17
MONTHLY STATUS REPORT – June 2011 LOS ALAMITOS UNIFIED SCHOOL DISTRICT LOS ALAMITOS UNIFIED SCHOOL DISTRICT McAuliffe Middle School Modernization Project June 28, 2011 Los Alamitos, California

MONTHLY STATUS REPORT – June 2011...MONTHLY STATUS REPORT – June 2011 LOS ALAMITOS UNIFIED SCHOOL DISTRICTLOS ALAMITOS UNIFIED SCHOOL DISTRICT McAuliffe Middle School Modernization

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

MONTHLY STATUS REPORT – June 2011LOS ALAMITOS UNIFIED SCHOOL DISTRICTLOS ALAMITOS UNIFIED SCHOOL DISTRICT

McAuliffe Middle School Modernization Projectj

June 28, 2011,Los Alamitos, California

PHASE 4- ACTIVITY SUMMARYPHASE 4- ACTIVITY SUMMARYFinish work ongoing throughout Classroom Building ‘J’ and for Rooms 60, and 61 at Multi-Use Building ‘E’

PHASE 5- ACTIVITY SUMMARYComplete move into storage complete for Multi-Purpose Building F, Media Center Building ‘H’ and for After School programs in Portable Classrooms.Abatement of Building ‘F’ Multi-Purpose.Kitchen portion of Building ‘F’ concrete floor completeKitchen portion of Building ‘F’ concrete floor complete.Rough framing, mechanical, plumbing and electrical installation in the Kitchen portion of Building ‘F’

�ON TIME AND ON BUDGET

ongoing.Building ‘F’ new Kitchen grease interceptor complete.Building ‘H’ Media Center demolition complete�ON TIME AND ON BUDGETBuilding H Media Center demolition complete.

SUMMARY OF PROGRESS

Exterior – SiteCrane Lift – Crane Removal of HVAC Units for Demolition and Installation of New Units.

SUMMARY OF PROGRESS

Exterior – Building ‘H’ Media CentergDemolition Underway.

SUMMARY OF PROGRESS

Interior– Building ‘H’ Library g yDemolition in Progress.

SUMMARY OF PROGRESS

Exterior – Building ‘E’ Multi-UsegRoof Tear-Off Complete.

SUMMARY OF PROGRESS

Interior – Building ‘E’ Multi-Use gConstruction Nearing Completion.

SUMMARY OF PROGRESS

Exterior – Building ‘F’ KitchengExcavation of Grease Interceptor Complete.

SUMMARY OF PROGRESS

Exterior – Building ‘F’ KitchengMasonry Infill Nearing Completion.

SUMMARY OF PROGRESS

Interior – Building ‘F’ KitchengDry Storage Area Prepped for New Concrete. Main Kitchen Concrete Complete.

SUMMARY OF PROGRESS

Interior– Building ‘F’ KitchengRough Framing Nearing Completion.

SUMMARY OF PROGRESS

Exterior– Classroom Building ‘J’gExterior Painting In Progress.

SUMMARY OF PROGRESS

Exterior– Classroom Building ‘J’gNew Roof In Progress.

SUMMARY OF PROGRESS

Interior – Classroom Building ‘J’gClassroom Finishes Ongoing.

SCHEDULEPhase 4 – Classroom Building ‘J’ and Multi-UsePhase 4 – Classroom Building J and Multi-Use Building ‘E’• Complete Architectural Finishes.• Complete Telecommunications Installation• Complete Demolition and Begin New Work for

Classroom 62 (Formerly Temporary Kitchen)Classroom 62 (Formerly Temporary Kitchen)Phase 5 – Building ‘F’ Kitchen, Multi-Purpose, Classrooms• Complete Demolition (Multi-Purpose and

Classrooms)• Continue Rough Mechanical Electrical andContinue Rough Mechanical, Electrical and

Plumbing• Begin Architectural Finishes.• Continue with Kitchen Equipment Fabrication.

Phase 5 – Building ‘H’ Media Center• Complete Demolition and Abatement