter than 10 in. (allotted space). The

initial body length of the rover did have to be modified due to “syncing” issues with the tread teeth

and the wheel holes. Dimensions can be seen below in Figure 9.5: Rover Body Dimensions.

Page 118: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

118

Figure 9.5: Rover Body Dimensions

Section 9.1.2: Movement

Figure 9.6: Rover Wheels and Tread

Page 119: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

119

Two initial designs where being considered. The first was a tread design and the second was a

four-wheel design. A tread design was chosen over a simple wheel design in order to provide

greater traction on rough terrain. The additional traction and support in between the wheels allows

the rover to easily deploy from the rocket this design can be seen in Figure 9.6: Rover Wheels and

Tread. The treads are 3D printed from a flexible nylon to allow for a customized size and spacing

of the wheels, teeth, and outer tread. The wheels are printed from the Onyx material.

The rover width and the body diameter set the wheel diameter. The teeth size was then determined,

and a MATLAB script used to calculate the wheel and teeth spacing. The script used is in Figure

9.7: MATLAB Script. After a test print of the tread and wheel it was discovered that there was not

enough clearance for the teeth to smoothly fit in the wheel during operation. These clearance issues

were addressed by adjusting the sizing of the holes in the wheels.

Figure 9.7: MATLAB Script

The two front wheels will drive the treads and are powered by two Pololu Micro Metal Gearmotors.

The back two wheels will provide tension to the tread and allowed to freely spin. The separate

motors allow the rover to be differentially steered.

Page 120: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

120

Figure 9.8: Rover Motor Inset

Section 9.1.3: Solar Panel Deployment System (SPDS)

Page 121: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

121

Figure 9.9: SPDS Stowed vs Deployed

Figure 9.10: SPDS Deployed Position Overview

The Solar Panel Deployment System (SPDS) consists of "accordion style" folding solar panels

combined with a gear and pinion deployment mechanism, as shown in Figure 9.9: SPDS Stowed

vs Deployed. The components of the SPDS are four solar panels, the solar panel tray, a gear, and

a motor which is identical to those used for rover movement. Solar panels will be deployed from

rear of the rover. The solar panels will be 3D printed panels with solar cells adhered to both sides.

Page 122: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

122

An "accordion style" folding mechanism was chosen for minimum storage footprint and low

complexity. The four solar panels will be fastened together by pins at each end which allow

rotation. The outermost panel will be pinned to the front of the solar panel tray, while the

innermost panel will be pinned to the rover body. Thus as the solar panel tray is pushed out the

innermost end of the panels will be held stationary while the outermost end is pulled out. This

results in the solar panels extending from the vertical stowed position to the horizontal deployed

position. Each solar panel will span the width of the rover body except for a small margin left to

allow movement, resulting in a panel width of 2.125 inches. A height of 0.75 inches was chosen

for the solar panels to maximize exposed area while maintaining proper clearance between the

body and the ground. Four panels of this height yield a lateral deployment of 3 inches, exceeding

the original Project Nova goal of 2 inches lateral deployment.

A gear and pinion driving mechanism was chosen for the SPDS because this method minimized

the volume footprint of the system. This small footprint allowed the storage of the motor driver

on the same side as the SPDS, reducing the overall length of the rover. The solar panel tray will

be deployed through a geared interface between the SPDS motor and the solar panel tray, as shown

in Figure 9.11: Solar Panel Tray, Motor, and Gear. The solar panel tray was design to pass under

the motor gear to further minimize the space required and to ensure firm contact between the tray

"tail" and motor gear. The motor will be electronically controlled; however, the tray "tail" was

also designed to limit the lateral deployment of the tray. The tail was sized such that the when the

SPDS has reached full deployment (3 inches) the motor will have reached the end of the "tail" and

no longer make geared contact. Thus, there is a mechanical safeguard against control malfunction.

The solar panel tray will slide through channels cut into the wall of the body which will keep the

tray stable and secure during deployment.

Page 123: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

123

Figure 9.11: Solar Panel Tray, Motor, and Gear

Section 9.2: Electrical Design

The rover electrical design entails any part of the rover that has an electrical aspect to it. This

design group includes the microcontroller, communication system, rover orientation, and how the

rover will be powered.

The rover will remain in the rocket until it is remotely activated from the team’s location. At that

point, the orientation will be read into the Arduino from the Adafruit 9DOF. Based on the

orientation of the rocket, the motors will spin one way or another in order to move the rover out

of the body of the rocket. Upon traveling the distance of the rover (distance needed for the rover

to be outside of the rocket), the rover will turn to the left or right and will then travel a

predetermined amount of time in order to ensure the proper distance has been travelled. This

distance will be measured in the amount of time it takes to travel that far. Once this time has been

reached, the rover will stop and the SPDS will deploy.

The electrical layout is shown in Figure 9.12: Rover Electrical Layout.

Page 124: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

124

Figure 9.12: Rover Electrical Layout

Section 9.2.1: Microcontroller

An Arduino Uno has been chosen to be the microcontroller, or the “brain”, of the rover based on

past experience with the unit. Powering the Arduino is ideal as it only requires a 9V battery which

does not take up much space and the board in general allows for the attachment of shields which

support our auxiliary components.

One of the biggest benefits of using Arduino is the large amount of codes, or sketches, that already

exist online that can be easily downloaded for different electrical components that we will be using.

Being able to draw on those sketches and simply integrate them to perform the ultimate goal will

save the team time and effort.

Section 9.2.2: Communication Method

The communication system basic requirements consist of only transmitting the initialization

sequence for the rover. This basic requirement indicates that only one-way communication is

required to our rover. An additional requirement is that we can deploy the rover a quarter mile.

Page 125: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

125

This is in addition to the low power requirements and limited size and weight of the receiver. To

efficiently meet these requirements and provide an easy interface, we decided on the X-Bee

module (Figure 9.13: X-Bee Module) which interfaces easily with our designated control board,

the Arduino Uno, with an easily installable, stackable shield module (Figure 9.14: X-Bee Shield

Module on Arduino).

Figure 9.13: X-Bee Module

Figure 9.14: X-Bee Shield Module on Arduino

The chosen modules have a rated range of one mile, sufficient to overcome our range requirements.

These features and the low power requirements of approximately 3.3V at 215 mA allow our

communication channel to be easily installed. In addition to these basic features, the X-Bee

contains additional optional features and advance networking capabilities. Such feature includes

basic IO for basic switched input and output in addition to serial communication to reprogram the

Page 126: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

126

two modules or interface with the Arduino. These modules have advance messaging support to

allow for advance networks to be built with routers and repeaters in addition to encryption support

to prevent tampering. These IO channels can be used to simplify communication with our rover

with a simple trigger mechanism for on-field deployment to advance functionalities such as a real-

time communication interface. In addition, these modules contain automatic transmission options

to aid possible transmission failures that may occur from signal degradation. With these modules,

we can program them to interface with each other exclusively despite other similar transceivers in

the area (Figure 9.15: X-Bee Setup). The software we are utilizing to configure these modules,

XCTU, also empowers us to commit range testing for our modules to ensure that these modules

will succeed in the field.

Figure 9.15: X-Bee Setup

Section 9.2.3: Orientation

During landing, the rocket will tip one of four ways due to the fins (the team is making the

assumption that the rocket will not tip over and have a fin stick into the ground perpendicularly).

Based on the orientation of the rocket, the motors will need to spin one way or another to prevent

Page 127: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

127

the rover from traveling back into the rocket. The team has chosen to use an Adafruit 9DOF

Breakout unit to determine the rover orientation inside the rocket. The team has past experience

with this unit.

The Adafruit 9DOF Breakout board consists of two sensors: an FXOS8700 3-axis accelerometer

and an FXAS21002 3-axis gyroscope. With these sensors, the orientation of the rover in the rocket

will be able to be determined.

Upon landing, the rover will be activated via the XBee communication system. Once the rover

receives the signal from the launch location, the orientation will be read into the Arduino.

The value of the z-vector (positive/negative) will determine the orientation the rocket is in. Based

on this value and the code, the motors will spin one direction or the other to move the rover out of

the rocket body.

Section 9.2.4: Power

To power both the motor shield and the Arduino, two 9V batteries were used. This decision was

based on ease of access and past experience using this model of motor shield and Arduino. An

Arduino Uno’s recommended operating voltage is 7-12V and the recommend voltage for the

Adafruit V2 motor shield is 5V-12V.

Something the team took into account was the possibility that other teams purposefully delay their

own launch in order to drain other teams’ batteries. A set of tests were completed where three

motors were run at full speed until the batteries died. After three hours, the batteries had drained

to a point where the motors were not providing enough torque even though they were still turning;

this was determined to be an acceptable safety factor by the team.

Prior to each launch, the 9V batteries will be replaced to ensure the best performance. The batteries

will be placed between walls that have been printed with the body that will hold them in place no

matter the orientation of the rover. The battery walls can be seen below in Figure 9.16: Rover

Battery Setup.

Page 128: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

128

Figure 9.16: Rover Battery Setup

Section 10: Altitude Control Module

The primary objective of the team this year is to accomplish precision apogee at a mile high is to

implement a system that provides the highest accuracy of altitude self-correction. Prior teams have

pursued a grid fin design to pursue this. This year’s team will be taking on a new system. In the

vein of variable input drag systems, just like past year’s grid fin designs, the team will be

implementing an entirely internal drag system. This design uses a single motor to actuate out

composite drag plates at variable degrees to produce the desired amount of drag on the vehicle.

All components in this system will be completely encapsulated within the vehicle. Slots in the

body will be cut to provide room for the actuation of the plates.

Page 129: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

129

Section 10.1: Drag Plates

The Auburn Student Launch Team has decided this year to pursue a different drag-producing

system this year. This year’s drag system will house flat drag plates that will actuate out from the

internals of the rocket. The plates will actuate perpendicular to the airflow and will receive a direct

moment of force from flight.

After boost phase, the internal drag system will read telemetry values and continuously self-correct

the vehicle’s trajectory. This will equalize the rocket’s trip to ascension to apogee. The current

design accounts for 3 internal plates that will carry the load of the system. An Arduino controller

will be the center of system input processing. A reading for the final altitude will continually be

calculated in order to more accurately deliver the vehicle to apogee. Included in the system will be

an IMU capable of reading in acceleration on all 3 axes as well as a barometric altimeter. These

inputs will drive the system’s self-correction. After the final altitude has been reached, the drag

plates will fully retract and the system will remain static.

The new design for this competition season was chosen due to simplicity and practicality. With

the current internal drag system in mind, the only mechanical interface needed is a single motor to

drive plate actuation. While last year’s system was proved to be effective, implementation of this

new design will provide returns in build time.

This year’s drag system was initially analyzed alongside last year’s grid fin design. The following

sections show a preliminary summary of these systems, along with corresponding system

characteristics and benefits.

Section 10.1.1: Internal Plate Drag System (IPDS)

The system that will be pursued for this year’s competition is the Internal Plate Drag System

(IPDS). The concept for this design was centered on the benefits of a modular system. The housing

for this system will be able to be predominantly printed with composite materials. The team printed

Page 130: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

130

components of the design in order to prove the feasibility of using additive techniques to produce

a prototype and ultimately a final product.

Figure 10.1: IPDS System Concept

Figure 10.2: IPDS Bottom-Up View

Page 131: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

131

Arms will interface with the drag plates, which revolve around the center point controlled by the

motor. These plates will be able to actuate from a completely revolved position all the way out to

a maximum determined by the controller.

These plates will be actuated out a variable degree in order to accurately bring the rocket to apogee.

The modularity of this design is a prime benefit of using this system. Preparation for launch will

be a small hassle since the housing can be dropped in with relative ease. Another benefit is the

lack of external components. This decreases drag on the system as a whole, since no fins or fairings

have to be attached. Another consideration is the ability to operate with just a single motor. This

allows for all arms to operate from a single stream of inputs.

A potential disadvantage of the system could be the weight added to rocket. Since the IPDS

requires extensive internal housing, the weight could add up quickly depending on the material

used for the structure.

Section 10.1.2: Wall Armed Fin-Lattice Elevator (WAFLE)

The Wall Armed Fin-Lattice Elevator (WAFLE) was the drag producing system of last year’s

AUSL team. This design was used as a primary alternative. Past experience with producing this

system lent a baseline of pros and cons for pursuing this system again. The design was pursued

due to its ability to both pursue the apogee requirement for the launch vehicle as well as the roll

induction experimentation option of last year’s competition. The structure is composed of a body

tube and external fairing.

Page 132: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

132

Figure 10.3: WAFLE

The inside of the external fairing would be hollow so that multiple servos can be housed and

actuated underneath each of the fairings. The system is comprised of two single-axis drag

producing servo-fin combos as well as two two-axis grid fins, which pursued the roll induction.

Due to the changing requirements of this year’s competition, the need for roll induction has been

taken out of the design considerations for this season.

A benefit of using this system is the weight. Due to the lattice design of the grid fins, the weight

of the system will be less of a factor since a solid fin would be heavier. An external fin system also

removes the need for extensive internals. Most of the effort here could be focused on the external

components of this system.

Since this system is largely external of the rocket, this brings the difficulty of reproducing the

system. This is not a modular design, so implementing it repeatedly every time another rocket is

built would increase overhead with system integration.

Page 133: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

133

Section 10.1.3: Spherical Joint Actuator (SJA)

A design that was considered as an alternative to the IPDS is the Spherical Joint Actuator (SJA).

The structure is composed of a body tube, spherical rotator, external housing, and an internal

housing.

Figure 10.4: Spherical Joint Actuator

The spherical rotator is placed in between the internal housing and the external structure and is the

main driver of the grid fin. A threaded rod will connect the spherical actuator to the grid fin. Servos

mounted to the internal housing will be directly connected to the spherical actuator by means of

rubber dipped rods and gears. These servos will control the pitch and roll of the grid fins.

Therefore, two servos will be required to control each fin. The external mount is formed into a

fairing shape to allow for uniform flow around the grid fins when they are pitched parallel to the

airframe.

Page 134: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

134

Figure 10.5: SJA External Fairing

Attaching this system to servos and actuating the system accurately is problematic with this

configuration. If the spherical actuator creates enough friction to prevent the SJA from moving

due to drag force, the servos necessary to move the grid fins on command would have to use more

force than servos used in competing systems. If the spherical actuator does not create enough

friction to prevent the SJA from moving freely, the drag force will prevent the SJA from deploying.

This system, however, allows for the SJA to have two degrees of freedom.

Section 10.1.4: System Comparison

Included below is a table of comparison weighing the value of both systems against each other in

order to determine a result.

Table 10.1: Drag System Comparison

Option 1 2 3

Page 135: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

135

System Internal Plate Drag

System (IPDS)

Wall Armed Fin –

Lattice Elevator

(WAFLE)

Spherical Joint

Actuator (SJA)

Overall Volume 2 3 2

Optimization

Quality 3 2 3

Reliability 3 2 2

Cost 3 3 2

Total 11 10 9

The IPDS is the optimal path forward due to its modularity and its use of a single motor to interface

with all mechanical components. The small number of parts will allow the system be very simple

in implementation and reliable in flight. Once the system is tested, it can be used in flight. The

IPDS will be the system used to achieve the altitude goal.

Section 10.2: Drag Plate Deployment

The team is utilizing the single-motor benefit to its advantage. This allows for all 3 plates in the

system to be actuated out at the same degree relative to each other with minimal risk. There is less

risk with this than if each plate had its own mechanical driver (motor or servo). A ring connector

will interface with the rod of the motor, which connects the three arms that are attached to each

plate. When the controller reads input from the flight, this will trigger a responsive from the motor,

which spins a variable degree. This will move the arms that same degree around which will result

in the plates actuating outside of the rocket exterior producing a determined amount of drag on the

vehicle.

Page 136: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

136

Alternatively, each plate could have had its own motor or servo. As described above, this would

not be ideal. Implementing the system in this manner would add weight, complexity, and risk to

the system; Added weight due to the extra motors/servos, added complexity due to the need to talk

to each different driver, and added risk because of all of the extra components needed.

Section 10.3: Components

Section 10.3.1: Controller

The Arduino Uno was chosen as the right choice to implement into the IPDS. A selection table is

shown below to represent weighing factors of choosing a driver. The chosen controller contains

the right number of I/O pins needed for the project, as well as open source libraries included due

to a large development community. This significantly reduces the overheard when prototyping our

design. The controller will act as the decision maker for the system, determining the rate at which

the vehicle should self-correct its trajectory.

Table 10.2: Arduino Options

Board Operating Voltage

(V) Analog I/O

Digital I/O

Mega 5/7-12 16/0 54/15

Micro 5/7-12 8/0 20/7

Uno 5/7-12 6/0 14/6

Page 137: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

137

One of the most important considerations when choosing a controller for this system was size. The

Uno has an ideal size for integration with the IPDS. While the Micro takes up less space, it does

not provide the same ease-of-use that the Uno does. The Mega maintains the most I/O ports, but

the board takes up more system space. Due to unnecessary number of pins that comes with the

Mega, the Uno is the ideal choice. With a rocket inner diameter of 6 inches, size is an important

design consideration. A 9V battery will power the board.

Figure 10.6: Arduino Uno Microcontroller

Figure 10.7: IMU Breakout

Page 138: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

138

Table 10.3: Microcontroller Data

Values Adafruit IMU

Breakout

StratoLogger

Altimeter

SparkFun Triple-

Axis Gyro

Cost $29.95 $54.95 $24.95

Area Covered 1.35 1.68 0.6264

# of Other

Components Needed 0 2 2

Avg. Supply Voltage 7.5 1.5 2.85

Data Logged (DOF) 10 4 3

Table 10.4: Normalization of Data

Values 1 2 3 4 5 6

Cost >300 >200 >100 >50 >25 <25

Area

Covered >2 >1.5 >1.0 >0.5 >0.25 <0.25

# of Other

Components

Needed

2 1 0

Avg. Supply

Voltage >10 >8 >6 >4 >2 <2

Page 139: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

139

Data

Logged

(DOF)

3 4 5 6 9 10

Table 10.5: Trade Study Weighting Factors

Item Factor Reason

Cost 3

The team may need other

parts depending on which

unit.

Area Covered 1 Space in the rocket must be

efficiently used.

# of Other Components

Needed 4

It needs to be taken into

consideration because we

might need to purchase

separate units vs just one

IMU.

Avg. Supply Voltage 2 The supply voltage affects the

power drain of the system.

Data Logged (DOF) 5

The more DOF, the more data

in one unit, which is a factor

for our data storage and

process capabilities.

Page 140: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

140

Table 10.6: Sensor Trade Study (Normalized Values)

Values Adafruit IMU

Breakout

StratoLoggerCF

Altimeter

SparkFun Triple-

Axis Gyro

Cost 5 4 6

Area Covered 3 2 4

# of Other

Components Needed 6 1 1

Avg. Supply Voltage 3 6 5

Data Logged (DOF) 6 2 1

Table 10.7: Sensor Trade Study (Weighted Values)

Values Adafruit IMU

Breakout

StratoLoggerCF

Altimeter

SparkFun Triple-

Axis Gyro

Cost 15 12 18

Area Covered 3 2 4

# of Other

Components Needed 24 4 4

Avg. Supply Voltage 6 12 10

Data Logged (DOF) 30 10 5

Total 78 40 41

Page 141: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

141

Section 10.3.2: Motor

For our motor, which is driving the drag plate actuation, we chose to use the NeveRest 40 DC

Motor made from AndyMark. This motor is ideal because of its inexpensiveness coupled with its

effectiveness for our application compared to other DC motors. The NeveRest motor comes pre-

crimped while using eight-teen gauge wire, along with fifth-teen connectors. For the weight and

diameter of the motor it delivers the most power out of any other similar 40 DC motor. The body

and gears are manufactured with top of the line steel, which is vital for the durability of the system.

Figure 10.8: AndyMark NeveRest 40 DC Motor

Table 10.8: AndyMark NeveRest 40

Motor Specifications

Price $28.00

Weight 0.18lb

Pulse/Revolution 28

RPM 160

Page 142: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

142

Alternatives to our motor choice are displayed below. They were not chosen due to weight and

pricing.

Table 10.9: Uxcell 40 RPM 24V Motor (Alternative)

Motor Specifications

Price $90.00

Weight 2.87lb

Pulse/Revolution 25

RPM 40

Table 10.10: New Guanlian RE 40 (Alternative)

Motor Specifications

Price $90.00

Weight 2.87lb

Pulse/Revolution 25

RPM 40

Section 10.3.3: Electronics

The entire system is powered by 2 9V batteries in parallel. One will provide the power for the

Arduino controller, while the other provides power to the motor shield that will be attached to the

controller. The motor shield serves as a power regulator as well as a medium of communication

for the DC motor. Commands in the Arduino IDE can be used to communicate with the motor and

Page 143: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

143

control factors such as direction and rotations-per-minute. This will allow for better control of the

launch vehicle in flight.

Section 10.3.4: Interfaces

Three flat plates will be paired with a 9-volt battery, an Arduino Uno, and a single DC motor

embedded within the body of the launch vehicle. The plates as well as the housing for the plates

and electronics will be 3D printed using HIPS (high impact polystyrene). The internal system is

also more durable since it uses a honeycomb shape to maximize strength and minimize weight.

The motor used in this year’s design is a NeveRest Classic 40 Gearmotor. The benefit of using a

single motor is the simpler circuit compared to last year’s design, which used a total of six servos

to control four grid fins. The plates will be actuated outwards by the DC motor outwards in order

to increase drag. The horizontal deployment causes less resistance to the motor since it does not

force the fins against the drag directly.

Section 10.3.5: Precision of Instrumentation

The Arduino Uno will receive the required altitude information from an Adafruit 9-DOF IMU

Breakout unit. This unit was chosen based on its versatility as a comprehensive measurement

system: a 3-axis gyroscope (±250, ±500, or ±2000 degree-per-second scale), a 3-axis compass

(±1.3 to ±8.1 gauss magnetic field scale), a 3-axis accelerometer (±2g/±4g/±8g/±16g selectable

scale), and a barometric (300 - 1100hPa range)/temperature (-40 to 85 °C) gauge. The precision of

the control system, the inertial-measurement-unit, and the production process allows for accurate

repetition of measurement and production in all stages of this project. The data obtained from the

Adafruit 9-DOF IMU Breakout unit will be stored on an 8GB 9p SDHC Class 4 Secure Digital

Card attached to the Arduino Uno.

Page 144: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

144

Section 10.4: Dimensional Drawings

Figure 6.7: IPDS

Section 11: Project Plan

Section 11.1: Testing

In addition to the creation of requirements, it is essential to verify that they are satisfied. The pre-

competition full scale launches provide a method to check the function of all components, but

testing all systems at once introduces a large degree of risk and reduces the time to make changes

if needed. Therefore, although the goal is for all requirements to be verified through launching a

full-scale rocket with fully functional payloads, when possible components should be tested

previously and separately. Each of the following tests lists first the Auburn University

requirements that the test aims to confirm compliance with, the procedure used, and then reports

whether the test was determined to be a success.

Page 145: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

145

Section 11.1.1: Rover Battery and Motor Test (AU 4.4, 4.5)

Test Objective

This test aimed to verify the longevity of the electronics of the rover, in accordance with AU

requirements:

AU 4.4 Rover electronics must be able function after being left on for more than two hours.

AU 4.5 Rover motors must be able to function after more than two hours of battery drain.

This test was to be considered successful if the rover electronics were still functional after two or

more hours of intense battery drain.

Justification

Between time spent on the launch pad and time waiting to be deployed after landing, the rover

system will be experiencing power drain for a significant period of time. This power drain will

be less strenuous than two hours of continuous motor operation, however simply leaving the

system in its highest power consuming state provides a useful benchmark for the test. If the Rover

system could not sustain this level of operation, the Rover would need to be redesigned to ensure

mission completion.

Test components

-Arduino Uno

-New 9V batteries

-Rover Motors

-Multimeter

Procedure

1. Assemble the motors, control circuits, and batteries into the planned launch

configuration.

Page 146: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

146

2. Turn on the Arduino and the motors.

3. Measure the initial voltage from the batteries using the multimeter. Battery 1 was

connected to the Arduino, while battery 2 was providing power to the motors.

4. Take voltage measurements every thirty minutes, ending the test if any components

stopped functioning.

Results

Voltage Reading (Volts)

Time (AM) Battery 1 Battery 2

7:45 9.2 8.8

8:15 8.4 7.6

8:45 8 7

9:15 7.8 6.8

9:45 7.6 6.5

10:15 7.4 6.2

10:45 7 5.9

11:15 7 5.4

11:45 7 5.4

Although very simple, this test has provided some very important data. The motors were able to

run continuously for over three and a half hours off of a single 9V battery. This is a much higher

power drain than expected for simply standing idle in the launch configuration, so even in a case

of extreme battery usage the rover will still exceed AU requirement AU 4.5. The Arduino was

still functional after four hours, double AU 4.4 and four times NASA requirement 2.10 for vehicle

components endurance in the standby launch position.

Design Changes due to Test

Page 147: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

147

None, the Rover electronics met and exceeded all requirements for the test. This confirms that the

planned electronics setup can be used in the final design.

Section 11.1.2: Recovery and Altitude Control Battery Tests (AU 3.1, 6.9)

Test(s) Objective

Since these two tests are very similar, they have been combined here. They are both intended to

address NASA requirement 2.10, and the more strenuous AU requirements

AU 4.4 Recovery electronics must be able function after being left on for more than two hours.

AU 4.5 Altitude electronics must be able to function after more than two hours of battery drain.

These tests will be considered successful if the respective electronics are still operational after two

or more hours of intense battery drain.

Justification

Both electronics systems, like the rover, may need to standby in the on position for quite some

time on the launchpad before launch. The recovery system must still operate after this time for

mission completion. Although not as critical, the altitude control system must still operate as well

in order to not overshoot the mile altitude goal. If these systems cannot sustain this level of

operation, they will need to be redesigned to incorporate longer lasting batteries.

Test components

-Recovery altimeters

-Fully charged batteries

-Altitude control system Arduino Uno

-Multimeter

Procedure

Page 148: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

148

1. Assemble the motor (in the case of the altitude control system), control circuits, and

batteries into the planned launch configuration.

2. Turn on the Arduino and the motor or the two altimeters.

3. Measure the initial voltage from the batteries using the multimeter.

4. Take voltage measurements every thirty minutes, ending the test if any components

stopped functioning.

Results

Once the electronics in question are completed for full scale, these tests will be performed

Possible Design Changes due to Test

If any issues arise, they should be solvable by increasing the storage ability of the batteries used

by the systems.

Section 11.1.3: Full-Scale and Subscale Separation Test (AU 3.2)

Test Objective

This test is highly essential for both successful flight execution and safety. Ground Separation

testing was used to verify AU requirement

AU 3.2 Recovery system will be able to separate rocket into desired sections using the minimum

amount of black powder for reliable results, to ensure safety.

and NASA requirement

3.2 Each team must perform a successful ground ejection test for both the drogue and main

parachutes. This must be done prior to the initial subscale and full-scale launches.

Justification

Too little black powder, and the rocket will not separate, preventing parachute deployment, leading

to mission failure and more importantly a dangerous projectile. Too much black powder, however,

provides a fire and explosive hazard to team and launch personnel, and similarly can damage rocket

components. Therefore, it is important to use ground separation testing to determine the minimum

amount of black powder necessary to separate sections and eject the parachutes.

Page 149: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

149

This test must be performed for both the subscale and full-scale rocket. Although rules exist for

scaling and theoretically determining the required powder, the team prefers to use these methods

as a starting point to be checked with proper testing.

Test components

-Recovery Barometric Avionics Enclosure (BAE) structure

-Launch configuration upper or lower recovery section, secured with shear pins, including

● Main parachute (with drogue in upper section)

● Shock cord

● Recovery wadding

● Assembled black powder charges

● Nose cone or first lower body section coupler (depending on upper or lower

section)

-Electronic matches

-Ignition system

-Fire extinguisher (have not needed to use it, but always will be located beforehand)

Procedure

1. Fill charge cups according to equation established in the Recovery Section, or to

increased amount based on the result of the previous test/launch. (The equation from the

recovery section is an ideal case, and has been found from previous years to undershoot

the required amount).

2. Assemble structural components of the BAE with the electronic matches threaded

through to reach the charge cups. (Using the complete electronics system is possible but

not necessary)

3. Attach recovery section tube to the BAE, packing charges, wadding, parachutes, etc. as

they would be for a launch.

4. Seal the recovery section with the coupler or nose cone that completes the enclosure,

securing with shear pins.

Page 150: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

150

5. Place the assembled system on the ground or a test stand away from all personnel.

6. Attach the electronic matches to the power supply, and after verifying everyone is at a

safe distance, fire the charges.

7. If the components separate, record the amount of black powder used. If the charges do

not separate the components, disassemble the rocket and increase the charge.

Figure 11.1: Subscale Separation Test

Figure 11.1: Subscale Separation Test shows the subscale lower section prior to conducting

separation testing. The BAE is orange, on the right, and the wires to the electronic matches can

be seen trailing off to a further distance that all members retreated to in order to conduct the test

after this photo was taken.

Results

Separation testing was completed for the subscale rocket at the launch field in Samson, Alabama

on November 4, 2017. Through a series of tests, it was determined that both the upper and lower

sections recovery sections would require 4 grams of black powder to successfully separate the

subscale sections and deploy the parachutes. When flown in this configuration, the subscale was

successfully recovered.

A date and location for full scale separation testing has not yet been determined, as it is reliant on

the completion of several full scale components, such the the BAE.

Page 151: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

151

Design Changes due to Test

The 4 grams of black powder per charge cup determined still fit within the original charge cup

design, and all recovery components fit into the section, so no changes were necessary.

Section 11.1.4: Tension Testing of Composite and 3D Printed Material (AU 2.1,

2.2)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

properties of composite materials vary heavily depending on such factors as matrix orientation,

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

Page 152: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

152

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

1. For the tensile testing, the team took the plates of Onyx 3D-printed Carbon Fiber, Epoxy

Carbon Fiber, and Epoxy Fiberglass, and measured their length, width, and depth using

dial calipers.

2. Once in the materials testing lab, the team outfitted the Instron Multipurpose testing

machine with the hardware appropriate for the thickness of each material.

3. After proper setup of the machine, measurements were taken again to ensure absolute

accuracy.

4. The material sample dimensions were then inputted into the computer interface.

5. The material was then placed between the grips of the apparatus and the chuck was

torqued to ensure proper grip on the material being tested

6. The load and strain were then zeroed out on the computer interface, after which the test

was commenced.

7. The data was then analyzed and plotted until the max stress and load of each specimen

was reached, and the sample torn, at which point the machine automatically ended the

test.

Results

Figure 11.2: Epoxy - Carbon Fiber Tension Test Results

Page 153: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

153

Figure 11.3: Epoxy - Fiberglass Tension Test Results

Page 154: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

154

Figure 11.4: Onyx Tension Test Results

This test provided the data that allows for the calculation of the maximum stress, modulus, tensile

strength and the tensile strain at the maximum load of all of the materials used in the structural

aspects of the rocket. This allows for the determination of the wall dimensions to allow for the

rocket to be stable in flight and during recovery. The stresses that the samples were put under were

much higher than would be seen in a normal flight/recovery pattern, proving the structural integrity

of the materials used.

Section 11.1.5: 3-Point Bend Testing of Composite and 3D Printed Material

(AU 2.1, 2.2, 6.7)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

Page 155: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

155

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

properties of composite materials vary heavily depending on such factors as matrix orientation,

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

-The machine used for this test was the Instron Multipurpose testing machine.

1. First, five samples of each type of material were constructed and their length, width, and

thickness were measured using calipers for accuracy.

2. Once in the materials lab, measurements were taken again to ensure absolute accuracy

within the machine.

3. The material sample dimensions were then input into the computer interface.

4. The material sample was then placed within the apparatus and lined up by eye to center it

between two solid contact points. The machine was then positioned with accuracy using

various dials to ensure the contact arm was slightly in contact with the material species.

Page 156: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

156

5. The load and extension were zeroed then the user began the test within the interface of

the computer.

6. The data was then analyzed and plotted until the max flexure load of each specimen was

reached, at which point the machine automatically ended the test.

Results

Figure 11.5: Epoxy - Carbon Fiber Bend Test Results

Page 157: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

157

Figure 11.6: Epoxy - Fiberglass Bend Test Results

Figure 11.7: Onyx Bend Test Results

Page 158: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

158

This test provided the data that allows for the calculation of the maximum stress of all of the

materials used in the structural aspects of the rocket. This allows for the determination of the wall

thicknesses to allow for the rocket to be stable in flight and during recovery. The stresses that the

samples were put under were much higher than would be seen in a normal flight/recovery pattern,

proving the structural integrity of the materials used. This does not result in any design changes,

but instead was useful for design creation.

Section 11.1.6: Compression Testing of Composite and 3D Printed Material

(AU 2.1, 2.2, 6.7)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

properties of composite materials vary heavily depending on such factors as matrix orientation,

Page 159: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

159

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

-The machine used for this test will be the Instron Multipurpose testing machine. Due to

equipment availability restraints, these tests could not be completed this year, and instead data

from previous years were used during construction.

1. First, five samples of each type of material were constructed and their length, width, and

thickness were measured using calipers for accuracy.

2. Once in the materials lab, measurements were taken again to ensure absolute accuracy

within the machine.

3. The material sample dimensions were then input into the computer interface.

4. The material sample was then placed within the apparatus and lined up by eye to center it

between two solid contact points. The machine was then positioned with accuracy using

various dials to ensure the contact arm was slightly in contact with the material species.

5. The load and extension were zeroed then the user began the test within the interface of

the computer.

6. As the progressively larger load was applied, the data was then analyzed and plotted until

each specimen reached -30% elongation, at which point the machine automatically ended

the test.

Results

Current results are not yet available, as this test is still only planned

Potential design changes

Page 160: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

160

Although unlikely, if this year’s data varies significantly from the previous structural data used to

design the rocket, design changes to reinforce vulnerable rocket components.

Section 11.1.7: Rover Maneuverability (AU 4.2, 4.3, 4.6, 4.7)

Test Objective

As outlined in requirements

AU 4.2 Rover can be activated remotely from a distance

AU 4.3 Rover must be able to traverse various expected terrains

AU 4.6 Rover must be able to exit the vehicle body from any orientation

AU 4.7 Rover will successfully deploy solar panels after travelling at least 5 feet

This test will aim to determine the cross country performance of the rover, and whether it will be

able to cross the farm field after leaving the rocket from any orientation. While already on testing

all these other aspects of the rover, it makes sense to test the remote activation as well. Success

will be defined as accomplishing all mission objectives.

Justification

The competition launch will take place on a farmer’s field. Cropland, whether left fallow or

planted in, will be very rough terrain for a small rover. Tufts of grass, grooves in the dirt from the

plow, eroded paths left by water runoff, and mud are all major obstacles when compared to the

size of the rover. To reach the desired distance, however, the rover must be able to cross these

obstacles. To complete its objective, the rover must then also be communicated with and deploy

solar panels.

Test Components

-Completed Rover

-Rocket rover bay (optional)

Page 161: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

161

-Shovel

-Measuring equipment

Procedure

The expected obstacles are characteristics shared by many open fields, including those used as

extra parking on Auburn’s Campus. Therefore, the rover can simply be taken to one of these

locations and activated to see if it can cross the terrain. If the team cannot find particular terrain

features outlined in AU 4.3, the shovel will be used to construct that feature.

After finished testing that capability, the lower section of the rocket, or at least the rover bay, can

be staged on the field as if it had just landed. AU 4.2 will be tested to see if the rover can be

activated remotely while it is inside the rocket. Once remote activation has been verified, the rover

will be remotely activated while the rover bay is rotated off the horizontal at various angles to

determine if it can leave the rocket after landing in any orientation and will be commanded to

deploy solar panels to verify AU 4.6 and 4.7.

Results

The rover is still under construction, so results are not yet available

Possible design impacts

Since the rover is made entirely of 3D printed components, the design can be rapidly iterated in

response to any issues arising from this series of tests. The most likely changes would be

adaptations of the tread design, or changes with regards to the wheels.

Section 11.1.8: Altitude Control System (AU 6.4 – 6.8)

Test Objective

This test aims to address several closely related team derived requirements for the altitude control

system, which are seen in the table below.

Page 162: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

162

AU

Requirement Description

AU 6.4 Subsystem components must engage accordingly after boost phase and stay online

for the remainder of the flight.

AU 6.5 Controller and IMU must be able to correctly predict the projected altitude of the

launch vehicle.

AU 6.6 Drag plates must deploy after boost phase in order to self-correct the trajectory of

the launch vehicle.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow.

AU 6.8 The altitude control system must be able to correct the vehicles altitude from

overshoot to 5280 ft.

To test all of these requirements at once, a special test 6” rocket will be constructed (time and

funds permitting). This rocket will be 6” diameter, like the actual full scale, but will be shorter,

possessing a weaker motor and greatly simplified recovery. The altitude control system will

control this rocket to a lower altitude of 3200 ft. The test will be considered a success if the altitude

control system can fulfill all the above requirements, albeit to a lower altitude.

If this cannot be tested in a separate rocket, these requirements will be verified by a launch of the

system inside the completed full scale rocket.

Justification

A major component of the competition is the altitude requirement. However, an altitude control

system can also be the most dangerous aspect of a rocket, even in the case of our team’s design

where an engineering control has been applied to prevent asymmetric drag. The system is also

difficult to meaningfully ground test. Therefore, by first testing the system on an expendable

Page 163: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

163

rocket with a lower apogee, the team can improve safety and avoid risking any of the other full

scale components, such as the isogrid body tube, that are difficult to replace at short notice.

Finally, more construction will provide additional experience for the team’s junior members.

Test Components

-Completed Altitude control system (designed to be easily added and removed from the rocket,

and retargetable for different altitudes)

-6” Diameter, 88” length test rocket with recovery system

-Aerotech K560W-P Motor

Procedure

Due to the similarity of this test to a full scale launch, the procedure for this test will be the same

as the procedure of a full scale launch, as seen in the launch checklist.

Results

This test has not yet been completed

Possible design impacts

If the altitude system over or under corrects, the software controlling the estimated drag plate drag

and therefore position will be adjusted. If the system cannot be safely implemented, it will be

eliminated from the final full-scale rocket.

Section 11.2: Requirements Verification

Section 11.2.1: General Requirements

Table 11.1: General Requirements Verification

Page 164: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

164

Requirement

Number Requirement Statement Verification Method

Execution of

Method

1.1

Students on the team will do

100% of the project,

including design,

construction, written reports,

presentations, and flight

preparation with the

exception of assembling the

motors and handling black

powder or any variant of

ejection charges, or preparing

and installing electric

matches (to be done by the

team’s mentor).

Demonstration

Students on the team

will do 100% of the

project.

1.2

The team will provide and

maintain a project plan to

include, but not limited to the

following items: project

milestones, budget and

community support,

checklists, personnel

assigned, educational

engagement events, and risks

and mitigations.

Demonstration

The team will

provide and maintain

a project plan.

1.3

Foreign National (FN) team

members must be identified

by the Preliminary Design

Demonstration

FN team members

have been identified

by the PDR.

Page 165: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

165

Review (PDR) and may or

may not have access to

certain activities during

launch week due to security

restrictions. In addition, FN’s

may be separated from their

team during these activities.

1.4

The team must identify all

team members attending

launch week activities by the

Critical Design Review

(CDR)

Demonstration

The team will

identify all members

attending launch

week by the CDR.

1.5

The team will engage a

minimum of 200 participants

in educational, hands-on

science, technology,

engineering, and mathematics

(STEM) activities, as defined

in the Educational

Engagement Activity Report,

by FRR. An educational

engagement activity report

will be completed and

submitted within two weeks

after completion of an event.

A sample of the educational

engagement activity report

can be found on page 31 of

the handbook. To satisfy this

Demonstration

The team will

complete the

Educational

Engagement

requirements.

Page 166: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

166

requirement, all events must

occur between project

acceptance and the FRR due

date

1.6

The team will develop and

host a Web site for project

documentation.

Demonstration

The team has

developed and will

host a Web site for

project

documentation.

1.7

Teams will post, and make

available for download, the

required deliverables to the

team Web site by the due

dates specified in the project

timeline.

Demonstration

The team will post

the required

deliverables to the

team Web site by the

due dates specified.

1.8 All deliverables must be in

PDF format Demonstration

All deliverables will

be in PDF format.

1.9

In every report, teams will

provide a table of contents

including major sections and

their respective sub-sections

Demonstration

Every report will

contain a table of

contents.

1.10

In every report, the team will

include the page number at

the bottom of the page.

Demonstration

Every report will

include page

numbers.

1.11

The team will provide any

computer equipment

necessary to perform a video

Demonstration

The team will

provide all necessary

equipment for the

Page 167: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

167

teleconference with the

review panel. This includes,

but is not limited to, a

computer system, video

camera, speaker telephone,

and a broadband Internet

connection. Cellular phones

can be used for speakerphone

capability only as a last

resort.

video

teleconferences.

1.12

All teams will be required to

use the launch pads provided

by Student Launch’s launch

service provider. No custom

pads will be permitted on the

launch field. Launch services

will have 8 ft. 1010 rails, and

8 and 12 ft. 1515 rails

available for use.

Demonstration

The team will use the

launch pads

provided.

1.13

Teams must implement the

Architectural and

Transportation Barriers

Compliance Board Electronic

and Information Technology

(EIT) Accessibility Standards

(36 CFR Part 1194)

Demonstration

The team will

implement the EIT

Accessibility

Standards.

1.14 Each team must identify a

“mentor.” A mentor is Demonstration

The team has

identified a mentor.

Page 168: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

168

defined as an adult who is

included as a team member,

who will be supporting the

team (or multiple teams)

throughout the project year,

and may or may not be

affiliated with the school,

institution, or organization.

The mentor must maintain a

current certification, and be in

good standing, through the

National Association of

Rocketry (NAR) or Tripoli

Rocketry Association (TRA)

for the motor impulse of the

launch vehicle and must have

flown and successfully

recovered (using electronic,

staged recovery) a minimum

of 2 flights in this or a higher

impulse class, prior to PDR.

The mentor is designated as

the individual owner of the

rocket for liability purposes

and must travel with the team

to launch week. One travel

stipend will be provided per

mentor regardless of the

number of teams he or she

Page 169: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

169

supports. The stipend will

only be provided if the team

passes FRR and the team and

mentor attends launch week

in April.

Section 11.2.2: Vehicle Requirements

Table 11.2: Vehicle Requirements Verification

Requirement

Number Requirement Statement

Verification

Method Execution of Method

2.1

The vehicle shall deliver

the science or

engineering payload to

an apogee altitude of

5,280 feet above ground

level (AGL).

Analysis

Demonstration

Testing

The vehicle will be designed

to reach 5,280 ft AGL, test

launches will be performed,

and altimeters will be

assessed post launch.

2.2

The vehicle shall carry

one commercially

available, barometric

altimeter for recording

the official altitude used

in determining the

altitude award winner.

Inspection

Demonstration

The team has purchased and

calibrated several

commercially available

altimeters.

Page 170: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

170

2.3

Each altimeter will be

armed by a dedicated

arming switch that is

accessible from the

exterior of the rocket

airframe when the rocket

is in the launch

configuration on the

launch pad.

Inspection

Demonstration

The team will make the

altimeters capable of being

armed from the exterior of

the rocket airframe in launch

configuration.

2.4

Each altimeter will have

a dedicated power

supply.

Inspection

Demonstration

The altimeters will have

dedicated power supplies.

2.5

Each arming switch will

be capable of being

locked in the ON position

for launch (i.e. cannot be

disarmed due to flight

forces).

Demonstration

The team will use an arming

switch that cannot be

disabled due to launch

forces.

2.6

The launch vehicle shall

be designed to be

recoverable and reusable.

Reusable defined as

being able to launch

again on the same day

without repairs or

modifications.

Testing

Analysis

Demonstration

Inspection

Trajectory simulations and

testing will ensure the launch

vehicle is recoverable and

reusable

Page 171: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

171

2.7

The launch vehicle shall

have a maximum of four

(4) independent sections.

Demonstration

Team will design and build a

launch vehicle that can have,

but does not require, four

independent sections.

2.8

The launch vehicle shall

be limited to a single

stage.

Demonstration Team will design and build a

single-stage launch vehicle.

2.9

The launch vehicle shall

be capable of being

prepared for flight at the

launch site within 3

hours, from the time the

Federal Aviation

Administration flight

waiver opens.

Demonstration

Team will be timely and

organized to ensure vehicle

is prepared on time.

2.10

The launch vehicle shall

be capable of remaining

in launch-ready

configuration at the pad

for a minimum of 1 hour

without losing the

functionality of any

critical on-board

component.

Demonstration

Team will design vehicle

with ability to remain

launch-ready for at least one

hour.

Page 172: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

172

2.11

The launch vehicle shall

be capable of being

launched by a standard

12 volt direct current

firing system. The firing

system will be provided

by the NASA-designated

Range Services Provider.

Demonstration

The team will use systems

compatible with a standard

firing system.

2.12

The launch vehicle shall

require no external

circuitry or special

ground support

equipment to initiate

launch (other than what

is provided by Range

Services).

Demonstration

The team has designed a

vehicle requiring no external

circuitry or special ground

support equipment

2.13

The launch vehicle shall

use a commercially

available solid motor

propulsion system using

ammonium perchlorate

composite propellant

(APCP) which is

approved and certified by

the National Association

of Rocketry (NAR),

Tripoli Rocketry

Association (TRA),

Demonstration

Vehicle will be designed

around commercially

available, certified motors

Page 173: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

173

and/or the Canadian

Association of Rocketry

(CAR).

2.13.1

Final motor choices must

be made by the Critical

Design Review (CDR).

Demonstration A final motor choice has

been made.

2.13.2

Any motor changes after

CDR must be approved

by the NASA Range

Safety Officer (RSO),

and will only be

approved if the change is

for the sole purpose of

increasing the safety

margin.

Demonstration

If the change is made to

increase safety margin,

NASA RSO will allow the

change

2.14

Pressure vessels on the

vehicle shall be approved

by the RSO and shall

meet the following

criteria:

Demonstration Any pressure vessels will be

approved by the RSO.

2.14.1

The minimum factor of

safety (Burst or Ultimate

pressure versus Max

Expected Operating

Pressure) shall be 4:1

Inspection

Analysis

Testing

Team will design the

pressure vessels to have a

factor of safety of 4:1.

Page 174: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

174

with supporting design

documentation included

in all milestone reviews.

2.14.2

Each pressure vessel

shall include pressure

relief valve that sees the

full pressure of the tank.

Demonstration Pressure vessels will include

a pressure relief valve.

2.14.3

Full pedigree of the tank

shall be described,

including the application

for which the tank was

designed, and the history

of the tank, including the

number of pressure

cycles put on the tank, by

whom, and when.

Inspection

Demonstration

The team will inspect the

tank along with

documentation of testing and

history

2.15

The total impulse

provided by a College

and/or University launch

vehicle shall not exceed

5,120 Newton-seconds

(L-class).

Demonstration

Analysis

The team has choosen a

motor with a total impulse

that does not exceed 5,120

Newton-seconds (L-class).

2.16

The launch vehicle shall

have a minimum static

stability margin of 2.0 at

the point of rail exit.

Testing

Demonstration

Analysis

The team will design and test

the vehicle to ensure that it

has a stability margin of 2.0

at the point of rail exit.

Page 175: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

175

2.17

The launch vehicle shall

accelerate to a minimum

velocity of 52 fps at rail

exit.

Demonstration

Analysis

Testing

The team will design the and

test the vehicle to ensure that

it’s minimum velocity at rail

exit is at least 52 fps.

2.18

All teams shall

successfully launch and

recover a subscale model

of their rocket prior to

CDR.

Demonstration

Testing

A successful subscale model

has been launched and

recovered.

2.18.1

The subscale model

should resemble and

perform as similarly as

possible to the full-scale

model, however, the full-

scale shall not be used at

the subscale model.

Demonstration

The subscale model was

designed to resemble and

perform similarly to the full

scale model.

2.18.2

The subscale model shall

carry an altimeter

capable of reporting the

model’s apogee altitude.

Demonstration

An altimeter capable of

reporting the model’s apogee

altitude was implemented on

the subscale model.

2.19

All teams shall

successfully launch and

recover their full-scale

rocket prior to FRR in its

final flight configuration.

The rocket flown at FRR

must be the same rocket

Testing

Demonstration

Analysis

A test of the full-scale rocket

will be exhibited,

demonstrating all hardware

functions properly.

Page 176: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

176

flown on launch day. The

following criteria must

be met during the full

scale demonstration

flight:

2.19.1

The vehicle and recovery

system shall have

functioned as designed.

Testing

Testing of vehicle will show

how recovery system

functions.

2.19.2.1

If the payload is not

flown, mass simulators

shall be used to simulate

the payload mass.

Testing

Demonstration

Analysis

Payload will be flown.

2.19.2.1.1

The mass simulators

shall be located in the

same approximate

location on the rocket as

the missing payload

mass.

Inspection

Inspection of the rocket

payload will be done by the

team to ensure it is properly

placed.

2.19.3

If the payload changes

the external surfaces of

the rocket (such as with

camera housings or

external probes) or

manages the total energy

of the vehicle, those

systems shall be

Demonstration

The payload does not change

the external surface of the

vehicle.

Page 177: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

177

activated during the full-

scale demonstration of

flight.

2.19.4

The full-scale motor does

not have to be flown

during the full-scale test

flight.

Demonstration

The full-scale motor may or

may not be flown during the

full-scale test flight.

2.19.5

The vehicle shall be

flown in its fully

ballasted configuration

during the full-scale test

flight.

Demonstration The vehicle will be fully

ballasted during test flights.

2.19.6

After successfully

completing the full-scale

demonstration flight, the

launch vehicle or any of

its components shall not

be modified without the

concurrence of the

NASA Range Safety

Officer (RSO).

Demonstration

The team will demonstrate

that it did not alter any

components or vehicle after

demonstration flight.

2.19.7

Full scale flights must be

completed by the start of

FRRs (March 6th, 2018).

If necessary, an extension

to March 28th, 2018 will

be granted. Only granted

for re-flights.

Demonstration A full-scale flight will be

completed by FRRs.

Page 178: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

178

2.20

Any structural

protuberance on the

rocket shall be located aft

of the burnout center of

gravity.

Demonstration

Any structural protuberances

on the vehicle will be aft of

the burnout center of gravity.

2.21.1

The launch vehicles shall

not utilize forward

canards.

Demonstration The team will not utilize

forward canards.

2.21.2

The launch vehicle shall

not utilize forward firing

motors.

Demonstration The team will not utilize

forward firing motors.

2.21.3

The launch vehicle shall

not utilize motors that

expel titanium sponges

(Sparky, Skidmark,

MetalStorm, etc.)

Demonstration

The team will not utilize a

motor that expels titanium

sponges.

2.21.4 The launch vehicle shall

not utilize hybrid motors. Demonstration

The team will not utilize a

hybrid motor.

2.21.5

The launch vehicles shall

not utilize a cluster of

motors.

Demonstration

A demonstration and

inspection of the launch

vehicle shall be carried out to

Page 179: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

179

validate it does not use a

cluster of motors.

2.21.6

The launch vehicle shall

not utilize friction fitting

for motors.

Demonstration

The team will design the

vehicle so that it does not

utilize friction fitting for the

motor.

2.21.7

The launch vehicle shall

not exceed Mach 1 at any

point during flight.

Demonstration

Testing

Analysis

The team will design, test,

and demonstrate vehicle

performance to ensure that

the vehicle does not exceed

Mach 1 at any point during

flight.

2.21.8

Vehicle Ballast shall not

exceed 10% of the total

weight of the rocket.

Demonstration

Testing

Analysis

The team will design ballast

so that it does not exceed

10% of the total weight of

the rocket.

Section 11.2.3: Recovery Requirements

Table 11.3: Recovery Requirements Verification

Requirement

Number Requirement Statement Verification Method

Execution of

Method

Page 180: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

180

3.1

The launch vehicle shall

stage the deployment of its

recovery devices, where a

drogue parachute is deployed

at apogee and a main

parachute is deployed at a

much lower altitude. Tumble

recovery or streamer

recovery from apogee to

main parachute deployment

is also permissible, provided

that kinetic energy during

drogue-stage descent is

reasonable, as deemed by the

Range Safety Officer.

Demonstration

Testing

The team will stage

the deployment of

our recovery devices

with a drogue

parachute deployed at

apogee (5280 ft.), and

two main parachute

deployed at 750 ft.

3.2

Each team must perform a

successful ground ejection

test for both the drogue and

main parachutes. This must

be done prior to the initial

subscale and full scale

launches.

Testing

Prior to the initial

subscale and full

scale launches, the

team will perform a

ground ejection test

for both the drogue

and upper main

parachute section as

well as the lower

main parachute

section.

Page 181: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

181

3.3

At landing, each independent

sections of the launch vehicle

shall have a maximum

kinetic energy of 75 ft-lbf.

Analysis

Demonstration

The team will

calculate and test

both sections of our

launch vehicle to

ensure that a

maximum energy of

75 ft-lbf at landing is

not exceeded.

3.4

The recovery system

electrical circuits shall be

completely independent of

any payload electrical

circuits.

Demonstration

The team will create

independent circuits

for our recovery

system so that they

are independent of

any payload electrical

circuits.

3.5

All recovery electronics will

be powered by commercially

available batteries.

Demonstration

The recovery system

will feature to

commercially

available 9V batteries

to power the two

altimeters.

3.6

The recovery system shall

contain redundant,

commercially available

altimeters. The term

“altimeters” includes both

simple altimeters and more

Demonstration

The recovery system

will include a

TeleMetrum and

TeleMega altimeter

each with their own

independent set of

Page 182: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

182

sophisticated flight

computers.

charges for each

section.

3.7

Motor ejection is not a

permissible form of primary

or secondary deployment.

Demonstration

The team will not use

motor ejection as a

primary or secondary

deployment. An

electronic form of

deployment will be

used.

3.8

Removable shear pins will be

used for both the main

parachute compartment and

the drogue parachute

compartment.

Demonstration

The team will use

removable shear pins

for both the main

parachute

compartment and the

drogue parachute

compartment.

3.9

Recovery area will be limited

to a 2500 ft. radius from the

launch pads.

Demonstration

The main parachutes

will deploy from a

low enough altitude

so that the rocket will

not drift more than

2500 ft.

Page 183: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

183

3.10

An electronic tracking device

shall be installed in the

launch vehicle and shall

transmit the position of the

tethered vehicle or any

independent section to a

ground receiver.

Demonstration

The team will install

a tracking device on

both sections of the

launch vehicle so that

the location of both

pieces can be

determined after

landing.

3.10.1

Any rocket section, or

payload component, which

lands untethered to the

launch vehicle, shall also

carry an active electronic

tracking device.

Demonstration

All separating

sections of the rocket

will contain their own

tracking device.

3.10.2

The electronic tracking

device shall be fully

functional during the official

flight on launch day

Verification

The team will test

and make sure the

electronic tracking

devices will be fully

functional during the

official flight.

3.11

The recovery system

electronics shall not be

adversely affected by any

other on-board electronic

devices during flight (from

launch until landing).

Testing

The team will test

and make sure that

the recovery system

will not be adversely

affected by any other

Page 184: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

184

on-board electronic

devices during flight.

3.11.1

The recovery system

altimeters shall be physically

located in a separate

compartment within the

vehicle from any other radio

frequency transmitting

device and/or magnetic wave

producing device.

Demonstration

The recovery system

altimeters will be

located in a separate

compartment within

the vehicle from any

radio frequency

transmitting devices,

and magnetic wave

producing devices.

3.11.2

The recovery system

electronics shall be shielded

from all onboard transmitting

devices, to avoid inadvertent

excitation of the recovery

system electronics.

Demonstration

The recovery

electronics will be

sealed in their own

separate compartment

separate from all

other transmitting

devices in the rocket.

3.11.3

The recovery system

electronics shall be shielded

from all onboard devices

which may generate

magnetic waves (such as

generators, solenoid valves,

and Tesla coils) to avoid

Demonstration

The recovery

electronics will be

sealed in their own

separate compartment

separate from all

other magnetic wave

inducing devices in

the rocket.

Page 185: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

185

inadvertent excitation of the

recovery system.

3.11.4

The recovery system

electronics shall be shielded

from any other onboard

devices which may adversely

affect the proper operation of

the recovery system

electronics.

Demonstration

The recovery

electronics will be

sealed in their own

separate compartment

separate from all

other devices in the

rocket which could

adversely affect the

proper operation of

the recovery system.

Section 11.2.4: Deployable Rover Requirements

Table 11.4: Deployable Rover Requirements Verification

Requirement

Number

Requirement

Statement

Verification

Method Execution of Method

4.5.1

Teams will design a

custom rover that will

deploy from the internal

structure of the launch

Demonstration,

test, inspection

Demonstration and testing

before the launch will ensure

the rover can fit inside the

rocket and is fit to maneuver

difficult terrain

Page 186: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

186

4.5.2

At landing, the team will

remotely activate a

trigger to deploy the

rover from the rocket

Demonstration,

test, inspection

Demonstration and testing will

be done before the flight to

validate that the rover will

receive the deployment signal.

Inspection afterward will also

ensure successful rover

deployment

4.5.3

After deployment, the

rover will autonomously

move at least 5 ft from

the launch vehicle

Demonstration,

test, inspection

Demonstration and testing will

be conducted before the launch

to determine the exact distance

the rover will travel

4.5.4

Once the rover has

reached its final

destination, it will deploy

a set of foldable solar cell

panels

Demonstration,

test, inspection

Demonstration and testing will

be performed on the solar panel

deployment system (SPDS) to

ensure that the system can

successfully deploy the solar

panels

Section 11.2.5: Safety Requirements

Requirement

Number Requirement Statement

Verification

Method Execution of Method

5.1

Each team will use a launch

and safety checklist. The final

checklists will be included in

Demonstration The team will use

checklists.

Page 187: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

187

the FRR report and used

during the Launch Readiness

Review (LRR) and any

launch day operations.

5.2

Each team must identify a

student safety officer who

will be responsible for all

items in section 5.3.

Demonstration The team has identified a

safety officer.

5.3

The role and responsibilities

of each safety officer will

include, but not limited to: a

bunch of things.

Demonstration The safety officer is aware

of his responsibilities.

5.4

During test flights, teams will

abide by the rules and

guidance of the local rocketry

club’s RSO. The allowance of

certain vehicle configurations

and/or payloads at the NASA

Student Launch Initiative

does not give explicit or

implicit authority for teams to

fly those certain vehicle

configurations and/or

payloads at other club

launches. Teams should

communicate their intentions

to the local club’s President

or Prefect and RSO before

Demonstration The team will follow the

rules.

Page 188: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

188

attending any NAR or TRA

launch.

5.5 Teams will abide by all rules

set forth by the FAA. Demonstration

The team will follow the

rules.

Section 11.3: Team Requirements

The following are tables of team-derived requirements and the associated verification methods.

More information on planned or completed tests necessary to the verification of these requirements

can be seen in Section 11.1: Testing.

Section 11.3.1: General Requirements

Table 11.5: AU General Requirements

Team Requirement Requirement

Statement Verification Method

Method of

Execution

AU 1.1

All Educational

Engagement forms

will be submitted and

verified to have been

received within 1

week of an outreach

event.

Demonstration

The team will

submit EE reports

within a week and

check that they have

been properly

received.

Page 189: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

189

Section 11.3.2: Vehicle Requirements

Table 11.6: AU Vehicle Requirements

Team

Requirement Requirement Statement Verification Method

Method of

Execution

AU 2.1

Materials used to

construct any portion of

the rocket will undergo

testing to ensure that

materials characteristics

are consistent with

expected values.

Test

Tension and 3-point

bend tests have

already been

completed.

Compression tests

will be conducted

soon.

AU 2.2

3D printed components

will have strength

comparable to

alternatives and

appropriate for their role

Test

Tension and 3-point

bend tests have

already been

completed.

Compression tests

will be conducted

soon.

AU 2.3

Isogrid structure strength

will be verified to be in

line with or superior to

filament wound carbon

fiber tubes.

Test

Samples of filament

wound material and

Isogrid structures will

be created and tested

under various loading

conditions.

Page 190: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

190

Section 11.3.3: Recovery Requirements

Table 11.7: AU Recovery Requirements

Team

Requirement Requirement Statement

Verification

Method Method of Execution

AU 3.1

Recovery electronics must be

able function after being left

on for more than two hours.

Test

The recovery electronics

(excluding e-matches and

black powder for safety

reasons) will be assembled

and left in the on/standby

position until loss of function

to determine system longevity

AU 3.2

Recovery system will be able

to separate rocket into desired

sections using the minimum

amount of black powder for

reliable results, to ensure

safety.

Test

Extensive ground separation

tests will be performed before

launch: subscale tests have

been completed and full-scale

tests will be.

Section 11.3.4: Deployable Rover Requirements

Table 11.8: AU Rover Requirements

Team

Requirement Requirement Statement

Verification

Method Method of Execution

Page 191: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

191

AU 4.1

With the exception of

electronic parts, the rover will

be 3-D printed in-house

Demonstration

Rover parts will be

designed to be printed in-

house so that the team can

continue to precisely

manufacture rover parts

AU 4.2

Rover activation signal will

successfully reach the rover

up to a certain distance plus a

large tolerance distance

Demonstration

XBee will be tested at

different distances to ensure

that the signal will reach the

rover

AU 4.3

Rover will be able to traverse

various terrains (examples

include 45 degree inclines

and 3 inch divots)

Demonstration

Test

Rover treads will be tested

on various terrains before

the launches to ensure

adequate traction

AU 4.4

Rover electronics must be

able function after being left

on for more than two hours.

Test

The rover electronics were

run continuously for several

hours and have been proven

to be functional for more

than two hours.

Page 192: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

192

AU 4.5

Rover motors must be able to

function after more than two

hours of battery drain.

Test

The rover motors were run

continuously for several

hours and have been proven

to be functional for more

than two hours.

AU 4.6

Rover must be capable of

exiting rocket from any

orientation of rocket body.

Test

Rover will be placed in

section, rotated to various

angles in increments of 30

degrees from horizontal,

and be commanded to drive

out.

AU 4.7

Rover will successfully

deploy solar panels after

travelling at least 5 feet

Demonstration,

test

SPDS will be shown to

deploy after travelling over

various terrain and

travelling varying distances

Section 11.3.5: Safety Requirements

Team

Requirement Requirement Statement

Verification

Method

Method of

Execution

AU 5.1

All team members will work

in groups of at least two,

ensuring immediate assistance

for any team member in need.

Demonstration Team members will

not work alone.

Page 193: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

193

Section 11.3.6: Altitude Control Requirements

Table 11.9: AU Altitude Control Requirements

Team

Requirement

Requirement

Statement

Verification

Method Method of Validation

AU 6.1

All aerodynamic data

must be validated

through analytical and

experimental testing.

Analysis

An aerodynamic analysis of the drag plates

and the internal system will be conducted

through computational fluid dynamics

(CFD) and sensor tests.

AU 6.2 Drag plates must stay

static throughout launch Demonstration

Timer will be implemented through the

controller that will prevent any system

action prior to the end of the boost phase.

AU 6.3

Electronics must stay

secured throughout

flight.

Demonstration A housing will be made for all electrical

components to keep everything in place.

AU 6.4

Subsystem components

must engage

accordingly after boost

phase and stay online

for the remainder of the

flight.

Test Testing will verify that the behavioral

integrity of the system remains intact.

Page 194: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

194

AU 6.5

Controller and IMU

must be able to

correctly predict the

projected altitude of the

launch vehicle.

Test

Testing will verify that both components

will behave according to the requirement

specification.

AU 6.6

Drag plates must

deploy after boost

phase in order to self-

correct the trajectory of

the launch vehicle.

Test “Hardware In-The-Loop” testing and test

flights will validate deployment precision.

AU 6.7

Drag plates must be

able to withstand the

perpendicular force of

the airflow.

Test

Wind tunnel testing and structural testing

will be conducted to ensure the integrity of

the plates and the materials used to

construct them.

AU 6.8

The subsystem must be

able to correct altitude

by at least 400 feet and

be accurate to 200 feet.

Analysis

Demonstration

The subsystem will be designed to conform

to accuracy requirements and will then be

demonstrated to be accurate in a test flight.

AU 6.9

Altitude control

electronics must be able

to function after being

left on for more than

two hours.

Test

The batteries, motors, and Arduino with all

relevant electronics were assembled and

ran as intended for several hours,

confirming the electronics ability to

function for more than two hours.

Page 195: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

195

Section 11.4: Budget

The budgets displayed in Table 11.13: Budget Allocation are an updated approximation of the

costs of the remaining expenditures, and a representation of already allocated funds for the project.

The approximations are conservative, assuming excess quantities of materials and no price breaks.

Hoping to bring a large number of students to the competition this year, the team has already

reserved 6 hotel rooms from the block. The Auburn Aerospace Engineering department has

informed us that we should expect to pay $3,000 for that, but that they will try to lessen that sum

as they can. Thanks to the success of the subscale on its first flight, the team did not have to do

any rebuilding, and all the electronic components are reusable. Factoring this is to the initial

estimate of $2,700 for the subscale, the actual cost of the subscale came out to $2,000. Our

educational outreach has spent $300 so far, and is estimated to cost $1,200 more. Assuming

$3,055.13 for the rocket on the pad, $2,000 for the sub-scale vehicle, and $3,000 for travel, this

leaves $8,444.87 for promotional items, overhead costs and any other testing and development

costs, based on the $16,500 amount for total funding presented in Table 11.14: Funding Sources.

Table 11.10: Vehicle Costs

Vehicle (Full Scale)

Item Cost Per Unit Unit Quantity Total

Carbon fiber and

resin for open

weave structure.

$284 Per tube 2 $568

Fiber glass sleeve $33 Per tube 2 $66

Pre-preg Carbon

Fiber $118 Per yard 5 $590

Page 196: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

196

Aerotech L1420R $259.99 Per unit 1 $259.99

RMS 75/3840

Motor Case and

Associated

Hardware

$385 Per unit 1 $385

Rail Buttons $3 Per unit 2 $6

Total $1,575

Table 11.11: Recovery Costs

Recovery (Full Scale)

Item Cost Per Unit Unit Quantity Total

Ripstop Nylon $8 Per yard 25 $200

Nylon Thread $8 Per spool 3 $24

Tubular Nylon $1 Per foot 50 $50

Paracord $5 Per roll 1 $5

Telemetrum $200 Per unit 1 $200

Telemega $300 Per unit 1 $300

Jolly Logic $130 Per unit 2 $260

Total $1,039

Page 197: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

197

Table 11.12: Rover Costs

Item Cost Per Unit Unit Quantity Total

1000:1 Micro

Metal Gearmotor

HPCB 12V

$22.95 Per Unit 3 $68.85

Elegoo Uno

Project $35.00 Per Unit 1 $35.00

Xbee Pro 60 mW

Wire Antenna

and dongle

$62.90 Per Pair 2 $125.80

Arduino

Wireless SD

shield

$17.49 Per Unit 1 $17.49

Flexible Solar

Panel 1W 6V $13.99 Per Unit 1 $13.99

Onyx $189.99 Roll .5 $95.00

Nylon $169.99 Roll .5 $85.00

Total $441.13

Cost of Rocket On the Pad $3,055.13

Page 198: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

198

Table 11.13: Budget Allocation

Item Cost

Full-Scale $3,055.13

Sub-Scale $2,000

Travel $3,000

Educational Outreach $1,500

Test flights (5) $1,000

Research and Development $3,000

Promotional Items $1,000

Total $14,555.13

Figure 11.8: Spending Comparison

Budget Breakdown

Full-Scale Sub-Scale Travel

Educational Outreach Test Flights (5) Development

Promotional Items

Page 199: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

199

The team is very happy with the state of its budget. The success of the subscale vehicle on its first

launch certainly saved the team money and ensured the full-scale vehicle can reuse some expensive

electronics. The team also secured additional sponsorship funds, to be discussed in the following

section. The excess funds have been allocated to research and development projects, which will

help to construct a second test rocket that can fly experimental payloads without risking the

progress of the competition. Even with the extra resources allocated, the team maintains a

comfortable cushion of approximately $2,000 in case of unforeseen expenditures.

Section 11.5: Funding Plan

The team has secured funding from the sources presented in Table 11.14: Funding Sources. This

money will cover the cost of the rocket on the pad, the purchase of capital equipment as needed,

the cost of subscale and full-scale test launch motors, programming and materials for our

educational engagement events, travel and housing for the team at the competition in Huntsville,

Alabama, and any other costs associated with designing, building, and launching our competition

rocket. Since PDR, the team has secured an additional sponsorship from Lockheed Martin totaling

$2,000 and Dynetics has increased their contribution to the team by $500. With these additional

funds, and the subscale test vehicle costing less than budgeted, the team has covered all necessary

expenditures and has allocated additional resources to research. Additionally, all of the anticipated

costs were estimated on the high end to provide a safety factor to the funding plan. The Auburn

University Student Launch team is confident that the current financial situation is quite stable, and

will continue to be for the remainder of the competition.

Table 11.14: Funding Sources

Source Amount

Alabama Space Consortium $12,000

Dynetics $2,500

Page 200: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

200

Lockheed Martin $2,000

Total Funding $16,500

Section 11.6: Timeline

Two Gannt charts have been created to illustrate the project timeline. They are broken up by

semester, as this separation most closely imitates how the students operate, and the conclusion of

CDR aligns almost exactly with the start of Auburn University’s Spring semester. These can be

found in below in Figure 11.9: Fall Timeline and Figure 11.10: Spring Timeline.

Figure 11.9: Fall Timeline

8/23/17 9/13/17 10/4/17 10/25/17 11/15/17 12/6/17 12/27/17 1/17/18

Conceptual Design

Proposal

Preliminary Design Review

Materials Testing

CFD Testing

Trade Studies

Detailed Design

Critical Design Review

Sub-Scale Development

Payload Development

First Subscale Launch

Junior E-Day EE Event

Detailed Design Review

Page 201: New Auburn University Student Launch Project Tiger Launch · 2018. 1. 12. · Title of Project Project Nova Date of CDR January 12th, 2018 Experiment Option 2: Deployable Rover Section

201

Figure 11.10: Spring Timeline

As seen in the timelines, the team is slightly behind on materials testing. However, the majority of

the tests are complete and the findings correlate with the research the team has completed, so the

team is not concerned. Those tests will be completed within a week of CDR being submitted.

Conversely, both the construction of the payload and the development of the full-scale vehicle are

ahead of schedule. Overall, the team is quite happy with the progress made so far. A well-

constructed vehicle will most likely not be ready to launch at the first launch opportunity on

February 3rd, so the team will have a full-scale vehicle and a test vehicle ready to launch on

February 17th. Should anything function incorrectly, the team can adjust and relaunch the

following day because this is a two-day launch event. As an emergency measure, there is another

launch opportunity March 3rd. With several opportunities available to launch a full-scale rocket,

and progress on the rocket already ahead of schedule, the team is confident that progress is on

track.

1/10/18 1/31/18 2/21/18 3/14/18 4/4/18 4/25/18

Payload Construction

Full-Scale Development

Flight Readiness Review

Rocket Week EE Event

Auburn E-Day EE Event

Full-Scale Flight

Two Day Full-Scale Flight Opportunity

Emergency Full-Scale Flight

Competition Preparation

Huntsville Competition

Post-Launch Assessment Review