12
NER Finals Checklist for Construction Project You have 81 days from substantially complete (time stopped) to submit your records Click on the link below to find the most recent check list in pantry, save under Finals/SubmittedPantryForms folder prior to submitting project finals records. https://awpkb.dot.wi.gov/Content/constr/PantryFiles/RegionSpecifi c/NE/Manuals/FinalsChecklistForConstructionProjects.docx

NER Finals Checklist for Construction Project

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NER Finals Checklist for Construction Project

NER Finals Checklist for Construction Project You have 81 days from substantially complete (time stopped) to

submit your records

Click on the link below to find the most recent check list in pantry, save under Finals/SubmittedPantryForms folder prior to

submitting project finals records.

https://awpkb.dot.wi.gov/Content/constr/PantryFiles/RegionSpecific/NE/Manuals/FinalsChecklistForConstructionProjects.docx

Page 2: NER Finals Checklist for Construction Project

 Electronic Field Files 

 

BOX Construction Folder Structure & Guidance 

 Tier 1  Tier 2  Tier 3  Guidance 

ChangeMgmt 

Claims 

ContractModCMJ 

Draft 

Executed 

CRI 

Issue  ROM, WAF, RFP 

ProjectControl  CostToComplete  RFI_DIN 

ConstrOps 

Electrical  add subfolders as needed for Lighting, Signals, ITS 

Railroad 

SoilsPavement 

Structures 

SurveyStaking 

Traffic 

Utilities  utility conflict reports 

DesignLinks  Bookmark to design folder(s) or all relevant design documents needed for construction; Do not copy documents from 

Design to this folder 

Environmental 

ArcHist 

HazMat 

StormwaterEC  include WPDES (TCGP) certificate of permit coverage and NOT confirmation 

ECIP 

InspectionOrder 

Release 

FieldManager 

Backups 

EstimatesStockpiles 

ImportExport 

Finals  MaterialsFinals 

ProjectMaterialRecords  product data, certs, test reports, pictures, etc. 

MaterialArchives eguide, certs, test reports, heat #, pictures, final QMP (w/155 reports, tracking spreadsheets, QC/QV data, random #), etc. 

DT1310  Buy America (WS4567 & exemptions), Nonconforming, Non‐Performance 

Reports 

DQI, explanation of variation, contractor performance reports, DT2509/2510; contractor evals, completion certificate, IDR Summary & Index 

ReviewForms  contract items review DT2076, statement of contract time, records issue list 

SubmittedPantryForms  beamgaurd verification spreadsheet, curb ramp compliance form, anchor bolt forms, piling forms, structure clearance 

forms, maintenance forms, submitted to region/BOS/BPD 

ItemSourceDocs 

CADDFiles  .dwg, .dgn or other drawing files used for item measurement/payment 

Spreadsheets  Pantry spreadsheets or other compsheets used for item measurement/payment 

Tickets  tickets used for item measurement/payment 

Materials  Submittals  materials documentation submitted by contractors 

Meeting  add subfolder for Traffic as needed 

PreCon 

PrePave 

PrePour 

Progress 

Plan  Sublet information should be located in labor compliance folder 

Asbuilt 

BidDocs  bid tabs, prebid inquiries 

Let  asLet plan & proposal (including addenda) 

ProjectMgmt 

ConsultantContracts (DOT Only)  engineering delivery estimate, negotiation documentation, etc. 

ContractCorr  award letter, post award letter, NTP, acceptance letters, punchlist, emails, etc. 

LaborCompliance  request to sublet, payment issues, NOTE: confidential info should be filed with Labor Compliance specialist 

PubInv 

PropertyOwner 

Bookmark to RE Commitments in design folder; property owner letters, public inquiry & outreach, Construction Permits 

PublicMtg 

invites, agendas, minutes for Public/Construction Involvement Meeting, Local Officials Meeting, Business Meeting 

WeeklyUpdate  weekly construction updates, media inquiries 

Schedule  CPM schedule, weekly progress, monthly review 

Initial 

Updates 

SiteDocumentation  Unlimited space available to upload all photos/videos (Haul routes, Box Capture app to pic, etc.) 

 

Page 3: NER Finals Checklist for Construction Project

1aSiteHealthAndSafetyChecklist.docx Updated 2/16/15

Site Health & Safety Checklist (post near telephone in field office)

Project ID: HWY or Route: County:

Site Address & Location:

Project Begin Date: Click here to enter a date. Project End Date: Click here to enter a date.

Local Emergency Telephone Numbers: Ambulance:

Poison Control Center:

Fire Department:

Police Department:

Hazardous Materials Response Unit:

Medical Emergency: (In any medical emergency dial 911) Hospital: Phone:

Hospital Address:

Directions to Nearest Hospital:

Severe Weather Emergency: Shelter Area I:

Shelter Area II:

Notify District Contact Region Office: Northeast Region Phone: 920-492-5623

Supervisor: Phone:

Project Manager: Phone:

Other: Phone:

Safety Equipment Inventory:

Item Qty Location Inspect. Freq. Comment

First Aid Kit 1 Office Weekly

Fire Extinguisher 1 Office Monthly

Ear Plugs 1 box Office Weekly

Safety Glasses several Office Weekly

Safety Vests several Office Weekly

Hard Hats several Office Weekly

Other:

Contractor MSDS Location:

REVIEW IS REQUIRED BY ALL ONSITE PERSONNEL BEFORE BEGINNING WORK Name: Initials: Date: Click to enter date.

Name: Initials: Date: Click to enter date.

Name: Initials: Date: Click to enter date.

Name: Initials: Date: Click to enter date.

See Attached Map for Shelter Areas and Route to Hospital

Page 4: NER Finals Checklist for Construction Project

SBD-9301P (04/17)

Public Employee Safety and Health

Authority Wisconsin statute section 101.055 requires the Wisconsin Department of Safety and

Professional Services to adopt and enforce safety and health standards that will provide

protection to public employees at least equal to that provided to private sector employees under

standards promulgated by Federal Occupational Safety and Health Administration (OSHA).

Inspection A public employee or public employee representative who believes that a safety or health

standard is being violated, or that a situation exists which poses a recognized hazard likely to

cause death or serious physical harm, may request the department to conduct an inspection. If

the requestor so designates, the identity of the requestor will be kept confidential. If the

department decides not to make an inspection, the requestor will be notified.

A representative of the employer and a public employee representative will be permitted to

accompany the department inspector during the inspection. The employee shall not be

discriminated against with respect to either pay received or withheld for time spent on the

inspection.

Enforcement If the department finds a violation of state standards, abatement orders will be issued to the

employer. The employer shall post a copy of the orders at or near the site of the violations for 3

days or until the violation is corrected, whichever is longer. Copies of the order will be sent to the

top elected official, the bargaining unit and to the person requesting the inspection.

If the department decides not to issue orders in response to a request, a written notice of that

decision shall be sent to the public employee who requested the investigation. If decisions are

disputed they will be reviewed.

Discrimination No public employer may discriminate against or discharge any public employee for exercising

any right afforded by his section. A state employee who believes he or she has been

discriminated against may file a complaint with the personnel commission within 30 days of

employee’s receipt of knowledge of the discrimination. A public employee, other than a state

employee, may file a complaint with the state Division of Equal Rights within 30 days.

For more information, contact: Wisconsin

Department of Safety and Professional Services

Industry Services Division

PO Box 7302

1400 E Washington Ave. Madison, WI 53707-7302 608-266-2112

PUBLIC EMPLOYERS ARE REQUIRED TO POST THIS NOTICE

WHERE NOTICES TO EMPLOYEES ARE USUALLY POSTED

Page 5: NER Finals Checklist for Construction Project

Hazardous Chemicals in the Workplace?

You as a public employee have the right, under the Wisconsin public employees' right-to-know law, to be informed about hazardous chemicals and substances in the workplace. *

EMPLOYEES MUST BE PROVIDED WITH:

A list of all hazardous chemicals and information on toxic substances,

pesticides, and infectious agents in the workplace.

Access to Material Safety Data Sheets and container labels.

Formal training in proper procedures for managing hazardous chemicals.

A written chemical hazard communication program.

For more information contact:

Wis. Dept. of Safety and Professional Services Industry Services Division 1400 E Washington Avenue

Madison, WI 53703

608-266-2112

* State Statute 101.581(1)

SBD-6894-P (R01/17)

Page 6: NER Finals Checklist for Construction Project

WisDOT’s Contact List Leaks, Spills and Other Hazardous Materials

Who do you call? Spills on the Right of Way – caused by others If you need assistance in stopping or containing the spill, use the Emergency Response (24-hour) hotline: 1-800-943-0003 (Note: this is a touch-tone only number)

To report a spill during work hours, contact the Department of Natural Resources (DNR) Emergency Spill Response Coordinator (7:45 AM – 4:30 PM)

Spill Response Coordinator Region Office

24 Hour Hotline 800-943-0003 Rick Joslin Northeast 920-424-7077 Matt Rahn Northern 715-623-4190 ext. 3110 Mike Schmoeller South Central 608-275-3303 Riley Neumann Southeast 414-263-8699 Pat Collins West Central 715-684-2914 ext.117

If you have internet access, refer to the WDNR Website for the most current list: http://dnr.wi.gov/topic/spills/documents/coordinators.pdf

To report a spill at all other times, or if you cannot reach the DNR spill response coordinator, use the 24-hour Emergency Response Hotline (1-800-943-0003).

Agricultural Product Spills To report an agricultural product spill, in addition to the DNR Emergency Spill Response Coordinator or the Emergency Response Hotline, contact the Department of Agriculture, Trade and Consumer Protection (DATCP) spill coordinator, Rick Graham at (608) 224-4502.

If there is no immediate threat to public health, public welfare, or the environment, reporting requirements are based on the quantity released, as follows:

• Dry Fertilizer: Report the discharge to the Spill Hotline if the amount is 250 lbs. or greater. • Liquid Fertilizer: Report the discharge to the Spill Hotline if the amount is 25 gallons or greater. • Registered Agricultural Pesticides: Report the discharge to the Spill Hotline if the amount,

when diluted according to the label, would cover one acre or more of land if applied according to the label instructions.

For further guidance on agricultural chemical spills refer to https://datcp.wi.gov/Pages/Programs_Services/AgriculturalChemicalSpills.aspx

Page 7: NER Finals Checklist for Construction Project

For further information, or to receive an update of this contact list, contact the Bureau of Technical Services, Environmental Services Section

Shar TeBeest (608) 266-1476; [email protected] Last Revised –February 11, 2019

Abandoned Containers

1. Contact the DNR Region Spill Coordinator in the area the containers were found (refer to DNR region map on Page 1):

Spill Response Coordinator Region Office

24 Hour Hotline 800-943-0003 Rick Joslin Northeast 920-424-7077 Matt Rahn Northern 715-623-4190 ext. 3110 Mike Schmoeller South Central 608-275-3303 Riley Neumann Southeast 414-263-8699 Pat Collins West Central 715-684-2914 ext.117

2. Notify Risk, Safety and Facilities Management : Scott Mau (608) 266-5659 and BTS:

Shar Te Beest (608) 266-1476 Petroleum Spills by DOT Personnel – on the R/W (over one gallon)

1. Contact the DNR Emergency Spill Response Coordinator (see list above). 2. Also contact the Bureau of Technical Services, Robert Pearson at 608-266-7980 or Shar

TeBeest at 608-266-1476 to arrange for cleanup. Petroleum Spills by County Personnel, Contractor or Consultant (any quantity) Contact DNR Emergency Spill Response Coordinator (see list above). The county, contractor or consultant is responsible for cleanup of the spill.

Hazardous Waste Spills by DOT Personnel Petroleum Spills at DOT Non-Highway Facilities

1. Contact the DNR Emergency Spill Response Coordinator (see list above). 2. Contact Risk, Safety and Facilities Management – Scott Mau (608) 266-5659 and BTS –

Shar Te Beest (608) 266-1476 to arrange for cleanup. Hazardous Waste Spills by County Personnel, Contractor or Consultant Contact the DNR Emergency Spill Response Coordinator (see list above). The county, contractor or consultant is responsible for cleanup of the spill.

DOT Remediation of Petroleum Contaminated Sites Contact DTSD – Bureau of Technical Services (BTS) – Robert Pearson at 608-266-7980, or Shar Te Beest 608-266-1476.

Remediation of DOT Owned Facilities (Sign Shops, Radio Towers, State Patrol Offices, Weigh Stations, etc.) Contact DBM Risk, Safety and Facilities Management – Scott Mau (608) 266-5659 and BTS – Shar Te Beest (608) 266-1476.

DOT Remediation of Hazardous Waste Contact BTS – Shar Te Beest (608) 266-1476

Third Party Liability Claims If there is a claim or potential for a claim by a third party who is damaged by a release of a contaminant from a source that is under DOT’s control or from a source which we own or control, contact DBM Risk, Safety and Facilities Management – Scott Mau (608) 266-5659.

Page 8: NER Finals Checklist for Construction Project

1eTopSafetyTips.docx 2/7/18

1. Watch out for traffic: Don’t ever forget where you are…particularly on jobs being build under traffic.

2. Wear protective clothing and equipment: Today’s high visibility clothing lets you be seen and can give you the edge on the job. Hard hats, vests, safety shoes, safety glasses, and sometimes earplugs may be appropriate…Use them!

3. Bridge safety is fundamental: Be alert and be careful! There is always a lot of hanging from bridges. Ladder safety is crucial. Use your harness.

4. Watch out for heavy equipment: Stay as far away from heavy equipment as you can, and remember, all construction equipment can easily topple over. Don’t be downhill!!

5. Beware of trenches and tight spaces: You may not get a second chance to practice trench safety. The walls can collapse or trap you. Make sure others know where you are, and that you know where they are. Be able to identify a confined space and do not enter if a permit is required to enter.

6. Practice good job safety habits: Identify and report unsafe conditions. Correct them if you can and warn others about them. Remember to report accidents. Everyone is responsible for safety. Do your part to prevent an accident from happening to someone else.

7. Look up and live: Live wires, cranes, booms and loads, tree branches, and scaffolding are a few things that may be overhead on your job. Be alert! Look up and live!

8. Be sure of your footing: Slips and falls can cause sprains, strains, breaks, fractures, and worse. Uneven footing on construction jobs is the rule. Think about your next step!

9. Lifting things properly: Carry a balanced load, pick it up properly, and don’t let your load obstruct your vision.

10. Always following safety rules and procedures: Professional athletes know the importance of fundamentals. Retrain yourself regularly on the fundamental rules of safety procedures. Remember Lombardi’s training camp opener, ‘This gentlemen, is a football!’

Safety is a team effort. Make sure all members of your construction staff follow these habits, especially the employees that are new to your construction project. Remember to report all accidents or injuries as soon as they occur.

Northeast Region

TOP 10 SAFETY TIPS

Page 9: NER Finals Checklist for Construction Project

WisDOTEAP

Employee Assistance Program for State of Wisconsin Employees

Confidential Convenient Free

Available 24/7 at 1.833.539.7285

online at https://sowi.mylifeexpert.com username: SOWI

Page 10: NER Finals Checklist for Construction Project

1/30/21

NER CONSTRUCTION ESS EMERGENCY CHECKLIST ESS Contacts: Bob Pearson 608-266-7980; Shar Te Beest 608-266-1476, 608-381-4789 (cell)

Date: Click to enter date. Time: Your Initials:

ESS person who took call: Phone:

Consultant ESS contacted:

Who will be the consultant representative?

When will they be able to get on- site?

INFORMATION TO REPORT

In describing the problem for ESS please include as much of this information as possible.

DESCRIPTION OF THE PROJECT:

Project ID: REGION: NE COUNTY: Choose County

HIGHWAY NO./STREET NAME:

Stationing/Plan Sheet number:

LOCATION OF PROBLEM:

SITE CHARACTERISTICS

Appearance, odor of soils in area:

Appearance, odor of liquids in area:

Tanks (UST's) or pipes present:

Approximate size and dimension of UST:

Location of UST or contamination relative to centerline and station:

Obvious liquid or product in the tank:

Are utilities marked? Yes/No

Any previous land use knowledge that would be useful:

Soil types, depth to groundwater:

STATUS OF CONSTRUCTION PROJECT

Status of highway construction near site (type of job, are you just starting, or at the end of the job?)

How soon does work in the impacted area need to be completed?

Can work continue in an area away from contamination? Yes/No; for how long?

Can the impacted area be avoided? Yes/No

Could design in the contaminated area be changed? (Easier to tell once consultant has defined

nature and extent of contamination). Yes/No

Page 11: NER Finals Checklist for Construction Project

1/30/21

NOTIFICATION OF AUTHORITIES and SITE SAFETY CHECKLIST

Has the Construction or demolition contractor: 1. Stopped work in the area? Yes/No

2. Secured the area? Yes/No

3. Contacted the local fire department? Yes/No

4. Contacted the area DNR representative? Yes/No

5. Located an area where contaminated soil could be stockpiled if necessary? Yes/No

[See CMM 1.30.2 for further instructions]

See following page for NE Region HazMat construction emergency contact

info.

Page 12: NER Finals Checklist for Construction Project

1/30/21

HAZMAT CONSTRUCTION EMERGENCY CONTACTS – NE

REGION

• Have contractor stop work in the area. Secure area and contact fire department if there is an

immediate risk associated with the release.

• Record as much information as possible on the NER Construction ESS Emergency Checklist (a

copy can be found in the project binder). Additional instructions can be found in CMM 1.30.2.

• NER first point of contact is:

Kathie VanPrice 920-492-7175

• If Kathie is not available, contact:

Jen Gibson 920-492-4160

• If NER staff are not available, contact one of the following (BTS-ESS):

Shar TeBeest 608-266-1476

Bob Pearson 608-266-7980

• If you are unable to reach any WisDOT contacts listed above, contact one of our hazmat

consultants directly. Current contact info is listed below. If you are working directly with our

consultants, please send an e-mail to Kathie VanPrice and [email protected] that

includes project ID, description of construction emergency, and which consultant you are working

with. NOTE: if Shar TeBeest is out of the office and has her automatic reply set, you can find a list

of current contact info in her Out of Office Reply.

- GEI:

Roger Miller 920-455-8657 or 920-737-6373 (cell)

Mike DeBraske 920-455-8200 or 920-412-4779

- AECOM:

Kyle Wagoner 715-342-3038

- TRC:

Dan Haak 608-826-3628 or 608-886-7423 (cell)

- NRT:

Mark Walter 414-837-3563 or 608-220-2480 (cell)