WisDOT Utility Coordination&

TRANS 220

Mike BaumannStatewide Utility Engineer

January 22, 2015

Page 2: Mike Baumann Statewide Utility Engineer January 22, 2015

TRANS 220

Proposed Highway Improvement Notice, DT1077

Project Plan Transmittal, DT1078

Utility Worksheet, DT2236

Special Provisions

Overview

2

Page 3: Mike Baumann Statewide Utility Engineer January 22, 2015

3

Administrative Rule

TRANS 220, Utility Facilities Relocation

It’s the Law!

TRANS 220

Page 4: Mike Baumann Statewide Utility Engineer January 22, 2015

4

Improvement Notice, DT1077

Page 5: Mike Baumann Statewide Utility Engineer January 22, 2015

5

Improvement Notice, DT1077

Page 6: Mike Baumann Statewide Utility Engineer January 22, 2015

6

Improvement Notice, DT1077

Page 7: Mike Baumann Statewide Utility Engineer January 22, 2015

Improvement Notice, DT1077

7

Page 8: Mike Baumann Statewide Utility Engineer January 22, 2015

Improvement Notice, DT1077

8

Page 9: Mike Baumann Statewide Utility Engineer January 22, 2015

Improvement Notice, DT1077

9

Page 10: Mike Baumann Statewide Utility Engineer January 22, 2015

Improvement Notice, DT1077

10

Page 11: Mike Baumann Statewide Utility Engineer January 22, 2015

11

Improvement Notice, DT1077

Page 12: Mike Baumann Statewide Utility Engineer January 22, 2015

Utility facility owner review of 1077 packet Review 1077 Proposed Highway Improvement Notice Review and understand project scope/work Review and understand project limits Compare system maps to project limits Review limits of other projects in area Utilize knowledge from other projects

Potential issues from review of 1077 process System maps require updating? Request clarification on project scope/work? Request clarification on project limits?

12

Improvement Notice, DT1077

Page 13: Mike Baumann Statewide Utility Engineer January 22, 2015

Designer review of 1077 process Review 1077 Acknowledgements Review system maps Review TUMS list of utility facility owners Review Diggers Hotline locate request Consider experience from other projects/studies Review field survey

Potential issues from review of 1077 process Utility facility owner (UFO) provide correct response for

1077 process? All system maps received? Utility facilities marked correctly by Digger’s Hotline? Which UFO’s to send 1078 packet to? Coordinate changes with design team?

Improvement Notice, DT1077

13

Page 14: Mike Baumann Statewide Utility Engineer January 22, 2015

14

Project Plan Transmittal, DT1078

Page 15: Mike Baumann Statewide Utility Engineer January 22, 2015

15

Project Plan Transmittal, DT1078

Page 16: Mike Baumann Statewide Utility Engineer January 22, 2015

Designer review for Non-Comp.1078 packet Cover letter DT1078 Project Plan Transmittal/Acknowledgement Plan DT2236 Utility Worksheet Project synopsis (typically in cover letter or transmittal) Construction schedule (typically part of transmittal) Map of general project area (typically part of plan) List of possible conflicts List of utility contacts List of environmentally sensitive areas

historical archaeological environmental

Project Plan Transmittal, DT1078

16

Page 17: Mike Baumann Statewide Utility Engineer January 22, 2015

Designer review for Comp.1078 packet All items from Non-Comp. 1078 packet Plat List of real estate commitments Agreement Release of rights document DT1850 Utility Estimation Report – Lump Sum or Audit

Type DT2249 Utility’s Certificate of Compliance for Steel and

Iron Items

Project Plan Transmittal, DT1078

17

Page 18: Mike Baumann Statewide Utility Engineer January 22, 2015

Designer review of 1078 packet All documents in packet? Are documents filled out accurately? Is there sufficient information for what’s being planned? Review plan to determine if additional detail(s) are

required?

Project Plan Transmittal, DT1078

18

Page 19: Mike Baumann Statewide Utility Engineer January 22, 2015

Utility company review of 1078 packet Confirm all necessary documents in packet? Is there sufficient information for what’s being planned? Review potential conflict list? Review plan to determine if additional detail(s) are

required? Request electronic files? Contact consultant designer and/or Regional Utility

Coordinator about anything missing or questions? Return the DT1078 Project Plan Acknowledgement

within 7 days

Project Plan Transmittal, DT1078

19

Page 20: Mike Baumann Statewide Utility Engineer January 22, 2015

20

Utility Worksheet, DT2236

Page 21: Mike Baumann Statewide Utility Engineer January 22, 2015

21

Utility Worksheet, DT2236

Page 22: Mike Baumann Statewide Utility Engineer January 22, 2015

Key to completing the worksheet is answering the following for each situation:

Who What Where When How

Utility Worksheet, DT2236

22

Page 23: Mike Baumann Statewide Utility Engineer January 22, 2015

Who

Wisconsin Public Service, Field Contact Dan Druff AT&T Wisconsin, Field Contact Forrest Green Time Warner Cable, Field Contact Kerry Oki Brown County, Field Contact Olive Branch Village of Howard, Field Contact Rowan Boatman Etc………

Utility Worksheet, DT2236

23

Page 24: Mike Baumann Statewide Utility Engineer January 22, 2015

What

69 kV overhead electric line in conflict with bridge work 34.5 kV underground electric line in conflict with signs 25 pair copper cable laying on top of ground in conflict

with guardrail 24 strand undergound fiber optic cable in conflict with

retaining wall 4 inch gas main in conflict with signal lights 16 inch water main in conflict with storm sewer Sanitary sewer manhole in conflict with concrete paving Pedestal in conflict with excavation common Transformer in conflict with street lighting Vent in conflict with culvert pipe Etc……

Utility Worksheet, DT2236

24

Page 25: Mike Baumann Statewide Utility Engineer January 22, 2015

Where

USH 41 at STA 100+00 RT USH 41 from STA 100+00 RT to STA 105+00 RT Mason Street from STA 50+00 LT to STA 52+00 LT Shawano Avenue crossing at STA 45+22 Etc…..

Utility Worksheet, DT2236

25

Page 26: Mike Baumann Statewide Utility Engineer January 22, 2015

When

Prior to construction Start January 22, 2015, 10 working days as defined in

Trans 220 During construction, start once existing pavement is

removed, 2 working days as defined in Trans 220 During construction, start once ground is within one foot

of finished elevation, 5 working days as defined in Trans 220

During construction, start once topsoil is placed but prior to seed/fertilizer/erosion mat, 7 working days as defined in Trans 220

Etc…..

Utility Worksheet, DT2236

26

Page 27: Mike Baumann Statewide Utility Engineer January 22, 2015

How

Joint use Bore machine at STA 50+00 LT Open trench that is 2 feet wide by 3 feet deep Protect in place with sheet piling and concrete cap Excavate 10 foot long by 10 foot wide by 5 foot deep pit

at STA 100+00 LT Backfill excavation with granular material Clear and grub from STA 100+00 to STA 100+50 LT Rock blasting from STA 51+50 LT to STA 52+00 LT Material storage will require 100 foot by 50 foot area

from STA 52+00 LT to STA 53+00 LT. Storage area is from right-of-way to 5 feet inside slope intercept.

Utility Worksheet, DT2236

27

Page 28: Mike Baumann Statewide Utility Engineer January 22, 2015

How

Access to work site from USH 41 at STA 100+00 NB Shoulder and lane closures are required Equipment will be stored 30 feet from edge line of USH

41 during non-working hours Restoration will be completed within 2 days where work

is finished

Utility Worksheet, DT2236

28

Page 29: Mike Baumann Statewide Utility Engineer January 22, 2015

Example Wisconsin Public Service, Field Contact Dan Druff 4 inch gas main in conflict with signal lights Mason Street from STA 50+00 LT to STA 52+00 LT During construction, start once existing pavement is

removed, 2 working days as defined in Trans 220. Bore machine at STA 50+00 LT Open trench that is 2 feet wide by 3 feet deep Rock blasting from STA 51+50 LT to STA 52+00 LT Material storage will require 100 foot by 50 foot area

from STA 52+00 LT to STA 53+00 LT. Storage area is from right-of-way to 5 feet inside slope intercept.

Restoration will be completed within 2 days where work is finished

Utility Worksheet, DT2236

29

Page 30: Mike Baumann Statewide Utility Engineer January 22, 2015

Example

Wisconsin Public Servie (WPS) has a 4 inch gas main in conflict with the signal lights on Mason Street from STA 50+00 LT to STA 52+00 LT.

WPS will relocate the gas main so that it is 5 feet from the right-of-way. The existing gas main will be discontinued in place.

During construction, notify WPS as required by Trans 220.05(10) so this work will start work once the existing pavement is removed. This work will take 2 working days to complete as defined in Trans 220.03(20).

Utility Worksheet, DT2236

30

Page 31: Mike Baumann Statewide Utility Engineer January 22, 2015

Example

WPS will have a bore machine at STA 50+00 LT and will bore to STA 51+00 LT.

WPS will open trench from STA 51+00 LT to STA 52+00 LT. The trench will be 2 feet wide by 3 feet deep.

WPS anticipates rock blasting from STA 51+50 LT to STA 52+00 LT.

Utility Worksheet, DT2236

31

Page 32: Mike Baumann Statewide Utility Engineer January 22, 2015

Example

Material storage will require a 100 foot by 50 foot area from STA 52+00 LT to STA 53+00 LT. Storage area is from right-of-way to 5 feet inside slope intercept.

Restoration will be completed within the 2 working days specified earlier.

The field contact for this work is Dan Druff. Dan’s phone number is (920) 867-5309.

Utility Worksheet, DT2236

32

Page 33: Mike Baumann Statewide Utility Engineer January 22, 2015

Utilities. This contract comes under the provisions of

Administrative Rule Trans 220. 107-065 (20080501)

When interpreting the term “working days” within the “Utilities” article of these special provisions (and only within this article), use the definition provided in Trans 220.03(20) of the Wisconsin Administrative Code rather then the definition provided in Section 101.3 of the State of Wisconsin Standard Specifications for Highway and Structure Construction.

Special Provisions

33

Page 34: Mike Baumann Statewide Utility Engineer January 22, 2015

Wisconsin Public Service (WPS) has an under ground gas main along Mason Street from approximately STA 20+00 LT to approximately STA 52+00 LT

During construction, WPS plans to relocate the gas main along Mason Street from approximately STA 50+00 LT to approximately STA 52+00 LT. The existing gas main will be discontinued in-place.

WPS will store material in a 100 foot by 50 foot area from approximately STA 52+00 LT to approximately STA 53+00 LT. The storage area extends from the right-of-way to 5 feet inside of the slope intercept.

Special Provisions

34

Page 35: Mike Baumann Statewide Utility Engineer January 22, 2015

As required by Trans 220.05(10), notify Dan Druff of WPS at (920) 867-5309 so this work will start after the existing pavement is removed.

WPS anticipates this work will take 2 working days to complete.

Special Provisions

35

Page 36: Mike Baumann Statewide Utility Engineer January 22, 2015

Other Topics or Answer Questions