43
Microsoft Project 2002 Sessions 5-6

Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

Microsoft Project 2002

Sessions 5-6

Entering Tasks

During this first session we will enter a set of tasks that comprise building a shed – data sheet will be supplied

Cost Data

The following slides we will go through cost terms and some data

These terms will be used in future weeks

Cost Data Overview

Factors

Earned Value

50/50 Rule

Examples

Factors

BCWS - Budgeted Cost Work Scheduled - Budget entry numbers

ACWP - Actual Cost Work Performed - Actuals, what you spent

BCWP - Budgeted Cost Work Performed - Earned Value, what you have accomplished

Factors

BAC - Budget at Completion - the total of all the budget numbers, the bottom line

EAC - Estimate at Completion - based on your rate of expenditures, what you probably will spend by the end of the project

CV - Cost Variance, BCWP - ACWP = CV SV - Schedule Variance, BCWP - BCWS = SV

Factors

CPI - Cost Performance Index

BCWP/ACWP = CPI

SPI - Schedule Performance Index

BCWP/BCWS = SPI

BCWP - Earned Value

Calculating Earned Value should be easy if you set up your budget correctly.

Earned Value or BCWP is the value of what you have produced. If you have produced $500,000 worth of the $1,000,000 project, your BCWP is $500,000 or 50%.

BCWP - Earned Value

Let’s use a wall as an example: There are $50 per foot in materials It will take 4 labor hours per foot to build at $20/hour There will be $200 in other labor charges There is a crew of four working The wall is 80 feet long On the first and last days the crew has 8 hours of set

up and tear down time each

BCWP - Earned Value

Budget Materials - $50 X 80 = $4000Labor for wall - 4 X 80 X $20 = $6400Labor for set up and tear down - 16 X $20 =

$320Additional Labor - $200Total = $10,920

Budget for WallDay 1Set up – 8 hours$160.

Work on wall 24hours$480Additional LaborSpread amongstthe 11 days$18.18

Materials 24/4 =6

6 X $50 = $300

Total for day =$958.18Feet Done = 6

Day 2

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 14Cum Cost =$2016.36

Day 3

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 22Cum Cost =$3074.54

Day 4

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 30Cum Cost =$4132.72

Day 5

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 38Cum Cost =$5190.90

Budget for WallDay 6

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 46Cum Cost =$6249.08

Day 7

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 54Cum Cost =$7307.26

Day 8

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 62Cum Cost =$8365.44

Day 9

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 70Cum Cost =$9423.62

Day 10

Work on wall 32hours$640Additional LaborSpread amongstthe 11 days$18.18

Materials 32/4 =8

8 X $50 = $400

Total for Day =

$1058.18

Feet Done = 78Cum Cost =$10481.80

Budget for WallDay 11

Tear Down - 8 Hours X $20= $160

Work on wall 8 hours$160Additional Labor Spreadamongst the 11 days$18.18

Materials 8/4 = 2

2 X $50 = $100

Total for Day =$438.18

Feet Done = 80Cum Cost = $10919.98

Wall

QuestionHow would you do this budget different?

Actual Construction

Actuals For Wall Day 1 Set up – 6 hours

10 feet done

Materials - 10 X $50 = $500

Labor = $18.18 +(32 X $20) = $668.18

Total = $1168.18 BCWS = $958.18 ACWP = $1168.18

BCWP = ?

BCWP

How would you allocate the budget so you could determine BCWP?

BCWP

Easiest is to take total costs and prorate over some easy thing to measure, like the length of the wall.

$10,920/80 = $136.50 / foot completed

Actuals For Wall Day 1 Set up – 6 hours

10 feet done or a value of (10 X $136.50) = $1365.00 or $1365.00/10,920 complete = 12.5% complete

Materials - 10 X $50 = $500

Labor = $18.18 +(32 X $20) = $668.18

Total = $1168.18 BCWS = $958.18 ACWP = $1168.18 BCWP = $1365.00

Actuals for Wall - Day 1

BCWS = $958.18 ACWP = $1168.18 BCWP = $1365.00 CV = BCWP - ACWP = 1365.00 - 1168.18 = $196.82 Positive so it is

favorable SV = BCWP - BCWS = 1365.00 - 958.18 = $406.82 Positive so it is

favorable CPI = BCWP/ACWP = 1365/1168.18 = 1.168 or for every dollar that is

spent, we earn $1.17 in value SPI = BCWP/BCWS = 1365/958.18 = 1.42 or we are doing about 40%

better on schedule than anticipated. EAC = BAC/CPI = $10,920/1.17 = $9333.33

Actuals For Wall Day 2 It rained - no work performed

Labor = $18.18 +(32 X $20) = $668.18

Total = $668.18 BCWS = $2016.36 ACWP = $1836.36 BCWP = $1365.00

Actuals for Wall - Day 2

BCWS = $2016.36 ACWP = $1836.36 BCWP = $1365.00 CV = BCWP - ACWP = 1365.00 - 1836.36 = - $471.36 Negative so it is

unfavorable SV = BCWP - BCWS = 1365.00 - 2016.36 = - $651.35 Negative so it is

unfavorable CPI = BCWP/ACWP = 1365/1836.36 = 0.74 or for every dollar that is spent,

we earn $0.74 in value SPI = BCWP/BCWS= 1365/2016.36 = 0.67 or we are doing much worse

than we budgeted EAC = BAC/CPI = $10,920/0.74 = $14756.76

Actuals For Wall Day 3

Sunny day, crew motivated, did 14 feet today.

Materials = 14 X $50 = $700 Total Done = 24 BCWP = 24 X 136.50 = $3276.00

Labor = $18.18 +(32 X $20) = $668.18

Total = $1368.18 BCWS = $3074.54 ACWP = $ 3204.54 BCWP = $3276.00

Actuals for Wall - Day 3

BCWS = $3074.54 ACWP = $ 3204.54 BCWP = $3276.00 CV = BCWP - ACWP = 3276.00 - 3204.54 = $71.46 Positive so it is

favorable SV = BCWP - BCWS = 3276.00 - 3074.54 = $201.46 Positive so it is

favorable CPI = BCWP/ACWP = 3276/3204.54 = 1.02 or for every dollar that is spent,

we earn $1.02 in value SPI = BCWP/BCWS= 3276/3074.54 = 1.06 or we are doing much worse

than we budgeted EAC = BAC/CPI = $10,920/1.02 = $10,705.89

S - Curves

Ok, so now we can calculate the statistics

Next we want to be able to graph the numbers and see where we are from a visual perspective.

S Curves

S Curves are a good way to see at a glance what is going on.

The following curve shows our data on a graph.

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

S Curves

BCWS

BCWP

ACWP

Wall Example Continued

The following Excel example shows how the curves can be used.

50/50 Rule

Frame has an easier way to calculate earned value.

It is called the 50/50 rule. With this rule, you earned 50% of the

earned value the instant you start a task and the other 50% when the task is complete.

50/50 Rule

Task 1 = $50k

Task 2 = $25k

Task 3 = $40k

50/50 RuleTask 1 = $50k: Started so, we have earned $25k

Task 2 = $25k

Task 3 = $40k

BCWP = ?

50/50 RuleTask 1 = $50k: Started so, we have earned $25k

Task 2 = $25k

Task 3 = $40k

BCWP = 25K

50/50 RuleTask 1 = $50k: Started so, we have earned $25k

Task 2 = $25k: Started so have earned $12.5k

Task 3 = $40k

BCWP = ?

50/50 RuleTask 1 = $50k: Started so, we have earned $25k

Task 2 = $25k: Started so have earned $12.5k

Task 3 = $40k

BCWP = $37.5K

50/50 RuleTask 1 = $50k: Finished so, we have earned $50k

Task 2 = $25k: Started so have earned $12.5k

Task 3 = $40k: Started so we have earned $20k

BCWP = $82.5K

Reminders

BCWP can never exceed BCWS

At the end of a project the schedule variance will always equal zero

Cost variance can exceed BCWS