14
M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 1.0 EXECUTIVE SUMMARY 1.1 Introduction Road Metal of M/s. Siva Stone Crusher covering an extent of 1.214 Ha (3.00 Ac.) is located at Sy. No. 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh The quarry lease area has been granted for 15 years. The salient features of the project are given Table 1.1. Table 1.1 : Salient features of the project Project Name Road Metal Of M/s. Siva Stone Crusher Mining Lease Area 1.214 Ha. Location of mine Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh. Minerals of mine Road Metal Proposed production of mine 15,000 cu. m./annum of Road Metal Method of mining Open cast Semi Mechanized method. Drilling/Blasting Drilling & Blasting is required in production of boulders. No of working days 300 days Water demand Nil Sources of water Quarry lease area is surrounded by water bodies Man power Total : 22 Solid Waste Nil Nearest railway station Perecherla railway Station – 0.5 km Nearest airport Gannavaram Airport – 54 km (NE) Project Cost Rs. 10.00 Lakhs

M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

1

1.0 EXECUTIVE SUMMARY

1.1 Introduction

Road Metal of M/s. Siva Stone Crusher covering an extent of 1.214 Ha (3.00 Ac.) is located at Sy. No. 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh The quarry lease area has been granted for 15 years.

The salient features of the project are given Table 1.1.

Table 1.1 : Salient features of the project

Project Name Road Metal Of M/s. Siva Stone Crusher

Mining Lease Area 1.214 Ha.

Location of mine

Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh.

Minerals of mine Road Metal

Proposed production of mine

15,000 cu. m./annum of Road Metal

Method of mining Open cast Semi Mechanized method.

Drilling/Blasting Drilling & Blasting is required in production of boulders.

No of working days 300 days

Water demand Nil

Sources of water Quarry lease area is surrounded by water bodies

Man power Total : 22

Solid Waste Nil

Nearest railway station Perecherla railway Station – 0.5 km

Nearest airport Gannavaram Airport – 54 km (NE)

Project Cost Rs. 10.00 Lakhs

Page 2: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

2

2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION

2.1 Identification of Project and Project Proponent The proposed project area is found to have good deposits of Road Metal. It is used in infrastructure development.

2.2 Brief Information about the Project The mining lease area of 1.214 Ha., is located in Non-forest, Government land. Open cast mining is followed and it has been proposed to produce approximately 15,000 cu. m./annum of Road Metal. The nearest habitation is Perecherla Village located at a distance of 1.0 Km due NW of Quarry Lease.

2.3 Need for the Project and Its Importance to the Country or Region The demand for Road Metal has increased due to rapid industrialization and growth in infrastructure. So the number of Road Metal producing quarries is increasing in India. Due to bifurcation of State, there is a huge demand for Road Metal.

As per EIA notification 2006 project proponent is submitting the proposal to get Environment Clearance for QL area of 1.214 Ha. from District Level Environmental Appraisal Committee/District level Impact Assessment Authority of Guntur constituted by MoEF, GOI for the purpose of operating the quarry lease for which Notification is issued.

2.4 Demands-Supply Gap There is huge demand since the material is used extensively in building construction infrastructure development. This project will help in reducing the Demand-Supply gap in the area.

2.5 Domestic/ Export Markets The material is used in the domestic market and in there is no scope for exporting the material.

2.6 Employment Generation Proposed mining is semi-mechanized method and this project operation will provide livelihood to the 22 workers. It will provide employment to the people residing in vicinity.

Page 3: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

3

3.0 PROJECT DESCRIPTION

3.1 Type of Project Including Interlinked and Interdependent Projects, If Any.

The proposed Road Metal is of 1.214 Ha. No interlinked projects were associated with this project.

3.2 Location

The Quarry lease area is located in Sy. Nos. : 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, A.P. The mining lease area falls in Survey of India toposheet No.s 65 D/7.

The latitude & longitudes of the Quarry lease area are:

GCP LATITUDE LONGITUDE A 16°18'55.09"N 80°20'8.59"E B 16°18'57.52"N 80°20'9.58"E C 16°18'54.81"N 80°20'13.76"E D 16°18'52.39"N 80°20'12.82"E

Location of the mining lease in Guntur District is shown in Figure – 1. Google Image of Mine lease area is enclosed as Figure-2. 10 km radius map around the quarry lease area is shown in Figure -3.

Page 4: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

4

FIGURE – 1

LOCATION MAP

QUARRY LEASE AREA

Page 5: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

5

FIGURE – 2

GOOGLE IMAGE OF QUARRY LEASE AREA

Page 6: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

6

FIGURE – 3 : 10 KM RADIUS MAP

Page 7: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

7

3.3 Details of Alternate Sites

No alternate site was considered as the project is mineral specific and site specific.

3.4 Size or magnitude of operation

The proposed mine has lease over an area of 1.214 Ha., and the production rate is 15,000 cu. m./Annum. The lessee follows open cast semi mechanized mining.

Production parameters

The Mineral production target for five years is given in Table 3.1.

Table 3.1 : Year wise Production Programme

Year Area Bench Height Volume

I Year (2017-18) 1666.67 6 10000 II Year (2018-19) 2500.00 6 15000 Total 4166.67 25000 Average 12500

3.5 Geology and Reserves

3.5.1 Regional Geological setup

The Eastern Ghat Mobile Belt (EGMB) in Andhra Pradesh occupying large parts of Coastal District, Prakasam, Guntur, Krishna, East & West Godavari, Visakhapatnam, Vizianagaram and Srikakulam Districts for more than 600 Km in length with maximum width of 100 Km in Northern District and tapers it to 20 Km in Southern District. It is NNE – SSW trending in Southern part and charge to NE – SW, West of Eluru.

Page 8: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

8

Stratigraphy & Lithology

Eastern Ghat Mobile Belt in Andhra Pradesh is devided into 3 longitudinal zones based on the lithological characteristics.

1) Western Charnockite Zone (WCZ) 2) Central Khondalite Zone (CKZ) 3) Eastern Migmatite Zone

The Southern half of the coastal belt is mainly represented by Western Charnockite zone with minor patches of Central Khondalite Zone like near Mangalagiri, where as in the Northern District of Andhra Pradesh, Central Khondalite Zone predominant with bands of Charnockite Rock.

3.5.2 Local Geology

Present area constitutes part of Western Charnockite zone represented mainly of Charnockite and basic granulite with minor banded iron formation. Lithologically the lease area is underlain by Charnockite, which is fresh looking, greasy, dark coloured with domination of hypersthenes, blue quartz minerals in it.

The Charnockite in the area forms dome shaped, steepy sloping hills. The rock is medium to coarse grained texture composed of greasy quartz, hypersthene, orthoclase and plagioclase with or without garnet.

The rock is massive, with widely spaced vertical to sub vertical joints trending in NE-SW direction. It is observed that sheet joints are absent. Owing to its compact and hardness charnockite with stand to weathering and form huge, steepy sloping dome shaped hills in the area.

3.5.3 Exploration

Road Metal quarries as the lease area is located on undulating land with surface relief of 12 m. The Road Metals found to be normal in that area, the deposit is being worked out to an maximum depth of 14 m only.

3.5.4 Reserves

Reserves of Road Metal are estimated by Cross Sectional Area method. One cross section was drawn in the lease area and the summary of reserves are given in the below table:

Page 9: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

9

TABLE 5.1: Geological Reserves

S. No.

Category Section Sectional

Area (m2)

Influence (m)

Volume (m3)

1 Proved A - A' 1107 75 83025 Proved B -B' 960 75 72000 Total Proved Reserves 155025 2 Probable A - A' 407.5 75 30563 Probable B -B' 407.5 75 30563 Total Probable Reserves 61125 3 Possible A - A' 407.5 75 30563 Possible B -B' 407.5 75 30563 Total Possible Reserves

61125

Grand Total 277275

Mineable Reserves

Mineable reserves are calculated by deducting the reserves blocked under benches and reserves blocked in 7.5 m buffer zone from the total geological reserves. Only proved reserves were considered for calculating the mineable reserves. The details of reserves blocked under benches & safety/buffer zone are given in table below:

A. Total Proved Reserves (m3) : 155025 B. Reserves Blocked under Benches (m3) : 8625 C. Reserves Blocked under 7.5 m Buffer zone (m3) : 27525 D. Reserves Blocked under Crusher (m) : 34072.5 E. Mineable Reserves [A-(B+C+D)] (m3) : 84802.5 Yearly production : 12,500 Life of mine : 84802.5/12500

=6.78 Say 7 Years

100% recovery of the Road Metal is considered from the quarry.

3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS

3.6.1 Method of Mining

The Road Metal in the lease area is exposed on the surface. Hence, it is proposed to mine the Road Metal by open cast, using semi-mechanized method, by developing the benches of 6 M height with 2 slices of 3 m and 1.5 M bench width with shallow drilling and blasting. The development of benches will be maintained @ 40 - 600 safety slopes.

Page 10: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

10

Drilling

Drill holes of 1.5 – 3.0 m depth will be drilled in a staggered pattern at 3 m. interval:

i) Drill hole diameter : 32 mm up to 1.5 – 3.0 m long

ii) Depth and inclination of drill hole : Generally drilled vertically in an alignment

iii) Explosive type : Detonator Fuse/Anfo with detonators

It is proposed to produce 25000 cu. m. of Road Metal during next 2 years plan period with an average annual production of 12500 Cu. M. from an area of 4166.67 m2. Benches of 6 m height and 3 m width will be developed during the plan period in depth of previous year workings successively. The lessee proposes to take up quarrying operations in entire quarry lease area The excavation activity will be taken up in West of the quarry lease area and then continue moves to North and South.

a) Removal / Excavation of O.B. and other Quarry Waste:

No Waste is generated in Road Metal.

3.7 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area of Final Product/S, Mode of Transport of Raw Material and Finished Product

No raw material will be required in the proposed project. The operation involves the extraction of Road Metal and dumping in stock yard.

3.7.1 Use of Mineral The Road Metal is used for formation of roads, leveling areas for civil construction works etc. No mineral rejects are anticipated.

3.7.2 Processing

The rock excavated in large sizes will be subjected to crushing and sizing to various sizes as suitable construction and road formation.

3.8 Resource Optimization/ Recycling and Reuse

Not envisaged.

Page 11: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

11

3.9.1 Availability of Water Its Source, Energy/ Power Requirement and Source

3.9.1 Water Requirement

Water is required only for drinking purposes, green belt and dust suppression. The number of working people is around 22 so the total water requirement will be around 2.5 KLD. This water will be supplied through tankers from nearby area.

Table 3.3: Water Requirement

S. No. Description Water Requirement (KLD)

1. Domestic 0.7

2. Dust suppression 1.3

3. Greenbelt 0.5

Total 2.5

3.10 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL

3.10.1 Solid Waste Generation& its Disposal

No Solid waste will be generated from Road Metal Mine

3.10.2 Liquid Effluent

No liquid effluent will be generated at the mine site. The domestic wastewater generated will be sent to septic tanks followed by soak pits.

4.0 SITE ANALYSIS

4.1 Connectivity

4.1.1 Nearest Railway Station

Perecherla Railway Station – 0.2 km due from the Quarry lease area.

4.1.2 Nearest Port Facility

Krishnapatnam port is 230 km from the quarry lease area.

Page 12: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

12

4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP

The mining lease is located in Non-Forest, Government land. Already mining was taken up in this quarry lease area.

4.3 Topography

The Quarry lease area is a part of small mound. Lease area is elevated in the Western part and gently sloping towards Eastern & NE side. The Western part of the area has a maximum RL 87 m and slopes gently towards East side having minimum RL of 75 M observed at NE side of the QL area. Surface relief in QL area is 12 m. General ground level in the surrounding areas is observed as 70 m. R.L.

Three benches were opened in the QL area with 1 - 2 m bench depth. QL area is having other Quarry leases on Northern & Western side.

Assumed Bench Mark (ABM) is considered as 80 m. at NE corner of the lease area at boundary pillar “C”. A concrete pillar will be laid at ABM and it will be protected from mining operations.

5.0 PLANNING BRIEF

5.1 Planning Concept

It is proposed to produce 15,000 Cu. m./annum of Road Metal from the Quarry lease.

5.2 Population projection

The project will employ mostly workers from nearby villages. There will not be any increase in population due to the project.

5.3 Land use planning

The project is located in 1.214 Ha. of Non-Forest, Government land. There will be change in land use as the Road Metal will be excavated. After the exhaustion of materials, the pit will be used for storing the rain water.

5.4 Assessment of Infrastructure Demand (Physical & Social)

On the basis of the preliminary site visit, the infrastructure demand in the villages was assessed on the basis of need and priority. The assessment will be made in the socio economic survey & will be submitted at the time of final presentation regarding EC.

Page 13: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

13

5.5 Amenities/Facilities

Mines Office, Rest shelter, first aid station and drinking water facilities will be constructed.

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area (Processing Area)

No infrastructure is proposed.

6.2 Residential Area (Non Processing Area)

As the local persons will be given employment, no residential area/housing is proposed within the mining lease area.

6.3 Green Belt

Green belt will be developed along the along the approach road to the mine lease area.

6.4 Water Management

About 1.3 KLD will be required for dust suppression, 0.5 KLD for greenbelt purpose, and about 0.7 KLD for domestic therefore total water requirement is 2.5 KLD. This water will be supplied through tankers from nearby villages.

6.5 Sewerage System

The domestic wastewater generated will be sent to septic tanks followed by soak pits.

6.6 Industrial Waste Management

Not applicable.

6.7 Solid Waste management

There is no waste of either topsoil or mineral rejects to be stacked separately. Hence, management does not arise.

7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN

There will be no displacement of houses. Hence rehabilitation and resettlement is not envisaged.

Page 14: M/s. Siva Stone Crusher - Welcome to Environment · 2017-07-21 · M/s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P Pre-Feasibility Report 1 . 1.0 EXECUTIVE

M/ s. Siva Stone Crusher Perecherla Village, Medikonduru Mandal, Guntur Dt., A.P

Pre-Feasibility Report

14

8.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

8.1 Financial and Social Benefits with Special Emphasis on the Benefit to the Local People Including Tribal Population, If Any, In the Area.

This project will help in providing employment to local people and help them to earn livelihood. It also increases state revenue in by paying royalty and taxes.

-----------xxxx----------