6
STATE OF KUWAIT KUWAIT UNIVERSITY ELECTRICAL METHOD STATEMENT TENDER NO. KU/KUCP/C0251/10-11 Page 1 of 6 METHOD STATEMENT FOR INSTALLATION OF INSTALLATION OF PVC CONDUITS AND ACCESSORIES IN THE CONCRETE SLABS, COLUMNS, BLOCK WORKS AND CONCRETE WALLS 0 Issued for Review & Comments Rev. Date Description Eng. A.H Prepared by Checked by Approved by

METHOD STATEMENT for INSTALLATION of PVC Conduits and Accessories in the Concrete Slabs, Columns, Block Works and Concrete Walls

Embed Size (px)

DESCRIPTION

METHOD STATEMENT FOR INSTALLATION Of PVC Conduits And Accessories In The Concrete

Citation preview

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 1 of 6

    METHOD STATEMENT FOR INSTALLATION OF INSTALLATION OF PVC CONDUITS AND

    ACCESSORIES IN THE CONCRETE SLABS, COLUMNS, BLOCK WORKS AND CONCRETE

    WALLS

    0 Issued for Review & Comments

    Rev.

    Date

    Description

    Eng. A.H Prepared by

    Checked by Approved by

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 2 of 6

    REVISION CONTROL SHEET

    REV. NO.

    DATE

    PAGE NO.

    DESCRIPTION

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 3 of 6

    TABLE OF CONTENTS

    1 Purpose.. 4 2 Scope of Work.. 4 3 Responsible Personnel on Site.. 4 4 Storage.. 4

    5 Pre-Installation 4

    6 Installation 5

    7 Reference Documents. 5

    8 Safety 6

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 4 of 6

    1. Purpose

    This method of statement covers the in-site installations of Installation of PVC Conduits and Accessories in the Concrete Slabs, Columns, Block Works And Concrete Walls as defined in the General Specification.

    2. Scope of Work

    This procedure will define the method to be used to ensure that the PVC Conduits and Accessories installations, on-site assembly, final connection and workmanship are acceptable, correct, safe and conforms the Contract Documents and Specification.

    3. Responsible Personnel on Site

    3.1. Construction Manager 3.2. Electrical Field Engineers 3.3. Safety Officer 3.4. QA/QC Engineer 3.5. Electrical Supervisors

    4. Storage

    4.1 Deliver PVC Conduits and Accessories to site, completely identified in accordance with shop and certified drawings prepared for this work.

    4.2 Store in accordance with the manufacturers instructions, above ground, properly

    protected from the weather and construction activities.

    4.3 Make sure that the storage area is safe.

    5. Pre-Installation

    5.1 All materials and documentation relevant to this particular section of works shall be checked prior to installation.

    5.2 Ensure that the location wherein the PVC Conduits and Accessories were installed are

    accessible, clean and free of debris and foreign materials and suitable for installations.

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 5 of 6

    6. Installation

    6.1 During the course of the installation of the conduit system, procedures for working and dressing the installation as recommended shall be employed.

    6.2 All bends and sets shall be in accordance with regulation and specifications formed with

    the aid of a helical spring fitted internally, with if necessary, the conduit warmed sufficiently for it to move without avoidable wall thinning of the out side of the bend.

    6.3 Joints between PVC conduit + fittings shall be made with suitable adhesive, but

    expansion couplings shall be installed where any length of conduit , inclusive of draw in boxes etc, exceeds five meters in length.

    6.4 Conduits in floors shall be routed and installed so as to avoid the fixings of floor

    standing equipment to be installed on the floor.

    6.5 The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm.

    6.6 Where conduits are left "open ended" prior to wiring they shall be protected by caps or

    plugs to prevent the ingress of building material.

    6.7 All conduits runs must be designed to permit wiring to be readily installed after the complete erection of the conduits through the available draw-in, accessory and luminary suspension boxes.

    6.8 Where surface mounted equipment (other than luminaries) is specified, all concealed

    conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.

    6.9 Where conduits pass through an external wall/roof the conduit box shall be fitted on the

    side and after wiring filled with an inert, permanently plastic compound having a high insulation value.

    6.11 Make provision in conduit and trunking, installation where building expansion joints are

    crossed or settlement is likely.

    6.12 Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.

    .

  • STATE OF KUWAIT KUWAIT UNIVERSITY

    ELECTRICAL METHOD STATEMENT

    TENDER NO.

    KU/KUCP/C0251/10-11

    Page 6 of 6

    7. Reference Documents 7.1 Approved Electrical Shop Drawings 7.2 Approved Material Submittals for PVC Conduits and Accessories 7.3 Approved QA/QC Installation and Test Plan

    7.4 Approved Material Inspection Report 7.5 Approved Safety Plan

    8. Safety

    8.1 All safety precautions shall be followed as per approved safety plan & procedure. Ensure all involved persons are aware of the same.

    8.2 Ensure that tradesman will keep their working places clean, tidy and free from

    rubbish.

    ------------------------ Procedure End----------------------