Upload
buidan
View
219
Download
0
Embed Size (px)
Citation preview
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 1
Method Statement: Site Set Up: Compound, Parking & Material Storage
Version Issue.
Issue Date Version Details Revised by
0 7/5/14 Issue
Acceptance / Approvals.
Name Signature Date
Prepared by: M Blackweir 7/05/2014
Reviewed by: A McGinley
12/05/2014
Accepted by:
D Meade 12/05/2014
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 2
Title: Site Set Up Location: N60 Balla to Claremorris Road Realignment at Heathlawn Scheme Task at Hand This method statement outlines the procedure and methodology for the site compound set up, including Parking and Material Storage.
Timing of Task To be advised subject to Contractor appointment. Supervision of Task (Typical) Name Contact Number Contracts Manager: TBC Site Agent: TBC Foreman: TBC Suitably Qualified Ecologist: TBC Employees Involved (Typical)
Plant Operators
Banksman
Site Supervisor
General operatives Plant & Equipment to be used (Typical)
20 ton Excavator
Komatsu D65 Dozer
A25 Volvo Dump Truck
100mm De watering pump
10 Ton Vibtomax Roller
Hiab trucks Specific Training
All site personnel shall have FAS „Safe Pass‟ certification.
All Excavator, Dumper and Crane drivers shall have CSCS certification.
CSCS certified representative in underground service location
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 3
Personal Protective Equipment
Safety Gloves Hearing Protection
Eye Protection
Respiratory Protection
Coveralls Other
Hi Vis- Vest Hard Hats Boots
Yes
Where required
Yes
NO
No
Yes
Methodology
Traffic Management (TM) on existing N60 shall be set up as per TM plan. All TM will be confined to existing N60.
Before any excavations shall commence a permit to excavate shall be issued by authorised representative.
All personal involved in the operation shall be site inducted and briefed before works commence.
Topsoil shall be stripped using excavators and stockpiled within perimeter of compound fencing
Stone for compound surfacing shall be delivered in tipper truck and graded in to place using excavator
Once stone base is in place perimeter fencing shall be erected, all within the project permanent fenceline. This shall consist of steel palisade fencing. Once compound fencing and gates are in place mobilization of site offices and containers shall commence.
Typical Site layout shall be as shown on Fig 1 in Appendix A (attached)
Containers shall be delivered in flat-bed trucks and lifted off by excavators. Site Agent/Supervisor to ensure all lifting equipment has relevant GA 1 certificates before any lifting operations commence
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 4
Potential Ecological / Environmental Impacts, including impacts on Balla Turlough cSAC and/ or other European sites NIS / EAR: Relevant Extracts: Potential Impacts (in the absence of below Mitigation):
Potential Surface & groundwater contamination during construction.
Potential Increase in run-off volumes to Turlough during construction.
Pollution from Surface Water run-off during Construction. .
Mitigation:
The site compound shall not be placed within 100m of Turlough.(Refer to Figure 2 in appendix A for proposed Site Compound location)
All fuels, oils, greases, hydraulic fluids and chemical storage areas will be stored in bunded compounds/areas on impermeable bases at least 10m from the proposed drainage system and 100m from the cSAC and Un-named Turlough.
All waste from toilet blocks shall be stored in metal storage tank and disposed of by licensed waste company when required.
Fuel storage areas will be bunded to provide adequate retention capacity in the event of a leak or spillage occurring; and kept at least 10m from the proposed drainage system and 100m from the cSAC and Un-named Turlough.
Construction works carried out in the vicinity of the Turloughs will be monitored by a suitably qualified ecologist.
To reduce potential increases in flows into the drainage system and downstream Turloughs during construction, the period of exposure of bare areas and uncontrolled runoff from new hardstanding areas will be limited. Early covering/seeding/planting of exposed surfaces will be undertaken.
Material stockpiles will be kept to a minimum size, covered and located at least 10m from the drainage system and 100m from Turloughs.
To prevent contaminated or silt-laden runoff from entering the Turloughs, a range of temporary measures will be implemented, including silt fences, cut-off ditches, silt traps, straw bales, entrapment matting and drainage to vegetated areas.
Runoff will be controlled and, if required, directed to settlement ponds or sumps. Any temporary attenuation and treatment facilities will be designed and implemented in accordance with CIRIA C697 (2007). All temporary treatment systems will be regularly inspected and maintained.
The extent of construction activities will be controlled to limit vegetation removal and the exposure and/or compaction of soils. Land surrounding the immediate construction area will be fenced off, or otherwise demarcated, to prevent inadvertent intrusion from construction plant.
Construction works will be avoided during prolonged periods of very heavy rainfall adjacent to the Balla Turlough cSAC and Un-named Turlough.
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 5
No construction plant or construction vehicles to enter the Balla Turlough cSAC boundary other than where this boundary has already been generally encroached by the existing road.
Refuelling of machinery shall be carried out off-site, or when on-site not within 100m of turlough habitat.
No machinery to enter turlough habitats, no temporary access or haul routes are located in turlough habitats and no temporary storage areas, plant or other obstacles are located within turlough habitats.
Monitoring of turbidity (suspended solids) levels in Balla Turlough SAC and the Un-named Turlough will be undertaken on a monthly basis for a minimum of 6 months prior to construction and will include monitoring during the winter season when Turlough water levels are most likely to be present. Monitoring will also be undertaken on a weekly basis during construction for turbidity (suspended solids). In the event of suspended solids concentrations that are higher than the 95th %ile of those monitored during the pre-construction monitoring period, a review of the Sediment and Erosion Control measures and plan will be implemented and additional sediment control measures put in place as required. Daily visual inspections of Balla Turlough SAC and the Un-named Turlough will also be undertaken during the construction phase to confirm the absence of sediment from construction works.
The N60 Balla to Claremorris Erosion and Sediment Control Plan shall be implemented to prevent sediment or pollutants from reaching the Balla or Un-named Turloughs.
All mitigation contained within the N60 Environmental Assessment Report and NATURA Impact Statement shall be implemented in full.
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 6
Specific Identified Residual Risks to Civil Works The following is a list of identified particular risks associated with above works
Underground Services
Excavations
Plant and Equipment
Manual Handling
Lifting Operations
Biological Substances Appendix B (attached) gives detailed risk assessments for risks identified above.
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 7
Relaying of Information; to each operative: “I wish to confirm that the information in this method statement has been communicated to me and I have understood it. I shall bring to the attention of the supervisor any issues, which may affect Safety whilst carrying out the task”. Information provided by Supervisor;
NAME (BLOCK) Signature DATE
In the event of the need for a deviation from the Method Statement, no further work will be done until agreement has been reached and recorded in writing between the client & the contractor on the method of work to be followed in the new circumstances.
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 8
Appendix A
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 9
Parking Area
Fig 1 – Typical Site Layout –(refer to drawing attached for location)
Materials Storage
N60 ROADWAY
N60 ROADWAY
1
2
3
4 5 6
7
Layout
1 Storage Container
2 Toilet Block
3 Canteen
4 Site Office
5 Drying Room
6 Meeting Room
7 ER Site Office
� �� �� �� � � �� �
� �� � � �� � � �
� �� � � � � � � � � � � � � � �� � � �� � � �� � � �� �� �
� �� � � �� � � �� �
� �� �� �� ��
� �� ��
! " #$% &'
() *+, - . /
0 1 2 3 4 5 6 7 8 4 1 9 :; < = > < ? @ < ; > A B C C D E F B C G HI J K
LMNO
P Q RS TUV W XY
LMZ[ \]
^ _`a bcd ef
g h i
j k lm no
p q
� � � �� �� �
� � � �� � �� �� �� �� �
� �� r� �� �� �� �� � � � � � �� � � �
� �� �� �� �� �� �� �� �� �� �� s �
� � �� �� � � �� �
� � � � � �� � � �� �� �� r� �� r� � � �
� � � �� �� � �� � � �� �t u v� � � �� � � �� r � �� � � � �� � � �� � � �� �
w wxy z { |
} ~� � = = � ? � � � � ;
� � D A � � B � D F � B � B � �� � � ��
� �� � ��� { |��� � � � ���
lm
� � ¡¢ £
¤ ¥ ¦§
¨© � �� �� �� �� �� �� � � �� � � � r � �� �� �� �� � �� �� � � � �� �� �� �
� �� � � � � � � ª � ª � �� r � �� �� �� � � � r � � � � � � � rt t � � �� rt u� �� �� �� �� �� �
« ¬ ®¯ ¯°±² ³ ´ µ ¶·¸¹º
» ¼½ ¾
¼ ¿½ ¼ ¼ ¿ ½ ¼
À Á À» à ½ ¿ Ä Å½ ¾Æ Ç ÈÆ ÉÂ Ê » Ľ Ë
¼ Ä ½ ˼ »½ ü ¿½ ÌÄ Å½ »Ä à ½ ÍÄ Ì½ ¿À ΠÈÄ Ã ½ Ì
Ä »½ ¼Ä ¿½ ¼
« ¬ ® Ï Ð Ñ ÒÏ Ð Ñ Ò « ¬ ®« ¬ ® Ï Ð Ñ Ò « ¬ ®ÓÔÕÖ×Ø ÙÚ
Û Ü Ý Þ ß à á â ã ãä å ä å æçèéê
ë ì í î ï ð ñòó ô õ ö ö ÷ ö ö ø ù
Ä » ½ »¼ Ľ Í
Ä ¾½ ÄÄ Ä½ ÍÄ Í ½ ͼ Í ½ ¿ ¼ ¼½ Ì ¼ ¼½ Ä Ç À À ¼ ¾½ Í
Ä Ì½ Ë
¼ Ľ Ì
ú û ü ý ú þ ü ÿ ���� ��
� � � � efÀ Ç À  ÈÄ Ë½ ¼� � �À ΠÆÄ Ã ½ »¼ ¾½ ¾Ä Ž ¾¼ ¾½ Ë
Ä ¾½ ÄÄ Ä½ Å� � � � �
� � � �� � � �
� ����
!"#
$ %&'(
)*+,
- ./ 0 1 2 3 4
5 6 789: ; <
=>?@ABCD
EFG H
IJK IJK
LM NOP QRS T U U V W X U Y Z T
» Ž ¿Ä ̽ Ä
Æ À λ »½ ¼ [ \] ^ » Í ½ » » Í ½ Ì Ä ¿ ½ ¿Ä ¾½ ÄÄ ¾½ ¾ » Ž Ë
Æ ÈÂ É » ¿½ » » ¿½ » » ¿½ Ä » Ľ Ã Ä Í ½ ¼ Ä Ä½ Ä� � �Ä Ì½ ÄÄ Ë½ ËÄ Ë½ ËÄ Ë½ ËÄ Ì ½ ÍÄ »½ Ã[ ^ ] _» à ½ ÌÆ Â Ê» Ž ÄÀ ` ÀÄ ¾½ ÍÄ ¿ ½ ÍÀ Æ ÆÄ ¿½ ¿ Ä Ä½ Å Ä Ã ½ Å ¼ ¾½ Ã Ä Ë½ Ë Ä Ì½ ¾Ä ˽ ËÄ Ë½ Ã
Ä ¾½ Å Ä ¿½ ¿ ¯ ¯°±² a b c d
� � � �efg hijkl m nopqrstuv w x y z { | } ~ ���
���� � �� �� � � � � � �� � �� � � � � � � � � � �� � � �� �� � ¡ ¢ � � £ � � ¤¥¦ § ¦ ©� © � �ª« ¦ ¬� � �¤ ® � ° � £ � ± � ² ³ ¡ � µ � ¶ � �· � ¡ ¢ ¡ � � � � � � � � � ¡ � ¢ µ ¹º » ¼ ½ º ¾ ½ ¼ ¿ À Á Áà ÁÄ Å ÆÇÈ É Ê Ä Ë É È ¿ Ì Í Î ¿Ï ÐÑ Ã ÅÈ »ÒÓ Ô Ô ÕÖ × ØÖ Ù ÚÓ ÛÓ ÜÝ Þ ß à ß á â ã ä à ã ã ãÒÓ Ô Ô ÕÖ × åÖ æ ç è æ éÝ Þ ß à ß á â ã ä à ê ë ãì Ù í Ü Õ × î ï ï ïð ñ æ òÖ í Ú ð òÖ óô õ ö ÷ ¥ ÷ ø ù � ö ¥ ÷ ø ù ¥ ú ûüý þ ÿ þ � � �� � � þ ��� �� ô� � �¥� � �� �� « �� � � � � � � � � � � � � �� � �� §� �¦ ¦ ¦ � �� � � � � � � � � � � � � � � ! � � � " # � � � $ % � � & � � � � ' � � ' � � ( �) * + , , , - . )�/ 0 1 23 4 5 2 6 / 0 !7 2 8/ 9 # 2: 27 ;7 0 2 �/ ; </ 4 0 9= %: 3 > 6 0 ? : 0 9 ! : 27 3 6 : @ # 2/ 3 : ?7 # <: 57AÈ Æ B Í Â C C  D à ŠC Ä Ã Ñ E À Ì FÍ Â C C  D à ŠC Ä Ã Ñ E G  H Ð Á Á IJ ÁÈ Ë Á É K K LM N O P QR S T R U V � � W � � X � � Y Z [ \K N ] _
a b ` b cd e f g h
i j k k j l m a k b m no c j pi j k k j l m a k b m n o o j i q l j l d r ld f l c
s st tuvw E Ð C É Á Á E Ð É Ê ÅÄ Ê Ä É È x Ðy Ê ÅÄ zÈ y È Ë Á E Â É H È È Ë x È É ÐÑ Ë È x É Ã { { Ð| Ð È Ë Á C Æ Á Ä H ÈÉ E Ä } Ë Â É Â Ê Å | Á Ð |  C É| E È y È~ Á E È x È É ÐÑ Ë } Ð C C H È {à ŠÁ E È Å ÅÈ { Ð Ë È x x à ŠРËÑ Á E Èx È Á РC È x x È É ÐÑ Ë Ê ÅÄ | È É É } E Ð| E y Â Æ ÅÈ É Ã C Á Ð Ë | E  ËÑ È É ÁÄ Ê Â Å Á É Ä { Á E È C ÐÑ Ëy È Ë Á Â Ë x Á E Ð É y Â Æ Â { {È | Á Ä Á E È Å Ð Ë {Ä Åy  Á Ð Ä Ë Ä Ë Á E Ð É x Å } Ð ËÑ�
hi�� �� �� �R � T � �R � � � R � �� � � � �R � �R �� � M � � � � � K N � K � �� �� T� V � �� T � � � �� �� �� �� � � �� � � � � � � ¡ �� � �� � ¢£ � �� � ¤ �� ¥ £ ¦ � � ¡ �� �
m f f j § d e l m a k b m n oÀ Ð ÁÈ Ì| | È É É ¨  C Ä ËÑ È J Ð É Á Ð ËÑ © ª ½ «ÎÈ Åy Â Ë È Ë Á Ï È Ë| È ¬ Ð Ë È # 2: 2 4 2/ 3 �7 1 </ 0 17 ® � 0 �/ 3 9 % @7 : 0 : @ :¯ ° ± ² ³ µ ¶ · ° ¹ ¯ ² º ² » ¼ ¯ ½ ¾¿ À ¹ ¿ Á  ¹ Á ¿ à ¯Ä Å Æ Ä Ç È À ¯É Ê · ¶ É Ë ¶ ¶Ì Í º Î ³ Ï µ Ð ¹ Ê ³ Å Ñ Ã ¶ ÒÓÌ Ë ¶ ² Ñ Ñ ¹ Ð Ï Ñ ¿ Ã Ô Ð ¿ ¿ Å À ¯ ³ Å Ñ Ã Ê É Ó Õ ¹ ¹ Á ¹ Ð ¿ È Ö ¿ Ð Â Ã À À ¯ Í Ã À × Ð ½ À à À ¹ Ð ØÙ Ú Ã Â ¹ Å Ð ½ À ¯ º ² ÖÎ ÅÄ Ê Ä É È x À Ð ÁÈ F Ä y Ê Ä Ã Ë x ¬ Ä |  Á Ð Ä Ëw Ð C C Ð Ë| C à x È F Â Å Î Â Å Û Ð ËÑ Â Ë x Ü Â ÁÈ Å Ð Â CÀ Á Ä ÅÂ Ñ È Â ÅÈ Â É « Ì| | È É É { ÅÄ y } Ð Á E Ð ËÈ J Ð É Á Ð ËÑ F Î Ý «Þ Ë Ë Â y È x D à ŠC Ä Ã Ñ E
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 10
APPENDIX B
Risk Assessments
Hazard/Risk Assessment Proforma
Project: N60 Balla to
Claremorris Road
Realignment at
Heathlawn Scheme
Risk
Assessment
No:
N60/RA01 Rev 0 Review Dates:
May 2014
Operation/Task: Method
Statement
Title:
Compound
Construction
Location/Area: TBA Method
Statement No:
MS-N60-01 Rev 0
CATEGORY OF PERSONS AT RISK AND MEANS OF BRIEFING
CATEGORY OF PERSONS
Means of Briefing
RAMS SCS Othe
r
Occupations involved in
Activity (Specify): Plant operators, general operatives , Y
Others Persons at Work
(Specify): N/A
Public or Other Parties
(Specify): NA
Description of the task/operation
1. All aspects of excavations .
2. Lifting operations
KEY
: S = Severity Rating L = Likelihood of
Occurrence
Sev
erit
y
RR = Risk Rating 9 Unacceptable risk, plan out or add further controls
1. Negligible 1. Improbable
3 3 6 9 4-
6 Acceptable only if no other method viable and with
high level controls in place
2. Minor 2. Reasonably likely
2 1 4 6 2-
3 Acceptable if suitable controls
3. Notifiable/Major/Fa
tal
3. Certain or near certain 1 1 2 3 1 Acceptable, no further action required
1 2 3
Likelihood
Risk Assessment Prepared by (Name): Signature: Date:
Risk Assessment Reviewed by (Name): Signature: Date:
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 11
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
01 Existing
Services Work near significant existing
services in
addition to electricity
- ESB services
- Telecommunications
2 2 4 Detailed Method Statements and Risk
Assessments to be carried out for all
activities which have potential to impact on
existing services
- Request temporary outages on services
- Worker Briefings to be carried out
- Consult with Statutory Bodies to obtain service
drawings
- Adhere to Codes of Practice for avoiding
dangers from under ground services
- Trial holing in advance
- Permit to Dig system to be implemented
- Use of Catscan equipment
- Use of trained plant operators
- Use of Banksman
2 1 1 Full site Team Contr
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 12
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
02 Excavations
( Ducting and
sewage works )
-Burial under earthfalls
- Work in trenches or near
saturated ground / high water
table.
- Excavation Collapse
- Trench Collapse
- Falls from Height into
excavations
2 2 2 - Detailed Method Statements and Risk
Assessments to be carried out pertaining to
each particular activity
- Permit to Dig System to be Implemented
- Area to be scanned using CAT Scan
techniques.
- Suitable Plant to be utilised in excavation
operations
- All excavations to be monitored on a daily
basis. AF3 to be completed weekly.
- Competent Machine Operators to be utilised
FAS CSCS qualifications
- Adequate Trench Support Systems to be
utilised i.e. trench boxes/sheets, battering of
trenches
- Temporary Works procedures to be
implemented
- Dewatering systems to be implemented
where required.
- Suitable access to be provided to trenches
- Perimeter fencing and signage to be put in
place and secure excavations
2 1 1 Full site Team Contr
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 13
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
03
Moving Heavy
Plant
and
Equipment
Working adjacent to Heavy
Plant and
machinery including
excavation plant
and lifting appliances
Hazards
Noise.
Operated by untrained
individual
Incorrect use.
Speeding.
Poor maintenance.
Unsupervised reversing.
Overloading
Risks
Struck by site transport
Falls from vehicles.
Splashed by fuel during
refuelling.
Tipping or overturning of
vehicles.
Contact with moving parts of
machinery
3
2
6
- Detailed Method Statements and Risk
Assessments to be carried out for all
activities to address the movement use of
heavy equipment.
- Worker Briefings to be carried out
- Plant to be operated by Competent Personnel
- Plant to be in good order and inspected daily
prior to commencement of any works on site
- Auxiliary devices and visual aids on plant as
highlighted in Schedule 6 of 2006
Construction Regulations.
- Carry out plant checks and record on plant
checklists
- Vehicle Banksmen to be utilised where
required
- Segregate traffic from public and workforce
where possible
- Implement work exclusion zones where
appropriate
- Implement Traffic Management Plans
- Ensure all personnel were appropriate PPE
and high visibility clothing
3
1
3
Full site Team
Contr
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 14
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
04
Lifting
Operations
(Offloading
containers )
Unsupervised lifts leading to
collapse overturning of loads
Unstable ground causing
overturning or collapse of
loads
Uncontrolled pedestrians or
site traffic leading to
collisions with plant or
pedestrians.
3 2 5 Ensure permit to lift system is in place
Ensure all plant operators have relavant CSCS
certificates for plant they are operating.
Ensure all lifting equipment have relevant and up
to date GA 1 certificates .
Ensure all pedestrians and site vehicles are
cordoned off from lifting operations.
Use of stabilizing pads or beams under any
jacking legs used on lifting equipment.
3 1 3 Full Site Team Contr
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 15
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
05
Biological
Substances
(Refulling diesel
and oils )
Sewage
Connections
Works which put person at
work at risk
from Biological substances
- Leptospirosis /Weils Disease
- Contact with contaminated
ground or objects or materials
contaminants, Red Lead
- Handling construction
chemicals,cement, curing
agents etc
- Handling flammable
substances.
- Working on existing streams
and drains, particularly foul
drains.
3 2 4 - Detailed Method Statements and Risk
Assessments to be carried out for all
activities where biological substances are
envisaged including contaminated ground
and dealing with asbestos gaskets
- Specialist contractors to be utilised to deal
with asbestos
- Areas of potential contaminated ground to be
tested and areas segregated
- COSHH Assessments to be carried out and
briefed to workers
- MSDS Sheets to be available for
construction chemicals in use
- Ensure adequate assessment of PPE
requirements for works
- All operatives engaged in sewer tie in works
to wear appropriate PPE which will include
gloves and disposable overalls.
- All operatives to be briefed and trained
- Adequate awareness of and protection
against Weils disease
3 1 2 Full site Team Contr
N60 Balla to Claremorris Road Realignment at Heathlawn Scheme
Method Statement: Site Set Up:
Compound, Parking & Material Storage
Date
7/5/14
Ident No.
MS-N60-01
Date : 7/5/2014 Page 16
Item Activity Hazards/Risks
Identified
Pre-Control Risk
Rating Control Measures
Residual Risk
Rating Responsibility Monitoring
Responsibility S L RR S L RR
06 Manual
Handling
Fractures, Strains, Sprains
Cuts, Lacerations, Abrasions
Injury through aggravation of
previous/existing medical
condition
3 2 6 -Use of mechanical assistance wherever possible,
e.g. forklift, plant, lifting appliance etc.
- Reduce loads by making them smaller or lighter.
- Ensure the working environment is suitable i.e. -
-- - Access ways are unimpeded and properly
lighted. - Working platforms should be non-slip
and kept clean
Ensure that the individual is lifting correctly,
maintains good posture, and lifts with knees bent
and back kept straight.
All loads should be assessed individually for size
and weight, but generally loads greater than 25kg
should be handled by more than one person or
mechanical means employed.
Operatives must wear appropriate gloves and
other clothing to reduce the risk of injury.
Ensure that all previously experienced back
complaints are brought to the attention of
management, in order that allowances may be
made in ascertaining the safest method of manual
handling.
3 1 2 Full Site Team Contr