Upload
megamind02
View
217
Download
0
Embed Size (px)
Citation preview
8/12/2019 Module 5 CPM c(2)
1/26
PERT/CPM
CONSTRUCTION
8/12/2019 Module 5 CPM c(2)
2/26
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I 2
I J 2
J K 3K END 4
C M 5
M N 1
N O 6
O END 8
Draw the network diagram and determine the critical path.
8/12/2019 Module 5 CPM c(2)
3/26
1 A2
2
D6
F
3
3 E7 4 H
2
5G
5
6
B
2
I
27
J
3 8 K4
C
59
M
110
N
6
O
811
END
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I 2
I J 2
J K 3
K END 4C M 5
M N 1
N O 6
O END 8
8/12/2019 Module 5 CPM c(2)
4/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6
B
2
I
27
J
38
K
4
C
5 9M
110
N
6
O
811
END
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I 2
I J 2
J K 3
K END 4
C M 5
M N 1
N O 6
O END 8
0
2 4 7
112
8
15
17
5 10
5 6 12
200
8/12/2019 Module 5 CPM c(2)
5/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6
B
2
I
27
J
38
K
4
C
5 9M
110
N
6
O
811
END
0
2 4 7
202
8
15
20
5 20
5 6 12
200
161311
91811
5
1512
3
1265
0
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I 2
I J 2
J K 3
K END 4C M 5
M N 1
N O 6
O END 8
8/12/2019 Module 5 CPM c(2)
6/26
1 A2
2
D6
F
3
3 E7 4 H
2
5G
5
6
B
2
I
27
J
38
K
4
C
59
M
110
N
6
O
811
END
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I, E 2
I J, H 2
J K 3
K END 4
C M, G 5
M N 1
N O 6
O END 8
8/12/2019 Module 5 CPM c(2)
7/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6
B
2
I
27
J3 8
K
4
C
5 9M
110
N
6
O
811
END
0
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I, E 2
I J, H 2
J K 3
K END 4
C M, G 5
M N 1
N O 6
O END 8
2 4 7
24
112
815
17
5
5
0
5 6 12
20
10
8/12/2019 Module 5 CPM c(2)
8/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6
B
2
I
27
J3 8
K
4
C
5 9M
110
N
6
O
811
END
0
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I, E 2
I J, H 2
J K 3
K END 4
C M, G 5
M N 1
N O 6
O END 8
2 4 7
24
112
815
17
5
5
0
5 6 12
20
10
12
15
18
16
6
5
12
13
18
11
11
5
11
9
3
0
15
8/12/2019 Module 5 CPM c(2)
9/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6
B
2
I
27
J3 8
K
4
C
5 9M
110
N
6
O
811
END
0
ACT PRECEDES DUR
A D,F 2
D E 6
E H 7
H END 2
F G 3
G END 5
B I, E 2
I J, H 2
J K 3
K END 4
C M, G 5
M N 1
N O 6
O END 8
2 4 7
24
112
815
17
5
5
0
5 6 12
20
10
12
15
18
16
6
5
12
13
18
11
11
5
11
9
3
0
15
8/12/2019 Module 5 CPM c(2)
10/26
Definition of Terms
Critical Path the longest route in the network of activities representing the project- duration of CP = duration of the project
- there maybe more than one CP in a project and may shift as the projectmoves towards completion
Forward Pass
Earliest Start Time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors Earliest finish time (EF)
earliest time an activity can finish
earliest start time plus activity time
EF= ES + t
Latest Start Time (LS)Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Backward Pass
8/12/2019 Module 5 CPM c(2)
11/26
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6B
2
I2 7
J3 8
K
4
C
5 9M
110
N
6
O
811
END
0
ACT D ES EF
A 2
D 6
E 7
H 2
F 3
G 5
B 2
I 2
DM1 0
J 3
DM2 0
K 4
C 5
DM3 0
M 1
N 6
O 8
2 4 7
24
112
815
17
5
5
0
5 6 12
20
10
0 2
2 8
0 2
2 4
2 2
8 15
4 7
4 4
15 17
7 11
2 5
0 5
5 5
5 10
5 6
6 12
12 20
8/12/2019 Module 5 CPM c(2)
12/26
ACT D LF LS
A 2
D 6
E 7
H 2
F 3
G 5
B 2
I 2
DM1 0
J 3
DM2 0
K 4
C 5
DM3 0
M 1
N 6
O 8
1 A2
2
D6
F3
3 E7 4 H
2
5G
5
6B
2
I2 7
J3 8
K
4
C
5 9M
110
N
6
O
811
END
20
12
15
18
16
6
5
12
13
18
11
11
5
11
9
3
0
15
20 12
12 6
6 5
20 15
15 12
15 15
5 0
20 18
18 11
11 5
5 3
20 16
18 18
16 13
11 11
13 11
11 9
8/12/2019 Module 5 CPM c(2)
13/26
ACT D ES EF LF LS Float
TF
A 2 0 2 5 3
D 6 2 8 11 5
E 7 8 15 18 11
H 2 15 17 20 18
F 3 2 5 15 12
G 5 5 10 20 15
B 2 0 2 11 9
I 2 2 4 13 11
DM1 0 2 2 11 11
J 3 4 7 16 13
DM2 0 4 4 18 18
K 4 7 11 20 16
C 5 0 5 5 0
DM3 0 5 5 15 15
M 1 5 6 6 5
N 6 6 12 12 6
O 8 12 20 20 12
Total Float is the maximum amount of time that this activity
can be delay in its completion before it becomes a critical
activity, i.e., delays completion of the project
TF = LS - ES
3
3
3
3
10
10
9
9
9
9
14
3
0
10
0
0
0
8/12/2019 Module 5 CPM c(2)
14/26
ACT PRECEDES DURA C, D, F 4
B F, D 7
C E, G, I 5
D E, G, I 10
E H 2
F G, I 6
G H 4
H END 8
I END 9
Construct a Network Diagram and Deter mine the Critical Path
ACT PRECEDES DUR
8/12/2019 Module 5 CPM c(2)
15/26
ACT PRECEDES DUR
A C, D, F 4
B D, F 7
C E, G, I 5
D E, G, I 10
E H 2
F G, I 6
G H 4
H END 8
I END 9
1
2A4
C5
4
3B7
F6
5
E2
6
7
H8
I9
G 4D 10 END
START
J 0 K 0
ACT PRECEDES DUR
8/12/2019 Module 5 CPM c(2)
16/26
ACT PRECEDES DUR
A C, D, F 4
B D, F 7
C E, G, I 5
D E, G, I 10
E H 2
F G, I 6
G H 4
H END 8
I END 9
1
2A4
C5
4
3B7
F6
5
E2
6
7
H8
I9
G 4D 10 ENDSTART J 0 K 0
0
4
7
4
9
17
19
17
13
2129
26
0
ACT PRECEDES DUR
8/12/2019 Module 5 CPM c(2)
17/26
ACT PRECEDES DUR
A C, D, F 4
B D, F 7
C E, G, I 5
D E, G, I 10
E H 2
F G, I 6
G H 4
H END 8
I END 9
1
2A4
C5
4
3B7
F6
5
E2
6
7
H8
I9
G 4D 10 ENDSTART J 0 K 0
0
4
7
4
9
17
19
17
13
21 29
26
29
21
17
20
19
17
11
7
12
73
029
0
8/12/2019 Module 5 CPM c(2)
18/26
ACT PRECEDES DUR
A C, D, F 4
B D, F 7
C E, G, I 5
D E, G, I 10
E H 2
F G, I 6
G H 4
H END 8
I END 9
1
2A4
C5
4
3B7
F6
5
E2
6
7
H8
I9
G 4D 10 ENDSTART J 0 K 0
0
4
7
4
9
17
19
17
13
21 29
26
29
21
17
20
19
17
11
7
12
73
00
8/12/2019 Module 5 CPM c(2)
19/26
Reducing Time and Cost
1. To avoid penalties for not completing the project on time.2. To take advantage of monetary incentives for completing the project on or before
the target date.3. To free the resources such as money, equipment, and men for use on other
project.4. Reduce indirect cost associated with the project such as:
1. Facilities and equipment cost2. Supervision cost3. Labor Cost4. Personnel Cost
8/12/2019 Module 5 CPM c(2)
20/26
Crashing- spending more money to get something done more quickly.- The key is to attain maximum decrease in schedule time with
minimum cost.
Which Method is Best?
Increasing Your Resources - this essentially means decreasing the time it takes toperform individual activities by increasing the number of people working on thoseactivities.
Pros: This makes sense, at first glance. For example, if it takes Junior 4 hoursto complete an activity, it would logically take Bob and Thirdy 2 hours tocomplete the same activity.
Cons:Adding resources isnt always the best solution, though. Sometimes itends up taking moretime in the long run.
Consider the following:New resources aren't going to be familiar with the tasks at hand, so they willprobably be less productive than current team members.Who will guide the new members up the learning curve? Usually it will bethe most productive members of the team, who could themselves be working
to get the task finished more quickly.
8/12/2019 Module 5 CPM c(2)
21/26
Which Method is Best?
Fast Tracking - which involves over-lapping tasks which were initiallyscheduled sequentially. Or you might be able to optimize your schedule inother areas.
For example, maybe you can split long tasks into smaller chunks to
squeeze more work into a shorter period of time
reduce lag times between tasks
or reduce the scope to eliminate less important tasks.
8/12/2019 Module 5 CPM c(2)
22/26
When NOT to Crash
The key to project crashing is attaining maximum reduction in schedule time withminimum cost. Quite simply, the time to stop crashing is when it no longer becomescost effective. A simple guideline is:
Crash only activities that are critical.
Crash from the least expensive to most expensive.
Crash an activity only until:It reaches its maximum time reduction.It causes another path to also become critical.
It becomes more expensive to crash than not to crash.
8/12/2019 Module 5 CPM c(2)
23/26
Procedure in Crashing Project Time
1. Obtain an estimate of regular and crash time plus the cost of each activity.
2. Determine the length of all path and their float time.3. Determine which activities are on the critical path.4. Crash the critical activities in the order of increasing costs as long as crashing
cost do not exceeds the benefits.
Requirements for Crashing Time
1. Regular time and crash time estimates for each activity2. Regular cost and crash estimates for each activity.3. A list of activities that are on the critical path.
8/12/2019 Module 5 CPM c(2)
24/26
From the following data, develop an optimum time cost plan assuming thattotal crashing cost is P15, 000.
Act Normal
Time
Crash
Time
Cost/day
to CrashA 8 8
B 12 10 P6,000
C 7 6 2,000
D 6 2 6,000
E 9 7 4,500
F 4 2 7,000
1
2
3 4
5 6
A8
B12
C7
D6
E9
F4
Path 1-2-5-6 or A-B-F = 8+12+4 = 24days
Path 1-3-4-5-6 or C-D-E-F = 7+6+9+4= 26days Critical Path
8/12/2019 Module 5 CPM c(2)
25/26
Rank the Critical Path activities in order of lowest crashing cost.
Act NormalTime CrashTime AvailableDays Cost/day toCrash
C 7 6 1 2,000
E 9 7 2 4,500
D 6 2 4 6,000
F 4 2 2 7,000
A-B-F = 24daysC-D-E-F = 26days Critical Path
Shorten the project one day and then check after each reduction to see which path is critical
Shorten Activity C by 1 day at P2,000/dayCP1 = 26 1 =25 days
Shorten Activity Eby 1 day at P4,500/dayCP2 = 25 1 =24 days
A-B-F = 24daysCritical Path
C-D-E-F = 24days
1
2
3 4
5 6
A8
B12
C7
D6
E9
F4
1
2
3 4
5 6
A8
B12
C7
D6
E9
F4
8/12/2019 Module 5 CPM c(2)
26/26
Path Activity Crash Cost/day
A-B-F
A No more Reduction
B 6,000
F 7,000
C-D-E-F
C No More Reduction
D 6,000
E 4,500
F 7,000
A-B-F = 24daysCritical Path
C-D-E-F = 24days
Act NormalTime
CrashTime
AvailableDays
Cost/dayto Crash
C 7 6 1 2,000
E 9 7 2 4,500
B 12 10 2 6,000
D 6 2 4 6,000
F 4 2 2 7,000
Try shorten B and E23 days, Cost = 10, 500Shorten F,23 days, Cost = 7,000
Thus, Shortening F is more practical.Results, 23 daysProject Duration, Total Crashing Cost = 2000 + 4,500 + 7, 000 = 13, 500
1
2
3 4
5 6
A8
B12
C
6
D
6
E
8
F4