N End Widening 2012-256 - Responsive - 11

Embed Size (px)

Citation preview

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    1/17

    Obtained by Bob Mackin via Freedom of Information

    [email protected]

    twitter.com/bobmackin

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    2/17

    Report

    City of Vancouver

    Burrard Street BridgeNorth End WideningFeasibility Study

    July 2012

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    3/17

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    4/17

    REPORT

    iP:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    Table of Contents

    SECTION PAGE NO.

    Table of Contents i

    1 General Information 1

    2 Assumptions and Constraints 1

    3 Proposed North End Widening 3

    3.1 Alternative 1: Sidewalk Widening - Widen the Deck at Sidewalk Level 3

    3.2 Alternative 2: Roadway Widening - Widen the Deck at Roadway Level 5

    3.3 Lighting Requirements 6

    3.4 Heritage Impact 6

    4 Comparison and Evaluation 6

    5 Conclusion 8

    6 Closure 8

    Appendix A - North End Widening Sketches

    Appendix B - Heritage Evaluation Tables for North End Widening Alternatives

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    5/17

    REPORT

    1P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    1 General Information

    Associated Engineering (AE) was retained by the City of Vancouverto complete the retrofit and

    rehabilitation design of the Burrard Street Bridge. As part of that assignment, we have completed

    a feasibility study for widening the north end of the concrete approach spans to accommodate a

    north bound bike lane on the bridge deck plus a traffic queue due to turning traffic.

    The Burrard Street Bridge, shown in Figure 1-1, consists of steel truss main spans and concrete

    approach spans.

    Figure 1-1

    Burrard Street Bridge

    The bridge deck has a roadway net width of 18.3 m and currently carries two traffic lanes and a

    bike lane in the south bound direction and three traffic lanes north bound. The City is considering

    relocating the north bound cycle lane onto the bridge deck and restricting the north bound traffic to

    two lanes. Currently, north bound traffic exiting east onto Pacific frequently backs up onto the

    bridge deck restricting the capacity of through traffic to two lanes. To avoid a significant loss of

    capacity, third northbound traffic lane towards the north end will need to be maintained if one traffic

    lane is replaced by a bike lane. This study will present feasible alternatives, which not only meet

    the structural requirements, but also consider architectural objectives and the heritage character of

    the bridge.

    2 Assumptions and Constraints

    This study assumed that the traffic flow is acceptable with four traffic lanes across most of the

    bridge. Starting from the north end of the bridge, there are concrete approach spans from the

    North Abutment to Pier No. 6 and deck truss spans from Pier Nos. 6 to 4. Structurally, it is feasible

    to widen the deck truss spans by extending the floor beam cantilevers and adding a new sidewalk

    facility.

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    6/17

    City of Vancouver

    2P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    However, we do not recommend widening the deck truss spans for the following reasons:

    Negative visual impact on usage underneath the span.

    Negative visual impact on adjacent property.

    Increased heritage impact.

    High construction costs.

    The concrete approach span widening is structurally feasible by extending the existing cantilever

    floor beams and strengthening the existing cross beams. No new substructure is required. Pier

    No.6 is the critical point which separates the deck truss spans from the concrete approach spans.

    We recommend that Pier No. 6 be used as the introduction point for the additional north end traffic

    lane. We evaluated the existing concrete approach structure and determined that 3 m of deck

    widening is feasible between Pier No. 6 and the North Abutment as shown in Figure 2-1. The total

    length of the widening is about 120 m, which should provide sufficient traffic storage capacity.

    Figure 2-1

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    7/17

    Burrard Street BridgeNorth End Widening

    Feasibility Study

    3P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    3 Proposed North End Widening

    3.1 Alternative 1: Sidewalk Widening - Widen the Deck at Sidewalk Level

    The sidewalk widening, as shown in Figure 3-1, will extend the current sidewalk for another 3 m

    outside the current walkway fence while maintaining the existing deck, sidewalk and walkway fence

    unchanged. The existing pedestrian fence will remain in its current location, i.e., this character-

    defining element will be maintained and a visual symmetry of the bridge will be preserved along the

    roadway. The existing fence line will be suitably gapped north of Pier No. 6 to allow the sidewalk to

    transition to the outside. A lightweight pedestrian fence will be installed along the new sidewalk

    outer edge, to distinguish the new fence from the existing.

    Figure 3-1Deck Cross Section of Alternative 1 - Sidewalk Widening

    The existing cantilever beams will be modified and extended to support the widened walkway

    loads. A new concrete beam will be wrapped around the cantilever beam, as shown in Section C

    in Figure 3-2. The cross section of the cantilever beam will be increased in both width and depth to

    carry the additional loads. The overall shape of the new extension and modified portion of the

    cantilever beams will have a similar elevation profile as the existing cantilever beams and will be

    related to each other. This will give the impression that the beams were intended to be there rather

    than having been added awkwardly.

    As shown in Figure 3-1, a new concrete undelay will be constructed to increase the capacity of the

    cross beams between the facial girder and the center girder adjacent to the widening side. The

    cross section of the cross beam shown in Section B in Figure 3-2 will be thickened at the bottom

    and two concrete blister blocks will be constructed to anchor the new top reinforcing bars from the

    strengthened cantilever beams.

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    8/17

    City of Vancouver

    4P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    Figure 3-2

    Cross Beams of Alternative 1 - Sidewalk Widening

    The new lightweight fence will be designed to match the height and characteristics of the existing

    fence but using steel rather than concrete. One railing design in Figure 3-3 shows a steel frame

    mirroring the openings in the concrete fence, while the other shows a solid plate. The design

    details will be developed further as part of detail design.

    Figure 3-3

    If the suicide barrier is implemented, the north end fence design could be adapted as follows:

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    9/17

    Burrard Street BridgeNorth End Widening

    Feasibility Study

    5P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    Figure 3-4

    3.2 Alternative 2: Roadway Widening - Widen the Deck at Roadway Level

    The roadway widening, as shown in Figure 3-5, will provide an additional 3 m of roadway and

    extend the current walkway by 3 m. This widening strategy will relocate the current walkway fence.

    As a result, a heritage character-defining element will be displaced and roadway symmetry will not

    be preserved. However; the advantage of this option is the bike lane, which will always be at the

    same level of the roadway. To carry the new deck width, the cantilever beams and cross beams

    will be modified in a similar fashion to Alternative 1.

    Figure 3-5

    Deck Cross Section of Alternative 2 - Roadway Widening

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    10/17

    City of Vancouver

    6P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    3.3 Lighting Requirements

    The proposed street lighting is symmetrically located on the outside of the concrete fences. For the

    North End Widening, the current lighting will need to be modified to meet the new lightingrequirements. Under Alternative 1, a pedestrian luminaire will be mounted on the street light pole

    towards the widening side to illuminate the new sidewalk.

    Under Alternative 2, shown in Figure 3-5, the light pole for the roadway widening will be located on

    the outside of the new sidewalk. As a result, either more powerful LED lights or an extra light pole

    with a longer arm pole will be required to achieve the same lighting capability for both vehicular and

    pedestrian traffic. The light poles will be asymmetric for this solution.

    3.4 Heritage Impact

    The following changes applying to both alternatives will have a minimum heritage impact:

    x The cantilever beam extensions and cross beam underlays.

    x The exterior girder strengthening.

    Because the existing concrete fences are considered to be character-defining elements, any

    change to the fence and symmetry of the bridge will be assessed as high heritage impact. We

    believe that Alternative 1 has low heritage impact by maintaining the existing concrete fence

    location and maintaining fence and street light symmetry. In contrast, under Alternative 2 the

    existing fence is relocated and symmetry of the fence and light poles is lost. We consider that

    Alternative 2 has high heritage impact.

    s.13(1) and s.17(1)(c), (d), & (f)

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    11/17

    Burrard Street BridgeNorth End Widening

    Feasibility Study

    7P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    s.13(1) and s.17(1)(c), (d), & (f)

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    12/17

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    13/17

    REPORT

    A-1P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    Appendix A - North End Widening Sketches

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    14/17

    REPORT

    B-2P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    Appendix B - Heritage Evaluation Tables for NorthEnd Widening Alternatives

    Table B-1

    Conservation Standard Impact Evaluation

    North End Widening Alternative 1 Alternative 2

    Description Sidewalk Widening Roadway Widening

    Sketches

    1) Conserve the heritage value of a

    historic place. Do not remove, replace,

    or substantially alter its intact or

    repairable character--defining elements.

    Low High

    2) Conserve changes to a historicplace, which over time, have become

    character-defining elements in their own

    right.

    N/A N/A

    3) Conserve heritage value by adopting

    an approach calling for minimal

    intervention.

    medium High

    4) Recognize each historic place as a

    physical record of its time, place and

    use. Do not create a false sense of

    historical development by adding

    elements from other historic places orother properties or by combining

    features of the same property that never

    co-existed.

    medium High

    5) Find a use for a historic place that

    requires minimal or no change to its

    character-defining elements.

    low High

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    15/17

    Burrard Street BridgeNorth End Widening

    Feasibility Study

    B-3P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    North End Widening Alternative 1 Alternative 2

    Description Sidewalk Widening Roadway Widening

    6) Protect and, if necessary, stabilize a

    historic place until any subsequent

    intervention is undertaken.

    N/A N/A

    7) Evaluate the existing condition of

    character-defining elements to

    determine the appropriate intervention

    needed. Use the gentlest means

    possible for any intervention. Respect

    heritage value when undertaking an

    intervention.

    Low Medium

    8) Maintain character-defining

    elements on an ongoing basis. Repair

    character-defining elements by

    reinforcing their materials using

    recognized conservation methods.

    Replace in kind any extensively

    deteriorated or missing parts of

    character-defining elements, where

    there are surviving prototypes.

    Low (railing replaced in-kind) Medium (railing replaced but

    relocated)

    9) Make any intervention needed to

    preserve character-defining elements

    physically and visually compatible with

    the historic place and identifiable upon

    close inspection. Document any

    intervention for future reference.

    Low Medium

    10) Repair rather than replace

    character-defining elements. Where

    character-defining elements are too

    severely deteriorated to repair, and

    where sufficient physical evidence

    exists, replace them with new elements

    that match the forms, materials and

    detailing of sound versions of the sameelements. Where there is insufficient

    physical evidence, make the form,

    material and detailing of the new

    elements compatible with the character

    of the historic place.

    Low Low

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    16/17

    City of Vancouver

    B-4P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc

    North End Widening Alternative 1 Alternative 2

    Description Sidewalk Widening Roadway Widening

    11) Conserve the heritage value and

    character-defining elements when

    creating any new additions to an historic

    place and any related new construction.

    Make the new work physically and

    visually compatible with, subordinate to

    and distinguishable from the historic

    place.

    Low Medium

    12) Create any new additions or related

    new construction so that the essential

    form and integrity of an historic place

    will not be impaired if the new work is

    removed in the future.

    Low Low

    13) Repair rather than replace

    character-defining elements from the

    restoration period. Where character-

    defining elements are too severely

    deteriorated to repair and where

    sufficient physical evidence exists,

    replace them with new elements that

    match the forms, materials and detailing

    of sound versions of the same

    elements.

    N/A N/A

    14) Replace missing features from the

    restoration period with new features

    whose forms, materials and detailing

    are based on sufficient physical,

    documentary and/or oral evidence.

    N/A N/A

    OVERALL IMPACT Low Medium-High

  • 7/30/2019 N End Widening 2012-256 - Responsive - 11

    17/17

    Burrard Street BridgeNorth End Widening

    Feasibility Study

    Table B-2

    Heritage Impact Ranking and Heritage Expression

    North End Widening Alternative 1 Alternative 2

    Description Sidewalk Widening Roadway Widening

    Sketches

    Road Gate Parti: Primary Character-Defining ElementsPylons and Brazier Lights Medium High

    Concrete Piers N/A N/A

    Concrete Fences Low High

    Curved Retaining Walls N/A N/A

    Flanking Staircases N/A N/A

    Suspended Galleries N/A N/A

    Sculptural Program N/A N/A

    Tile Roofs N/A N/A

    Central Steel Truss N/A N/A

    Perceived Width of Roadway Low HighOriginal Plaque N/A N/A

    Wrought Iron Grilles N/A N/A

    View from the Bridge Low High

    Sea Gate Part: Primary Character-Defining Elements

    Concrete Piers N/A N/A

    Steel Trusses of Centre Span N/A N/A

    Concrete Fences Low High

    Gradual Sweep of Rising Roadbed Low Medium

    Views of the Bridge Low Medium

    Road Gate Parti: Secondary Character-Defining ElementsConcrete Abutments and Columns N/A N/A

    Steel Trusses under Bridge N/A N/A

    Interior Staircase, Pier One N/A N/A

    OVERALL IMPACT Low Medium