PETROVEITNAM NHON TRACH 2 POWER JOINT STOCK COMPANY
NHON TRACH 2 - 750 MW COMBINED CYCLE POWER PLANT PROJECT
Monthly Progress Report July 2009
Client Petrovietnam Nhon Trach 2 Power Joint Stock CompanyTitle Monthly Progress Report July 2009Project Nhon Trach 2 Combined Cycle Power ProjectPhase Project ImplementationProject No. 9A000069.30External distribution ClientInternal distribution PMC Project FilesAuthor / position Max Stoessel, Project Manager.
Contents
1 INTRODUCTION...............................................................................................3
2 EXECUTIVE SUMMARY...................................................................................3
3 OVERVIEW OF ACTIVITY................................................................................3
4 PROJECT STATUS...........................................................................................3
4.1 General................................................................................................................................. 3
5 OVERALL PROJECT SCHEDULE...................................................................3
6 MANNING SCHEDULE.....................................................................................4
7 WORK RECORDS.............................................................................................4
7.1 Timesheets................................................................................................................................. 4
8 HEALTH, SAFETY AND ENVIRONMENT........................................................4
9 FINANCIAL / INVOICE STATUS.......................................................................4
9.1 PMC............................................................................................................................................ 49.2 LILAMA AND PVC......................................................................................................................4
10 KEY ACTIVITIES AND CONCERNS IN COMING MONTH..............................4
10.1 Site............................................................................................................................................. 410.2 Design and Engineering.............................................................................................................410.3 Procurement and Manufacturing.................................................................................................510.4 Construction............................................................................................................................... 510.5 Health and Safety....................................................................................................................... 5
Appendix 1 - Work Records
Appendix 2 - Invoice Status for July 2009
Appendix 3 - Document Review Database
1 INTRODUCTIONThis monthly report provides a record of activities, program for the project management service Phase of the Nhon Trach 2 Combined Cycle Power Plant Project.
The report presents project information for the month of July 2009.
2 EXECUTIVE SUMMARY
SIW ongoing and supervision underway
Site occupancy from PMC so design review all disciplines started.
3 OVERVIEW OF ACTIVITY The main activities in July were:
Fecon / Shanghai established on site as the Soil Improvement Work sub-contractor.
Continuing supervision of site activity related to Soils Improvement Works (SIW) being car-ried out by PECC2, PMC’s appointed site inspectors.
Vendor assessments of proposed new vendors from the contractor
Continuing review of Lot1, 2, 3 and 4 design works as follows
o Civil – Temp design documentation, structural, SIW, Gas, Oil, water & general layout docs.
o Elect – HV & Aux transformers, LV & MV motors
o Mech – Noise protection concept
o General – QA/QC, HSE & General layout docs reviewed.
Key events during the project month
Continuation of soil improvement works on site in all Zones.
4 PROJECT STATUS
PMC - Site Supervision Specific activity during the reporting month has been as follows:
4.1 General
Site Work: Please refer to section 3 for detail
5 OVERALL PROJECT SCHEDULE
5.1 Key Milestones
Start of Soil Improvement Works 24th April 2009
Effective date of EPC Contract 29th April 2009
Water required from Owner 27th May 2010
Fuel Gas required from Owner 20th November 2010
Fuel Oil required from Owner 2nd January 2011
GT11 Open Cycle PAC 1st March 2011
GT12 Open Cycle PAC 31st March 2011
Commercial Operation Date (COD) 30 October 2011 (from a 29 month EPC period)
Gas supply availability end November 2010 would allow a sufficient commissioning period for Open Cycle Operation in March 2011.
6 MANNING SCHEDULE
The PMC team continued as for the preceding month:
Stand in Project Manager (Mr. Max Stoessel based in Poyry’s Bangkok office)
Lead Civil Engineer
Project Secretary
PECC2 Civil Inspector
7 WORK RECORDS
7.1 Timesheets
The July timesheets are given in Appendix 1.
8 HEALTH, SAFETY AND ENVIRONMENT
Nothing to report
9 FINANCIAL / INVOICE STATUS
9.1 PMC
The status of invoices (to end of July 2009) is given in Appendix 2.
9.2 LILAMA AND PVC
Handled directly by PVNT2
10 KEY ACTIVITIES AND CONCERNS IN COMING MONTH
10.1 Site
Continuation of supervision of Soil Improvement Works
10.2 Design and Engineering
Continuation of detail design, engineering review and approval for civil, mechanical, electrical and C&I works.
10.3 Procurement and Manufacturing
Not applicable at the moment
10.4 Construction Soil Improvement works continuing
10.5 Health and Safety
Nothing to report.