Method Statement for Steel Structure & Erection

Embed Size (px)

Citation preview

  • 8/10/2019 Method Statement for Steel Structure & Erection

    1/16

    INSPECTION Gr

    FIELD INSPECTION REPORT ffi:-'-"INSPECTION TYPE

    STEEL STRUCTURE INSTALLATION INSPECTIONWORK No.

    ITEM NoAREA / LOCATION

    ITEIM No. DESCRIPTION SIGNATUREINSPECTION NOTICE No OWNER CONSORTIUM CONTRACTOROWNER'S INSPECTOR

    CONSORTI UM'S INSPECTOR

    CONTRACTOR'S INSPECTOR

    REFERENCE Drawing. No

    I'IGHTENING METHOD

    I Calibrated Wrench Method Twist-of-Type Tensron Control

    INSPECTION

    ffiTACC-T--REJ1 LOCATION2. VERTICALITY

    3. HEIGHT

    4 HORIZONTALITY5. FOUNDATION AND ANCHOR BOLT

    6. SHIMMING

    7 WELDINGB, BOLT I"ORQUI NG/I'IG HTEN'NG

    9. GIlOUTING

    1O PAINTING (TOUCH-UP)

    OTHERS

    1 TORQUE WRENCH CALIBRATION2 CRANE / HOIST RAIL INSTALLATION

    COMMENTS

    LEGEND ACC ACCEPI- N.A. Not Apptjcabte REJ REJECT

    fjoRfi/ No. c-40

  • 8/10/2019 Method Statement for Steel Structure & Erection

    2/16

    @u qr r,ffiffiffi a F-{ w'Ia *- &*l l 1^:." .---* G0obalTryn ffiars*piffiilll$ i,,.;) c ro.

    FIELD INSPECTION REPORT

    ITP NO- :INSPECTION Gr. :REPORT NO. :

    INSPECTION TYPE:

    STEEL STRUCTURE ALIGNMENT INSPECTION

    LEGEND ACC ACCEPT N.A. : NotApplicable REJ: ttEJECT

    FORMNO

    C.41

    ITEM No. :AREA / LOCATION

    SIGNATURETEM No. DESCRIPTION:CONTRACTORNSPECTION NOTICE No

    OWNER S INSPECTOR

    CO lr SOniTVLY r'f .S P rCrO nCONTRACTOR'S I NSPECTOR

    REFERENCE Drawing. No

    l ctlt IIA.ililldluile ut' 5 tanr:aril

    '['* rrunce ttl erc,(tiil rllr*r:tict l'rr tl*cl lrluilrling entJ Llrirlge*.)

    COLUMN VERTICALITY

    T*[trur,;e ValC;i

    Jurr; tlqr[,x],f.q.e1p19,;l

    I,{cr:lhcrr l.]L rulrc{jnH tl f i: lu::rn:;e rir,nntll l nlcn:lrc::)

    L)il- i:{h,leflll,,J]; {Y*r{ir,*lr I

    TOP OF BEAM LEVEL

  • 8/10/2019 Method Statement for Steel Structure & Erection

    3/16

    .ffie -rr r\/n ,$ffiW __{ nYU Hob;tTwffi***$[ffi

    TNSPEC ttoN Gr

    FIELD INSPECTION REPORT ffi;:-,-"INSPECTION TYPE:

    STEEL STRUCTURE ACCESSORIES INSPECTIONAREA / LOCATION :

    WORK No.

    ITEM No DESCRIPTION SIGNATUREINSPECTION NOTICE No OWNER CONSORTIUM CONTRACTOR

    OWNER'S INSPECTOR

    CONSORTI UM'S INSPECTOR

    CONTRACTOR'S I NSPECTOR

    REFERENCE Drawing. No.

    VISUAL INSPECTION

    o c0'=soqa

    6.oIo

    6coNoI

    oc-6

    o

    oC

    .ce0_

    REMARKS

    ACCESSORIES'l . Platform

    2. Ladder

    3. Grating

    4. Checker Plate

    5. Handrail

    6. Stair

    7

    B

    9

    10

    COMMENTS

    LEGEND ACC: ACCEPT N.A. NotAppllcable REJ: REJECT

    FORM NO. C-042

  • 8/10/2019 Method Statement for Steel Structure & Erection

    4/16

  • 8/10/2019 Method Statement for Steel Structure & Erection

    5/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.S-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 2 of 13

    TABLE OF CONTENTS

    1.0 SCOPE ................................................................................................................ 3

    2.0 REFERENCE DOCUMENTS .............................................................................. 3 2.1 A BBREVIATIONS ........................................................................................... 32.2 C ODES ........................................................................................................ 32.3 C ONTRACTOR 'S DOCUMENTS ....................................................................... 4

    2.4 A SSOCIATED P ETROJET P ROCEDURES ......................................................... 43.0 RESPONSIBILITY .............................................................................................. 4

    3.1 C ONSTRUCTION M ANAGER ........................................................................... 43.2 QA/QC M ANAGER ........................................................................................ 4

    4.0 MATERIAL AND EQUIPMENT........................................................................... 4 4.1 S TEEL S TRUCTURES ................................................................................... 54.2 W ELDING FILLER METAL .............................................................................. 54.3 E QUIPMENT AND TOOLS .............................................................................. 5

    5.0 PLANNING OF ACTIVITIES AND MONITORING OF PROGRESS ................. 5

    6.0 ERECTION DRAWINGS .................................................................................... 5 7.0 RECEIVING, HANDLING AND STORING MATERIAL ..................................... 6

    8.0 CHECK FOR FOUNDATIONS........................................................................... 6

    9.0 PRELIMINARY CHECKS .................................................................................. 6

    10.0 MATERIAL WITHDRAWAL............................................................................... 7

    11.0 ERECTION .......................................................................................................... 7 11.1 GENERAL ..................................................................................................... 711.2 M OUNTING GUIDELINES ................................................................................ 811.3 I NTERMEDIATE INSPECTION .......................................................................... 1011.4 F INAL INSPECTION ....................................................................................... 1011.5 T OLERANCES .............................................................................................. 1011.6 R EPAIR OF G ALVANIZED S TEEL .................................................................... 10

    12.0 TESTING AND INSPECTION ............................................................................. 11

    13.0 GROUTING ........................................................................................................ 12

    14.0 QUALITY RECORDS......................................................................................... 12

    15.0 APPENDIX ......................................................................................................... 12

  • 8/10/2019 Method Statement for Steel Structure & Erection

    6/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 3 of 13

    1.0 SCOPE

    This procedure describe the minimum requirements that shall be observed at site for handling and

    storing materials, erection of hot dip galvanized primary and secondary steel structure to be installed .

    It also covers the tests and inspections that are to be carried out during the execution of the

    assembly works.

    And this procedure covers Steel Structures, Steel from Building, Supporting Steel, Steel Pipe Rack,

    and Miscellaneous Structure Steel.

    The objective is to ensure that all the activities are carried out:

    In accordance with approved procedures, specifications and drawings,

    Using special working and control process which have been previously qualified;

    employing qualified and, when required, certified personnel;

    using material which are kept under control from receiving throughout entireworking cycle;

    Performing all tests, measurements and inspection required by Contract.

    2.0 REFERENCE DOCUMENTS

    2.1 ABBREVIATIONS

    ITP = Inspection & Testing PlanQC = Quality Control

    2.2 CODES (BRITISH STANDARDS )

    AISC (9 th edition) The American Institute of Steel Construction.AWS D1.1 Structural Steel Welding Code.

    (B S) British Standard.

    (ISO) International Standard Organization.

    ANSI American National Standard Institute.

    ASTM American Society for Testing and Materials.

    2

  • 8/10/2019 Method Statement for Steel Structure & Erection

    7/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 4 of 13

    2.3 CONTRACTOR'S DOCUMENS

    Minimum Quality Requirements for Site Activity.Steel Structural Works Technical Specification.Steel Structure Standard Drawings and Details.

    ED-9999-STR-SPEC-000-JB611 Specification Of Steel Structure.

    CD-9999-FQC-PRC-000-001 QC Procedure.

    ED-9999-PJM-PEP-000-006[1] Project Quality Plan.

    ITP NO: 2001 : 2011 Inspection & Test Plan for Mechanical Works.ITP NO:20 Structural Steel (Erection).

    2.4 ASSOCIATED PETROJET PROCEDUR

    PJ-EEP2-MRI-PRO-0001 Method of Statement of Material Handling , Storage Procedure

    PJ-EEP2-NR-PRO-0001 Non Conformance Management Procedure.

    PJ-EEP2-NDT-PRO-0001 Visual Inspection Procedure.

    3.0 RESPONSIBILITY

    3.1 CONSTRUCTION MANAGER

    The Construction Manager is responsible for the implementation of this procedure for

    the over all direction and coordination with the QA/QC Manager for monitoring,

    coordinating

    and control of all the erection activities.

    3.2 QA/QC MANAGER

    The Site QA/QC Manager is responsible to verify the proper implementation of the quality

    systems and to implement quality control activities related to erection.

    4.0 MATERIAL AND EQUIPMENT

    4.1 STEEL STRUCTURES

    The Steel Structures shall mainly consist of the following: Steel Building and Shelter Pipe Racks / Steel Structure Equipment Platform, Stair and Walkways / Handrails/Cross over /Shetters. Minor Steel Structure / Supports / Ladders / Grouting /Beams, etc.

    2

  • 8/10/2019 Method Statement for Steel Structure & Erection

    8/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 5 of 13

    4.2 WELDING FILLER METAL

    When required for any modificat ion Welding filler metal shall conform now to BS 5135,

    BS 639 and ISO 5182 /E7018 welders and welding WPS as per BS4871 & BS 4872

    4.3 EQUIPMENT AND TOOLS

    All tools and equipments to be used for erection shall be standard (not allow any

    fabricated or hand made fouls) in good order, safe condition and sufficient quantity.Examples of tools and equipment are:

    Cranes

    Lifting gear including sling wires,belts,chackles,ect.

    Plastic Ropes to be used as guide only during lifiting not for any lift.

    Standard tools such as spanners, Transportation Trucks

    Torque Wrenches5.0 PLANNING OF ACTIVITIES AND MONITORING OF PROGRESS

    The Project Planner is responsible to plan the sequence of erection of steel structure

    according to the Construction Master Schedule.

    He is also responsible to monitor the progress of the work and to keep informed the

    Construction Manager and Project Manager for any deviation from the original schedule.

    Planning of steel structure erection shall be made according to erections priority

    and material availability.6.0 ERECTION DRAWINGS

    The Technical Office (TO) receive the steel structures drawings from engineering department.

    Based on the availability of drawings, material after fabrication, specifications and in

    congruence with planning, TO shall issue detailed drawings for erection and copy to all the

    concerned departments (AFC DWGS & Last Rev).

    The following information shall be provided in the detailed drawings:

    Identification of each item, part or assembly number with match mark and otherinformation as necessary for easy identification and erection;

    Specific instruction, as necessary for erection;

    1

    2

  • 8/10/2019 Method Statement for Steel Structure & Erection

    9/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 6 of 13

    7.0 RECEIVING, HANDLING AND STORING MATERIAL

    The Material Control Manager (MCM) shall receive all steel structures in accordance with the

    procedure and shall be responsible for checking quantity and type of materials indicated in

    the packing list and QC inspector checks for quality. The damages shall be immediately

    notified to take the required measures.

    The materials shall be stored, handled and preserved in accordance with the procedure.

    8.0 CHECK FOR FOUNDATIONSBefore commencing work, center lines, locations, orientation, chipping and

    elevations of foundations shall be checked for prescribed tolerances.

    Support shims shall be located after marking the centre lines on the plinths.

    At least 3/4 shims packs with levelling mortar shall be provided for the base plates of each

    column. Centre lines marked on plinths shall have a tolerance of 1 mm and elevation

    of 1 mm.

    The foundation bolt surface that will come in contact with concrete shall be free fromdirty and oily matters or points. Foundation surface shall be chipped prior to erection activity.

    9.0 PRELIMINARY CHECKS

    According to the sequence and schedule of erection, the following preliminary checks

    shall be carried out before erection activities begin, in order to verify:

    The availability of experienced, qualified personnel and equipment necessary to

    carry out the works;

    The availability of fabricated steel structure and its status of acceptance.

    The status and availability o f approved for Construction drawings and

    /or specifications.

    All tools and equipments used for erection are calibrated as per Calibration of

    Inspection and Testing Equipment procedure

    The status of torque wrench calibration the above preliminary checks shall be

    jointly made by all the concerned as i n responsibility matrix.

  • 8/10/2019 Method Statement for Steel Structure & Erection

    10/16

  • 8/10/2019 Method Statement for Steel Structure & Erection

    11/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 8 of 13

    The contact surfaces of bolted elements shall be free from rust, mill scale, grease, etc. Bolts

    already used and previously tightened shall not be re-used.

    All site bolted connections shall be assembled and torque tightened in accordance with Appendix

    A. After the torque tightening of bolts shall be identified by the paint on the bolt head.

    All material, plant and equipment used shall be of sound construction and free from flaws.

    Bolts designed for transmitting forces in structural member connections, shall have a minimum

    diameter as follows :

    Minimum diameter For main members, bracings and struts 20mm

    For secondary, i.e. bracings, purlins, 16mm

    Ladders, handrails, etc.

    ( Unless noted otherwise on standard drawings).

    Except otherwise noted on design drawing, hole diameter for bolts shall be as followsDiameter bolt, plus:

    For steel-to steel connections : 2mm For steel-to-concrete connections (anchor bolts):

    o Up to 24 mm bolt diameter : 4mm

    o 24 to 32 mm bolt diameter : 6mm

    o 32 mm bolt diameter and over : 8mm

    The spacing of bolts in the direction in which the force is applied shall be at least three bolt

    diameters (measured in the direction of the force).

    The minimum distance from center of bolt edge of plate measured in the direction of force shall be two bolt diameters, and measured at r ight angles to the direction o f force, one and a half bolt

    diameters.

    Slotted hole connections are to be executed in such away, that these connections may perform

    their design function, as indicated on the design drawings, and shall be provided with washers.

    High-strength bolts shall be used for structural steel-to-steel connections.

    High-strength bolts shall be used for in bearing-type connections and not as friction grip bolts

    11.2 MOUNTING GUIDELINESIf required, additional drilling of beams, columns or other components shall be made to

    remedy fabrication mismatch / faults. Magnetic base drills shall be used for such work.

  • 8/10/2019 Method Statement for Steel Structure & Erection

    12/16

  • 8/10/2019 Method Statement for Steel Structure & Erection

    13/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 10 of 13

    Checking at a pre-erection stage for correct distance of the connected column

    Flanges to beam.

    Handrails and toe plates shall be not welded to the columns; however they shall be

    Adequately jointed in the vicinity of the columns.

    When not provided in the design drawings, the tube passage through grating shall

    be admissible only in case grating is adequately reinforced at the pass hole.

    A toe plate shall be provided around the pass hole.

    11.3 INTERMEDIATE INSPECTION

    Each framework floor shall be checked for verticality and diagonals before and after tightening of

    bolts.

    Survey instrument shall be used for checking of verticality. When executing the tests, proper

    consideration shall be given to the deformation changes occurring in the steel structure during a day

    on account of exposure to the sunlight.

    Verticality:

    Verticality and levelness shall be checked by means of a Survey instrument.

    For verticality reference shall be made to points (flags) marked on columns;

    Diagonals (in plan):

    Diagonals shall be checked using a metric roller;

    All structural framework / floors shall be checked;

    11.4 FINAL INSPECTION

    Check for steel structure framework verticality, horizontal alignment and height shall be carried

    out after mounting.

    Splicing shall be executed in accordance with prescriptions listed para 9.4. Bolt torque

    tightening shall be as mentioned in the Appendix Completeness check as per approved for

    construction drawings.

    After checking of connection, the erecion drawing shall be marked to indicate acceptance.

    11.5 TOLERANCES

    The deviation in overall dimensions, positions, alignments, plumpness and

    elevations shall not exceed the limits specified in specification.

    1

  • 8/10/2019 Method Statement for Steel Structure & Erection

    14/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 11 of 13

    11.6 REPAIR OF GALVANIZED STEEL

    Any damage to galvanized steel shall be repaired in accordance with ASTM A780.

    Before repairing the damaged galvanized coating, the exposed substrate metal shall be cleaned to bright

    metal

    and free of all visual rust, oil or grease. Any none adhering galvanizing shall be removed to the

    extent that the surrounding galvanizing is integral and adher ent.

    12.0 TESTING AND INSPECTION

    Inspection and test shall be carried out by qualified personnel, coordinated by SQM, according to

    the Inspection & Testing Plan (ITP).

    All structural steel material and fabrication shall be subject to inspection by client

    Welds shall be inspected by contractor according to the previsions of regulatory requirements with

    respect to technique, equipment, and acceptance criteria and personnel qualifications. All welds

    shall be subject to random visual inspection by client .in addition, the following specialrequirements shall apply to welding inspection.

    Grating shall be tagged with metal plate having raised letters so that the mark shall be seal welded

    to the grating prior to galvanizing.

    Contractor may submit alternate proposal for marking galvanized members, subject to clients

    written approval.

    SQM shall manage all Witness and Hold Points shown on the ITP, including convocation to

    Contractor.The form worked out toyo shall be used for issue of the certificates listed in the Inspection and

    Test Plan The Inspection mentioned in the Inspection and Test Plan shall be carried out using the

    following calibrated instruments:

    Optical levels, steel metric rollers, water levels, manual dial type torque wrench for torque read-out.

    10% of all connections for each bolt size shall be randomly selected and inspected, of each

    joint shall show the tightening value of high strength bolts. Such test shall be conducted on

    minimum 2 bolts per each joint.

    Tested bolts shall be clearly marked with paint.

    Each high strength bolts assembly shall consists of one heavy semi-finished hexagon structure

  • 8/10/2019 Method Statement for Steel Structure & Erection

    15/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 12 of 13

    bolts one heavy semi-finished hexagon nuts and one hardened washer to be used the nut

    In presence offload indication Washers ,turn-of nut tightening follow-up; one nut sample per each

    size of bolts shall be unscrewed by at least 1/6 turn and then to check whether the prescribed torque

    brings the nut back to its original position.

    Galvanized bolts shall not be reused after unscrewed; bolts may be reused after repaint

    by galvanize spray.

    13.0 GROUTING

    All bearing plates, loose lintels, beams and columns shall be shimmed to proper grade and

    level before grouting.

    Grout material as specified in the technical specification or on drawing shall be used.

    The sand-cements mixture shall be combined with the least amount of water to produce a low

    slump, place able grout.

    Prior to setting structure, the concrete surface to receive grout shall be chipped to a depth of

    6 mm to obtain a roughened surface.

    After the structure is a place, positioned and shimmed immediately before grouting, the surface to

    receive grout shall be cleaned and wetted. Excess water shall be removed.

    Grout shall be placed and thoroughly worked to eliminate voids and provide a uniform bearing

    surface under the base plate.

    When specified on drawings, epoxy grout shall be used for grouting under heavy equipment

    where large bearing and /or vibration stresses occur. Epoxy grout shall be mixed by mechanical

    mixer and placed in accordance with manufacturer instruction.

    14.0 QUALITY RECORDS

    The following records shall be provided:

    ITP and Procedure

    Certificates of materials supplied

    Dimensional reports

    Bolt torque tightening reports

    Surface treatment reports

    Grouting reports

    Final dossier containing the report of the test carried out

  • 8/10/2019 Method Statement for Steel Structure & Erection

    16/16

    Document Description METHOD OF STATEMENT FOR STEELSTRUCTURE & ERECTION

    Client The Egyptian Ethylene and Derivatives Company(ETHYDCO)On Shore JV TOYO and ENPPI Document No. PJ-EEP2-ST.ST-PRO-0001 Rev. SheetJob Location Ameriya Alexandria, Egypt 2 13 of 13

    15.0 APPENDIXB

    1- Torque Tightening of Steel Structure Table 001.

    2- Steel structure installation inspection C-40.

    3- Steel Structure Alignment Inspection C-41.

    4- Steel Structure Accessories Inspection C-42.

    TORQE TIGHTENING OF STEEL STRUCTURE

    Bolts Classes 8.8 and 10.9

    The tightening torque shall be in accordance with the following Table 001.

    Nominal Diameter of Bolt in mm Tightening Torque in NM

    12 94

    14 148

    16 234

    18 320

    20 456

    22 616

    24 787

    27 1150

    30 1562

    33 2125

    36 2729 39 3532

    Form No. Table :001

    1