Upload
shawn-collins
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
Narcoossee Roadway Corridor Analysis
Osceola County Board of County Commissioners Meeting
December 4, 2006
http://www.osceola.org/index.cfm?lsFuses=department/Engineering/EngCurrentProjects&nChapterID=15776
Narcoossee Road
• Corridor Study from US-192 to Orange County line (~7.4 miles)
• Primary north-south arterial road in Northeast County
Existing Conditions
• 2 lane rural arterial road
• 12 – foot travel lanes
• 4 – foot shoulders
• Open drainage system
• 55 MPH speed limit
Need for Improvement
• Current Average Annual Daily Trips (AADT) = 15,002 – 16,247
• Projected to fail adopted Level of Service (LOS) ‘D’ in 2010
• By 2030, projected 44,000 – 47,500 AADT
Need for Improvement
• Safety– 2005: 21 accidents (7 injuries)
– January 2006 – March 2006: 9 accidents (10 injuries)
Typical Sections
• Urban section
• Closed drainage
• Design for 6-lane
• Construct 4-lane
• 45 MPH design speed
Methodology - Roadway
• Typical section requires 130’ of R/W
• Minimize R/W takes– Existing R/W Typically 100’– Many segments of 130’ R/W
• Minimize impacts to existing buildings
• Minimize environmental impacts
Cyril’s Dr. to Orange County Line
Existing Conditions:
• Single family residential on both sides
• Houses on left are closer to road
• Reduced typical section
Preliminary Recommendation:
• Right widening
• 15’ additional R/W required
Orange County Line to Boggy Creek Rd.
• Inter-local agreement
• Maintain reduced typical section
• Orange County is constructing 6-lanes
• Possibly re-align Boggy Creek Rd. intersection
Schedule
Phase I - US 192 to Rummel Road
Design 1/07 To 12/07
R/W 4/07 To 5/08
Construction 7/08 To 1/10
Phase II - Rummel Road to Jack Brack Road
Design 10/07 To 10/08
R/W 4/08 To 5/09
Construction 7/09 To 7/11
Phase III – Jack Brack Road to Boggy Creek Road
Design 8/08 To 8/09
R/W 2/09 To 3/10
Construction 5/10 To 5/12
Cost
Right-of-way $12,600,000
Engineering $6,102,000
Construction $61,024,000
CEI $6,102,000
Program Mgmt. $6,102,000
Total $91,930,000
Recommendations
• Continue public involvement• Reduce speed limit• Closed drainage system• Investigate landscape options• Investigate noise abatement options• On street bicycle lanes and/or multi-use paths• Reduced typical section at north end to minimize
impacts