Upload
ocenkt
View
8.776
Download
41
Embed Size (px)
Citation preview
View Publication
• You have asked to view a publication
• When you have finished viewing, click on in the toolbar to return to this screen.
• Now choose one of the following options:
return topublicationslist
viewpublicationchosen
A survey of 40 office buildingswith long-span concrete floors
P.W. Matthew BE, MSc, MIE(Aust)
and D.F.H. Bennett BSc, MSc, CEng, MICE
FOREWORDThis publication was commissioned by the ReinforcedConcrete Council.
The Group was set up in 1988 to promote betterknowledge and understanding of reinforced concrete designand building technology.
Its members are Co-Steel Sheerness plc and Allied Steel& Wire, representing the major suppliers of reinforcing steelin the UK; and the British Cement Association, representingthe major manufacturers of Portland cement in the UK.
The authors of this publication are Peter Matthew, partnerwith consulting engineers Powell, Tolner & Associates andDavid Bennett, Senior Engineer in the Marketing Divisionof the British Cement Association.
ACKNOWLEDGEMENTSThe authors wish to thank the following organizations fortheir considerable help in providing the building data forthe survey:
Anthony Hunt/YRM PartnershipBeersBison LimitedBunyan Meyer & PartnersComposite Structures LimitedDGI International plcFerguson & McIlveenFrank Hodgson & AssociatesJames-Carrington and PartnersJan Bobrowski and PartnersOve Arup & PartnersPowell, Tolner & AssociatesSkidmore, Owings & MerrillWaterman PartnershipThanks are also due to Brian Dyer of Tower Associatesfor drafting the floor plans.
97.311First published 1990Reprinted 1994, 1995
ISBN 0 72101386 4
Price Group F
@ British Cement Association 1990
Published by the British Cement Association on behalf ofthe industry sponsors of the Reinforced Concrete Council.
British Cement AssociationTelford Avenue, CrowthorneBerks RG45 6YSTel (01344) 762676Fax (01344) 761214
All advice or information from the British Cement Association is intended for those who will evaluate the significance and limitations ofits contents and take responsibility for its use and application. No liability (including that for negligence] for any loss resulting from suchadvice or information is accepted. Readers should note that all BCA publications are subject to revision from time to time and should thereforeensure that they are in possession of the latest version.
CONTENTS
INTRODUCTION 2
NOTES ON SURVEY
DESIGN FEATURES OF SPECIAL INTEREST
CHOICE OF FLOOR SLAB DESIGN
Solid flat slabs
Ribbed slabs
Waffle slabs
One-way spanning solid slabs and beams
Precast slabs
Composite precast slabs
CONCLUSION
SURVEY DATA
Section 1:
Section 2:
Section 3:
Section 4:
Section 5:
Section 6:
Solid flat slabs
Reinforced - Buildings 1 to 7 8-14
Prestressed - Buildings 8 to 12 15-19
Ribbed slabsReinforced - Buildings 13 to 15
Prestressed - Buildings 16 to 22
Waffle slabs
Reinforced -Buildings 23 to 25 30-32
Prestressed - Buildings 26 to 28 33-35
One-way spanning solid slabsand beamsBuildings 29 to 33
Precast slabs
Buildings 34 to 36
Composite precast slabs
Buildings 37 to 40
2
3
4
6
7
20-22
23-29
36-40
41-43
44-47
INTRODUCTIONTraditional concrete designs for office building have beenassociated with either beam and slab or flat slab floors,typically with 6 to 7.5 m spans. Occasionally, longer-spanfloors have been designed using ribbed or waffleconstruction. In recent times, changes in the requirementsof end-users and in developers’ specifications have led tomore open-plan offices and larger floors. This hasincreased spans from 6 to 9 m, even to 15 m and more.
To verify the competitiveness of concrete long-spanfloors, a survey has been conducted of concrete-framedoffice buildings, the majority constructed in recent years.Forty buildings of in situ, precast and compositeconstruction with long spans have been surveyed. In eachcategory, examples were found of floors designed inreinforced and prestressed concrete to carry similar officefloor loadings.
For in situ structures, solid flat slabs and ribbed slabdesigns were common, with spans varying from 6 to 15 m.
A number of precast structures with long spans, someover 20 m, are reported, with composite in situ slabs actingwith precast ribs or other precast members.
NOTES ON SURVEYThe survey data are presented in the second part of thispublication, beginning on page 7. The information hasbeen arrangedfollows:
Section 1 -Section 2 -Section 3 -Section 4 -Section 5 -Section 6 -
according to structural floor types as
Solid flat slabsRibbed slabsWaffle slabsOne-way spanning solid slabs and beamsPrecast slabsComposite precast slabs
The structural information and quantities of materialfor each building surveyed are presented in tabular formand are accompanied by a typical floor plan and floorsection.
For each building studied, quantities of concrete,reinforcement and prestressing steel are expressed inunits/m2 of floor area. All quantities related to verticalcomponents, i.e. columns, walls, etc., have been excluded,thus the effect of storey height and number of storeys iseliminated.
The span/depth ratios given in the tables are based onthe maximum spans.
Notes on the design Code of Practice, concrete gradeand method of achieving frame stability have been addedto provide useful information on the design of thestructure.
The column headed ‘Design loads’ gives the floorloadings used in the structural design, i.e. imposed load,finishes, partition and service loads: it does not include theself-weight of the floor.
The method of achieving frame stability for eachbuilding is indicated in the column headed ‘Stability’ by‘shear walls’ or ‘frame action’. The term ‘shear walls’
(Figure 1) indicates a braced structure where the horizontalforces are transmitted to shear walls by the floors acting asdiaphragms. In the case of an unbraced structure [Figure 2),stability is provided from within the frame by theinteraction of columns and floors and referred to as ‘frameaction’.
All tables should be read in conjunction with thecorresponding floor plans and section details.
a Shear walls
Figure I: Lateral stability provided by shear walls.
Figure 2: Lateral stability provided by frame action.
2
DESIGN FEATURES
OF SPECIAL
INTERESTNotes on a few of the buildings surveyed are given below tohighlight certain construction and design features thatprovide particular economic advantages for a given floortY Pe.
Building 5310 mm reinforced solid flat slab, span 9.5 x 7-3 m.
Lightweight aggregate concrete with a compressivestrength of 30 N/mm2 was used in order to reduce theself-weight of the floor and the cost of the foundations.
As the span/depth ratio exceeded the guiding limits inthe Code (CPllO), compliance with maximum deflectionin the serviceability limit state was proved by calculation.The floor slab was designed as a beam supporting aone-way spanning flat slab, all within the 310 mm depth ofconstruction. The beam, 2.5 m wide, spans longitudinallyfrom the interior column to the lift core. The one-wayspanning slab is simply supported at the perimeter andcontinuous over the beam.
Building 7255 mm reinforced solid flat slab, span 9.2 x 6-0 m.
The deflection of the 255 mm flat slab was checked byfinite element analysis, taking full account of edgestiffening from the perimeter columns and beams inaddition to the internal columns and frame. A lateralstability check was carried out on a three-dimensionalcomputer model of the structure. The inherent stiffness ofthe perimeter beams and columns plus the internal frameeliminated the need for shear walls.
Building 10300 mm post-tensioned solid flat slab, span 9.4 x 9.0 m.
Steel cross-bracing, in combination with the floor slabacting as a diaphragm, provided the lateral stability. Droppanels were eliminated by forming shearheads within theslab depth (Figure 3). All external columns were connectedto steel beams, composite with the slab, to cater forpunching shear.
Building 13450 mm reinforced ribbed slab, span 9.0 m.
The wide-rib profile, spaced at 1.5 m centres, providesadequate flexibility to accommodate small and largeservice openings in the floor. The rib profile made itpossible to use table forms with integral grp rib moulds toensure a fast building programme (Figure 4).
Building 14425 mm reinforced ribbed slab, span 9.0 m.
The irregular floor plan of the building and the client’srequirement for minimum column sizes resulted in it beinginappropriate to provide stability by frame action. Shearwalls, with no returns and a minimum of cross walls, werespecified to facilitate rapid construction of walls.
Overall to suit column sizec
650J--rr
-A-Plan
Section
Figure 3: Detail of steel shearhead.
Figure 4: Grp rib moulds fixed to table forms.
3
Building 26500 mm prestressed/reinforcement waffle slab,span 12.0 X 12-O m.
The solid beam strips were post-tensioned, with the wafflesection reinforced. This allowed the waffle section to bereinforced independently of the beams, thus speeding upconstruction, whilst maintaining an economical floordepth.
Building 31335 mm one-way spanning prestressed solid slab,span 12.6 m.
The frame was designed as a stacked portal, with 160 mmprecast per imeter wal ls support ing a 335 mmpost-tensioned solid slab. An important benefit inpost-tensioning the slab was that the end momentstransferred to the precast walls, due to dead load, werenegligible. This in turn led to manageable transfermoments in the wall under ultimate load conditions.
The structural solution proved both economic and fastto build, with a maximum net to gross floor area.
Building 36200 mm precast floor slab, span 7.7 m.
The precast columns were designed as vertical cantilevers
CHOICE OF FLOOR
fixed at the base to provide frame stability. The precast l
floor beams were simply supported and designed as pinjoint connections to the columns.
Building 370
560 mm double-T floor units with in situ topping,span 14.5 m. 0Stability was achieved by a combination of shear walls atthe ends of the building and frame action developed fromthe precast perimeter H frames. The H sections are formedby adjacent perimeter columns and the perimeter edgebeam (Figure 5a). The precast column joints are positionedat mid-storey height, i.e. the point of contra-flexure, so afull moment connection to the double-T floor beam waspossible (Figure 5b). The precast frame was erected in just
The need for long spans to provide floor spaceuninterrupted by cores and columns.
A maximum floor-to-floor height which allowsadequate space for services and ducts, balanced againstplanning pressure to limit overall building height.
An adaptable floor structure which can accommodatefuture tenant alterations with maximum speed andminimum disruption.
The wide range of floor construction in bothreinforced and prestressed concrete, highlighted in thissurvey, demonstrates that concrete floors can be designedeconomically to meet these requirements.
The types of floors and the reasons for choosing them
SLAB DESIGNIn assessing the structural cost of a multi-storey building, itis evident that the bulk of the cost is often for the floor slabconstruction. Therefore, the overall economy of a structuremay depend on the efficiency and economy of the floorslab’ system. While quantities of materials reflect theefficiency of the design and structural layout, the actualcost of the structure may also depend on such factors asspeed of construction, local market conditions,competitive tendering, availability of labour andequipment and cost of construction finance. Consequentlya structural design that has proved to be competitive in oneregion may not always be competitive in another.
For a building to meet the needs of major financialoccupiers in today’s market, the choice of floor design isoften determined by one or more of the followingconsiderations:
under ten weeks. are given opposite.
2400 4800 2400I/ I/-I I II I4,
(a) Elevation (b) Section
Figure 5: Detail of precast H frame.
4
Solid flat slabs (with or withoutdrops)The principal feature of the dropless floor is its flush soffitwhich requires only simple formwork and is easy toconstruct (Figure 6a). The overall depth of this floor is aminimum and it allows great flexibility for locatinghorizontal services. However, the economical span rangeof a reinforced floor is limited by shear in the vicinity of thecolumn supports and the need to control long-termdeflection.
The provision of drop panels at the column supports(Figure 6b) avoids the need for shear reinforcement andincreases the stiffness of the slab and the economical spanrange. Alternatively, a structural steel shearhead can beincorporated to maintain a flush soffit to allow for easyconstruction and efficient use of large forming systems(Figure 6c).
Ribbed slabsProviding ribs to the soffit of the floor slab can reduce thequantity of concrete and reinforcement, and thus theweight of the floor. The deeper, stiffer floor permits longer
spans to be used. Formwork complexity can be minimizedby the use of standard modular, re-usable formwork. Whenflying form panels are used, the ribs should be positionedaway from the column lines. Ribbed slab floors are veryadaptable for accommodating a range of service openings(Figure 7).
Waffle slabsWaffle slab floors are commonly used when buildings aresubjected to heavy imposed loading. They are veryefficient in the use of materials and provide veryeconomical long spans, but the additional complexity offormwork can often slow the construction. Where speed ofconstruction is critical, a ribbed slab or a shallow beamsolution is often preferred.
One-way spanning solid slabsand beamsA wide, shallow beam profile is often preferred in order toreduce the overall depth of the floor, whilst permittinglonger spans. The one-way spanning solid slab betweenthe beams facilitates the use of table forms for fastconstruction (Figure 8).
(b)
Figure 6: Solid flat slab: (a) without drop panels;(b) with drop panels; (c) with shearhead.
1-2-1:::1r-1 I-- “~~-~~-l'-' '-::-~J--,:-;:-: :-,r-
Figure 7: Ribbed slab for flexibility to accommodate openings.
Figure 8: Band beam and slab construction using tableforms.
5
Precast slabs Composite precast slabsComposite precast slabs combine precast floor elementswith in situ concrete in an economical way, eliminatingtraditional formwork for floor construction, and providinglong-span floors. Thin precast concrete floor plates can becombined with an in situ topping to form compositeone-way spanning floors up to 6 m long, or, in combinationwith precast beams, to form a composite ribbed slab(Figure lOa). For extremely long spans, double-T precastbeams and a composite in situ topping is preferred(Figure 10b).
Precast slabs offer the advantage of off-site manufacture,with a reduction in site labour and site formwork. Whenthe slabs are prestressed there are additional benefits oflonger spans and higher load capacity. A popular type ofprecast floor is the hollow core slab (Figure 9). Therelatively lightweight units form a flush soffit whenplaced. A shear key between units ensures load sharingand the construction is commonly capable of developingdiaphragm action without the need for a structuraltopping. The precast units are easy to remove and canaccommodate a wide range of floor openings.
Figure 9: Precast hollow core planks:flexibility for alterations.
CONCLUSIONThe buildings surveyed in this publication demonstratethat reinforced and prestressed concrete floors with spansranging from 6 to 20 m, are technically feasible andeconomically competitive.
This is a direct consequence of improved design andanalysis techniques, higher strength materials, betterconstruction methods and finally, more construction-leddesign.
Figure IO: Composite floors: (a) precast ribbed floor;(b) double-T beam floor.
6
SURVEY DATA
Section 1: Solid flat slabs
Reinforced - Buildings 1 to 7
Prestressed - Buildings 8 to 12
Section 2: Ribbed slabsReinforced -Buildings 13 to 15
Prestressed -Buildings 16 to 22
Section 3: Waffle slabsReinforced -Buildings 23 to 25
Prestressed - Buildings 26 to 28
Section 4: One-way spanning solid slabs and beams
Buildings 29 to 33
Section 5: Precast slabsBuildings 34 to 36
Section 6: Composite precast slabsBuildings 37 to 40
7
SECTION 1SOLID FLAT SLABS
Solid flat slab -reinforced
m m m ratio 1 m3 1 kg 1I I I I I I
2 7.2x7.2 300 24 0.30 30.0 6-O ’ r ~~~~ ’ GradeC40Frameaction Code BS 8110
Jr 3600 Ji 3600 1" 7200 'i 3600 1" 3600 I
7-J
7-_I
-
n
n
300 slab
I-
n
8
Solid flat slab -reinforced
No. Slab Materials per m2of floor area Design
of l o a d Notesfloors Span Depth Span/depth Conc;ete Rebar kN/,,$
Stability
m m m ratio kg
10 7.5x6.1 3 0 0 25 0.30 45.0 6-O Shear Grade C35walls Code BS 8110
300 slab
I - I I I I I I
I
I
I
I
8
I
I
I
I
Typical floor plan
A
9
Solid flat slab -reinforced
82E
mi1
I
3000A
i
5 i(J 7500 3000
n
400 slab
n
1 / _L
i
400 slab
Typical floor plan
10
Solid flat slab -reinforced
No.of -
Spanfloors m
Slab Materials per m*of floor area Design
load NotesStabilityDepth Span/depth Conc;ete Rebar kN/,-,-,*
mm ratio kg
7 6 5 x 4 5 250 26 0.25 29.0 5 0 Shear Grade C35walls Code BS 8110
Typical floor plan
I
17 ccc 45 1̀
Solid flat slab -reinforced
No. Slab Materials per m*of floor area Design Notes
of load Stabilityfloors Span
mDepth Span/depth Conc;ete Rebar kNirn2 (See page 3)
m m ratio kg
4 9-5x 7.3 310 30.6 0.31 41.5 5.0 Shear C30 lightweightwalls Code CP 110
Typical floor plan
Solid flat slab -reinforced
No. Slab Materials per m2
o fof floor area Design
loadfloors Span
mDepth Span/depth Co;;ete Rebar kN/r-$
Stability Notes
mm ratio kg
13 8 0x7.2 275 29 0.28 40.7 5-o Shear Grade C35walls Code BS 81 10
5800 3 irr 7200 5800
275 slab
Typical floor plan
Solid flat slab -reinforced
-
I I I I I II I I I
7 9.2x6.0 255 36I I
0.26I I24.0 5.2
I I I I I I
StabilityNotes
(See page 3)
6200h 4
5 ((I 6000
255 slab
Typical floor plan
14
Solid flat slab - prestressed
No. Slab Materials per m2of floor area Design
of load Notesfloors Span Depth Span/depth Con$ete Rebar Strand kN/r-$
Stability
m mm ratio kg kg
2 8.0x8-0 275 29.1 0,275 10-2 4 8 10..0 Shear Grade C40walls Code BS 8110
Gl P
(”,.~- . .
Ii..tx x :* x x x x
I” m
Atrium
.‘j----
X
x
x
x
X
x
X
X
m m PI m m m m P1 JFirst-floor plan
0
Eico
0
Column head detail I I
15
Solid flat slab - prestressed
a 7.2x 7.2 240 30.0 0.240 2.4 4.7 6.5
Stability
Shearwalls
Notes
* See Concrete Society TechnIcal Reports No 17 and No 25
3 ((I 7200 4800
00cuP-
Typical floor plan
950
n
nc :i,
I /’ 240
$ 50i 250
Column head detail c ”475
Solid flat slab - prestressed
No.of
floors
SlabMaterials per m’
of floor area Designl o a d Stability Notes
Spanm
Depth Span/depth Conx$ete Rebar Strand kN/mzm m ratlo kg kg
(See page 3)
Grade C40Steel Code BS 8110
9 9 4x9 -o 300 31 3 0 300 14-l 78 50 bracing to CS TR 17 & 25*
columns Steel co lumns with shearheads
* See Concrete Society TechnIcal Reports No 17 and No 25
45000
P m B
I aI m
Typical floor plan Cross-bracing
17
Solid flat slab - prestressed
No SlabMaterials per m*
of floor area Designof load
floors Span Depth Span/depth Concrete Rebar Strand kN/mzm m m ratio m3 kg kg
7 11 5 x 7 5 325 35 4 O-325 11 1 6 5 5 0
See Concrete Society TechnIcal Reports No 17 and No 25
Stability Notes
Frame Grade C40
action Code BS8110CSTR 17&25*
Typical floor plan
8
Slab
Solid flat slab - prestressed
Stability Notes
7200 3600 7 2 0 0 2 4 0 0 7 2 0 0 3600 7200r c * *- II + * J
Typical floor plan
Typical column head detail
SECTION 2
RIBBED SLABSRibbed slab -reinforced
No. Rib Beam Materials per m*of floor area Des
of,__
floors Span Depth Span/depth Span B x D Span/depth Concrcm mm ratio m mm ratio m3
ignwad Stability
Notes
?te Rebar kN/m* (See page 3)
kg
10 9.0 450 20.0 8.0 1200 13.3 0.23 39.5 7.5 Frame Grade C35x 450 action Code BS 8110
7 ((1 9000
1 I
Typical floor plan
Typidal rib section Typical beam section
20
Ribbed slab - reinforced
Rib BeamMaterials per m2
No. of floor area f$$” Stability Notesof (See page 3)
floors Span Depth Span/depth Span B x D Span/depth ConcJete Rebar kN/m*m m m ratio m m m ratio kg
11 9.0 4 2 5 21 .l 9.0 1800x425
21.1 0.27 38.5 5.0Shear Grade C35walls Code BS 8110
1500_~~ __~125
9000 6750 4 @ 7500 6750 9000i 1
Typical floor plan
5 (u, 9000
L -t
‘T 1425 7I-I Il-l i
1800250
Typical rib section Typical beam section
:425
Ribbed slab - reinforced
No. Rib BeamMaterials per m2
of floor area Dri,n Stability
floors Span Depth Span/depthSpan B x D Span/depth Conc;ete Rc??r kN/mzm mm ratio m mm ratio
5 9.0 3 0 0 30.0 18007-2 x 4 0 0 18.0 0.32 29.0 5.0 Shear
walls
Notes
Grade C35Code BS 8110
6 ((I‘ 7200 9000 7200I i i
1800
Typical rib section Typical beam section
22
Ribbed slab - prestressed
No. Rib Beam Materials per m*Design
ofof floor area
l o a d Notesfloors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/&
Stability
m m m m m ratio m m m ratio kg kg
3 9.0 3 2 5 1200 27-71800
6.0 x 3 2 5 18-5 Pt’ 0 194 12 6 3.65 6.0 Frame Grade C35action Code BS 8110
‘Prestressed
Typical floor plan
Typical rib section ki!
100
325
23
Ribbed slab - prestressed
I INo.of
floors-I22
*Prestressed
Rib BeamMaterials per m*
of floor area Designload
Span Depth Spacing Span/depth Span B x D Span/depth Type Con;;ete Rebar Strand kN/t-$m m m m m ratio m m m ratio kg kg
9.0 2 5 0 750 36.0 22007.5 x 2 5 0 30.0 Pt’ 0.186 7 . 0 3 5.79 5.0
Stability
Shearwalls
Notes
Grade C40Code CP 110
10 @ 7500i
Typical floor plan
750
125
A - ,
-r - .250 250
2200
I-
s \
175
Typical rib section Column head detail
24
Ribbed slab - prestressed
NO. Rib BeamMaterials per m2
of floor area Designof load Stability Notes
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Con;;ete Rebar Strand kN/m*m m m m m ratio m m m ratio kg kg
8 9 . 8 4 0 0 725 24.5 1 9 4 1200 Shear Grade C40x 800 24.2 Pt” 0.354 16.9 9.76 6.0 walls Code CP 110
‘Prestressed
I. I. I. I. I13000 9350 9350 10000
Typical floor plan
725c 725 725P
75
Typical rib section
25
Ribbed slab - prestressed
No. Rib Beam Materials per m2Design
o fof floor area
load Notesfloors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/r-$
Stability
m m m m m ratio m m m ratio m3 kg kg
5 10.85 450 850 24.1 12.5 1500x 4 5 0
28.0 Pt* 0.280 8.3 6-63 5.0Shear Grade C40wallsL L Code CP 110
‘Prestressed
Typical floor plan
Typical section
Ribbed slab - prestressed
No. Rib BeamMaterials per m*
of floor area Designo f load Stability Notes
floor s Span Depth Spacing Span/depth Span B x D Span/depth Type Conc;ete Rebar Strand kN/m*m m m m m ratio m m m ratio kg kg
5 1 3 5 4 7 5 1500 28 4 9 . 0 1500x475
18.9 Pt* 0,285 15.0 4.93 6 0Shear walls Grade C40and frameaction Code BS 8110
l Prestressed
Iririr
I I I I I I I I I I I I I II II II II II II II II II II II II II II I I II I I II I I II II II II I
I II I I II II II I I II II II I I II I I II II I
I I I II II II I I II II II I I II I I II I I II I
L~LJLJL~LJLJLJLJLJLJLJLJLJL.~L.-
w n n Iriririr~r~rlrlr~r~r~r~r~r~r~r~,
/’/ Iu I I I II II II II II II I I I I II II II II I I I I II II II I
I I /I II I I II II I I II II II II II II II II II II II I/ I/
I I II II II II II II II II II II II II 11 II II II I’ II IL~L~L~L~L~L~L~L~L~L~~~~~~~~~~~~~~~~~,~~r-i r iririr~r-lr~r~r~r1rlrlrlr~r~r~r~rlrlI II II I
L J
nr -1I ILA
II II III II III II I
-JLJLJ
-1rir-iII II I
_ _J L A L A
I II II II II II II II II II II II II II II II II II I
LJLJLJL-ILJLJ
nr IririririrlI II II II II II ILJLJLJLJLALJ
I II II II II II II II II II II II II II II II II II II II II II II II II II II I
LJL~ILJLJLJLJLJLJLJ
n n Iriririririr - ll~-lrlrlI II II II II II II II II ILJLJLJLJLJLJLJLJL.~J
Typical floor plan
1500
125
I108I”
‘r 1500 1
Typical beam section Typical rib section
1, J:425
27
Ribbed slab - prestressed
No. Rib Beam Materials per m2of floor area Design
of load Notesfloors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/m2
Stability
m m m m m ratio m m m ratio kg kg
5 14.4 650 2400 22.2 12007.2 x 6 5 0 11 .0 R.C.* 0,268 1 4 . 7 4 . 3 3 7.0 Shear Grade C40
walls Code BS 8110
“Reinforced
0B- 8 @ 7200
f 1
:jl n n E n I7 11 r7 fl II11 II II II I i II II II II II II
I II II III II II II
I II II ll II II
I II II iI II II
I II II iI II II
I II : I II II I ;I II II ll II II
H H H H H J u u u I4 M
““““““/- u .-IL Al- u -IL ii- il -IL II_ L L -IL I I - I I AIL u lb
Typical floor plan
2400
Typical section 500
28
Ribbed slab - prestressed
No. Rib BeamMaterials per m’
of floor area Designof load Stability Notes
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/m’m mm mm ratio m m m ratio kg kg
4 16.3 525 850 31 .0 6.3275
X1000 6.3 R.C.* 0.225 9.8 5.66 6.0 Shear Grade C40walls Code CP 110
i7 @ 6300_
t
Typical floor plan
I850 8 5 0 850%
i100
Typical section
‘Reinforced
29
SECTION 3
WAFFLE SLABS Waffle slab - reinforced
No. ColumnMaterials per m*
of floor area Designof spacing Depth Span/depth l o a d Stability Notes
floors m mm ratio Con-v$ete Rebar Strand kN/m2kg kg
5 6.6 X 7.43 350 21.2 0.245 24.0 - 6-O Frame Grade C35action Code BS 8110
5835 7425 3 @ 4950
I ---*
Typical floor plan
Ribs at 900 crs
!125
4;7I
1600
Section at column head
3 0
Waffle slab - reinforced
No. ColumnMaterials per m2
of floor area Designof spacing Depth Span/depth load Stability Notes
floors m mm ratio Con;;ete Rebar Strand kN/m2kg kg
3 7.5x10 5 525 20.0 0.450 67.0 - 6-O Frame Grade C35action Code BS 8110
, 7500 typical ,
Typical floor plan
Typical section
31
Waffle slab - reinforced
No. ColumnMaterials per m*
Depth Span/depth _ of floor area Designof spacing
ratioload Stability Notes
floors m mm Conc;ete Rebar Strand kN/m2kg kg
3 10.18x10.18 550 18-5 0.396 37.0 - 9.0 Shear Grade C35
walls Code BS 8110
kTypical floor plan
3 @ 10180
Typical section125 14
32
Waffle slab - prestressed
Materials per m2No. Column of floor area Designof spacing Depth Span/depth
ratioload Stability
Notes
floors m mm Compete Rebar Strand kN/m2(See page 4)
kg kg
1 12.0x12.0 500 24.0 0.349 15.9 2.52 6.0Shear Grade C40walls Code BS 6110
4 @ ’ 12000 6000
q CIOOOOOOOrlnnnnnnrin
Typical floor plan
125Typical section
33
Waffle slab - prestressed
No. ColumnMaterials per m*
Depth Span/depth of floor area Designof spacing
ratioload Stability Notes
floors m mm Cor?$ete Rebar Strand kN/m*kg kg
2 12.7x12.7 500 25.4 0.341 12.2 5.60 6.0 Shear Grade C35walls Code BS 8110
12700*
Typical floor plan
Typical section
Waffle slab - prestressed
Stability Notes
~c~~~Grade C40Code BS 8110CS TR No. 17*
*See Concrete Society Technical Report No 17
5 @ 15000
1 1
,;:j; ji ‘: :’ ‘: ‘_-:::~:: ::p::-::-:,
;.:I. :’ ij :
‘-7..:.::. .I! j: :: :::.:1 :.
: li .::
a :,: .;_;; 1_~1;.1;.1;:1:.:1~1!_.
~.. :.~:.~::~’
. -. ..-.:.::..:..:.::.:: ::..LL: ‘:~::..l‘i‘: .::. ~.i[:lI::~::z..
: :I.. i., .iilii::.!:~:.~I:.::.::.::.:!.:L.:: !
:-:“:.::‘I:.‘,~ . . . . .
.~..~_. ,..,: ., !L :
Atrium
: :: ::r:: :: :: ‘: :, :__,: ::~:: ::=:: ::-::-::.:,Lo:! !! :, ,, ,! ,I ,I ., ,,
.-..-. . . ..i.:
Typical floor plan
Typical section 225
35
SECTION 4
ONE-WAY SPANNINGSOLID SLABS & BEAMS
One-way spanningsolid slab and beam
No. Slab Beam Materials per m2of floor area Design
of . loadfloors Span Depth Span/depth Type Span B x D Span/depth Type Concrete Rebar Strand kN/+’
Stability Notes
m m m ratio m m m ratio m3 kg kg
4 7 . 4 3 2 0 0 37.2 Pt* 9.0 1 5 0 0x 500 18.0 Pt* 0.261 1 4 . 0 4.11 4.0
Shear Grade C35walls Code BS 8110
‘Prestressed
Typical floor plan
Typical beam section
3 6
One-way spanningsolid slab and beam
No. Slab BeamMaterials per m2
of floor area Designo f load Stability Notes
floors Span Depth Span/depth Type Span BxD Span/depth Type Conc;ete Rebar Strand kN/m*m m m ratio m m m ratlo kg kg
6 10.30 250 41.2 Pt* 15006.0 x 4 5 0 13.3 R.C.+ 0.298 13.9 3.93 6.8 Shear Grade C30
walls Code CP 110t‘Prestressed + ReInforced
250 slab
Typical floor plan
Typical beam section
37
One-way spanningsolid slab and beam
No. Slab Beam Materials per m2of floor area Design
of load StabilityNotes
floors Span Depth Span/depth Type Span BxD Span/depth Type Concrete Rebar Strand kN/m2(See page 4)
m m m ratio m mm ratio m3 kg kg
7 12.6 3 3 5 37.6 Pt* Precast perimeter wall support 0 335 11.8 8.25 6.8 Shear C40 lightweightwalls Code BS 8110
‘Prestressed
335 slab
Typical floor plan
38
One-way spanningsolid slab and beam
No. Slab Beam Materials pe r m2of floor area Design
of load Stability Notesfloors Span Depth Span/dept Tyee Spnn B xD Span/depth Type Conc;et e %??r StFgn d kN/m2
m m m ratio m m m ratio
10 6 75 220 30 7600xR.C.* 10 0 6oo 16.7 R.C.* 0.26 42-O - 5 0 Shear C40 lightweight
walls Code CP 110
*ReInforced
Typical floor plan
Main beam section
E0
39
One-way spanningsolid slab and beam
No. Slab Beam Materials per m2
ofof floor area Design
load Notesfloors Span Depth Span/depth Type Span B x D Span/depth Type Con-$ete Rebar Strand kN/&
Stability
m mm ratio m mm ratio kg kg
5 6.0 175 34.3 1500R.C.* 9.0 x425 21.2 R.C.* 0.25 52.0 - 5.0 Shear Grade C40walls Code BS 8110
‘Reinforced
Typical floor plan
:425
Typical section
40
SECTION 5Precast slab
PRECAST SLABS
SlabMaterials per m2 of floor area
No. Beam Designof
Precast In situload Stability
floors Span Section Span/depth Span B x D Span/depth Conc;ete Rebar Strand Conc;ete Rebar kN/r-$m m m ratio m m m ratio kg kg kg
12 7.0 203 34.5 3006.0 x 6 0 0 10.0 0.145 4.8 40 0,011 0.4 7.0 Shear
walls
Notes
C50, BS 81107% in situHollow coreplanksNo topping
6 @ 6000
. 1
Typical floor plan
Precast “yqFy= :z300
Centre beam section
41
Precast slab
Materials per m’ of floor areaNo. Slab Beam
Precast In situ Designof load
floors Span Section Span/depth Span B xD Span/depth Concrete Rebar Strand Conc$ete Rebar kN/m2m mm ratio m mm ratio m3 kg kg kg
4 7.2 200 36.0 6007.2 x600
12.0 o-193 7.9 3.0 - - 7.0
I I I I I I I I I
Stability
Shear
Notes
Grade C50Code BS 8110Hollow coreplanksNo topping
7200 7200 5400 7200 7200 5400 7200 7200
1 1 1 1 1 1
Typical floor plan
Typical section
42
Precast slab
SlabMaterials per m2 of floor area
No. Beam - Designof
Precast In s i tuload Stability
Notes
floors Span Sectlon Span/depth Span B x D Span/depth Concrete Rebar Strand Con$ete Rebar kN/m* (See page 4)
m m m ratio m m m ratio m3 kg kg kg
Grade C50
3 7 7 200 38.5 7 . 4 3 ,$;o 1 2 . 4 0.157 10.5 2.55 - - 6.5 Frame Code BS 6110
action Hollow coreplanksNo topplng
Typical floor plan
Typical section
43
SECTION 6
COMPOSITEPRECAST SLABS
Composite precast slab
No. Rib Beam Materials per m2 of floor area
of . Precast In situ Designload Stability
Notes
floors Span Depth Span/depth Spanratio
Depth Span/depth Concrete Rebar Strand Concrete Rebar kN/m2 (See page 4)
m mm m mm ratio m3 kg kg m3 kg
500x Frame Grade C60Code CP 110
9 14.5 560 25.9 4.8 1000 4.8 0.150 5.75 6.3 0.080 2.2 5.0(Perimeter)
any$$ar Double Tees, wrth
wallsIn situ toppingPrecast H frame
4800 typical
14500. I
Typical floor plan
I
47600
1200i , In situ t o p ping
-/
Typical section Precast double-T beams
44
Composite precast slab
Rib BeamMaterials per m” o
No. Precast In situ
f10 2 Span
load Stability NotesDepth Span/depth Span
m mm ratio mDepth Span/depth Con;;ete Rebar Strand Conc;ete Rebar kN/m’
mm ratio kg kg kg
Grade C60600x Code CP 110
4 16.7 785 22.0 4.9 900 5.4 0,133 5 - 4 8 7 . 7 9 0,075 1.54 5.0 Frame Double Tees, with(Perimeter) action in situ topping
Precast H frame
2438 9 @ 4877 2438‘i * 8 J
? ~f?~+kPl-rr~P~~~n’n-n n~n’n~n~n-n’n~~n~~n~nLr~~n111141ild 1’1111Vfb111 1) 11 II II I I II II II II II II II II II II II I I I I II II II II I I II II I I I I I I I I II II II II II II II I I I I III
‘II II III I II III
‘I I II IIII II IllII II lib
‘II II IIz ‘II II Ii
II II III
co ‘II II II II I I III
Il l II IIII II III
‘I I II IIII II IIP
‘II II IIII II III
‘II II III I II III
‘II II II II II II II II II II II II II II II I I I I II I I II II I I II II II I I II I I I I II I I II II II II II II I I II III
i - + tit - c b !, L km c hL c Lu,u--u-uLu~ u -u~u-u,u-u-uLu, u u 4 Ad 4 u Am11 4 4 44 -IF
Typical floor plan
1200
/’In situ topping
75 (average) 1
j-=-f ;710
Precast double-T beams
Typical section
Composite precast slab
No. Rib Beam Materials per m2 of floor area
ofPrecast In situ Design
floors Span Depth Span/depth Span. load
m mm ratioDepth Span/depth Concrete Rebar Strand Concrete Rebar kN/m*
m mm ratio m3 kg kg m3 kg
750x6 / 12.0 1 610 / 19.7 j 9.0 1 ,in”;FU, 1 14.8 1 0.134 (13,751 - 1 0.111 110 721 5.7
Stability Notes
In situ C35Frame Precast C45action Code BS 8110
55% In situ
I II II II II II I
r ir’ir’ir i r ’ i r ’ i r ir’ir ir ir’ir’ir irwirlir irII II II II II II II II II II II II II II II II II
I II II II II II II II II II II II II II II II II II
I II II II II II Ii II II II II II II II II II II II II II II II II II II II II II II II II II II II’
Typical floor plan
55 precast soffit plankPrecast rib
Typical rib section Typical in situ beam section
46
Composite precast slab
No. Beam Materials per m2 of floor area
o fPrecast In situ Design
load Notesfloors Span Depth Span/depth Concrete Aebar Strand Concrete Rebar kN/m’
Stability
m m m ratio m3 kg kg m3 kg
Grade C62
3 21.2 750Precast 28.3 0,123 4.9 7.6 0.060 2-28 5 .0 Shear Codes CP 115,
walls CP 11640% In situ
72000
c 1
, _~n-=-rt-~n-“-~-un~~~~nn~~~“~h~~n~n~n~~~~~nnnunu~~~=-n~~n~~~~,, ,, II Ii II I I I II II I I I I I II 11 II II II II il II II II II I I’ II II II ‘I II II II II II II ‘I II II II II I, II II II II II ,, ,,
‘1, I I 11 I I tII II
‘II IIII llr
11, IIII ‘I ~:I~_:~ ” I’ II II ‘I Nt ~~ ‘I ” I’ I’ II :! Id
8 II II I I II II lli:cv AlI II
!I, III I II I I II
i;II II!
‘I, I! R#~~11 II- 11~;I I
v ;~I I IIL
JIl IIII ,I Ii II IlL
II IILII II II IILII II II II II II II 1: 1: I’ II I’ I! I’ II II II II II II II II II II II II II II II II II !I II II II II II II II II II II II II II II II II
vYv-Y~~Y~4_yu~~~L-L_-v~y~.~_yu_u_y-y-y _ y--y-y4~-y~y-&icy~~ 4 y u y~y-y~y--y~yy-yy
Typical floor plan
Beams @ 1500 crs.
Precast soffit planks
Precast beam
Typical section
Economic long-span concrete floors
P.W. Matthew and D.F.H. Bennett
BRITISH CEMENT ASSOCIATION PUBLICATION 9 7.3 11
CI/SfB
I (13) I q4 I (Y6)
U D C
624.073.012.4.003.1