88
E2065 v29 HORYAN ENERGY INC. HORYAN REGULATOR AND HEPP (HYDROELECTRIC POWER PLANT) PROJECT INFORMATION FILE Province of Trabzon, Araklı District Horyan and Kara Creeks ppm kirlilik önleme ve yönetimi ltd. şti. ppm pollution prevention and management ltd. co. Sümer - 2 No:34/15, Kızılay/ANKARA Tel: (312) 231 41 69 - 230 23 69 Fax: (312) 230 23 69 e-mail : [email protected] www. ppm.com.tr

Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

E2065 v29

HORYAN ENERGY INC.

HORYAN REGULATOR AND HEPP (HYDROELECTRIC POWER PLANT) PROJECT

INFORMATION FILE

Province of Trabzon, Araklı

District Horyan and Kara Creeks

ppm kirlilik önleme ve yönetimi ltd. şti.ppm pollution prevention and management ltd. co.

Sümer - 2 No:34/15, Kızılay/ANKARATel: (312) 231 41 69 - 230 23 69Fax: (312) 230 23 69e-mail : [email protected]. ppm.com.tr

TRABZON- 2009

Page 2: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

NAME OF THE PROJECT OWNER Horyan Energy Inc.

ADDRESS Piri Reis Cad. No:3 Dragos Maltepe / İSTANBUL

TELEPHONE AND FAX NUMBERS 0216 305 50 480216 371 37 99

NAME OF THE PROJECT Horyan Regulator and HEPP

PROJECT’S WORTH 15.599.202 TLOPEN ADDRESS OF THE LOCATION SELECTED FOR THE PROJECT (PROVINCE, DISTRICT, POSITION)

Province of Trabzon, Araklı DistrictHoryan and Kara Creeks

COORDINATES OF THE ZONE SELECTED FOR THE PROJECT

Pointname

Type: UTMDatum: ED 50Projection: 6 DegreeDOM: 39Zone: 37

Type: GeographicDatum: WGS-84Projection: -DOM: -Zone:

Y(Right)

X(Upwards)

Y(Latitude)

X(Longitude)

Regulator CoordinatesR-1 586653.737 4520307.724 40.028 40.829R-2 586652.680 4520169.490 40.028 40.827R-3 586600.082 4520161.561 40.027 40.827R-4 586591.889 4520286.315 40.027 40.828GRP Pipe(Transmission Channel) Coordinatesİ-1 586613.059 4520266.442 40.027 40.828İ-2 586677.000 4520893.983 40.028 40.834İ-3 586750.533 4521573.592 40.029 40.840İ-4 586936.421 4522518.558 40.031 40.848İ-5 587083.486 4523072.109 40.033 40.853İ-6 586829.090 4523448.452 40.030 40.857İ-7 586612.602 4523946.283 40.028 40.861İ-8 586501.617 4524076.450 40.026 40.862Transmission Tunnel Coordinates T-1 586491.983 4524076.974 40.026 40.862T-2 586271.658 4524052.859 40.024 40.862Penstock Pipe Coordinates |C-1 586271.658 4524052.859 4 .024

40.862C-2 585982.561 4524203.403 40.020 40.864HEPP CoordinatesS-1 585969.950 4524239.400 40.020 40.864S-2 585994.833 4524223.080 40.020 40.864S-3 585969.046 4524181.391 40.020 40.863S-4 585944.144 4524198.121 40.020 40.864Tallow Area CoordinatesP1 586098.000 4525993.000 40.022 40.880P2 586167.000 4526030.000 40.023 40.880P3 586229.000 4526042.000 40.023 40.880P4 586290.000 4526043.000 40.024 40.880P5 586281.000 4525953.000 40.024 40.879P6 586246.000 4525900.000 40.024 40.879P7 586261.000 4525804.000 40.024 40.878P8 586223.000 4525754.000 40.023 40.878P9 586150.000 4525833.000 40.022 40.878P10 586116.000 4525907.000 40.022 40.879

PLACE OF THE PROJECT WITHIN THE In terms of project capacity, while the project was out of the

ii

Page 3: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

SCOPE OF EIA REGULATION (SECTOR, SUB-SECTOR)

scope according to provisions of Environmental Impact Assessment (EIA) Regulation which entered into force by being published in the Official Gazette No. 25318 dated 16.12.2003, with the demand of the project owner to improve its capacity the project was considered under the scope of Article 28 of “The List of Projects to be Applied Election Selection Criteria (Annex-II) of the EIA Regulation titled Energy Tourism Housing which entered into force by being published in the Official Gazette No. 26939 dated 17.07.2008, and has been evaluated Under the scope of river type power plants with established power of 0,5 MW and higher and accordingly this Project Information File hereby was prepared. Arsan Energy Inc. is planning to construct and operate Horyan Regulator and HEPP Project. In this regard, water utilization right agreement has been signed with SHW General Directorate and production license no EÜ/1398-8/1022 dated 06.12.2007 dated has been obtained. The production license that was obtained on behalf of Arsan Energy Inc. has been transferred to Horyan Energy Inc. with EPDK writing with 25.05.2009 decision date and 86 decision number.

5574PPF(PROJECT INFORMATION FILE)/NAME OF THE INSTITUTION/WORK GROUP PREPARED LAST EIA REPORT

PPM Pollution Prevention and Management Con. Eng. Cons. Ltd. Co.

PPF/EIA REPORT/ADDRESS, TELEPHONE AND FAX NUMBER OF THE INSTITUTION/WORK GROUP PREPARED LAST EIA REPORT

Address: Sümer-2 Sokak No: 34/15Kızılay/ANKARATel: (0312) 231 41 69Fax: (0312) 230 23 69

PPF/EIA REPORT /PRESENTATION DATE OF LAST EIA REPORT OCTOBER 2009

iii

Page 4: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

TABLE OF CONTENTSPageNo

Table of Contents ITables index IIList of annexes III

1. PROPERTIES OF THE PROJECT.......................................................................................11.a The Project’s Work Flow Scheme, Capacity, Covered Area, Technology, Personnel

Number......................................................................................................................................11.b Utilization of the Natural resources (Land Use, Water Use, Type of the Used Energy

etc.).............................................................................................................................................61.c Waste Production Amount (Solid, Liquid, Gas etc.) and chemical, Physical and

Biological Properties of the Wastes.......................................................................................101.d. The Accident risk to be Caused by the Technology and Materials to be Used.................331.e. Measures to be Taken Against Possible Environmental Effects of the Project................34

2. PROJECT PLACE.................................................................................................................402.a. Utilization and Quality of the Existing Area (Agricultural Area, Forest Area, Planned

Area, Water Surface etc.).......................................................................................................402.b. By taking the Invulnerable Regions list given in Annex-V into consideration; wetlands,

coastal areas, mountainous and forest areas, agriculture areas, national parks, special protection areas, intense population areas, historical, cultural, archeological and similar importance areas, erosion areas, landslip areas, forested areas, potential erosion and forestation areas and aquifers required to be protected according to Act on protection of underground waters No. 167..................................................................................................42

3. ALTERNATIVES TO PROJECT AND PLACE................................................................49

4. CONCLUSIONS.....................................................................................................................50

ANNEXES

PROJECT INFORMATION FILE PREPARED BY

iv

Page 5: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

TABLES INDEX

Table 1 Covered Area of the Units in scope of Horyan Regulator and HEPP...............................4Table 2 Horyan Regulator Area Approximate Coordinates...........................................................4Table 3 Horyan GRP Pipe Route Approximate Coordinates.........................................................4Table 4 Horyan Transmission Tunnel, Penstock Pipe and HEPP Coordinates..............................5Table 5 Tallow and Construction Site Coordinates........................................................................5Table 6 Tennant (Montana) Method:..............................................................................................7Table 7 Horyan Regulator Monthly Average Flow Rates (m3/s)...................................................8Table 8 Tennant Method Estimation Results.................................................................................9Table 9 Lifeline water value esitmated with Tennant Method HEPP............................................9Table 10 Excavation Places and Amount in Scope of the Project..................................................11Table 11 Preparation of the Land and Equipment and Heavy Duty Vehicles to be Used at Horyan

Regulator Site..................................................................................................................13Table 12 Physical and Chemical Properties of the Fuel to be Used...............................................14Table 13 Emission Factors Used in Estimation (Economopoulos, 1993)......................................14Table 14 Equipment and Machinery to be used in Land Preparation and Construction Period at

Transmission Tunnel Site................................................................................................15Table 15 Equipment and Machinery to be used in Land Preparation and Construction Period at

Transmission Channel Site..............................................................................................15Table 16 Equipment and Machinery to be used in Land Preparation and Construction Period at

Penstock Pipe Site...........................................................................................................16Table 17 Equipment and Machinery to be used in HEPP Site at the Land Preparation Phase......17Table 18 Noise Power Levels Defined According to Device Type and Net Sound Level.............24Table 19 Engine Power and Estimated Noise Levels of the Machinery Used at the Project.........26Table 20 Environmental Noise Limit Values for the Construction Site.........................................27Table 21 Atmospheric Absorption Estimation...............................................................................27Table 22 Correction Factors...........................................................................................................27Table 23 Regulator Site Machinery Sound Power.........................................................................28Table 24 Sound Pressure Level at 4 Octave Band for the Machinery to be Used at Horyan

Regulator, Transmission Channel, Penstock Pipe and HEPP Site..................................29Table 25 Net Sound Level for 4 Octave Band according to Distance at Horyan Regulator, GRP

Pipe, Penstock Pipe and HEPP Site.................................................................................30Table 26 Net Sound Pressure Level at Horyan Regulator, Spiral Pipe, GRP Pipe, Penstock Pipe

and HEPP Site.................................................................................................................31Table 27 Total Sound Level of all Sources of Noise at Horyan Regulator, Transmission Channel,

Penstock Pipe and HEPP Site construction according the distance at 4 octave band.....32Table 28 The Total Sound Level of all Sources of Noise at the Construction of the Transmission

Channel According to Distance at 4 Octave Band..........................................................33

v

Page 6: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

INDEX OF THE FIGURES

Figure 1 Vegetation Formations of Balck Sea Phytogeographic Regiom.......................................45

LIST OF ANNEXESAnnex 1: Site Location MapAnnex 2: 1/25000 Scaled General Settlement PlanAnnex 3: Regulator Plan and its SectionsAnnex 4: Opinion of the InstitutionAnnex 5: Horyan Penstock Pipe Longitudinal SectionAnnex 6: Power Plant Building and Longitudinal Section Annex 7: Fish Passage SectionAnnex 8: Horyan Regulator and HEPP Estimated Investment ProgramAnnex 9: Satellite Vision and Photos of the Project area

Annex 10: Geological Data and 1/25000 Scaled Geology MapAnnex 11: Flora and FaunaAnnex 12: Province of Trabzon Earthquake Map

vi

Page 7: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

1. PROPERTIES OF THE PROJECT

1.a The Project’s Work Flow Scheme, Capacity, Covered Area, Technology, Personnel Number

Horyan Regulator and HEPP Energy Project that are subjects to the Project, located over the Horyan Creek and Kara Creek within the borders of province of Trabzon, Araklı district. Project area Site Location Map is given in Annex-1, and 1/25.000 Scaled General Settlement Plan is given in Annex-2. The project in question is located at Trabzon G44-a4 section. There are no other facilities in the basin where Horyan Regulator and HEPP project is located. The purpose of the project is only generation of electrical power and it does not have any other goals such as irrigation and overflow control.

In terms of project capacity, while the project was out of the scope according to provisions of Environmental Impact Assessment (EIA) Regulation which entered into force by being published in the Official Gazette No. 25318 dated 16.12.2003, with the demand of the project owner to improve its capacity the project was considered under the scope of Article 28 of “The List of Projects to be Applied Election Selection Criteria (Annex-II) of the EIA Regulation titled Energy Tourism Housing which entered into force by being published in the Official Gazette No. 26939 dated 17.07.2008, and has been evaluated Under the scope of river type power plants with established power of 0,5 MW and higher and accordingly this Project Information File hereby was prepared.

Arsan Energy Inc. is planning to construct and operate Horyan Regulator and HEPP Project. In this regard, water utilization right agreement has been signed with SHW General Directorate and production license No EÜ/1398-8/1022 and dated 06.12.2007 has been obtained. The production license that was obtained on behalf of Arsan Energy Inc. has been transferred to Horyan Energy Inc. with EPDK writing with 25.05.2009 decision date and 86 decision number. (see Annex-4).

Technology and Work Flow Schedule of the Project

The recommended facilities within the scope of the project are Horyan Regulator and sedimentation tank, GPR pipe (Channel + Tunnel), surge chamber, penstock pipe and power plant building. Moreover, in order to store the earthmovings of the excavation works the non-operating tallow area with approximate size of 34.780 m2 at Kaşıkçı position that belongs to Kaletepe Stone mill management shall be used as casting area. Within the same area there shall be an in-site building to provide accommodation and meet the daily needs of the construction personnel. The property of the Stone mill belongs to the treasury. In case of this storage area is not evacuated by the Treasury a protocol shall be conducted with Araklı Municipality and the earthmovings shall be stored in an area that the Municipality considers suitable in accordance with provisions of “Earthmoving Soil, Construction and Debris Control Regulation”. All covered areas and coordinates of all units are given at the below tables and their locations within the project area are given in Annex-2 1/25000 Scaled General Inhabitance Plan.

In order to provide transportation within the scope of the project, utilization of the existing roads shall be provided after they are restored as much as possible. During the road restoration private areas will not be damaged. In case of damage to private areas during road works, after the panel of experts determines that the damages are caused by project construction activities, the damages of the private area owners shall be covered by the project owner. In case of opening new roads, minimizing logging shall be decisive for the selection of the routes.

Page 8: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Waters taken from Horyan Creek with the assistance of Horyan Regulator, as protected inside 1013,00 m Transmission Tunnel, shall be transferred to the valve chamber via GPR pipe of 4428,18 m and later shall be moved to the power plant building located at 57,45 m tailwater level via 360,00 m long penstock pipe. The waters turbined at the power plant shall be released to Kara Creek.

Characteristics of Horyan Regulator and HEPP Project:

Horyan Regulator And Water Intake Structure

Type : Lidless Full BodyThalweg Level : 280.50 mBase Level : 274.30 mHeight from the Thalweg: 5.00 mHeight from the Base : 11.20 mGravel Pass Entrance Level: 280.50 mAmount of the Cycled Water: 38.79 hm3

Overflow Yield (Q100) : 63.70 m3/sWater Intake Basement Level: 283.70 mWater Intake Structure Design Yield : 3.00 m3/sRegulator Crest Level: 285.50 mHighest Water Level: 287.09 mBody Length: 14.00 m

Horyan Regulator plan and sections are given in Annex-3.

Sand and gravel piled up inside the Regulator shall be released to the river via concrete pipe. In case of finding a buyer, this equipment shall be sold after obtaining a permit from the authorized institutions.

GRP Pipe

Location : Left CoastDiameter : Ф1400 mmLength : 4428.18 m (3415.18 +1013.00 (In tunnel))Design yield : 3.00 m3/sc

Transmission Tunnel

Type : Circular Section Tunnel (horseshoe digging)Location : Left CoastTunnel Diameter : Φ 3.00 mTunnel Wall Thickness: 0.30 mTunnel Length: 1013.00 mTunnel Entrance Level: 184.10 mTunnel Exit Level : 270.40 mTunnel Slope : 0.085 m/m

1

Page 9: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

The route to be installed GRP Pipe within the scope of Horyan Regulator and HEPP project placed in 3 km. part of the Yeşilyurt city road, at the splitting bevel side. A protocol has been signed between Arsan Energy Inc. and Province Special Administration about the mentioned works to be performed in the city road and the covering the possible damages to be done during this working period (Annex-4). During the construction stage of the project the provisions of the subject protocol shall be complied with, the route given in the project will not be exceeded and the existing art works will not be harmed during channel digging, in case of harming those the damaged art works shall be put back according to artistic structures’ project, in control of the administration. Road passages shall be kept open to traffic continuously.

Penstock Pipe

Penstock Pipe Diameter : Φ 1000 mmPenstock Pipe Wall Thickness: 8.00 ~ 10.00 mmPenstock Pipe Length: 360.00 mDesign Yield : 3.00 m3/sManifold Number : 2 itemsManifold Diameter : Φ 700 mmManifold Wall Thickness: 8.00 mm

Horyan Penstock Pipe Profile is given in Annex-5.

The property of the area on which the Penstock Pipe is to be constructed is owned by T.R. Ministry of Environment and Forestry, Forestry General Directorate. Explanations regarding the issue are included in Section 1.b.

Horyan HEPP

Power Plant Type : TerrestrialDimensions : 20.10 x 33.00 mHeight : 9.40~17.70 mInstalled Power : 2x2.84 MW (Total= 5.68 MW)Tailwater Level : 57.45 m

Horyan Power Plant Building Plan and Sections are given in Annex-6.

In order to connect the electricity to be produced within the power plant to inner network (interconnected system) an Energy Transfer Line of 31.5 kV, 9.00 km shall be established and shall be connected to a transformer center that is approved by TEİAŞ. The transfer line to be established is out of scope according to provisions of EIA Regulation. Required permits shall be obtained from the related authorities.

CapacityIn result of the conducted optimization studies the annual energy consumption of the power

plant is as given below.

2

Page 10: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Installed Power : 5,68 MWFirm Energy Generation : 5.29 GWh / yearSecondary Energy Generation : 15.77 GWh / yearTotal Energy Generation: 21.06 GWh / year

Table 1 Covered Area of the Units in scope of Horyan Regulator and HEPP

Unit Covered AreaRegulator 11.000 m2

GRP Pipe (Pipe+Tunnel) 24.900 m2

Penstock Pipe 2.340 m2

Power Plant Building 1.500 m2

Tallow + Construction Site 34.780 m2

Total 74.520 m2

Approximate coordinates of the Regulator area are given below

Table 2 Horyan Regulator Area Approximate Coordinates

PointName

Type: UTMDatum: ED 50Projection: 6 Degree DOM: 39Zone:37

Type: GeographicDatum: WGS-84Projection: -DOM: -Zone: -

Y (Right)

X(Upwards)

Y(Latitude)

X(Longitude)

Regulator CoordinatesR-1 586653.737 4520307.724 40.028 40.829R-2 586652.680 4520169.490 40.028 40.827R-3 586600.082 4520161.561 40.027 40.827R-4 586591.889 4520286.315 40.027 40.828

Horyan Regulator and HEPP Project GRP Pipe route approximate coordinates are given below.

Table 3 Horyan GRP Pipe Route Approximate Coordinates

PointName

Type: UTMDatum: ED 50Projection: 6 DegreeDOM: 39Zone:37

Type: GeographicDatum: WGS-84Projection: -DOM: -Zone: -

Y(Right)

X(Upwards)

Y(Latitude)

X(Longitude)

GRP Pipe (Transmission Channel) Coordinatesİ-1 586613.059 4520266.442 40.027 40.828İ-2 586677.000 4520893.983 40.028 40.834İ-3 586750.533 4521573.592 40.029 40.840İ-4 586936.421 4522518.558 40.031 40.848İ-5 587083.486 4523072.109 40.033 40.853İ-6 586829.090 4523448.452 40.030 40.857İ-7 586612.602 4523946.283 40.028 40.861İ-8 586501.617 4524076.450 40.026 40.862

3

Page 11: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Horyan HEPP approximate coordinates are given below.

Table 4 Horyan Transmission Tunnel, Penstock Pipe and HEPP Coordinates

PointName

Type: UTMDatum: ED 50Projection: 6 Degree DOM: 39 Zone:37

Type: GeographicDatum: WGS-84Projection: -DOM: -Zone: -

Y(Right)

X(Upwards)

Y(Latitude)

X(Longitude)

Transmission Tunnel CoordinatesT-1 586491.983 4524076.974 40.026 40.862T-2 586271.658 4524052.859 40.024 40.862Penstock Pipe CoordinatesC-1 586271.658 4524052.859 40.024 40.862C-2 585982.561 4524203.403 40.020 40.864HEPP CoordinatesS-1 585969.950 4524239.400 40.020 40.864S-2 585994.833 4524223.080 40.020 40.864S-3 585969.046 4524181.391 40.020 40.863S-4 585944.144 4524198.121 40.020 40.864

Tallow Site approximate coordinates are given below.

Table 5 Tallow and Construction Site Coordinates

PointName

Type: UTMDatum: ED 50Projection: 6 DegreeDOM: 39Zone:37

Type: GeographicDatum: WGS-84Projection: -DOM: -Zone: -

Y(Right)

X(Upwards)

Y(Latitude)

X(Longitude)

Tallow Site CoordinatesP1 586098.000 4525993.000 40.022 40.880P2 586167.000 4526030.000 40.023 40.880P3 586229.000 4526042.000 40.023 40.880P4 586290.000 4526043.000 40.024 40.880P5 586281.000 4525953.000 40.024 40.879P6 586246.000 4525900.000 40.024 40.879P7 586261.000 4525804.000 40.024 40.878P8 586223.000 4525754.000 40.023 40.878P9 586150.000 4525833.000 40.022 40.878P10 586116.000 4525907.000 40.022 40.879

Number of the Personnel

Under the scope of the Horyan Regulator and HEPP project, mostly unqualified approximately 20 people are planned to be hired for the construction stage. In management stage, mostly qualified approximately 5 people are planned to be hired to work in the power plant for maintenance and control works.

Life of the Project

4

Page 12: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

The construction activities of the project are planned to be completed in 2 years. Economical life of the project is determined as 49. However, as a result of renewal of the electromechanical equipment and regular performance of periodical maintenance it is possible to provide service for more years.

After the facility completes its life span, if necessary area leveling, shaping and terracing works shall be conducted for land development.

Also, during the land development works, in order to prevent deposition of the surface flow on the area that may be caused by precipitations, surface drainage shall be controlled by digging drainage channels and dykes at necessary locations.

1.b Utilization of the Natural resources (Land Use, Water Use, Type of the Used Energy etc.)

Land Use

The facilities under the scope of the project and the area covered by these facilities are given in Table-1. According to this approximately 74.520 m2 area shall be used Under the scope of the project.

Within the area on which the Horyan HEPP project is to be provided there are treasury, private property and forestry lands. Necessary permits for the total area of 22.102 m2 that the Penstock Pipe, GRP Pipe Route, Regulator and Sedimentation tank shall be located has been obtained from the Ministry of Environment and Forestry, General Directorate of Forestry and related documents and Area Delivery Receipt Report are given in Annex-4. Before the project in question begins to its activities, plans and reports of confiscation shall be prepared. The applications that shall be carried out according to qualifications of the land that the project shall be located are explained at Section 2.a.

Water Use

In scope of the project, preparation of the land, providing drinking and cleaning water for the workers during construction and management stages is necessary. The water is also needed to prevent the dust. Under the scope of the construction there shall be 20 workers and as estimated at Section 1.c, daily 3 m3 water supply is foreseen. For dust control approximately 5 m3 water supply is needed daily. The subject drinking water shall be provided from the hygienic commercial water in the market and the potable water shall be provided from the water tanks at the near inhabitant areas.

In the project in question, the waters taken from the Horyan Creek through regulator structure shall generate power and be released to Kara Creek bed. For this reason, a specific amount of the water in the Horyan Creek shall be utilized for energy use. In order to support the natural life in Horyan Creek life line water shall be released.

During the conducted feasibility studies, it is detected that the tunnel construction does not block the underground water. However, in case the ground water comes up during the tunnel excavation works, this water shall be removed according to provisions of WPCR (Water Pollution Control Regulation).

There is no water usage between the Regulator and the power plant such as well, fish production facility.

5

Page 13: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Life Span Water Estimation

The structures build over the rivers in scope of the water resources development projects affect water amount, quality and consequently the water ecosystem. In this direction, in order to provide continuity of the economic and ecological values of the realized projects by protecting them, the life span water that shall be let flowing downstream should be determined and released to the river bed.

Life span water is determined as the amount of water flow within the rivers needed to preserve the habitats in these rivers.

Today regulation/legislations that manage the flow that is necessary for the biological needs of a river are not present in many countries. However, there are many methods to be used to determine the amount of the water that should be left in the river for supporting the life within the river. What is the important thing for aquatic creatures in each method is different. For this reason, these methods depend on different acceptances. Consequently, the estimation was carried out via Tennant method that is approved and used frequently by SHW.

Tennant (or Montana) method (1976) is used in at least 25 countries as its original and modified versions. The most important reason to choose this method is its simplicity and easy application. A percentage of annual average flow (AAF) is used in order to define the flowing conditions regarding the flow regime, wild life, recreation and similar environmental values for different two 6 months period (Table 6). Tennant (1976) gave them some recommended flow regime names as October-March and April-September.

Table 6 Tennant (Mortana) Method:

Definition of General Flow Conditions

Recommended Flow(as a Percentage of AAF)

Recommended Flow(as a Percentage of AAF)

Overflow or Maximum 200 % 200 %Optimum Range 60-100 % 60-100 %Perfect 40 % 60 %Very Good 30 % 50 %Good 20 % 40 %Moderate 10 % 30 %Poor 10 % 10 %Very Poor <10 % <10 %

In this method 10% of annual average flow indicated as “poor”, 30% as “moderate”, %40 and more as “good” for habitat conditions.

Water resource of Horyan Regulator and HEPP Project is Kara Creek and its branches. Horyan Regulator is over Horyan Creek which is a branch of Kara Creek.

Flow Observation Stations and Project Place Flow Estimations

Water supply of Horyan Regulator area; is estimated from the daily flow data of Sürmene Creek – Ortaköy Flow Observation Station (FOS)No. 22-53 (SHW) that is established over Sürmene Creek. FOS No. 22-53 (DSİ) has benn active since 1979. No. 22 -53 (SHW) flow monitoring station 1979-1989 and 1992-1993 period has been evaluated. There is no flow

6

Page 14: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

monitoring data 1990 - 1991 and 1994 - 2002 monitoring period. Invaluable years have been obtained via correlation carried out for 1979 – 1989 the matching years of Kara Creek – Ağnas FOS No. 2202 (EİE). The meaningful correlation equation between FOS’s No. 22-53 (SHW) and No. 2202 (EİE) has been found as: y = 0.8976 * X07212, R = 0.80. With this found correlation equation daily average flow values has been completed for the missing 1990 - 1991 and 1994 - 2002 years period and for the FOS place No. 2253 (DSİ) 1979-2002 monitoring period uninterrupted flow monitoring values was obtained.

The daily flow rates of Horyan Regulator location was found by transferring the daily flow values of the FOS No. 22-53 (DSİ) between 1979 - 2002 monitoring period Horyan Regulator precipitation for 50.0 km2 Q = C x An (n = 1.0) formula with area rate. Later these values were controlled with FOS No. 22/77 and found consistent.

Horyan Regulator monthly average flow rates are given in Table 7.

Table 7 Horyan Regulator Monthly Average Flow Rates (m3/s)

YEAR OCT. NOV. DEC. JAN. FEB. MAR. APR. MAY. JUN. JUL. AGU. SEP. AVR1979 0.45 0.92 1.43 0.92 0.97 1.33 3.06 3.39 1.21 1.63 0.77 0.74 1.401980 1.82 2.21 1.10 1,01 1.06 2,03 4.22 4.54 0.67 0.17 0.84 0.89 1.711981 2.28 1.95 1.37 0.79 0.87 1.63 3,00 3.70 1.85 1.42 1.11 1.37 1.781982 0.83 1.40 0.62 0.85 0.96 1.46 4.44 2.55 0.86 1.08 0.63 1.28 1.411983 1.13 1.29 0.62 0.85 0.95 2.19 2.33 2.39 1.17 0.51 0.47 0.62 1.211984 1.30 1.53 0.54 0.19 0.27 0.76 1.73 1.83 0.61 0.75 1,03 0.54 0.921985 0.89 0.88 0.57 0.75 1.10 1.91 2.91 2.36 2.29 1.51 0.40 0.62 1.351986 1.97 0.98 1.41 1.13 1.25 1.39 1.82 2.29 1.83 0.64 0.52 0.80 1.331987 1.26 1.49 1.16 1.36 0.98 1.23 2.20 2.64 1.12 1,04 1.66 1.10 1.441988 1.25 1.41 1.19 1.26 1.45 1.61 2.78 3.21 2.14 1.46 1.45 0.81 1.671989 1.78 2.91 1,04 0.74 1.08 2.49 4.30 2,00 1.44 0.61 0.57 0.80 1.651990 1.05 0.72 1.13 0.74 0.72 1.27 3.45 2.87 1.70 0.88 0.75 0.65 1.331991 1.45 1.72 0.58 0.35 1.11 1.36 2.75 2.29 1.33 0.69 0.85 0.58 1.251992 1.77 1.28 0.73 0.86 1.10 1.75 2.99 3.19 3.34 1.89 1.05 1.24 1.771993 2.11 2.19 1.76 1,04 1.26 0.86 2.01 3.48 2.74 0.97 0.93 1.38 1.681994 0.40 0.71 0.84 0.53 0.89 1.33 2.13 1.68 0.93 0.70 0.58 0.40 0.921995 0.62 0.66 0.87 0.73 0.67 1.06 2.20 2.74 1.99 1.45 0.78 0.89 1.221996 1.52 1.86 1.07 0.72 0.64 0.83 1.95 2.89 1.52 0.74 0.90 0.79 1.291997 0.94 0.77 0.90 0.88 0.85 1.05 2.42 2.45 1.36 0.89 0.75 0.97 1.191998 1.26 1,01 0.53 0.72 0.98 1.30 2.32 2.81 1.62 0.72 0.88 0.50 1.221999 0.53 0.76 1.09 0.51 0.59 1.12 2.77 3.76 1.89 1,01 0.69 0.98 1.312000 0.85 1,00 0.87 0.78 1.10 1.49 3.13 2.13 1.71 0.61 0.49 0.78 1.252001 1.10 0.85 0.58 0.46 0.65 1.45 2.25 2.28 1.19 0.64 0.54 0.37 1,032002 0.48 0.88 0.78 0.85 0.85 1.31 2.66 2.54 1.84 0.84 0.68 0.94 1.22TOT. 29.04 31.39 22.77 19.03 22.37 34.22 65.84 66.01 38.35 22.87 19.32 20.04 32.60AVR. 1.21 1.31 0.95 0.79 0.93 1.43 2.74 2.75 1.60 0.95 0.80 0.83 1.36

The year is separated to two periods as July-March and April-June. Wet and dry periods are determined, average flow is estimated for wet and dry periods according to various percentages. Wet and dry period water need estimation results are given in Table 8.

July-March = (0,95 +0,80 + 0,83 + 1,21 + 1,31 + 0,95 +0,79 + 0,93+ 1,43) / 9 = 1,02 m 3/s (Dry Period)April - June = ( 2,74 + 2,75 + 1,60 ) / 3 = 2,36 m3/s (Wet Period) Annual Average Flow= 1,36 m3/s

Estimation results carried out via Tennant method are given in Table 8.

7

Page 15: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 8 Tennant Method Estimation Results

April - June (Wet Period)

July - March (Dry Period)

% m3/s % m3/sOverflow or Maximum 200 2.72 200 2.72Optimum Range 60-100 0.81 60-100 0.81Perfect 40 0.54 60 0.81Very Good 30 0.41 50 0.68Good 20 0.27 40 0.54Moderate 10 0.14 30 0.41Poor 10 0.14 10 0.14Very Poor <10 0.14 <10 0.14

20% 0.27

Table 9 Lifeline water value estimated with Tennant Method

Tennant Method (m3/s)Moderate Poor

Wet Period

10 % 10%0,14 0,14

Dry Period

30% 20% 10%1,41 0,27 0,14

In result of the estimations carried out via Tennant Method, 0,14 m3/sc. value has been obtained for survival of the aquatic ecosystem at the Regulator area. However, according to T.R. Ministry of Environment and Forestry, Nature Protection and National Parks General Directorate’s opinion no. 2697 dated 19.10.2009, in order to protect the natural life Under the scope of the Regulator 0,21 m3/sc lifeline water should be released from the Regulator continuously. This opinion writing is placed in Annex-4. Also, in order to control the amount of lifeline water released to the river an online flow meter shall be placed by the project owner, flow rates shall be recorded on daily basis and data transfer to SHW 22nd Zone and Province of Trabzon Environment and Forestry Directorate shall be provided at the management stage in time intervals demanded by the related authorities.

The amount of the water to be released to the river mouth in order to protect the natural life’s continuity shall be released at 10% of the average flow of the last 10 years that is taken essential for the project. During the EIA process, ecological needs shall be taken into consideration and in case of this amount determined as inadequate the amount may be increased. Other water rights established on the river mouth will also be added to this amount and certain project works shall be carried out by taking this total amount into account. In case the flow at the river is less than 10% of the last 10 years, all of it shall be released.

Structures and facilities such as fish passage etc. that allow sea creatures to pass through the place that the Regulator shall be built shall be established and they shall be provided to be operating continuously. Fish Passage Section is given in Annex-7. All kinds of measures and precautions shall be taken at each phase of the activity in order the protect the river ecosystem.

According to 22nd SHW Regional Directorate letter No. 956-5973 dated 21.07.2009, the

8

Page 16: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

existing bed width of the river shall be preserved after moving to the application phase, no activities shall be carried out that would narrow the river bed, the given rehabilitation section shall be provided to be applied by obtaining the opinion of 22nd SHW Regional Directorate to determine the overflow precautions for the facilities to be established next to the river. Also, no materials shall be shed on the river bed (see Annex-4).

Energy Type to be Used

The energy type to be used in scope of the project is the diesel fuel to be used by Heavy Duty Vehicles at the construction stage.

1.c Waste Production Amount (Solid, Liquid, Gas etc.) and chemical, Physical and Biological Properties of the Wastes

In scope of the Horyan Regulator and HEPP Project, there shall be preparation of the land, construction and operation stages.

Together with the project, preparation of the land, dust formation caused by excavations during the construction stage, emission formation after the fuel used in heavy duty vehicles and noise generation, solid and liquid waste originated from the workers etc. shall be the subjects to consider.

In Horyan Regulator and HEPP project, land preparation and construction stages are foreseen to be completed approximately within 24 months period. Horyan Regulator and HEPP Estimated Investment Program are given in Annex-8.

In order to store the earthmovings of the excavation works caused by the project temporarily the non-operating tallow area with approximate size of 34.780 m2 at Kaşıkçı position that belongs to Kaletepe Stone mill management shall be used as casting area. The property of the Stone mill belongs to the treasury. In the 21.07.2009 dated writing No. 9565973 of the 22nd SHW Regional Directorate, it is stated that the determined place for storage area to be used Under the scope of the project is not adjacent to the river and there is no objection to utilize it (see Annex-4). Within the same area there will also be an in-site building to provide accommodation and meet the daily needs of the construction personnel. The locations of the abovementioned areas are shown at the General Settlement Plan and the land to be covered is given in Table-1, their approximate coordinates are given in Table-2, Table-3, Table-4 and Table-5.

Amount and Features of Solid Waste

Land Preparation and Construction stage

During the land preparation and construction stage;

Domestic waste caused by meeting the daily needs of the workers, Earthmoving wastes resulted from excavation works, Formation of solid wastes resulted from construction shall be the subjects.

Domestic Solid Wastes

In total 20 workers are planned to be employed in scope of the project. The daily needs of the workers shall be met at the construction site building. Daily domestic solid waste production per

9

Page 17: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

person; is estimated by using 1,34 kg1 value as shown below:

Number of workers : 20 personUnit solid waste amount : 1,34 kg/person/dayAmount of solid waste : 20 x 1,34 = 26,8 kg/day

Within the domestic solid wastes; the type of the content shall be food remaining, plastic, glass, consumables (paper etc.) etc..

Earthmoving Wastes

Land preparation and base excavation works shall be caries out before the construction of the facilities in scope of the project. Under the scope of this work, firstly the botanic soil on the surface shall be removed and shall be stored separately from the other earthmoving material. In result of the woks to be conducted, earthmoving waste formation shall be present. The approximate earthmoving amounts to be formed during the construction of the units are given in Table-10.

Table 10 Excavation Places and Amount in Scope of the Project

Units Excavation AmountRegulator 11.181 m3

GRP Pipe 22.453 m3

Penstock Pipe 8.552 m3

Power Plant Building 29.950 m3

According to this, the total amount of earthmoving waste including the botanic soil cover estimated as approximately 72.136 m3.

Solid Wastes Caused by Construction

During the construction works formation of die block timber wastes, concrete packing paper, structural iron, iron pipe, concrete and injection waste materials etc. shall be present.

Operation stage

Solid wastes to be formed at the operation stage shall be only domestic solid wastes caused by the working personnel. In total there will 5 persons working in scope of the project during the operation stage.

Daily domestic solid waste production per person; is estimated by using 1,34 kg1 value as shown below:

Number of workers : 5 personUnit solid waste amount : 1,34 kg/person/dayAmount of solid waste : 5 x 1,34= 6,7 kg/day

Within the domestic solid wastes; the type of the content shall be food remaining, plastic, glass, consumables (paper etc.) etc.

The removal methods of the solid wastes are mentioned at Section 1.d.1 TurkStat 2004 Municipality Solid Waste Statistics

10

Page 18: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Nature and Features of Hazardous Waste

Land Preparation and Construction stage

Used rubber, accumulator, battery, cable, waste oils, oil holding filter etc. will form the hazardous wastes during land preparation and construction stage.

The removal methods of the solid wastes are mentioned at Section 1.d.

Operation stage

There are no hazardous wastes during the operation stage.

Amount and Features of Waste Water

Land Preparation and Construction stage

Domestic waste water shall be formed in result of meeting the daily needs of the workers working during the land preparation and construction stage. 20 people are planned to work in scope of the project. The amount of the waste water and pollution loads caused by the waste water are estimated below. The average water consumption per person in estimations is accepted2 as 150 liters and the pollution load is estimated as 54 g BOD2.

Potable water need = person x avr. Water consumption = 20 x 150 = 3.000 lt/day Total Pollution Load = person x avr. Pollution load = 20 x 54 = 1.080 g BOD/day

By accepting that the 100% of the water consumed by the personnel shall be waste water,

Amount of Waste Water = potable water need x deployment percentage = 3.000 lt/day x 1,0 = 3.000 lt/day (3 m3/day).

The waste water to be formed in result of domestic use (drinking and potable water) contains physical and biological contamination. Water to be used to prevent dust formation will not be recycled as waste water.

Operation stage

Domestic waste water shall be formed in result of meeting the daily needs of the workers working during the operation stage. 5 people are planned to work during the operation stage. The amount of the waste water and pollution loads caused by the waste water are estimated below. The average water consumption per person in estimations is accepted as 150 liters and the pollution load is estimated as 54 g BOD.

Potable water need = person x avr. Water consumption = 5 x 150 = 750 lt/day Total Pollution Load = person x avr. Pollution load = 5 x 54 = 270 g BOD/day

By accepting that the 100% of the water used by the personnel shall be recycled,

Amount of waste water = potable water need x deployment percentage = 750 lt/day x 1,0

2 İller Bankası

11

Page 19: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

= 750 lt/day (0,75 m3/day).

The waste water to be formed in result of domestic use (drinking and potable water) contains physical and biological contamination.

The removal methods of the waste waters to be formed during construction and operation stages are mentioned at Section 1.d.

Amount and Features of Emission

Preparation of the Land and Construction stage

During the land preparation and construction stage dust formation shall be caused by the heavy duty vehicles at the project sites in emission and excavation works. There is no borrow pit in scope of the project. Demanded material shall be provided from the outside.

For the heavy duty vehicles diesel oil shall be used. As different units in the project are placed different points the gas and dust emission estimations are estimated and evaluated separately as;

a. Horyan Regulator Areab. Transmission Tunnelc. GRP Piped. Penstock Pipee. HEPP Area.

a) Regulator Area

Construction of structures such as Regulator, gravel pass, spillway, water intake tank shall be realized in Horyan Regulator. During this period there may be changes in numbers of the equipment and heavy duty vehicles to be used. However, for the equipment and heavy duty vehicles to be used in maximum conditions, working times and the fuel that they consume during this time are given in Table-11.

Table 11 Preparation of the Land and Equipment and Heavy Duty Vehicles to be Used at Horyan Regulator Site

Equipment and Heavy Duty Vehicles

Item Max. Work Time

(hour/1 day)

Vehicle Fuel Consumption

(l/hour)

Total Fuel Consumption

(l/1 day)Track Loader 1 8 12 96Van 1 8 10 80Excavator 1 8 10 80Sprinkler 1 8 8 64Total 4 320

It is foreseen that the heavy duty vehicles shall approximately consume 320 liters (294 kg. ≈ 0,29 ton) of fuel daily.

12

Page 20: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 12 Physical and Chemical Properties of the Fuel to be UsedCompound (% Weight) C : %86,5 - H : %12,2 - O : %1,0 - S : %0,3Density (P 15°C, gr/cm3) 0,92Lower Heating Value 40,4Viscosity (10-3 Pa S/C) 79,7/80Max. CO2 content (% volume) 15,5

Emission factors for unit fuel consumption in heavy diesel work vehicles according to Economopoulos 1993 are given in Table-13.

Table 13 Emission Factors Used in Estimation (Economopoulos, 1993)

Diesel Heavy Duty Machinery

UNIT(U)

TSP (kg/U)

SO2

(kg/U)NOx

(kg/U)CO (kg/U)

VOC (kg/U)

In city 1.000 km 0,9 4,29 11,8 6 2,6Ton Fuel 4,3 20 55 28 12

Outside City 1.000 km 0,9 4,15 14,4 2,9 0,8Ton Fuel 4,3 20 70 14 4

Driving at Highways 1.000 km 0,9 4,15 14,4 2,9 0,8

The emissions to be occurred are foreseen as indicated below by taking daily 0,29 ton fuel consumption and above inventory coefficient

TSP: 4,3 kg/ton fuel x 0,29 ton/day x 1 day / 8 hours = 0,16 kg TSP/ hours <1,5 kg/ hoursSO2: 20 kg/ton fuel x 0,29 ton/day x 1 day / 8 hours = 0,73 kg SO2/ hours <6 kg/ hoursNOx: 70 kg/ton fuel x 0,29 ton/day x 1 day / 8 hours = 2,54 kg NOx/ hours <4 kg/ hoursCO: 14 kg/ton fuel x 0,29 ton/day x 1 day / 8 hours = 0,5 kg CO/ hours <50 kg/ hoursVOC: 4 kg/ton fuel x 0,29 ton/day x 1 day/ 8 hours = 0,15 kg VOC/ hours <3 kg/ hours

When this values estimated for Horyan Regulator Site are compared with “Molar Values” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, it is observed that none of the emission values exceed the threshold value stated at the regulation. For this reason, no modeling has been conducted.

The precautions to be taken in order to reduce the amount of emission caused by the fuel are explained at Section 1.d.

b ) Transmission Tunnel (GRP Pipe)

In scope of the project, an approximately 1013 m. long tunnel shall be opened along the Transmission Channel, at the site that is not suitable for building channel and GRP Pipe shall be put inside of it. During tunnel construction period there may be changes in numbers of the equipment and heavy duty vehicles to be used. However, for the equipment and heavy duty vehicles to be used in maximum conditions, working times and the fuel that they consume during this time are given in Table-14.

13

Page 21: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 14 Equipment and Machinery to be used in Land Preparation and Construction Period at Transmission Tunnel Site

Equipment and Heavy Duty Vehicles

Item Max. Working Time

(hour/1 day)

Vehicle Fuel Consumption

(l/hour)

Total Fuel Consumption

(l/1 day)Track Loader 1 8 12 96Van 2 8 10 160Digger 1 8 12 96Total 4 352

It is foreseen that the heavy duty vehicles shall approximately consume 352 liters (324 kg. = 0,32 ton) of fuel daily.

Emission factors for unit fuel consumption in heavy diesel work vehicles according to Economopoulos 1993 are given in Table-13.

The emissions to be occurred are foreseen as indicated below by taking daily 0,32 ton fuel consumption and above inventory coefficients.

TSP: 4,3 kg/ton fuel x 0,32 ton/day x 1 day /8 hour = 0,17 kg TSP/ hour <1,5 kg/ hourSO2: 20 kg/ton fuel x 0,32 ton/ day x 1 day /8 hour = 0,8 kg SO2/ hour <6 kg/ hourNOx: 70 kg/ton fuel x 0,32 ton/ day x 1 day /8 hour = 2,8 kg NOx/ hour >4 kg/ hourCO: 14 kg/ton fuel x 0,32 ton/ day x 1 day /8 hour = 0,6 kg CO/ hour <50 kg/ hourVOC: 4 kg/ton fuel x 0,3 ton/ day x 1 day /8 hour = 0,16 kg VOC/ hour <3 kg/ hour

When this values estimated for Transmission Tunnel are compared with “Molar Values” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, it is observed that none of the emission values exceed the threshold value stated at the regulation. For this reason, no modeling has been conducted.

c) Transmission Channel (GRP Pipe)

The total length of the Transmission Channel is 3.415,18 meters. During channel construction period there may be changes in numbers of the equipment and heavy duty vehicles to be used. However, for the equipment and heavy duty vehicles to be used in maximum conditions, working times and the fuel that they consume during this time are given in Table 15.

Table 15 Equipment and Machinery to be used in Land Preparation and Construction Period at Transmission Channel Site

Equipment and Heavy Duty Vehicles

Item Max. Working Time

(hour/1 day)

Vehicle Fuel Consumption

(l/hour)

Total Fuel Consumption

(l/1 day)Track Loader 1 8 12 96Van 2 8 10 160Excavator 1 8 10 80Sprinkler 1 8 8 64Total 7 400

14

Page 22: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

It is foreseen that the heavy duty vehicles shall approximately consume 400 liters (368 kg. = 0,37 ton) of fuel daily.

Emission factors for unit fuel consumption in heavy diesel work vehicles according to Economopoulos 1993 are given in Table-13.

The emissions to be occurred are foreseen as indicated below by taking daily 0,37 ton fuel consumption and above inventory coefficients.

TSP 4,3 kg/ton fuel x 0,37 ton/day x 1 day /8 hour = 0,2 kg TSP/ hour <1,5 kg/ hourSO2 20 kg/ton fuel x 0,37 ton/ day x 1 day /8 hour = 0,93 kg SO2/ hour <6 kg/ hourNOx 70 kg/ton fuel x 0,37 ton/ day x 1 day /8 hour = 3,2 kg NOx/ hour >4 kg/ hourCO 14 kg/ton fuel x 0,37 ton/ day x 1 day /8 hour = 0,65 kg CO/ hour <50 kg/ hourVOC 4 kg/ton fuel x 0,37 ton/ day x 1 day /8 hour = 0,19 kg VOC/ hour <3 kg/ hour

When this values estimated for Transmission Channel are compared with “Molar Values” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, it is observed that none of the emission values exceed the threshold value stated at the regulation. For this reason, no modeling has been conducted.

d) Penstock Pipe

During the construction period of 360 meters long Penstock Pipe there may be changes in numbers of the equipment and Heavy Duty Vehicles to be used. However, for the equipment and Heavy Duty Vehicles to be used in maximum conditions, working times and the fuel that they consume during this time are given in Table 16.

Table 16 Equipment and Machinery to be used in Land Preparation and Construction Period at Penstock Pipe Site

Equipment andHeavy Duty Vehicles

Item Max. Working Time

(hour/1 day)

Vehicle Fuel Consumption

(l/hour)

Total FuelConsumption

(l/1 day)Track Loader 1 8 12 96Van 1 8 10 80Excavator 1 8 10 80Sprinkler 1 8 8 64Total 5 320

The amount of emission to be formed, fuel to be consumed by the machinery used in land works for Penstock Pipe construction is the same as Horyan Regulator. For this reason, a new estimation has not been conducted and as the fuel emission to be formed at the construction site is below the notified threshold, no negative effect to the environment is expected.

e) HEPP Site

Horyan HEPP construction period is expected to be completed in 6 months. During this period there may be changes in numbers of the equipment and Heavy Duty Vehicles to be used. However, for the equipment and Heavy Duty Vehicles to be used in maximum conditions, working times and the fuel that they consume during this time are given in Table-17.

15

Page 23: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 17 Equipment and Machinery to be used in HEPP Site at the Land Preparation Phase

Equipment andHeavy Duty Vehicles

Item Max. Working Time

(hour/1 day)

Vehicle Fuel Consumption

(l/hour)

Total Fuel Consumption

(l/1 day)Track Loader 1 8 12 96Van 2 8 10 160Excavator 1 8 10 80Sprinkler 1 8 8 64Total 4 400

The amount of emission to be formed, fuel to be consumed by the machinery used in land works for HEPP Site construction is the same as GRP Pipe Route. For this reason, a new estimation has not been conducted and as the fuel emission to be formed at the construction site is below the notified threshold, no negative effect to the environment is expected.

Operation stage

The source of power at social buildings that shall be used for accommodation of the personnel to be working at the operation stage is electricity. For this reason, fuel consumption and emission for warming is out of subject. Emission formation is out of subject for operation stage.

Dust Emission Amounts

Within the scope of the project dust formation shall be present at three areas. These areas can be put under three main titles as land preparation and construction stage, during the storage of the material and during transportation.

Dust Emission Formation During Land Preparation and Construction

Under the scope of the project, dust formation shall be present in result of loading, unloading, transfer of the material come out after the excavation works and movements of the vehicles within the site.

Dust emission estimations within the scope of the project in question are gathered together under below titles.

a. Regulator Siteb. GRP Pipe (Channel+Tunnel)c. Penstock Piped. HEPP Site

a. Regulator Site

Total amount of earthmovings that is planned to be carried out for Horyan Regulator and sedimentation tank is 11.181 m3. Average density of Regulator site is taken as 1,7 ton / m3. The times of constructions are different and all construction works to be carried out at the Regulator site are foreseen to be completed approximately in 11 months.

16

Page 24: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Material density : 1,7 ton/m3

Total Amount of Production : 19.008 ton (11.181 m3)Monthly Production : 1.728 ton (1.016 m3)Daily Production : 69 ton (40,66 m3)Hourly Production : 8,64 ton (5,08 m3)Working Times : 11 months, Month/ 25 day, day/8 hour

Excavation

An amount of dusting shall be present during gathering earthmovings. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,025 kg dust/ton (Müezzinoğlu, A.) Excavation and loading : 8,64 ton/hour x 0,025 kg/ton = 0,216 kg/hour

Loading

An amount of dusting will occur during loading of the excavated earthmoving waste to the vans. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,01 kg dust/ton (Müezzinoğlu, A.) Loading: 8,64 ton/hour x 0,01 kg/ton = 0,087 kg/hour

Transportation

The material to be loaded to the trucks shall be transported at approximately 100 m distance that may affect the dust emission at the Regulator site construction. Daily amount of earthmovings waste is 69 ton/day and van capacities are 25 tons. According to this number of transportation is determined as 3 times/day.

Transportation emission factor : 0,7 kg dust/km.vehicle (Müezzinoğlu, A.)Trip length : 0,2 km/times (round trip)Transportation : 0,7 kg/km x 0,2 km/times x 3 times/day = 0,42 kg/day

: 0,42 kg/day x 1day/8 hour = 0,053 kg/hour

The amount of dust to be present during the movements of the vehicles in work area

There shall be a low amount of dust output during the movements of the vehicles in work area. In order to prevent this dusting, water spraying within the area shall be conducted in accordance with season and speed of evaporation.

Total Dust Emission to be Present at Horyan Regulator Site:

Total dust emission flow to be occurred after all of these works;

Total: 0,216 + 0,087 + 0,053 = 0,356 kg/hour

When the dust flow to be occurred at Horyan Regulator site is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

17

Page 25: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

b) GRP Pipe

Total amount of earthmoving to be conducted for the GRP pipe that is 4428.18 m long and 1013.00 meter of it preserved inside Transmission Tunnel is 22.453 m3. The density of the earthmoving material to be removed during the construction works in the GRP Pipe route is considered as approximately 1,7 ton/m3. All construction works to be carried out at the GRP Pipe route is foreseen to be completed approximately within 6 months period.

Material density : 1,7 ton/m3

Total Amount of Production : 38.170 ton (22.453 m3)Monthly Production : 6.362 ton (3.742 m3)Daily Production : 254,5 ton (149,7 m3)Hourly Production : 31,8 ton (18,7 m3)Working Times : 6 months, month/ 25 day, day/8 hour

Excavation

An amount of dusting shall be present during gathering earthmovings. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,025 kg dust/ton (Müezzinoğlu, A.) Excavation and loading : 31,8 ton/hour x 0,025 kg/ton = 0,795 kg/hour

Loading

An amount of dusting will occur during loading of the excavated earthmoving waste to the vans. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,01 kg dust/ton (Müezzinoğlu, A.) Loading: 31,8 ton/hour x 0,01 kg/ton = 0,318 kg/hour

Transportation

The material to be loaded to the trucks shall be transported at approximately 100 m distance that may affect the dust emission at the Regulator site construction. Daily amount of earthmovings waste is 254,5 ton/day and van capacities are 25 tons. According to this number of transportation is determined as 10 times/day. As there shall be 2 vans to be used during the work, each will make 5 round trips.

Transportation Emission Factor : 0,7 kg dust/km.vehicle (Müezzinoğlu, A.)Trip Length : 0,2 km/times (round-trip)Transportation : 0,7 kg/km x 0,2 km/times x 5 times/day = 0,7 kg/day

: 1,4 kg/day x 1day/8 hour= 0,088 kg/hour

The amount of dust to be present during the movements of the vehicles in work area

There shall be a low amount of dust output during the movements of the vehicles in work area. In order to prevent this dusting, water spraying within the area shall be conducted in accordance with season and speed of evaporation.

18

Page 26: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Total Dust Emission to be Present at GRP Pipe Construction:

Total dust emission flow to be occurred after all of these works;

Total : 0,795 + 0,318 + 0,088 = 1,2 kg/hour

When the dust flow to be occurred at GRP construction is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

c) Penstock Pipe

In scope of the project, the total amount of the needed earthmoving is 8.552 m3. Penstock Pipe excavation work is planned to be completed within 6 months.

Material density : 1,7 ton/m3

Total Amount of Production : 14.538 ton (8.552 m3)Monthly Production : 2.423 ton (1.425 m3)Daily Production : 96,9 ton (57 m3)Hourly Production : 12,1 ton (7,13 m3)Working Times : 6 months, month/ 25 day, day/8 hour

Excavation

An amount of dusting shall be present during gathering earthmovings. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,025 kg dust/ton (Müezzinoğlu, A.) Excavation and loading : 12,1 ton/hour x 0,025 kg/ton = 0,303 kg/hour

Loading

An amount of dusting will occur during loading of the excavated earthmoving waste to the vans. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,01 kg dust/ton (Müezzinoğlu, A.) Loading: 12,1 ton/hour x 0,01 kg/ton = 0,121 kg/hour

Transportation

The material to be loaded to the trucks shall be transported at approximately 100 m distance that may affect the dust emission at the Regulator site construction. Daily amount of earthmovings waste is 96,9 ton/day and van capacities are 25 tons. According to this number of transportation is determined as 4 times/day.

Transportation Emission Factor : 0,7 kg dust/km.vehicle (Müezzinoğlu, A.)Trip Length : 0,2 km/times (round-trip)Transportation : 0,7 kg/km x 0,2 km/times x 4 times/day = 0,56 kg/day

: 0,56 kg/day x 1day/8 hour = 0,07 kg/hour

19

Page 27: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

The amount of dust to be present during the movements of the vehicles in work area

There shall be a low amount of dust output during the movements of the vehicles in work area. In order to prevent this dusting, water spraying within the area shall be conducted in accordance with season and speed of evaporation.

Total Dust Emission to be Present at Penstock Pipe Site:

Total dust emission flow to be occurred after all of these works;

Total : 0,303 + 0,121 + 0,07 = 0,494 kg/hour

When the dust flow to be occurred during Penstock Pipe excavation is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

d) Horyan HEPP Site

Total amount of earthmoving needed to be performed for HEPP site is 25.950 m3. All construction works to be carried out for HEPP site are foreseen to be completed within 6 months. The density of the earthmovings at the excavation site is taken as approximately 1,7 ton / m3.

Material density : 1,7 ton/m3

Total Amount of Production : 44.115 ton (25.950m3)Monthly Production : 7.353 ton (4.325 m3)Daily Production : 294 ton (173 m3)Hourly Production : 36.7 ton (21,6 m3)Working Times : 6 months, month/ 25 day, day/8 hour

Excavation

An amount of dusting shall be present during gathering earthmovings. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,025 kg dust/ton (Müezzinoğlu, A.) Excavation and loading : 36,7 ton/hour x 0,025 kg/ton = 0,91 kg/hour

Loading

An amount of dusting will occur during loading of the excavated earthmoving waste to the vans. Estimation of dust to be formed is conducted below.

Material extracting emission factor: 0,01 kg dust/ton (Müezzinoğlu, A.) Loading: 36,7 ton/hour x 0,01 kg/ton = 0,37 kg/hour

Transportation

The material to be loaded to the trucks shall be transported at approximately 100 m distance that may affect the dust emission at the Regulator site construction. Daily amount of earthmovings waste is 294 ton/day and van capacities are 25 tons. According to this number of transportation is

20

Page 28: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

determined as 12 times/day. As there shall be 2 vans to be used during the work, each will make 6 round trips.

Transportation emission factor : 0,7 kg dust/km. vehicle (Müezzinoğlu, A.)Trip length : 0,2 km/times (round trip)Transportation : 0,7 kg/km x 0,2 km/times x 6 times/day= 0,84 kg/day

: 0,28 kg/day x 1day/8 hour = 0,105 kg/hour

The amount of dust to be present during the movements of the vehicles in work area

There shall be a low amount of dust output during the movements of the vehicles in work area. In order to prevent this dusting, water spraying within the area shall be conducted in accordance with season and speed of evaporation.

Total Dust Emission to be Present at Horyan HEPP Site:

Total dust emission flow to be occurred after all of these works;

Total : 0,91 + 0,37 + 0,105 = 1,38 kg/hour

When the dust flow to be occurred at Horyan HEPP Site is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

Dust Emission Formation During Storage:

In order to store the earthmovings of the excavation works the non-operating tallow area with approximate size of 34.780 m2 at Kaşıkçı position that belongs to Kaletepe Stone mill management shall be used as casting area. Within the same area there shall be an in-site building to provide accommodation and meet the daily needs of the construction personnel. Total amount of expected earthmoving waste in scope of the project is approximately 72.136 m3. A part of this amount shall be used as fill material at construction and road construction works.

Storage of the Earthmoving to be Formed at Regulator Area

The total amount of earthmoving planning to be performed for Horyan Regulator and sedimentation tank is 11.181 m3. The amount of material to be stored at tallow site is approximately 40,66 m3. If we think the length of the material to be stored at most 2 meters, daily need of storage area shall be approximately 20,3 m2.

The amount of dust to be formed during storage;

Storage: 5,8 kg/ha-day x 20,3 m2/day x 1 ha/10.000 m2 x 1 day/8 hour = 0,0014 kg/hour

When the dust flow to be occurred in result of storage of the earthmoving to be formed at Regulator area in tallow area is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

21

Page 29: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Storage of the Earthmoving to be Formed at GRP Pipe Route

The total amount of earthmoving planning to be performed for GRP Pipe is 22.453 m3. The amount of material to be stored at tallow site is approximately 149,7 m3. If we think the length of the material to be stored at most 2 meters, daily need of storage area shall be approximately 74,9 m2.

The amount of dust to be formed during storage;

Storage: 5,8 kg/ha-day x 74,9 m2/day x 1 ha/10.000 m2 x 1 day/8 hour = 0,005 kg/hour

When the dust flow to be occurred in result of storage of the earthmoving to be formed at GRP Pipe route in tallow area is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

Storage of the Earthmoving to be Formed at the Penstock Pipe Area

The total amount of earthmoving planning to be performed for Penstock Pipe is 8.552 m3. The amount of material to be stored at tallow site is approximately 57 m3. If we think the length of the material to be stored at most 2 meters, daily need of storage area shall be approximately 25,5 m2.

The amount of dust to be formed during storage;

Storage: 5,8 kg/ha-day x 28,5 m2/day x 1 ha/10.000 m2 x 1 day/8 hour = 0,002 kg/hour

When the dust flow to be occurred in result of storage of the earthmoving to be formed at Penstock Pipe route in tallow area is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

Storage of the Earthmoving to be Formed at HEPP Area

The total amount of earthmoving planning to be performed for HEPP is 25.950 m3. The amount of material to be stored at tallow site is approximately 173 m3. If we think the length of the material to be stored at most 2 meters, daily need of storage area shall be approximately 86,5 m2.

The amount of dust to be formed during storage;

Storage: 5,8 kg/ha-day x 86,5 m2/day x 1 ha/10.000 m2 x 1 day/8 hour = 0,006 kg/hour

When the dust flow to be occurred in result of storage of the earthmoving to be formed at HEPP area in tallow area is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values are detected to be below the limit value (> 1,5 kg/hour) and there is no need to perform dust distribution modeling oriented in detection of air quality.

Dust Emission to be Formed During Transportation Process

22

Page 30: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Yeşilyurt city road and Yoncalı village road shall be used during transportation of the earthmoving caused by the construction of structures Under the scope of Horyan Regulator and HEPP project. City road is asphalt covered and the village road is concrete. For this reason no dust formation is expected. Also, the roads where transportation is conducted via sprinkler shall be sprayed with water regularly in order to prevent dust formation. The roads that will utilized during the construction stage of the project will not be damaged under any circumstances and in case of occurrence of any damage its’ rehabilitation shall be provided.

Operation stage

There is no process to cause dust formation during operation stage.

Noise Pollution

Preparation of the Land and Construction stage

Noise formation shall be in question as a result of operating Heavy Duty Machines to be used Under the scope of the project. As different units shall be at different points and different machines shall be used in the project the noise level estimations were conducted separately as;

a. Regulator Site, Transmission Channel, Penstock Pipe and HEPP Siteb. Transmission Tunnel.

During the performed estimations evaluation realized in accordance with provisions of “Evaluation and Management of Environmental Noise Regulation” that was published in the O.G. No. 26809 dated 07.03.2008.

For the noise to be present at the site, the noise level of possible sources of noise; are determined with assistance of the formulas given according to engine power levels defined at the table of Article 5 of “Regulation Regarding Noise Emission in the Environment Caused by Devices Used at Open Areas” that was prepared by Ministry of Industry and Commerce and entered into force by being published in the Official Gazette No. 26392 dated 30.12.2006. From the machinery – equipment list presented at the table in Article 5; the Equipment Types and the formulas defined according to their engine power are presented in Table 18.

Table 18 Noise Power Levels Defined According to Device Type and Net Sound Level

Device Type Net installed power P(kW), Electric Power Pel (1)(kW), Application mass m(kg), Cutting width L (cm)

Allowed level of noise power dB/1 pWI. Phase since 3 July 2004

II. Phase since 3 January 2006

Pressing machines (vibrating rollers, vibrating plates, vibrating hammers)

P ≤ 8 108 105(2)8 < P ≤ 70 109 106(2)P > 70 89 + 11 log P 86 + 11 log P(2)

Caterpillar bulldozers, track loaders, diggerTrack loaders

P ≤ 55 106 103(2)P > 55 87 + 11 log P 84 + 11 log

P(2)Wheel bulldozers, wheel loaders,Wheel digger-loaders, dumper trucks, graders, loader type soil filling pressers, balance hydraulic lifting trucks with piston engine impulsion, mobile cranes, pressing machines (non-vibrating rollers), walkway glaze machines, hydraulic power forming machines

P ≤ 55 104 101(2)(3)P > 55 85 + 11 log P 82 + 11 log

P(2)(3)

23

Page 31: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Diggers, carriage elevators, construction cranes, engine weeding machines

P ≤ 15 96 93P > 15 83 + 11 log P 80 + 11 log P

Manual concrete crackers and drillers m ≤ 15 107 10515< m < 30 94 + 11 log m 92 + 11 log

m(2)m ≥ 30 96 + 11 log m 94 + 11 log m

Tower cranes 98 + log P 96 + log PWelding and power generators Pel ≤ 2 97 + log Pel 95 + log Pel

2 < Pel ≤ 10 98 + log Pel 96 + log Pel

Pel > 10 97 + log Pel 95 + log Pel

Compressors P ≤ 15 99 97P > 15 97 + 2 log P 95 + 2 log P

Grass cutter machines, garden streamer/grass edge streamer machines

L ≤ 50 96 94(2)50< L ≤ 70 100 9870< L ≤ 120 100 98(2)L > 120 105 103(2)

(1) For welding generators Pel : classic welding flow multiplied with the load tension of minimum value of the factor given by the producer.For power generators Pel : ISO 8528-1: main power according to 1993 standard article 13. 3. 2.

(2) Values belonging to II. Phase are completely examples for the below equipment types:- Walk-back vibrating rollers,- Vibrating plates (> 3 kW)- Vibrating hammers- bulldozers (with steal rail)- loaders (with steal rail > 55 kW)- balance hydraulic trucks operating with piston engine- walkway glaze machines with pressing part- manual concrete crackers and drillers with piston engine (15 < m < 30)- grass cutter machines, garden streamer / grass edge streamer machines. Absolute values shall be bounded to changes to be made by the Commission. In case of that kind of modification is not present the values of I. Phase will continue to be valid for II. Phase.

a. Values regarding mobile cranes with single engine at I. Phase shall be valid until 3rd of January 2008. After this date values of II. Phase shall be valid.

The level of allowed noise power should be rounded to nearest integer (small numbers for the ones smaller than 0,5 big numbers for the ones bigger than and equal to 0,5 are used).

By taking the formulas given in Table 18 into account the level of noise power for the equipment to be used at operation stage are estimated below.

24

Page 32: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 19 Engine Power and Estimated Noise Levels of the Machinery Used at the Project

Unit Engine Power Estimated Noise LevelExcavator 250 HP=187 kW 107 dBADriller 250 HP=187 kW 107 dBATruck 150 HP=112 kW 104 dBATrack loader 156HP= 116 kW 107 dBASprinkler 121 HP = 90 kW 103 dBA*** 1 HP= 0,746 Kw

Estimation of Sound Power Level of the Machinery

Following the formulas given in Table 18 Sound Power Level of each machine is estimated as below.

Excavator:

Engine power of the Excavator to be used at the project area is 250 HP = 187 kW. As the evaluation result for the Excavator given in Table 19 is, P = 187 kW > 15 kW, "80 + 11 logP" formula was used in sound power calculation;

Lw = 82+11 log 187= 107 dBA

Driller:

Engine power of the Driller to be used at the project area is 250 HP = 187 kW. As the evaluation result for the Driller given in Table 19 is, P = 187 kW > 15 kW, "80 + 11 logP" formula was used in sound power calculation;

Lw = 82+11 log 187= 107 dBA

Truck:

Engine power of the truck to be used at the project area is 150 HP = 112 kW. As the evaluation result for the truck given in Table 19 is, P = 112 kW > 55 kW, "Lw= 82 + 11 log P" formula was used in sound power calculation;

Lw = 82+11 log 112= 104 dBA

Track Loader:

Engine power of the Track loader to be used at the project area is 156 HP = 116 kW. As the evaluation result for the Track loader given in Table 19 is, P = 116 kW > 55 kW, "Lw= 84 + 11 log P" formula was used in sound power calculation;

Lw = 84+11 log 116= 107 dBA

Sprinkler:

Engine power of the Sprinkler to be used at the project area is 121 HP = 90 kW. As the

25

Page 33: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

evaluation result for the Sprinkler given in Table 19 is, P = 90 kW > 55 kW, "Lw = 82 + 11 log P" formula was used in sound power calculation;

Lw = 82+11 log 90 = 103 dBA

Average relative humidity to be used in noise estimations for the province of Trabzon is 71,3%. (Province Environment Status Report). Environmental Noise Limit Values for the Construction Site are given in Table 20.

Table 20 Environmental Noise Limit Values for the Construction Site

Activity type (construction, destruction and maintenance) Lmorning (dBA)Building 70Road 75Other sources 70

Atmospheric absorption estimation to be used for determining the level of noise caused by the machines used in the units to be constructed in scope of the project is given in Table 21 and the correction factors necessary for calculation of net sound levels (Lpi) at 4 octave band at distance is given in Table 22.

Table 21 Atmospheric Absorption Estimation

Atmospheric Absorption500 1000 2000 4000

50 0.01 0.05 0.21 0.83100 0.03 0.10 0.42 1.66200 0.08 0.21 0.83 3.32300 0.01 0.31 1.25 4.98400 0.10 0.42 1.66 6.64500 0.13 0.52 2.08 8.30750 0.20 0.78 3.11 12.451000 0.26 1.04 4.15 16.611250 0.32 1.30 5.19 20.761500 0.39 1.56 6.23 24.912000 0.52 2.08 8.30 33.213000 0.78 3.11 12.45 49.82

Table 22 Correction Factors

Correction Factor500 1000 2000 4000

50 -3,20 0,00 1,20 1,00100 -3,20 0,00 1,20 1,00200 -3,20 0,00 1,20 1,00300 -3,20 0,00 1,20 1,00400 -3,20 0,00 1,20 1,00500 -3,20 0,00 1,20 1,00750 -3,20 0,00 1,20 1,001000 -3,20 0,00 1,20 1,00

26

Page 34: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

1250 -3,20 0,00 1,20 1,001500 -3,20 0,00 1,20 1,002000 -3,20 0,00 1,20 1,003000 -3,20 0,00 1,20 1,00

a) Noise estimations caused by the construction machinery for Regulator Site, GRP Pipe, Penstock Pipe and HEPP Site

The list of the machinery to be used in construction works carried out at Horyan Regulator Site, Transmission Channel, Penstock Pipe and HEPP Site are given in Table 19.

Possible noise level caused by the Machinery to be used is given in Table 23.

Table 23 Regulator Site Machinery Sound Power

Source of Noise LegTrack Loader 107,00Truck 104,00Excavator 107,00Sprinkler 103,00

Sound pressure levels at 4 octave band for the machinery to be used at the sites are given in Table 24.

27

Page 35: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 24 Sound Pressure Level at 4 Octave Band for the Machinery to be Used at Horyan Regulator, Transmission Channel, Penstock Pipe and HEPP Site

Source of Noise

Distance(m) Sound Pressure Level (dB) Total Sound Pressure Level500Hz 1000Hz 2000Hz 4000Hz Lpt=Lwt+10(Q / 4 π r2)

Excavator

50 62.03 62.03 62.03 62.03 68.10100 56.01 56.01 56.01 56.01 62.00200 49.99 49.99 49.99 49.99 56.00300 46.47 46.47 46.47 46.47 52.50400 43.97 43.97 43.97 43.97 50.00500 42.03 42.03 42.03 42.03 48.10750 38.51 38.51 38.51 38.51 44.501000 36.01 36.01 36.01 36.01 42.001250 34.07 34.07 34.07 34.07 40.101500 32.49 32.49 32.49 32.49 38.502000 29.99 29.99 29.99 29.99 36.003000 26.47 26.47 26.47 26.47 32.50

Truck

50 59.03 59.03 59.03 59.03 65.10100 53.01 53.01 53.01 53.01 59.00200 46.99 46.99 46.99 46.99 53.00300 43.47 43.47 43.47 43.47 49.50400 40.97 40.97 40.97 40.97 47.00500 39.03 39.03 39.03 39.03 45.10750 35.51 35.51 35.51 35.51 41.501000 33.01 33.01 33.01 33.01 39.001250 31.07 31.07 31.07 31.07 37.101500 29.49 29.49 29.49 29.49 35.502000 26.99 26.99 26.99 26.99 33.003000 23.47 23.47 23.47 23.47 29.50

Track Loader

50 62.03 62.03 62.03 62.03 68.10100 56.01 56.01 56.01 56.01 62.00200 49.99 49.99 49.99 49.99 56.00300 46.47 46.47 46.47 46.47 52.50400 43.97 43.97 43.97 43.97 50.00500 42.03 42.03 42.03 42.03 48.10750 38.51 38.51 38.51 38.51 44.501000 36.01 36.01 36.01 36.01 42.001250 34.07 34.07 34.07 34.07 40.101500 32.49 32.49 32.49 32.49 38.502000 29.99 29.99 29.99 29.99 36.003000 26.47 26.47 26.47 26.47 32.50

Sprinkler

50 58.03 58.03 58.03 58.03 64.10100 52.01 52.01 52.01 52.01 58.00200 45.99 45.99 45.99 45.99 52.00300 42.47 42.47 42.47 42.47 48.50400 39.97 39.97 39.97 39.97 46.00500 38.03 38.03 38.03 38.03 44.10750 34.51 34.51 34.51 34.51 40.501000 32.01 32.01 32.01 32.01 38.001250 30.07 30.07 30.07 30.07 36.101500 28.49 28.49 28.49 28.49 34.502000 25.99 25.99 25.99 25.99 32.003000 22.47 22.47 22.47 22.47 28.50

28

Page 36: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 25 Net Sound Level for 4 Octave Band according to Distance at Horyan Regulator, GRP Pipe, Penstock Pipe and HEPP Site

Source of Noise

Distance(m) Sound Pressure Level (dB) Total Sound Pressure Level500Hz 1000Hz 2000Hz 4000Hz Lpt=Lwt+10(Q / 4 π r2)

Excavator

50 62.02 61.98 61.82 61.20 67.80100 55.98 55.91 55.60 54.35 61.50200 49.91 49.78 49.16 46.67 55.10300 46.46 46.16 45.23 41.49 51.20400 43.87 43.56 42.31 37.33 48.40500 41.90 41.51 39.95 33.73 46.20750 38.32 37.73 35.40 26.06 42.201000 35.75 34.97 31.86 19.40 39.301250 33.75 32.77 28.88 13.31 37.001500 32.10 30.93 26.26 7.58 35.202000 29.47 27.91 21.69 - 32.203000 25.69 23.36 14.02 - 27.90

Truck

50 59.02 58.98 58.82 58.20 64.80100 52.98 52.91 52.60 51.35 58.50200 46.91 46.78 46.16 43.67 52.10300 43.46 43.16 42.23 38.49 48.20400 40.87 40.56 39.31 34.33 45.40500 38.90 38.51 36.95 30.73 43.20750 35.32 34.73 32.40 23.06 39.201000 32.75 31.97 28.86 16.40 36.301250 30.75 29.77 25.88 10.31 34.001500 29.10 27.93 23.26 4.58 32.202000 26.47 24.91 18.69 - 29.203000 22.69 20.36 11.02 - 24.90

Track Loader

50 62.02 61.98 61.82 61.20 67.80100 55.98 55.91 55.60 54.35 61.50200 49.91 49.78 49.16 46.67 55.10300 46.46 46.16 45.23 41.49 51.20400 43.87 43.56 42.31 37.33 48.40500 41.90 41.51 39.95 33.73 46.20750 38.32 37.73 35.40 26.06 42.201000 35.75 34.97 31.86 19.40 39.301250 33.75 32.77 28.88 13.31 37.001500 32.10 30.93 26.26 7.58 35.202000 29.47 27.91 21.69 - 32.203000 25.69 23.36 14.02 - 27.90

Sprinkler

50 58.02 57.98 57.82 57.20 63.80100 51.98 51.91 51.60 50.35 57.50200 45.91 45.78 45.16 42.67 51.10300 42.46 42.16 41.23 37.49 47.20400 39.87 39.56 38.31 33.33 44.40500 37.90 37.51 35.95 29.73 42.20750 34.32 33.73 31.40 22.06 38.201000 31.75 30.97 27.86 15.40 35.301250 29.75 28.77 24.88 9.31 33.001500 28.10 26.93 22.26 3.58 31.202000 25.47 23.91 17.69 - 28.203000 21.69 19.36 10.02 - 23.90

Atmospheric absorption calculations for each octave band according to the distances at the project site are given in Table 21. Reduction of these values at 4 Octave Band Sound Pressure Level for Machinery to be Used is formed in Table 25.

29

Page 37: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 26 Net Sound Pressure Level at Horyan Regulator, Spiral Pipe, GRP Pipe, Penstock Pipe and HEPP Site

Source of Noise

Distance(m) Sound Pressure Level (dB) Total Sound Pressure Level500Hz 1000Hz 2000Hz 4000Hz Lpt=Lwt+10(Q / 4 π r2)

Excavator

50 58.82 61.98 63.02 62.20 67.80100 52.78 55.91 56.80 55.35 61.50200 46.71 49.78 50.36 47.67 54.90300 43.26 46.16 46.43 42.49 50.90400 40.67 43.56 43.51 38.33 48.00500 38.70 41.51 41.15 34.73 45.80750 35.12 37.73 36.60 27.06 41.501000 32.55 34.97 33.06 20.40 38.501250 30.55 32.77 30.08 14.31 36.101500 28.90 30.93 27.46 8.58 34.102000 26.27 27.91 22.89 - 30.903000 22.49 23.36 15.22 - 26.30

Truck

50 55.82 58.98 60.02 59.20 64.80100 49.78 52.91 53.80 52.35 58.50200 43.71 46.78 47.36 44.67 51.90300 40.26 43.16 43.43 39.49 47.90400 37.67 40.56 40.51 35.33 45.00500 35.70 38.51 38.15 31.73 42.80750 32.12 34.73 33.60 24.06 38.501000 29.55 31.97 30.06 17.40 35.501250 27.55 29.77 27.08 11.31 33.101500 25.90 27.93 24.46 5.58 31.102000 23.27 24.91 19.89 - 27.903000 19.49 20.36 12.22 - 23.30

Track Loader

50 58.82 61.98 63.02 62.20 67.80100 59.18 55.91 54.40 53.35 62.30200 53.11 49.78 47.96 45.67 56.00300 49.66 46.16 44.03 40.49 52.30400 47.07 43.56 41.11 36.33 49.60500 45.10 41.51 38.75 32.73 47.50750 41.52 37.73 34.20 25.06 43.601000 38.95 34.97 30.66 18.40 40.901250 36.95 32.77 27.68 12.31 38.701500 35.30 30.93 25.06 6.58 36.902000 32.67 27.91 20.49 - 34.103000 28.89 23.36 12.82 - 30.00

Sprinkler

50 54.82 57.98 59.02 58.20 63.80100 48.78 51.91 52.80 51.35 57.50200 42.71 45.78 46.36 43.67 50.90300 39.26 42.16 42.43 38.49 46.90400 36.67 39.56 39.51 34.33 44.00500 34.70 37.51 37.15 30.73 41.80750 31.12 33.73 32.60 23.06 37.501000 28.55 30.97 29.06 16.40 34.501250 26.55 28.77 26.08 10.31 32.101500 24.90 26.93 23.46 4.58 30.102000 22.27 23.91 18.89 - 26.903000 18.49 19.36 11.22 - 22.30

Net sound levels of all equipments at specified distances in 4 octave band (Lpi) are arranged under Table 26 according arrangement factors given in Table 22.

30

Page 38: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Table 27 Total Sound Level of all Sources of Noise at Horyan Regulator, Transmission Channel, Penstock Pipe and HEPP Site construction according the distance at 4 octave band

Distance (m) Ldaytime (dBA) Limit value at the Regulation50 72.40

Article 23; (70 dBA)

100 66.40200 59.90300 56.10400 53.20500 51.10750 47.001000 44.10

When Table 27, which was obtained by performing the necessary estimations is evaluated, the total sound level according to distance caused by the machinery used at the sites drops down the allowed value after 50 meters.

The closest settlement areas to Regulator site are Aşıklı Town approximately 800 m far away and Çapanlı (Yeniköy) village approximately 820 m far away. Nearest house is 100 m away from the area. The total sound level according to distance caused by the machinery to be used at the site drops below the allowed level after 50 meters. For this reason, it is foreseen that the noise level caused by the machinery at the site will not affect the nearest settlement areas and connected houses in a bad way.

In scope of Horyan Regulator and HEPP Project, the route that the GRP Pipe shall be installed is at 3 km. part of Yeşilyurt City road, at the cutting bevel side. Approximately 1000 m part of the GRP Pipe will pass through Yoncalı Village. There are structures like house, mosque, graveyard, well etc. on the village road. GRP pipe construction of in total 4.428,18 m length is planned to be finished in 6 months. The works on the village road is foreseen to be finished approximately in 2-3 months. For this reason, it is predicted that the bad effects of the noise caused by the operating construction machinery on local citizens shall be short term. Also, the noise level in reality is foreseen to be very lower than the estimated value as the estimations were conducted as the worst case scenario that all the machines are working together at the same time. All necessary measures shall be taken in order to provide the local citizens not to be affected by the noise during the works to be performed at the village road and prevent the accidents to be occurred at the working area and the construction works are planned to be finished within the shortest period.

Closest settlement area to the Penstock Pipe construction site is 420 m far Yoncalı Village. The nearest home is 95 m away from the area. It is predicted that the machinery to be operating at the construction works will not have any negative effects on the nearest settlement areas.

Closest settlement area to the HEPP site construction area is 660 m far Yoncalı Village. The nearest home is 125 m away from the area. It is predicted that the machinery to be operating at the construction works will not have any negative effects on the nearest settlement areas.

It is predicted that the real noise level shall be lower than the estimated value as we consider that the estimations are performed as the worst case scenario that all the machinery is operating at the same time and the project construction shall be improving continuously.

Provisions of “Evaluation and Management of Environmental Noise Regulation” that entered

31

Page 39: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

into force by being published in the O.G. No. 26809 dated 07.03.2008 shall be complied with strictly.

The measures to be taken against the noise to be present are stated at Section 1.d.

b)Estimation of Noise Level Caused by the Machinery to be used at Construction of Transmission Tunnel

The list of the machinery and the noise level of these machines that shall be used at construction of Transmission Tunnel are given in Table 19. This data was estimated in accordance with “Evaluation and Management of Environmental Noise Regulation” that entered into force by being published in the O.G. No. 26809 dated 07.03.2008. Noise estimations to be caused by the machinery to be used at the other sites and the noise estimation method of the machinery to be used at Transmission Tunnel construction site are the same and the estimations were repeated.

The total sound level of all sources of noise at the construction of the Transmission Channel according to distance at 4 octave band are given in Table 28.

Table 28 The Total Sound Level of all Sources of Noise at the Construction of the Transmission Channel According to Distance at 4 Octave Band

Distance (m) Ldaytime (dBA) Limit value at the Regulation50 72,40

Article 23; (70 dBA)

100 66,40200 59,90300 56,00400 53,10500 50,90750 46,901000 44,00

When Table 28, which was obtained by performing the necessary estimations is evaluated, the total sound level according to distance caused by the machinery used at construction of Transmission Tunnel drops down the allowed value after 50 meters. Yoncalı Village is the nearest settlement area to the Transmission Tunnel construction area that is planned to be conducted in scope of the project. The nearest home to the tunnel inlet is 40 m far away.

In order not to affect the houses close to tunnel area from the explosion works, the amount of explosives to be placed in each hole shall be reduced. These amounts shall be determined at decisive project phase. The explosions to be performed inside the tunnel are foreseen not to affect the close houses.

Also, it is predicted that the real noise level shall be lower than the estimated value as we consider that the estimations are performed as the worst case scenario that all the machinery is operating at the same time and the Transmission Tunnel construction works shall be performed underground. It is predicted that the machinery to be used at the construction works will not affect the closest settlement areas negatively.

The measures to be taken against the present noise are stated at Section 1.d.

1.d. The Accident risk to be Caused by the Technology and Materials to be Used

32

Page 40: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

During the construction of the units to be carried out in scope of the project, the mobile vehicles will pose danger. For this reason, necessary studies and organizations about work safety and health shall be carried out during the construction.

All kind of environmental measure shall be taken and necessary warning signs shall be placed within the construction site. The personnel shall be trained about work safety and health rules and shall be enable to prevent work accidents. Adequate illumination shall be provided at the construction site and working areas.

At Transmission Tunnel to be established within the scope of the project drilling and explosion method shall be used. For these explosions ANFO shall be used as explosive. The explosives shall be provided from military organizations on daily basis and they won’t be stored. Subjects of utilization, protection, transportation of the explosive material shall be carried out according to the legislation with decision No. 87/12028 published in the Official Gazette No. 19589 dated 29 September 1987 on “Procedure and essence of production, import, carriage, preservation, storage, sale, utilization, destruction, audition of unmonopolized explosives and hunting material and similar”.

Electrical system of the facility shall be controlled via residual current device at the Main Control Center and in case of a small electric leakage the power shall be cut off within whole system. Rubber protectors shall be placed at the sections where workers are working and where A.G. screens are placed.

Maintenance and repair works shall be carried out for efficient operation and safety of all machinery within the facility. Maintenance and repair processes will not affect or harm the existing infrastructure facilities.

1.e. Measures to be Taken Against Possible Environmental Effects of the Project

Solid Wastes

Land Preparation and Construction stage:

Domestic Solid Wastes:

Amount of domestic solid wastes caused by the workers working at the construction stage was calculated as 26,8 kg/day at Section 1.c. Needs of the workers working inn frame of Horyan Regulator and HEPP projects shall be met at the construction site building. Domestic solid wastes produced here shall be collected inside closed vessels at the construction site and regularly transferred to Araklı Municipality waste collection site with closed special vehicles. Removal of the package wastes included in the domestic wastes shall be carried out separately in accordance with the provisions “Control of Package Wastes Regulation” published in the O.G. No. 26562 dated 24.06.2007 and “Modification Making Regulation on Control of Package Wastes Regulation” published in the O.G. No. 27046 dated 06.11.2008.

Collection, piling and transfer of the solid wastes shall be in accordance with Solid Waste Control Regulation No. 20814 dated 14.3.1991 and its modification published in the Official Gazette No. 25777 dated 05.04.2005.

Earthmoving Wastes

33

Page 41: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Amount of botanic soil and earthmoving waste material formed in result of excavation works to be carried out in scope of the project at Horyan Regulator, GRP Pipe, Transmission Tunnel, Penstock Pipe and HEPP are given at Section 1.c.

Earthmoving waste material to be formed, will not be sacked to the area outside the construction site randomly but shall be stored at the tallow piling sites temporarily. Some part of this material shall be used as filling material in rehabilitation of the construction and service roads and some part shall be used as wall filling material.

For removal of the earthmovings performed in scope of the project the provisions of Earthmoving Soil, Construction and Debris Waste Control Regulation that entered into force by being published in the O.G. No. 25406 dated 18.03.2004 shall be complied with.

Solid Wastes Caused by the Construction

Besides this, during the construction works formation of die block timber waste, construction iron, iron pipe, concrete and injection waste materials etc. shall be in question. Formed die block timber wastes shall be collected in certain intervals and in case of demand shall be given to the villagers living adjacent for warming. Concrete iron, iron pipe etc. again shall be collected in certain intervals and shall be utilized by giving to scrap dealers. Concrete and injection waste material shall be used as filling material.

By taking the necessary measures, the solid wastes produced during the construction works will not affect the environment negatively.

Operation stage

The amount of domestic solid wastes caused by the personnel working during the operation stage are estimated at Section 1.c as 6,7 kg/day. The solid wastes to be produced shall be removed by transferring Araklı Municipality trash collection area.

Collection, piling and transfer of the solid wastes shall be in accordance with Solid Waste Control Regulation No. 20814 dated 14.3.1991 and its modification published in the Official Gazette No. 25777 dated 05.04.2005.

By taking the necessary measures, the solid wastes produced during the management works will not affect the environment negatively.

Hazardous Wastes

Management of the waste oils and fuels from the machinery shall be provided by reducing their negative effects to the human health and environment to minimum according to provisions of Hazardous Materials Control Regulation that was published in the O.G. No. 25755 dated 27.08.2005 and “Waste Oil Control Regulation” which entered into force by being published in the O.G. No. 26952 dated 30.07.2008. Especially for transport, collection and removal of waste oils to be produced by performance of the machinery during the construction stage provisions stated at “Waste Oil Control Regulation” Article 9 (Liabilities of Waste Oil Producer) shall be complied with and removal of the waste oils to be produced shall be provided accordingly. In this direction during the activity, according to provisions of the regulation, necessary measures shall be taken in a way to minimize the amount of waste oils in question, categories of the waste oils shall be determined according analysis conducted regarding the parameters given in Annex 1 of the same regulation,

34

Page 42: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

produced waste oils shall be provided to be transported via licensed firms and shall be given to licensed removal facilities.

Hazardous wastes such as used rubber, accumulator, battery, cable and oil binding filter etc. to be produced as waste during the construction of the project shall be stored at the facilities temporarily and shall be sent to the nearest licensed hazardous waste recycling facility or to a licensed hazardous waste disposal facility according to essences stated at “Hazardous Wastes Control Regulation” that entered into force by being published in the Official Gazette No. 25755 dated 27.08.2005. Licensed vehicles shall be used for transportation. During the activity the provisions of “Waste Accumulator and Battery Control Regulation” that was published in the O.G. No. 25569 dated 31/08/2004 shall be complied with.

Waste Water

Land Preparation and Construction stage

Daily needs of the 20 person to be working in scope of the project shall be met at the construction site building. The amount of domestic waste water caused by the daily needs of the 35 person working during land preparation and construction stage is estimated as 3 m3/day at Section 1.c. The domestic waste water to be produced shall be collected at leak-proof cesspool constructed according to provisions of “Regulation Regarding the Cesspools at the Places that Sewage Channel is Impossible to Establish” that was published by Ministry of Health in 1971. The waters collected at the cesspool, shall be taken by municipality’s sewage truck via conducting a protocol between Araklı Municipality and activity owner.

For removal of the domestic wastewater to be produced during land preparation phase the provisions of “Water Pollution Control Regulation” published in the O.G. No. 25687 dated 31.12.2004 and its modification published in the O.G. No. 26786 dated 13.02.2008 shall be complied with. By taking the necessary measures the waste waters to be produced during the construction works are foreseen to be harmless to the environment.

Operation stage

During the operation stage 5 personnel shall be working and the amount of domestic waste water caused by the daily needs of the workers is estimated as 750 m3/day at Section 1.3. The domestic waste water to be produced shall be collected at leak-proof cesspool constructed according to provisions of “Regulation Regarding the Cesspools at the Places that Sewage Channel is Impossible to Establish” that was published by Ministry of Health in 1971. The waters collected at the cesspool shall be taken by municipality’s sewage truck, via conducting a protocol between Araklı Municipality and activity owner.

For removal of the domestic wastewater to be produced during operation stage, the provisions of “Water Pollution Control Regulation” published in the O.G. No. 25687 dated 31.12.2004 and its modification published in the O.G. No. 26786 dated 13.02.2008 shall be complied with. By taking the necessary measures the waste waters to be produced during the construction works are foreseen to be harmless to the environment.

Emission

Land Preparation and Construction stage

35

Page 43: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Type and amount of the emission to be produced by the diesel burning by the vehicles to be working during the land preparation and construction stage are estimated at Section 1.c for all units.

When this values estimated for Horyan Regulator Site are compared with “Molar Values” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, it is observed that none of the emission values exceed the threshold value stated at the regulation. For this reason, the project is foreseen to be harmless to the environment.

All conducted estimations are performed as if all machinery is working in 1 hour. However, this is a very low possibility. Also the construction stage is predicted to last 42 months, so the estimated emissions will take place during this period and there shall be no problems after the construction is completed.

Exhaust measuring of the Heavy Duty Machines and trucks shall be performed regularly and the limit exhaust values will not be exceeded.

During the activity in question the provisions of “Controlling the Air Pollution caused by Industrial Facilities Regulation” that was published in the O.G. No. 26236 dated 22.07.2006 shall be complied with.

Operation stage

For accommodation of the personnel that shall be working at the operation stage the social facilities shall be utilized. Electric power is used for warming purposes at this place, fuel use or emission production is out of subject. There shall be no emission during the operation stage.

Dust Formation

Land Preparation and Construction stage

Dust emissions and their mass flows to be formed by the performed works during land preparation and construction stage are estimated at Section 1.c.

When the dust flow to be occurred at Horyan Regulator site is compared with “Molar Flows” according to “Controlling the Air Pollution caused by Industrial Facilities Regulation” given in Table 2.1, the values that estimated for construction stage are detected to be below the limit value (> 1,5 kg/hour). The dust formation to be occurred during land preparation and construction works is foreseen not to affect the close settlement areas for reasons such as the Horyan HEPP site is quite rough, the settlement units are very far from the work area and various measures shall be taken against dust formation at all work areas.

In all works to be performed in scope of the projects, in order to minimize the dust to be present the below measures shall be taken.

The material at the trucks shall be covered with canvas during transportation. Attention shall be paid to load and unload without winnowing. There shall be speed limits for the vehicles working at the site. Spraying work shall be conducted at working sites and service roads.

For workers health the provisions stated at T.R. Ministry of Labor and Social Security, Occupational Health and Safety Legislation shall be complied with.

36

Page 44: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Operation stage

There is no possibility of dust emission during Horyan HEPP project operation stage.

Noise

Land Preparation and Construction stage

The noise level to be formed is estimated at Section 1.c.

The estimations in question are preformed as if all sources of noise are working at the same time at the same place. However, it is a quite low possibility that all of them are working at the same during the same working hours continuously. Also; various effects such as the noise is not continuous but in certain time intervals and variable, the area is rough and surrounded by woodland are expected to reduce the received noise level by the inhabitants.

In order to protect the health of the workers at the noise exposure areas and keep the continuity of the activity adequate protective tools and equipment such as helmets, earpieces and ear taps shall be provided. During the management the workers are planned to be working for 8 hours in compliance with occupational health rules. Also, Heavy and Dangerous Works Legislation Article 2 shall be complied with.

During the operation activity provisions of Environmental Noise Evaluation and Management Regulation that was published in the Official Gazette No. 26939 dated 17.07.2008 and T.R. Ministry of Health and Social Assistance, Occupational Health Legislation shall be complied with.

Operation stage

After the facility passes to operation stage, movement of the turbine shaft around its axis at the power plant building will produce noise. However, as all kinds of insulation shall be established within the building, there is no noise in question that is caused by the power plant building and received by sensitive receiver. The nearest house to the power plant building is at 250 m distance.

Transmission Tunnel Explosion Technique and Details

For 1013 m tunnel within the scope of the project approximately 7.160 m3 tunnel excavation shall be carried out. 300 cm tunnel excavation shall be performed with a single explosion and the progress shall be made by daily explosions. For tunnel explosion 1.8 kg explosive material is planned to be used for 1 m3 tunnel excavation. In this case 26 m3 excavation material shall be provided for 300 cm tunnel digging. For 26 m3 tunnel digging 46,8 kg explosive material shall be used. In tunnel explosion in one shot 40 holes shall be opened and 1,80 kg dynamite, 1 capsule shall be used for each hole. In this case, in total for 7.160 m3 tunnel digging approximately 12.888 kg dynamite shall be used.

Except environmental problems such as vibration and dust caused by the explosions performed underground it will not affect the environment. Nevertheless, environmental problems may be caused by the explosion to be carried out at entrance and exit of the tunnel, but as both ends of the tunnel is far away from settlement areas and the amount of explosive material to be used is small, it is foreseen that no negative effects to the environment shall be made. No explosion shall be carried out for Transmission Channel construction.

37

Page 45: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Necessary permits for carriage and usage of explosive materials shall be obtained from Trabzon governorship. The explosive material will not be stored at the site and if considered necessary shall be transferred to project site.

Explosive materials shall be stored in wooden boxes according to related regulations, far away from construction site and settlement units. Dynamite and capsules shall be kept in separate places, the preservation of the area shall be provided with wire fences and warning and caution signs. For explosion works trained and experienced stoker shall be hired.

In order to transfer and use the flammable and explosive material (dynamite, capsule, gas, fuel oil etc.) safely the essences of “Code on the Measures to be Taken at Work Places and Works Working with Explosive, Flammable, Dangerous and Hazardous Material” published in the Official Gazette No. 14752 dated 24.12.1973 and “Code on Procedures and Principles of production, import, carriage, preservation, storage, sale, utilization, destruction, audition of unmonopolize explosives and hunting material and similar” published in the Official Gazette No. 19589 dated 29.09.1987 shall be complied with.

38

Page 46: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

2. PROJECT PLACE

Horyan Regulator and HEPP Energy Project that are subjects to the Project, located over the Horyan Creek and Kara Creek within the borders of province of Trabzon, Araklı district. Project area Site Location Map is given in Annex-1, and 1/25.000 Scaled General Settlement Plan is given in Annex-2. The project in question is located at Trabzon G44-a4 section. There are no other facilities in the basin where Horyan Regulator and HEPP project is located. The purpose of the project is only producing electrical power and it does not have any other goals such as irrigation and overflow control. The Satellite Image and photos belonging to the project area are given in Annex-9.

2.a. Utilization and Quality of the Existing Area (Agricultural Area, Forest Area, Planned Area, Water Surface etc.)

The facilities within the scope of the project and the areas to be covered by these facilities are given in Table 1. According to this, approximately 74.520 m2 area shall be utilized in scope of the project. Site Construction Plan shall be realized after EIA study.

Within the are that the Horyan HEPP project shall be framed there treasury, private property and forestry lands. Necessary permits for the total area of 22.102 m2 that the Penstock Pipe, GRP Pipe Route, Regulator and Sedimentation tank shall be located has been obtained from the Ministry of Environment and Forestry, General Directorate of Forestry and related documents and Area Delivery Receipt Report are given in Annex-4. Before the project in question begins to its activities, plans and reports of confiscation shall be prepared. In result of the studies to be carried out, for the areas that the Horyan Regulator and HEPP facilities are foreseen to be constructed;

In case of forest area: At the Code Regarding Modification of Forestry Code that entered into force by being published in the Official Gazette No. 25511 dated 03/07/2004 for facilities at the forest area the following statement is present; “In case of placing or establishing defense, transportation, energy, communication, water, waste water, petrol, natural gas, infrastructure and solid waste removal facilities; sanatorium, Regulator, lagoon and graveyards; health, education and sports facilities belonging to the State and all kinds of places and buildings related to those are at State forests cause public benefit or damage, by its cost against private and legal persons, the permit may be given by Ministry of Environment and Forestry”. In this scope, the necessary permits regarding forest areas shall be obtained from Regional Directorate of Forestry.

In case of agriculture and pasture area: In result of the investigation carried out by Trabzon Governorship Province Agricultural Directorate authorized persons at the project site, it has been detected that sown agriculture, tea and hazelnut agriculture is performed at the lands out of forest areas. As stated at the 13.07.2009 dated opinion letter No. 4038 of Provincial Agriculture Directorate, the necessary permits shall be obtained under the scope of Land Protection and Land Utilization Act No. 5403 and Pastures Act No. 4342 (see Annex-4)

For treasury areas: “Electricity Market Act” No. 4628 dated 03/03/2001 Article 15 Clause d) has been modified by Act No. 5496 dated 24/05/2006 as; "License owning private law legal persons that perform production or distribution activities in the market, regarding their activities may demand constitution of servitude, utilization permit or lease land from the Institution on estates at possession of the Treasury or under judgment or disposal of the State. In case of this demand is approved by the Institution, in accordance with the related legislation, constitution of servitude, utilization permit or lease land agreement is arranged between Finance Ministry and license owning

39

Page 47: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

private law legal persons limited with the time of license.

These agreements include a provision stating that validity of the agreement shall be limited with the validity period of the license. Liability of paying the cost of constitution of servitude, utilization permit or lease land that is obtained in this manner, belongs to the license owning private law legal person". According to this there are no legal obstacles for disposition of estates belonging to the treasury.

For expropriations: In scope of expropriation studies primarily mutual agreement is attempted with private property owners. Under the scope of expropriation studies, in case of conflicts Expropriation Act that entered into force by being published in the Official Gazette No. 24393 dated 05.05.2001 shall be applied.

According to Article 15/c (Modified: 5496 SK. 5. Art.) of Electricity Market Act No. 4628; expropriation studies shall be executed by EPDK, the expropriation decision made on this subject will replace public benefit decision and condemned estates shall be recorded to land register on behalf of the treasury.

Council of Minister Decision regarding application Expropriation Act No. 2942 Article 27 for expropriations to be carried out by Energy Market Regulatory Authority has been provided in the Official Gazette No. 25599 dated 30.09.2004.

At the Article 47 of the National Defense Obligation Act No. 3634 the following statement is present; "In expropriation of the necessary estates in cases that national defense need or precipitancy is decided by Council of Ministers or in emergency situations foreseen at private laws, as the out of esteem appraisal processes impending to be completed afterwards, the estate in question may be seized by the value of that estate to be determined by the consultants to be selected by the court according to essences of Article 10 department and Article 15 within seven days upon request of the related administration, is transferred by the administration to the bank specified at the invitation and statement made according to Article 10 on behalf of the property owner. The amount to be transferred for expropriation to be made in accordance with the situations stated at Article 3, Clause 2 of this code, is the first installment payment”. For this reason, firstly valuation shall be conducted by consultants in place and the determined value shall be transferred to the related bank by activity owner and shall be paid to the right owners via Governorship. After completion of this payment process the construction shall start. Afterwards the right owners shall be asked whether they want settling once again by the Governorship, the ones want settling again will repay the expropriation cost that was paid to them and may demand settling.

Geological data related to project area and 1/25000 Scaled Geology Map are given in Annex-10. During the works to be performed at the route of the project no geological negations (slipping, leaking etc.) shall be caused. However, below is the measures to be taken against natural disasters may occur due to construction activities.

Erosion

Water erosion that its damage reach to large amounts especially in our country, is the most important one among erosion types. The soil worn out in result of erosion is moved to the rivers. Because of the severe erosions, the utilization period of energy producing reservoirs is very short.

Measures to be taken in order to prevent water erosion and ensure that the Project is long lasting are given below.

40

Page 48: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

1) Administrative Measures

Administrative measures according to Act on the Organization and Duties of T.R. Ministry of Environment and Forestry No. 4856 Article 11 shall be attempted to be taken.

2) Cultural Measures

They are applications aiming to prevent erosion by establishing plant cover or improving the existing plant cover. Some of the measures to be taken are; forestation, plant cover improving, grass planting, plantation of plants suitable for the region at river beds that do not contain sediments.

3) Mechanical Measures

a) Measures to be taken at ramps (Terracing, diversion ditch, netting, fence etc.)b) Measures to be taken against gully erosion (Soil levee, drywall sill, mix sill, precipitation

Regulator, cost walls, rock-fill etc.)

Landslides

In result of the geological researches performed in scope the feasibility studies there is no landslip risk encountered in the project area.

2.b. By taking the Invulnerable Regions list given in Annex-V into consideration; wetlands, coastal areas, mountainous and forest areas, agriculture areas, national parks, special protection areas, intense population areas, historical, cultural, archeological and similar importance areas, erosion areas, landslip areas, forested areas, potential erosion and forestation areas and aquifers required to be protected according to Act on protection of underground waters No. 167

Vulnerable regions determined in scope of EIA regulation Annex-V are as below:

1. Areas needed to be protected according the legislation in our Country

a) There are no “National Parks”, “Natural Parks”, “Natural Monuments” and “Natural Protection Areas” that are defined in Article 2 of the National Parks Act No. 2873 dated 9/8/1983 and determined according to Article 3 of this act.

b) There are no “Protecting Wild Life Sites and Wild Animal Placement Areas” determined by Ministry of Environment and Forestry present according to Territorial Hunting Act No. 4915 dated 1/7/2003.

c) There are no areas which are determined as “Cultural Property”, “Natural Property”, “Archeological Areas” and “Protected Areas” in the Act on Protecting Cultural and Natural Properties No. 2863 dated 21/7/1983 Article 3, first clause “Definitions” titled paragraph (a), sub-paragraphs 1, 2, 3, 4 and 5 and detected and designated in accordance with the same act and the related articles of Act dated 17/6/1987 (Act on Modification of Some Articles of Act on Protecting Cultural and Natural Properties, and Adding Some Articles to This Act No. 2863).

d) There are no Fisheries Production and Growing Sites in scope of Fisheries Act No.1380 dated 22/3/1971.

e) There are no areas as defined at Articles 17. 18. 19 and 20 of Water Pollution Control Regulation published in the Official Gazette No. 25687 dated 31/12/2004.

f) “Vulnerable Pollution Areas” defined at Article 49 of Protecting Air Quality Regulation published in the Official Gazette No. 19269 dated 2/11/1986,

41

Page 49: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

g) There are no areas designated and stated by the Council of Ministers as “Special Environment Protection Areas” in accordance with Article 9 of Environmental Act No.2872 dated 9/8/1983.

h) There are no areas under protection according to Bosphorus Act No.2960 dated 18/11/1983.

i) There are areas defined as forestry areas according to Forestry Act No.6831 dated 31/8/1956, and necessary permits for consecration of the areas have been obtained (see. Section 1.b).

j) There are no areas with construction prohibition according to Coast Act No. 3621 dated 4/4/1990.

k) There are no areas as stated in the Act on Olive Production Improvement and Grafting Wild Olives No. 3573 dated 26/1/1939.

l) There are no areas as stated in Meadows Act No. 4342 dated 25/2/1998.m) There are no areas as stated in Regulation on Protection of Wetlands which entered into

force by being published in the Official Gazette No. 25818 dated 17/5/2005.

2. Areas needed to be protected according to international agreements that our Country is a party

a) There are no I. and II. Protection Areas stated at “Important Sea Turtle Breeding Areas”, “Mediterranean Seal Habitat and Breeding Areas” under protection according to “Agreement of Protecting Wild Life and Habitats in Europe” which entered into force by being published in the Official Gazette No. 18318 dated 20/2/1984.

b) There are no areas under protection according to “Protecting Mediterranean against Pollution Agreement” (Barcelona Agreement) that was published in the Official Gazette No. 17368 dated 12/6/1981.

i. There are no areas designated as “Special Protection Area” in our country in accordance with “Protocol On Protection of Special Protection Areas in Mediterranean” published at Official Gazette No. 19968 dated 23/10/1988.

ii. There are no areas included in the list of “100 Coastal Historical Archeological Area with Common Importance in Mediterranean” published by the United Nations Environmental Program selected in accordance with Geneva Declaration dated 13/9/1985.

iii. There are no coastal areas that is life and feeding habitat of “Mediterranean Endangered Sea Creatures” placed in Article 17 of the Geneva Declaration.

c) There are no cultural, historical and natural areas given status of “Cultural Heritage” and “Natural Heritage” that are under protection of Ministry of Culture according to 1st and 2nd Articles of “Agreement of Protecting World’s Cultural and Natural Heritage” which entered into force by being published in the Official Gazette No. 17959 dated 14/2/1983.

d) There are no areas under protection in accordance with “Protecting Wetlands with International Importance, Especially Water Birds Habitats Agreement” (RAMSAR Agreement) that entered into force by being published in the Official Gazette No. 21937 dated 17/5/1994.

e) European Landscape Agreement that entered into force by being published in the Official Gazette No. 25181 dated 27/7/2003 is not present.

3. Areas need to be protected

a) There are no areas that designated as their existing features should be protected and areas with construction prohibition (areas that their natural characteristics should be protected, biogenetic reserve areas, geothermal areas and similar), at Approved Environmental Landscape Plans.

b) Agricultural Areas: Agricultural developing areas, irrigated, irrigation possibility possessing and land utilization capability class I, II, III and IV areas, I and II class of precipitate

42

Page 50: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

depended agriculture and special harvest plantation areas are completely not present.c) Wetlands: The project shall be constructed on Horyan and Kara Creeks.d) ç) There are no lakes and underground water process sites. The project shall be

constructed on Horyan and Kara Creeks.e) There are no areas important for scientific research and/or habitat areas of endangered or

in danger of to be endangered species, biosphere reserve, biotopes, biogenetic reserve areas, areas with geological and geomorphologic formations.

Flora and Fauna

Flora and fauna studies belonging to activity area have been carried out; the tables containing the list of the species that are possible to encounter at the activity area and nearby area are given in Annex-11.

The activity area is placed at A7 square according to Grid Quadrature System, at North Anatolia Region. While forming the flora side of the report in identification of the plant species collected from the area Davis’s "Flora of Turkey and East Aegean Islands" titled work has been utilized, in order to keep the flora list complete and intact literature study has been conducted from the same work, the species has been confirmed from Turkish Plants Data Service prepared by TÜBİTAK (Turkish Scientific and Technical Researches Institution). Also, the data collected during preparation of various project previously at this region has been evaluated during preparation of flora and fauna part of this project.

When the area is analyzed phytosociologically the research shows that it is under effect of Europe – Siberia Phytogeographical Region. Vegetation forms of Black Sea Phytogeographical Region are shown at Figure 1.

At the flora table, endemic situation of species, danger classes, which endemic phytogeographical region element they are at project and affection are shown. Turkish versions of the plants are given by using ‘Turkish Plant Names Dictionary’ (Baytop,1994).

43

Page 51: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Expl

anat

ion:

1-B

road

-leav

ed d

ecid

uous

fore

sts

[Fag

us o

nent

atis

. Qtte

rcus

. Ain

us, T

Uia

. Cas

iane

a), 2

- - P

icea

ane

ntat

is fa

resL

s. 3

- -

Con

ifero

us f

ores

ts [

Ptnu

s ni

gra.

Abi

es a

nd P

imıs

syl

vest

nsì,

4-

Dry

mix

ed f

ores

ts 5

- D

ry f

ores

t {P

trnıs

bru

tia a

nd Q

uerc

us),

6-

Med

iterr

anea

n sh

rub

(maq

uis)

and

Pvm

s bur

iia fo

rest

, 7-.A

ntro

poge

nie

step

pe. 8

- Alp

ine

gras

s

Figure 1 Vegetation Formations of Black Sea Phytogeographic Region

44

Page 52: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Names, habitats and endanger status of the species that are possible to encounter at the work area are specified at the below flora list. Abbreviations and scales used at the flora list are given below.

Phytogeographic Region

Med; Mediterranean Flora ElementE.Med; East Mediterranean Flora ElementEur-Sib; Europe-Siberia Flora ElementIr-Tur; Iran-Turan Flora ElementW; WestE; EastN; NorthS; SouthWide; Shows broad distribution at the region End; Endemic

Rare and endemic species present at the work area are classified according to risk categories determined by IUCN. For endemic and rare plant species 1994 IUCN Red Data Book categories used at "Türkiye Bitkileri Kırmızı Kitabı" titled publication prepared by Ekim, T. and friends (2000) are explained below.

EX - Extinct : If there is no doubt the last unit is extinct, taxonomy is placed in this category. Some taxonomies that they are said to be present in Turkish Flora, but could not be found in spite of special searches are placed in this category.

EW - Extinct in the Wild: If the taxonomy could not be found in spite of searches carried out in areas that it may be present, so it is lost and keep living alone in a isolated culture it is placed in this group.

CR - Critically Endangered: If a taxonomy is in risk of being extinct in very near future it is placed under this group. In the floristic studies carried out, plant taxonomies that their future populations were thought to be harmed are placed in this category.

EN - Endangered: If a taxonomy is under very high risk and in danger of to be extinct in near future, but not in CR group it is placed in this category.

VU - Vulnerable: While they are not placed under CR and EN groups, taxonomies that are in high danger in the nature for intermediate term future are placed under this group.

LR - Lower Risk: Plants that are not placed in higher level danger groups, having better populations comparing to them are placed in this category. Ones with quite good populations and known at least in 5 locality are placed in this category. There are 3 sub-categories to be listed according to threat in future situation:

a- (cd) - Conservation Dependent: Taxonomies to be categorized under one of the groups in 5 years. The ones that require a special protection status both from angle of type and habitat.

b- (nt) - Near Threatened: Ones that are not placed in the previous group but close to be placed under VU category. May be under threat.

45

Page 53: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

c- (lc) - Least Concern: Ones that does not require any protection and is not under any threat.

DD - Data Deficient : If data regarding distribution and amplitude of a taxonomy is not adequate the taxonomy is placed under this group. Even if biology of a taxonomy under this group is well known, data concerning its distribution and amplitude is incomplete.

NE - Not Evaluated -: Taxonomies that could not be evaluated with any of the above criteria is placed under this group.

The studies on the Turkish fauna are mostly about taxonomy and fauna studies performed on the basis of region and basin are very low. In this regard, there are no fauna studies conducted previously for the project site and neighboring area.

Fauna types show seasonal differences and as determining fauna inventory of an area may last a couple of years, the species given at fauna lists were prepared by; besides field surveys, take observations and hearings of the local people, biotope properties of the region, present distribution areas and existing biogeography rules into consideration. Fauna lists, include the species that are put forth via literature researches carried out for their existence in the environment but were not seen during the field survey.

Although there is no important living habitat on the project area, in the studies conducted by taking the near area into consideration the fauna species at the region were investigated under three titles as Reptiles, Birds and Mammals. Species living or have the possibility of living at the project site and neighboring area are shown in a table in Annex-11.

For the species placed at the protection lists belonging to 2008-2009 Hunting Period that were prepared according to decisions of T.R. Ministry of Environment and Forestry Nature Protection and National Parks General Directorate Central Hunting Commission, activities shall be carried out in accordance with protection measures stated at this commission decisions.

Wild animals included in Annex-I List are put under protection with 2008-2009 Hunting Period Central Hunting Commission Decision of Ministry of Environment and Forestry Nature Protection and National Parks General Directorate.

Hunting animals included in Annex-II List are put under protection with 2008-2009 Hunting Period Central Hunting Commission Decision of Ministry of Environment and Forestry Nature Protection and National Parks General Directorate.

Hunting animals included in Annex-III List are species that are allowed to be hunted in certain periods according to 2008-2009 Hunting Period Central Hunting Commission Decision of Ministry of Environment and Forestry Nature Protection and National Parks General Directorate.

Fauna species are put under protection in two sections according to Bern Agreement. Those are:

II- Fauna species certainly put under protection

a) All kinds of catching, capturing and killing on purpose,b) Damaging and harming breeding and recess areas on purpose,c) Disturbing the wild fauna especially in breeding, growing and winter sleep periods on

purpose, against the purpose of this agreement,

46

Page 54: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

d) Collecting eggs from wild life or damaging on purpose or capturing eggs even if it is empty,

e) It is prohibited to keep fauna species alive or dead and performing internal trade over them.

III-Protected fauna species

1. All kinds of catching, capturing and killing on purpose,2. Damaging and harming breeding and recess areas on purpose,3. Disturbing the wild fauna especially in breeding, growing and winter sleep periods on

purpose, against the purpose of this agreement,4. Collecting eggs from wild life or damaging on purpose or capturing eggs even if it is

empty,5. It is prohibited to keep fauna species alive or dead and performing internal trade over

them.

If we look at the effects of the project on flora and fauna; Regulators are construction build over rivers. During the construction stage; the structures that field study to be conducted are Transmission Tunnel, Penstock Pipe and power plant areas. During the field studies, the species to be removed have a great distribution rate, so by removal of these species the generation of the species will not be endangered, but a biomass lost will in question. During site preparation and construction stage territorial fauna shall be affected. As there shall be explosions at the tunnel mouth, it is foreseen that the territorial fauna will back off to near similar biotopes because of the noise caused by explosions. The effect of the Regulator construction to the aquatic fauna, in result of grazing works to be conducted at slopes an amount of soil shall be mixed to the water and the river water may be muddy in certain time intervals. This temporal situation will spoil the suitable habitat in the water for the living creatures. In order to perform construction of Regulator, sedimentation tank and gravel pass dry Derivation Tunnel and Coffer Dam shall be built. During the construction stage primarily the water shall be derived from the right slope and the water reservoir structure and gravel pass at the left slope shall be established, later the water shall be taken into this part and the rest of the Regulator is planned to be completed. In terms of construction techniques, there no chemicals shall be used during concrete production.

47

Page 55: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

3. ALTERNATIVES TO PROJECT AND PLACE

The project in question is planned to be established on Horyan Creek and Kara Creek and it will not be used for any other purposes than power production. The fore geological studies conducted proved that the place is geologically adequate.

48

Page 56: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

4. CONCLUSIONS

Horyan Regulator and HEPP Energy Project that are subject of the Project are placed on Horyan Creek and Kara Creek within the borders of province of Trabzon, Araklı district.

The project subject to the report consists of Horyan Regulator, Transmission Tunnel, Transmission Channel, Penstock Pipe and Power Plant Building facilities.

Installed power of Horyan Regulator and HEPP project that is carried out by operation works with daily currents is 5,68 MW.

Effects to Aquatic Environment

In scope of the activity, in result of meeting the daily needs of the workers to be working at land preparation-construction and operation stage domestic waste water shall be produced. The cesspool to be established shall be placed within the construction site and the waste water collected at the cesspool, shall be removed by vacuum trucks of the municipality after conducting protocol between Araklı Municipality an activity owner.

For removal of the domestic wastewater to be produced during land preparation and operation stage the provisions of Water Pollution Control Regulation published in the O.G. No. 25687 dated 31.12.2004 shall be complied with. By taking the necessary measures the waste waters to be produced during the construction works are foreseen to be harmless to the environment.

Solid Waste Production and Its Effects

During land preparation-construction and operation stages, domestic solid waste shall be produced in result of meeting daily needs of the workers. Solid waste to be produced shall be collected in closed containers without polluting the environment and shall be transferred to Araklı Municipality solid waste collection site. For collection, storage and transfer of the solid wastes, the provisions of Solid Waste Control Regulation shall be complied with. By taking the necessary measures the solid wastes to be caused by the activity are foreseen to be harmless to the environment

Effects to Air

Emission type and amounts caused by the vehicles to be working during land preparation and construction stage are estimated at Section 1.c.

All dust estimations are performed as if all vehicles shall be working at the same time in the same area and this is a low possibility. Also, they are estimated as if there shall be no measures to be taken against dust to be formed. These estimated emissions shall be formed during 2 years that the construction works to be carried out and there shall be no emission in the operation stage of the activity.

During construction and management of the activity in question, the provisions of “Control of the Air Pollution Caused by Industrial Facilities Regulation” that was published in the O.G. No. 26236 dated 22.07.2006 shall be complied with.

Noise Formation and Its Effects

49

Page 57: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Estimation of the noise level to be caused by the land preparation and construction works in scope of Horyan Regulator and HEPP project is given at Section1.c. These values that were estimated according to closest settlement areas and distances and stated above have been evaluated under the scope of Evaluation and Management of Environmental Noise Regulation that was published in the Official Gazette No. 26809 dated 07.03.2008. The estimations in question has been estimated as if all sources of noise are working at the same time and in the same place. However, it is a quite low possibility that all of them are working at the same during the same working hours continuously. For this reason, no negative effect is expected on the closest settlement units caused by the activity. These works shall be only carried out during land preparation and construction stages and during operation stage there shall be no works to be carried out that would cause noise.

In order to protect the health of the workers at the noise exposure areas and keep the continuity of the activity adequate protective tools and equipment such as helmets, earpieces and ear taps shall be provided. During the management the workers are planned to be working for 8 hours in compliance with occupational health rules. Also, Code on Heavy and Dangerous Works Article 2 shall be complied with.

During the operation activity provisions of Environmental Noise Evaluation and Management Regulation that was published in the Official Gazette No. 26809 dated 07.03.2008 and T.R. Ministry of Health and Social Assistance, Occupational Health Legislation shall be complied with.

Earthquake Status

As it can be seen at Province of Trabzon Earthquake Map, the Project area and neighboring are is within 4th degree earthquake region according to data provided by Ministry of Public Works General Directorate of Natural Disasters Turkey Earthquake regions Map (1996). However, by taking the results of seismic risk analysis to be performed during the certain project phase and essences of 2nd of September, 1997 dated “Regulation Regarding the Buildings to be Constructed at Natural Disaster Areas” into consideration the rules of regulation shall be complied with.

Also,

“Hazardous Wastes Control Regulation” published in the O.G. No. 25755 dated 14/03/2005,

“Medical Waste Control Regulation” published in the O.G. No. 25883 dated 22/07/2005, “Soil Pollution Control Regulation” published in the O.G. No. 25831 dated 31/05/2005, “Environmental Control Regulation” published in the O.G. No. 27061 dated

21/011/2008, “Environmental Impact Evaluation (EIA) Regulation” published in the O.G. No. 26939

dated 17/07/2008, “Earthmoving Soil, Construction and Debris Waste Control Regulation” published in the

O.G. No. 25406 dated 18/03/2004, “Water Pollution Control Regulation” published in the O.G. No. 25687 31.12.2004, “Solid Waste Control Regulation” published in the O.G. No. 20814 dated 14/3/1991, “Industrial Facilities Originated Air Pollution Control Regulation” published in the O.G.

No. 26236 dated 22/07/2006, Provisions of related articles of “Environmental Noise Evaluation and Management

Regulation” published in the O.G. No. 26809 dated 07/03/2008 shall be complied with. Related provisions of “Waste Oil Control Regulation” published in the O.G. No. 26952

dated 30/07/2008 shall be complied with.

50

Page 58: Microsoft Word - Horyan HES PTD-DKMP.doc€¦  · Web viewmanual concrete crackers and drillers with piston engine (15 < m < 30) - grass cutter machines, garden streamer / grass

Horyan Enerji A.Ş. Horyan Regulator and Hepp (Hydroelectrıc Power Plant) Project

Related provisions of “Packing Waste Control Regulation” published in the O.G. No. 26562 dated 24/06/2007 shall be complied with.

In scope of the activity in question the provisions of Environmental Act No.2872 and all legislation published pursuant to this code shall be complied with.

In result of all of this evaluations, in case of applying the recommended control regulations regarding the activity precisely and completely no permanent environmental effects and damages are expected.

This report has been prepared, in accordance with the conditions of the agreement signed with the employer, in compliance and in accordance with general specifications of the work, in concurrence with the employer on selection and utilization of the resources. Any legal responsibility may arise in result of the performed agreements cannot be accepted by our party.

51