Upload
bobmackin
View
216
Download
0
Embed Size (px)
Citation preview
7/30/2019 N End Widening 2012-256 - Responsive - 11
1/17
Obtained by Bob Mackin via Freedom of Information
twitter.com/bobmackin
7/30/2019 N End Widening 2012-256 - Responsive - 11
2/17
Report
City of Vancouver
Burrard Street BridgeNorth End WideningFeasibility Study
July 2012
7/30/2019 N End Widening 2012-256 - Responsive - 11
3/17
7/30/2019 N End Widening 2012-256 - Responsive - 11
4/17
REPORT
iP:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
Table of Contents
SECTION PAGE NO.
Table of Contents i
1 General Information 1
2 Assumptions and Constraints 1
3 Proposed North End Widening 3
3.1 Alternative 1: Sidewalk Widening - Widen the Deck at Sidewalk Level 3
3.2 Alternative 2: Roadway Widening - Widen the Deck at Roadway Level 5
3.3 Lighting Requirements 6
3.4 Heritage Impact 6
4 Comparison and Evaluation 6
5 Conclusion 8
6 Closure 8
Appendix A - North End Widening Sketches
Appendix B - Heritage Evaluation Tables for North End Widening Alternatives
7/30/2019 N End Widening 2012-256 - Responsive - 11
5/17
REPORT
1P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
1 General Information
Associated Engineering (AE) was retained by the City of Vancouverto complete the retrofit and
rehabilitation design of the Burrard Street Bridge. As part of that assignment, we have completed
a feasibility study for widening the north end of the concrete approach spans to accommodate a
north bound bike lane on the bridge deck plus a traffic queue due to turning traffic.
The Burrard Street Bridge, shown in Figure 1-1, consists of steel truss main spans and concrete
approach spans.
Figure 1-1
Burrard Street Bridge
The bridge deck has a roadway net width of 18.3 m and currently carries two traffic lanes and a
bike lane in the south bound direction and three traffic lanes north bound. The City is considering
relocating the north bound cycle lane onto the bridge deck and restricting the north bound traffic to
two lanes. Currently, north bound traffic exiting east onto Pacific frequently backs up onto the
bridge deck restricting the capacity of through traffic to two lanes. To avoid a significant loss of
capacity, third northbound traffic lane towards the north end will need to be maintained if one traffic
lane is replaced by a bike lane. This study will present feasible alternatives, which not only meet
the structural requirements, but also consider architectural objectives and the heritage character of
the bridge.
2 Assumptions and Constraints
This study assumed that the traffic flow is acceptable with four traffic lanes across most of the
bridge. Starting from the north end of the bridge, there are concrete approach spans from the
North Abutment to Pier No. 6 and deck truss spans from Pier Nos. 6 to 4. Structurally, it is feasible
to widen the deck truss spans by extending the floor beam cantilevers and adding a new sidewalk
facility.
7/30/2019 N End Widening 2012-256 - Responsive - 11
6/17
City of Vancouver
2P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
However, we do not recommend widening the deck truss spans for the following reasons:
Negative visual impact on usage underneath the span.
Negative visual impact on adjacent property.
Increased heritage impact.
High construction costs.
The concrete approach span widening is structurally feasible by extending the existing cantilever
floor beams and strengthening the existing cross beams. No new substructure is required. Pier
No.6 is the critical point which separates the deck truss spans from the concrete approach spans.
We recommend that Pier No. 6 be used as the introduction point for the additional north end traffic
lane. We evaluated the existing concrete approach structure and determined that 3 m of deck
widening is feasible between Pier No. 6 and the North Abutment as shown in Figure 2-1. The total
length of the widening is about 120 m, which should provide sufficient traffic storage capacity.
Figure 2-1
7/30/2019 N End Widening 2012-256 - Responsive - 11
7/17
Burrard Street BridgeNorth End Widening
Feasibility Study
3P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
3 Proposed North End Widening
3.1 Alternative 1: Sidewalk Widening - Widen the Deck at Sidewalk Level
The sidewalk widening, as shown in Figure 3-1, will extend the current sidewalk for another 3 m
outside the current walkway fence while maintaining the existing deck, sidewalk and walkway fence
unchanged. The existing pedestrian fence will remain in its current location, i.e., this character-
defining element will be maintained and a visual symmetry of the bridge will be preserved along the
roadway. The existing fence line will be suitably gapped north of Pier No. 6 to allow the sidewalk to
transition to the outside. A lightweight pedestrian fence will be installed along the new sidewalk
outer edge, to distinguish the new fence from the existing.
Figure 3-1Deck Cross Section of Alternative 1 - Sidewalk Widening
The existing cantilever beams will be modified and extended to support the widened walkway
loads. A new concrete beam will be wrapped around the cantilever beam, as shown in Section C
in Figure 3-2. The cross section of the cantilever beam will be increased in both width and depth to
carry the additional loads. The overall shape of the new extension and modified portion of the
cantilever beams will have a similar elevation profile as the existing cantilever beams and will be
related to each other. This will give the impression that the beams were intended to be there rather
than having been added awkwardly.
As shown in Figure 3-1, a new concrete undelay will be constructed to increase the capacity of the
cross beams between the facial girder and the center girder adjacent to the widening side. The
cross section of the cross beam shown in Section B in Figure 3-2 will be thickened at the bottom
and two concrete blister blocks will be constructed to anchor the new top reinforcing bars from the
strengthened cantilever beams.
7/30/2019 N End Widening 2012-256 - Responsive - 11
8/17
City of Vancouver
4P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
Figure 3-2
Cross Beams of Alternative 1 - Sidewalk Widening
The new lightweight fence will be designed to match the height and characteristics of the existing
fence but using steel rather than concrete. One railing design in Figure 3-3 shows a steel frame
mirroring the openings in the concrete fence, while the other shows a solid plate. The design
details will be developed further as part of detail design.
Figure 3-3
If the suicide barrier is implemented, the north end fence design could be adapted as follows:
7/30/2019 N End Widening 2012-256 - Responsive - 11
9/17
Burrard Street BridgeNorth End Widening
Feasibility Study
5P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
Figure 3-4
3.2 Alternative 2: Roadway Widening - Widen the Deck at Roadway Level
The roadway widening, as shown in Figure 3-5, will provide an additional 3 m of roadway and
extend the current walkway by 3 m. This widening strategy will relocate the current walkway fence.
As a result, a heritage character-defining element will be displaced and roadway symmetry will not
be preserved. However; the advantage of this option is the bike lane, which will always be at the
same level of the roadway. To carry the new deck width, the cantilever beams and cross beams
will be modified in a similar fashion to Alternative 1.
Figure 3-5
Deck Cross Section of Alternative 2 - Roadway Widening
7/30/2019 N End Widening 2012-256 - Responsive - 11
10/17
City of Vancouver
6P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
3.3 Lighting Requirements
The proposed street lighting is symmetrically located on the outside of the concrete fences. For the
North End Widening, the current lighting will need to be modified to meet the new lightingrequirements. Under Alternative 1, a pedestrian luminaire will be mounted on the street light pole
towards the widening side to illuminate the new sidewalk.
Under Alternative 2, shown in Figure 3-5, the light pole for the roadway widening will be located on
the outside of the new sidewalk. As a result, either more powerful LED lights or an extra light pole
with a longer arm pole will be required to achieve the same lighting capability for both vehicular and
pedestrian traffic. The light poles will be asymmetric for this solution.
3.4 Heritage Impact
The following changes applying to both alternatives will have a minimum heritage impact:
x The cantilever beam extensions and cross beam underlays.
x The exterior girder strengthening.
Because the existing concrete fences are considered to be character-defining elements, any
change to the fence and symmetry of the bridge will be assessed as high heritage impact. We
believe that Alternative 1 has low heritage impact by maintaining the existing concrete fence
location and maintaining fence and street light symmetry. In contrast, under Alternative 2 the
existing fence is relocated and symmetry of the fence and light poles is lost. We consider that
Alternative 2 has high heritage impact.
s.13(1) and s.17(1)(c), (d), & (f)
7/30/2019 N End Widening 2012-256 - Responsive - 11
11/17
Burrard Street BridgeNorth End Widening
Feasibility Study
7P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
s.13(1) and s.17(1)(c), (d), & (f)
7/30/2019 N End Widening 2012-256 - Responsive - 11
12/17
7/30/2019 N End Widening 2012-256 - Responsive - 11
13/17
REPORT
A-1P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
Appendix A - North End Widening Sketches
7/30/2019 N End Widening 2012-256 - Responsive - 11
14/17
REPORT
B-2P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
Appendix B - Heritage Evaluation Tables for NorthEnd Widening Alternatives
Table B-1
Conservation Standard Impact Evaluation
North End Widening Alternative 1 Alternative 2
Description Sidewalk Widening Roadway Widening
Sketches
1) Conserve the heritage value of a
historic place. Do not remove, replace,
or substantially alter its intact or
repairable character--defining elements.
Low High
2) Conserve changes to a historicplace, which over time, have become
character-defining elements in their own
right.
N/A N/A
3) Conserve heritage value by adopting
an approach calling for minimal
intervention.
medium High
4) Recognize each historic place as a
physical record of its time, place and
use. Do not create a false sense of
historical development by adding
elements from other historic places orother properties or by combining
features of the same property that never
co-existed.
medium High
5) Find a use for a historic place that
requires minimal or no change to its
character-defining elements.
low High
7/30/2019 N End Widening 2012-256 - Responsive - 11
15/17
Burrard Street BridgeNorth End Widening
Feasibility Study
B-3P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
North End Widening Alternative 1 Alternative 2
Description Sidewalk Widening Roadway Widening
6) Protect and, if necessary, stabilize a
historic place until any subsequent
intervention is undertaken.
N/A N/A
7) Evaluate the existing condition of
character-defining elements to
determine the appropriate intervention
needed. Use the gentlest means
possible for any intervention. Respect
heritage value when undertaking an
intervention.
Low Medium
8) Maintain character-defining
elements on an ongoing basis. Repair
character-defining elements by
reinforcing their materials using
recognized conservation methods.
Replace in kind any extensively
deteriorated or missing parts of
character-defining elements, where
there are surviving prototypes.
Low (railing replaced in-kind) Medium (railing replaced but
relocated)
9) Make any intervention needed to
preserve character-defining elements
physically and visually compatible with
the historic place and identifiable upon
close inspection. Document any
intervention for future reference.
Low Medium
10) Repair rather than replace
character-defining elements. Where
character-defining elements are too
severely deteriorated to repair, and
where sufficient physical evidence
exists, replace them with new elements
that match the forms, materials and
detailing of sound versions of the sameelements. Where there is insufficient
physical evidence, make the form,
material and detailing of the new
elements compatible with the character
of the historic place.
Low Low
7/30/2019 N End Widening 2012-256 - Responsive - 11
16/17
City of Vancouver
B-4P:\20112789\00_Burrard_Rehab_Des\Engineering\03.02_Conceptual_Feasibility_Report\NorthEndWidening\RPT_06July2012\rpt_van_northendwide_20120706_sc.doc
North End Widening Alternative 1 Alternative 2
Description Sidewalk Widening Roadway Widening
11) Conserve the heritage value and
character-defining elements when
creating any new additions to an historic
place and any related new construction.
Make the new work physically and
visually compatible with, subordinate to
and distinguishable from the historic
place.
Low Medium
12) Create any new additions or related
new construction so that the essential
form and integrity of an historic place
will not be impaired if the new work is
removed in the future.
Low Low
13) Repair rather than replace
character-defining elements from the
restoration period. Where character-
defining elements are too severely
deteriorated to repair and where
sufficient physical evidence exists,
replace them with new elements that
match the forms, materials and detailing
of sound versions of the same
elements.
N/A N/A
14) Replace missing features from the
restoration period with new features
whose forms, materials and detailing
are based on sufficient physical,
documentary and/or oral evidence.
N/A N/A
OVERALL IMPACT Low Medium-High
7/30/2019 N End Widening 2012-256 - Responsive - 11
17/17
Burrard Street BridgeNorth End Widening
Feasibility Study
Table B-2
Heritage Impact Ranking and Heritage Expression
North End Widening Alternative 1 Alternative 2
Description Sidewalk Widening Roadway Widening
Sketches
Road Gate Parti: Primary Character-Defining ElementsPylons and Brazier Lights Medium High
Concrete Piers N/A N/A
Concrete Fences Low High
Curved Retaining Walls N/A N/A
Flanking Staircases N/A N/A
Suspended Galleries N/A N/A
Sculptural Program N/A N/A
Tile Roofs N/A N/A
Central Steel Truss N/A N/A
Perceived Width of Roadway Low HighOriginal Plaque N/A N/A
Wrought Iron Grilles N/A N/A
View from the Bridge Low High
Sea Gate Part: Primary Character-Defining Elements
Concrete Piers N/A N/A
Steel Trusses of Centre Span N/A N/A
Concrete Fences Low High
Gradual Sweep of Rising Roadbed Low Medium
Views of the Bridge Low Medium
Road Gate Parti: Secondary Character-Defining ElementsConcrete Abutments and Columns N/A N/A
Steel Trusses under Bridge N/A N/A
Interior Staircase, Pier One N/A N/A
OVERALL IMPACT Low Medium