Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Giovanni Rumolo H. Bartosik, Y. Papaphilippou
in LHC Performance Workshop (Chamonix 2012), 9 February 2012
H. Damerau, A. Findlay, S. Gilardoni, B. Goddard, S. Hancock, K. Hanke, G. Iadarola, B. Mikulec, E. Shaposhnikova
et al.
Necessary LIU studies in the injectors during 2012
Outline
2
Focus of the talk Review the progress made in 2011 with the LIU MDs and extract which questions still remain to be answered with beam in 2012
– 2011 LIU MDs by the machine – organization, distribution and
highlights → Linac2 + PSB → PS → SPS
– Questions to be followed up in 2012 – Priorities and organizational proposals – Concluding remarks
Overview 2011
3
– 2011 distribution of the MD days (priority to MDs in all machines) → Floating MDs biweekly → Long dedicated blocks
during LHC TS (4x)
– Total number of available MD hours was 408 (434 on original schedule, same planned for 2012)
– Parallel MDs → PSB + PS: at least one cycle
per supercycle always available for MDs (or MTE)
→ SPS: usually one parallel MD cycle available every week day for studies (some times used for set up)
– Types of PSB MDs
1. Prepare new beams, tune and check existing beams, for the downstream machines
2. Define the limitations of the machine, improve the performance
3. Specific machine studies in view of the future upgrades
Linac2 + PSB in 2011
4
Parallel MDs
Dedicated MDs – Linac2 MDs
1. Remove hot spots found with the 2010 radiation survey
2. Run with increased beam current (180 mA)
– Types of PSB MDs
1. Prepare new beams, fine tune and check existing beams, for the downstream machines
2. Define the limitations of the machine, improve the performance
3. Specific machine studies in view of the future upgrades
Linac2 + PSB in 2011
5
Parallel MDs
Dedicated MDs – Linac2 MDs
1. Remove hot spots found with the 2010 radiation survey
2. Run with increased beam current (180 mA)
Time, resources!
– Beam dynamics questions relevant for LIU-PSB
? Continue tests with higher beam current from Linac2 ① Identify the impedance source responsible for the known instabilities
and specify transverse damper requirements ① Determine resonance diagram with tune scans at 160 MeV to optimize
placement of working point at injection with Linac4 ② Optics model based on turn-by-turn data from the available BPMs ② Study the efficiency of the resonance compensation schemes ② Space charge induced emittance blow up
Linac2 + PSB
6
– LIU-PSB activities in 2012 (RF, hardware)
① Continue deployment of the digital RF control
① Test the newly installed Finemet prototype cavity hardware
PS in 2011
7
Parallel MDs
Dedicated MDs – PS MDs
1. Space charge studies at 1.4 GeV and 2 GeV and tune diagrams
2. Adjustment of working point at low energy with quads and PFW
3. Fast instability at transition with TOF-like beams
4. Tune shift with intensity at injection and extraction energy
5. Electron cloud at flat top with 25 and 50ns beams
6. Limitations from longitudinal coupled bunch instabilities during the ramp and flat top
7. Batch compression scheme h=9 10 20 21
8. One-turn feedback with C11
PS: space [email protected]
8
Nb (x 1010 p) ex,y (mm) 4st (ns) DQy
LHCINDIVhigh 40 1.7 90 -0.2
LHC50nom (DB) 80 1.1 180 -0.26
LHC50ult (DB) 120 1.8 180 -0.26
LHC25 (DB) 160 2.5 180 -0.26
AD 400 9.0/5.0 185 -0.28
TOF 800 12.0/8.0 230 -0.31
MD beams
LHC50 SB rebucketed
150.0-190.0 2.5-3.0 130 -0.34
LHChighbright 70 2.0 95 -0.25
Double batch LHC beams, 1.2sec @FB
Physics beams, short FB
For space charge studies @FB after bunch rotation
PS: space charge@2GeV
9 TUNE SCAN @ 2 GeV
E. Benedetto Shortened bunch @2GeV
→ DQx = -0.19, DQy=-0.27
→ Three working points analyzed
o Qx=0.15, Qy=0.196
o Qx=0.17, Qy=0.23
o Qx=0.17, Qy=0.30
- No losses - Little emittance growth
Is DQy=- 0.26 really the limit for the space charge tune spread at injection for double batch injection into the PS? Can we identify dangerous resonance lines and compensate them?
• Longitudinal coupled bunch instabilities with both 25ns and 50ns beams observed (previously also with 75ns and 150ns beams) During the ramp
At flat top when ramping down h=21 during bunch splitting
• What we have learnt about it ⇒ Instabilities during the ramp probably caused by the wide band
impedance of the 10MHz cavities
⇒ Coupled bunch mode spectrum changes between ramp and flat top
⇒ Little dependence on the number of bunches in the batch, but growth rates scale like Nb/ez
⇒ Small improvement with 2 gap relays, parking of unused cavities beneficial
• 2012 LIU-PS studies towards raising the thresholds ⇒ Additional feedback (decide if more hardware is needed after LS1)
⇒ PS/SPS transfer perhaps allow for larger ez to be injected into the SPS, optimize final bunch rotation
PS: longitudinal coupled
bunch instabilities
10
PS: Electron cloud
11
Systematic scans taken with
⇒ 50ns and 25ns beams
⇒ Simulation effort ongoing
0 0.5 1 1.5 20
0.02
0.04
time [us]
e-c
lou
d s
ign
al [a
.u. ] Av. intensity = 1.64*10
11 ppb
0 0.5 1 1.5 20
5
10
time [us]
Pic
k-u
p s
ign
al [a
.u.]
0 0.5 1 1.5 20
0.05
0.1
0.15
time [us]e
-clo
ud
sig
na
l [a
.u. ] Av. intensity = 1.33*10
11 ppb
0 0.5 1 1.5 20
2
4
6
time [us]
Pic
k-u
p s
ign
al [a
.u.]
50ns, 36b
25ns, 72b
0 0.5 1 1.5 20
0.2
0.4
0.6
0.8
1
Time [us]
Ele
ctr
on
clo
ud
in
dic
ato
r [a
.u]
Simulation 0 0.5 1 1.5 2
0
0.2
0.4
0.6
0.8
1
Time [us]
e-c
lou
d s
ign
al [a
.u.]
Measurement
dmax R0 Beam in the gap
Simulation 1.6 0.5 5%
Scans in bunch intensity and length done! 2012 MDs Measurements in presence of B field, study of double step bunch rotation
G. Iadarola, C. Yin-Vallgren
PS: miscellaneous
12
– More LIU-PS machine studies in 2012
➀ Batch compression scheme h=9 10 20 21, acceleration, transfer to SPS
➀ Batch compression + bunch merging ➀ One-turn feedback against transient beam-loading
➁ Commissioning of transverse feedback system ➁ Head-tail instabilities on the flat bottom ➁ Transverse instabilities of short intense bunches at flat top
(electron cloud?) ➁ Impedance identification for modeling
③ Injection studies
– Upgrade studies included → Push the SPS performance with the present 25 and 50ns beams, as well
as with single intense bunches (up to 4 x 1011 ppb) → Development of low gamma transition optics (Q20) → Electron cloud mitigation techniques (a-C coating, scrubbing, clearing
electrodes) → Beam tests for a high bandwidth feedback system
SPS in 2011
13
38%
41%
21%
Distribution of SPS MDs in 2011
Upgrade studies
Other MDs
Beam set up (ionand coasts)
Floating MDs 61% (efficiency slightly above 50%)
Dedicated MDs 39% (very high efficiency ~95%)
SPS: single bunch limits
14
Limitations on single bunch
⇒ TMCI threshold
⇒ Emittance blow up along an LHC-type cycle
TMCI threshold @26 GeV/c (xV =0)
Q26 – nominal optics
– 2–2.5 x 1011 ppb injected → Losses around 10% → No emittance
growth wrt PS extraction
– Above 2.5 x 1011 ppb injected, large losses (20%) and emittance blow up
xV=0.25
SPS: single bunch limits
15
Limitations on single bunch
⇒ TMCI threshold
⇒ Emittance blow up along an LHC-type cycle
TMCI threshold @26 GeV/c (xV =0)
xV=0.1
Q20 – low gt optics
– Q20 allows for injection of higher intensity bunches (up to 3 x 1011 ppb) → Low chroma → Losses below 10%
even above 2.5 x 1011 ppb
– Trend from injectors or space charge in the SPS?
SPS: single bunch limits
16
Comparison across machines
⇒ Effect of a 3 sec flat bottom in the SPS
⇒ Small blow up + losses above 2.5 x 1011 ppb Q20 – low gt optics
Blow up above 1.7 x 1011 ppb, during flat bottom (3 to 10 sec) or during ramp? Working point optimization needed?
From measurements at 450 GeV/c (previous slide)
SPS: multi-bunch beams
17
High intensity 50ns beams tested in MDs
⇒ Record intensity at flat top with Q20
⇒ Quoted transmission is from PS extraction to SPS flat top
Q20 – low gt optics
1.6 x 1011 ppb injected 1.5 x 1011 ppb at flat top
1.9 x 1011 ppb injected 1.7 x 1011 ppb at flat top
SPS: multi-bunch beams
18
High intensity 50ns beams tested in MDs
⇒ Longitudinally more stable on Q20
⇒ Margin for longitudinal emittance blow up, when needed
Q26 Q20
Courtesy T. Argyropoulos
no quadrupole oscillations
50ns beam at flat top (1 batch, 1.5x1011ppb)
– Without controlled
emittance blow-up – 800MHz cavity
(V800=0.15V200)
Continue work on optimization of multi-bunch beams on Q20 (also 25ns), especially wrt longitudinal quality and CBI
Injection tests into LHC
12h sessions every week instead of 24h every 2nd week could help (at least later in the run)
SPS: electron cloud,
scrubbing or coating?
19
– 2012 studies 1. Scrubbing week in W13 ☹ Perhaps negligible effect on the beam if we start like in 2011 ☹ Most interesting scrubbing techniques not possible for now
(5ns or 10+15ns spacings from PS) ☺ Testing efficiency of scrubbing with uncaptured beam ☺ Monitor and qualify beam induced scrubbing under different
beam/chamber conditions (beam observables, direct electron cloud observables)
☺ Validate simulation models on scrubbing times (like for LHC) 2. Some new setups for validation of a-C coating
– Electron cloud in 2011
1. Effects on the nominal 25ns beam have become less evident from the start
2. More studies on mitigation techniques done 3. Progress for the high bandwidth feedback system
SPS: miscellaneous
20
– More LIU-SPS machine studies in 2012
➀ Tests with increased peak RF power ➀ More on Q20
Nonlinear optics model Split tunes (20, 26), coupling correction Instabilities (TMCI, ECI) Extension of Q20 to fixed target physics cycles
➁ PS-SPS transfer studies ➁ Terminate phase (1) for high bandwidth feedback studies (i.e.
close feedback loop and prove damping of head-tail modes) ➁ Impedance identification
All the machines
21
– Emittance preservation across the injector chain
Systematic measurements with different beam types Define where the emittance blow up occurs
G. Arduini, LMC 12/10/2011
Closing remarks
22
Prioritized lists of needed/advisable LIU studies have been detailed out for each machine
– PSB More resources desirable for the key studies
→ Resonances at 160 MeV → Origin of instabilities, efficiency of transverse feedback in the enlarged
parameter range
– PS Important questions
→ Space charge limit at injection → Feedback against CBI → Alternative production schemes – like batch compression
– SPS Redistribution of the MD time + MD follow up meetings in the frame of SPSU-BD WG in 2012 recommended → More frequent – and shorter – MD blocks to allow for more continuous
effort on Q20 optimization (with experts available) → 3 to 5-day dedicated block for scrubbing studies
THANK YOU FOR YOUR ATTENTION!