25
Jakeer Mohammad Network Rail West side Offices Euston Road Kings cross N1C 4AP Tel: 02079 224922 07709 483135 Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrall.co.uk Rev 4 Method Statement Cover Sheet CONTRACTORS METHOD STATEMENT Method Statements will require a minimum of 10 days for review and comment. For works undertaken in a possession or where an associated Form -F002/F003- for temporary works is required 20 days should be allowed. A Method statement ACCEPTED BY Network Rail must be in place 10 days prior to work commencing on site. Project Title: Kings Cross Central Building S1 Contractor: Ramboll UK Method Statement Number: 33235.KXC.S1.ConditionSurvey.Ramboll.G.RAMS. As part of the works associated with the above Contract we wish to inform you that we propose to carry out the following operations of work, which may affect the operations of the Railway Activity: Condition survey of Network Rail Canal Tunnel Proposed Start Date: 30/07/16 Approximate Duration: 1 Night Shift Description of Works: Supervised condition survey of a relevant section of the Network Rail Canal Tunnel. Prepared by (Contractor) Sutharshan Sukumaran Geotechnical Engineer 21/11/17 Name Signature Designation Date Checked By (Contractor) Max Elliott Senior Engineer 21/11/17 Name Signature Designation Date Approved By (CRE Construction / Principal Contractor Representative) Richard Miller Director 21/11/17 Name Signature Designation Date Project Ref:PP2226/Lon

Method Statement Cover Sheet CONTRACTORS METHOD STATEMENT 35/Co… · NETWORK RAIL CANAL TUNNELS BUILDING S1 RISK ASSESSMENT & METHOD STATEMENT FOR THE CONDITION SURVEYS \\ukramlonfiler01\projects\61033235-003\Analysis\04_Geotechnics\Condition

Embed Size (px)

Citation preview

Jakeer Mohammad

Network Rail

West side Offices

Euston Road

Kings cross

N1C 4AP

Tel: 02079 224922

07709 483135

Network Rail Infrastructure Limited

Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN

Registered in England and Wales No. 2904587

www.networkrall.co.uk

Rev 4

Method Statement Cover Sheet

CONTRACTORS METHOD STATEMENT Method Statements will require a minimum of 10 days for review and comment. For works undertaken in a possession or where an associated Form -F002/F003- for temporary works is required 20 days should be allowed. A Method statement ACCEPTED BY Network Rail must be in place 10 days prior to work commencing on site. Project Title: King’s Cross Central Building S1 Contractor: Ramboll UK Method Statement Number: 33235.KXC.S1.ConditionSurvey.Ramboll.G.RAMS. As part of the works associated with the above Contract we wish to inform you that we propose to carry out the following operations of work, which may affect the operations of the Railway

Activity: Condition survey of Network Rail Canal Tunnel Proposed Start Date: 30/07/16 Approximate Duration: 1 Night Shift Description of Works: Supervised condition survey of a relevant section of the Network Rail

Canal Tunnel.

Prepared by (Contractor) Sutharshan Sukumaran

Geotechnical Engineer 21/11/17

Name Signature Designation Date

Checked By (Contractor) Max Elliott

Senior Engineer 21/11/17

Name Signature Designation Date

Approved By (CRE Construction / Principal Contractor Representative) Richard Miller Director 21/11/17

Name Signature Designation Date

Project Ref:PP2226/Lon

Intended for

Network Rail

Document type

Risk Assessment Method Statement

Date

November 2017

Job No

33235

NETWORK RAIL CANAL

TUNNELS

BUILDING S1 RISK ASSESSMENT & METHOD

STATEMENT FOR THE

CONDITION SURVEYS

NETWORK RAIL CANAL TUNNELS

BUILDING S1 RISK ASSESSMENT & METHOD

STATEMENT FOR THE CONDITION SURVEYS

\\ukramlonfiler01\projects\61033235-003\Analysis\04_Geotechnics\Condition Surveys\Pre-

works\33235.KXC.S1.Condition Survey.Ramboll.G.RAMS..docx

Ramboll

240 Blackfriars Road

London

SE1 8NW

United Kingdom

T +44 (0)20 7631 5291

www.ramboll.co.uk

Revision 001

Date 21/11/2017

Made by Sutharshan Sukumaran

_________________

Checked

by

Max Elliott

_________________

Approved

by

Richard Miller

_________________

Description RAMS

Ref 33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

BuIlding S1 RISK ASSESSMENT & METHOD STATEMENT FOR THE CONDITION SURVEYS

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

CONTENTS

1. SCOPE 1 2. METHODOLOGY 1 2.1 Pre-Works Condition Survey 1 2.2 Condition Survey during construction works 1 2.3 Post-Condition Survey 2 3. LABOUR FORCE & TRAINING 2 3.1 Personnel Contact Details 2 3.1.1 Ramboll Representatives & Staff 2 3.1.2 Network Rail Project Manager 2 3.1.3 Argent 2 3.2 Generic Training 2 4. PLANT, EQUIPMENT & TOOLS 3 5. HEALTH & SAFETY 3 6. EMERGENCY ARRANGEMENTS & CONTACTS 3 6.1 Emergency Arrangements 3 6.2 Emergency Contact 4 6.2.1 Network Rail Canal Tunnel Project Manager: 4 6.2.2 Ramboll Contact: 4 7. OTHER ARRANGEMENTS 4 7.1 Welfare Arrangements 4 7.2 Fire 4 7.3 Meeting Point 5 7.4 Programme of activities for the surveys: 5 8. RISK ASSESSMENT 5

APPENDICES

Appendix 1 Network Rail– Canal TUnnels Security and Access information pack

Appendix 2 Location of Buidling S1 in relation to the Canal Tunnels

1

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

1. SCOPE

As defined within the Form B the proposed development of Building S1, at King’s Cross Central,

has the potential to cause movement of the two Thameslink Canal Tunnels. For this reason it is

be necessary to carry out condition surveys before, once during construction (following piling)

and after the development is complete.

The location of Building S1 in relation to the tunnels is presented within Appendix 2.

The condition surveys will be undertaken in a 100m section of the northbound and southbound

tunnels below the S1 site. This is the maximum length covered by the calculated zone of

influence of the development proposal. The condition survey will be a walkthrough visual, non-

intrusive inspection of the tunnel, generally noting any defects and notable features and it is

expected that each survey can be completed in a single night shift with a minimum of 4no

personnel.

The location of the survey shall be related to the length of tunnel which has rail monitoring

installed by TPS. It is expected that chainage or tablet markers will not be available in all the

tunnels. This will be double checked within the tunnel by using a measuring wheel and chalk will

be used to mark out temporary markers at intervals along the sidewalls.

2. METHODOLOGY

2.1 Pre-Works Condition Survey

The Pre-works Condition Survey will be a visual, non-intrusive inspection, providing a detailed

record of the condition of the tunnel at the time of inspection. Subject to the time available within

the tunnels, this will also include a 360 degree photographic survey. The personnel shall carry

out the work on foot bearing cameras and notepads. The 360 degree GoPro camera will be

mounted on a tripod of an approximate 2.5 meter height. Each significant defect will be noted,

measured where possible, photographed and referenced on survey sheets. The survey will be

concerned with the condition of the following:

The structural concrete segments forming the tunnel structure

The interfaces between the concrete segments

Any potential water ingress

A visual examination of defects will be carried out for all accessible areas. Inspection of the

tunnel arches and soffit will be carried out on foot as no high level access is to be provided. An

appropriate source of lighting will be carried by the personnel.

2.2 Condition Survey during construction works

The Condition Survey during the construction works will be carried out in the same manner as

the Pre-works Condition Survey described in Section 2.1. This survey shall provide a detailed

2

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

record of the condition of the tunnel following the piling works. It shall identify all defects and

shall highlight any alteration to the condition of the tunnel as described by the Pre-Condition

Survey.

2.3 Post-Condition Survey

The Post-Condition Survey will also be carried out in the same manner as the Pre-Condition

Survey described in Section 2.1. This survey shall provide a detailed record of the condition of

the tunnel following the construction works. It shall identify all defects and shall highlight any

alteration to the condition of the tunnel as described by the Pre-Condition Survey.

3. LABOUR FORCE & TRAINING

3.1 Personnel Contact Details

3.1.1 Ramboll Representatives & Staff

Name: Sutharshan Sukumaran

Email: [email protected]

Telephone: 07929 050 125

Name: Sagar Sheth

Email: [email protected]

Telephone: 07929 046 655

Name: Richard Miller

Email: [email protected]

Telephone: 07501 464 415

Name: Max Elliott

Email: [email protected]

Telephone: 07929050125

Name: Kevin Hares

Email: [email protected]

Telephone: 079 2903 4283

3.1.2 Network Rail Project Manager

Name: David Smith

Email: [email protected]

Telephone: 07824410015

3.1.3 Argent

Name: Tom Callaway

Email: [email protected]

3.2 Generic Training

Confined space training is not mandatory for staff surveying the main network rail Canal Tunnel.

The “Network Rail Canal Tunnels Security and Access Pack” will be read and by all staff

undertaking the survey. A site specific pre-shift briefing will take place for all personnel on the

day prior to entry into the tunnel.

3

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

4. PLANT, EQUIPMENT & TOOLS

The nature of the works will be a visual inspection of the tunnel lining only. No intrusive works

are proposed.

Table 4-1: Survey Equipment Required

Type Quantity Model Plant Approval No. Power Source

Light Source As necessary NA NA Battery

Camera + Flash As necessary NA NA Battery

360⁰ Go-Pro Equipment As necessary NA NA Battery

Non-conductive foldable ruler As necessary NA NA None

Non-conductive tape measures As necessary NA NA None

Measuring wheel As necessary NA NA None

5. HEALTH & SAFETY

All staff will work in accordance with the Company’s Health, Safety and Environment Policy and

Procedures. As a minimum, the following are mandatory articles of PPE required to undertake the

activities described within the method statement. PPE equipment must also match the

requirements of the asset holders who are in this case Network Rail.

Hard Hat to EN 397;

Hi Visibility vest/jacket BS EN 471: 2003 Class 2;

Hi Visibility Trousers BS EN 471: 2003 Class 1;

Safety Boots (with midsole protection) BS EN ISO 20345: 2004; and,

Gloves and protective eyewear

Ear defenders

In addition,

Operatives will attend a pre-shift briefing before the commencement of the condition survey

works.

Health & Safety documents, method statements, risk assessments, permits and passes will

be arranged and submitted for approval before site work commences.

A task briefing will be carried out at the commencement of each shift.

All operatives and staff shall be CSCS certified.

Welfare facilities to be provided by the asset manager.

Access routes into and around site will be assessed prior to works commencing.

First-aid kit will be made available by the asset manager.

All personnel shall conduct themselves in a courteous and professional manner. No playing of

radios, making of excessive noise or use of abusive/foul language shall take place.

6. EMERGENCY ARRANGEMENTS & CONTACTS

6.1 Emergency Arrangements

The immediate priority in the event of an emergency is to ensure the safety of all personnel, deal

appropriately with any casualties and make the area safe. Figure 6-1 presents a map of nearest

hospital with an Accident and Emergency Unit.

4

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

Figure 6-1: Location of nearest hospital in relation to site

University College London Hospital

235 Euston Rd, Fitzrovia, London NW1 2BU

Tel: 020 3456 7890

6.2 Emergency Contact

Any emergencies will be the responsibility of Network Rail. The details of the designated network

rail contact are provided below:

6.2.1 Network Rail Canal Tunnel Project Manager:

Name: David Smith

Email: [email protected]

Telephone: 07824410015

6.2.2 Ramboll Contact:

Name: Richard Miller

Email: [email protected]

Telephone: 07436269130

7. OTHER ARRANGEMENTS

7.1 Welfare Arrangements

Site welfare facilities are to be made available with the permission from a Network Rail

representative. No smoking is allowed on site.

7.2 Fire

There will be no hot works, therefore no special fire precautions will be required. Procedures for

fire exit will be explained during the pre-shift briefing.

SITE LOCATION

A&E UNIT

5

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

7.3 Meeting Point

The meeting point will be at a designated point in Kings Cross St Pancreas Station. All personnel

shall meet the designated Site Supervisor at this location prior to progressing to the site access

entry point with the tunnel escort and contact.

7.4 Programme of activities for the surveys:

Meet at meeting point as given in Section 7.3;

A pre-shift briefing will be provided by the Duty ODM before the party enters the tunnel;

The party entering the tunnel will have to call the Network Rail Duty ODM before and after

leaving the tunnel.

The party will also contact the Kings Cross St Pancreas station Site Shift Manager (SSM) to

gain access to the tunnel through the station platform.

All persons entering the tunnel will sign-in with the Network Rail Duty ODM before entering

the tunnels;

Walk to the start of the condition survey extents;

Commence survey noting all significant items as the surveyor proceeds;

Photographs of significant items should be taken and referenced into the surveyor’s notes;

Once the survey is completed, return to the original entrance point;

All personnel will sign-out with the Network Rail Duty ODM when leaving the tunnel; and,

Sign-out at the meeting point as per the mentioned location in Section 7.3.

8. RISK ASSESSMENT

This risk assessment covers the activities to be carried out on site. The risk assessment has been

carried out by evaluating risks with regards to Probability x Outcome. ‘Probability’ is defined as

the likelihood of injury or damage and ‘Outcome’ is defined as severity of injury or damage.

Probability and Outcome are assessed on a 5 point ascending scale. The risks are then calculated

as follows:

0 – 5 Low Risk

6 – 10 Moderate Risk

11 – 15 High Risk

16 – 25 Very High Risk

6

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

No Activity Hazard Consequence Who is at

risk

Degree of risk Controls Residual risk

O P R HML O P R HML

1 Access to

site

Vermin

contaminated

water

Slips, trips,

falls

Fatality,

illness, injury

Site

personnel 5 3 15 H

Call and check in with the Network Rail

ODM

Read, sign & adhere to “Network Rail

Thameslink Information Pack –

Security and Access Arrangements at

Canal Tunnels Rev 6”

All personnel shall report to the

supervisor, sign-in, attend a

mandatory pre-shift briefing and

obtain a permit to enter the tunnel.

Avoid contact with pigeon detritus,

standing water.

Wash hands on completion of work.

No eating, drinking or smoking when

on site before washing hands.

Cover cuts with waterproof plasters.

Appropriate PPE to be worn.

Care to be taken when walking along

the tunnels.

Adequate lighting will be carried by all

staff.

Safety footwear with ankle support, hi-

vis clothing.

5 1 5 L

7

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

No Activity Hazard Consequence Who is

at risk

Degree of risk Controls Residual risk

O P R HML O P R HML

2

Working in

areas with

limited

lighting

Slips, trips

or falls Injury

Site

personnel 4 2 8 H

All site personnel to carry a high

powered personal torch 4 1 4 L

3 Driving to

site.

Road Traffic

Accidents as

a result of

driving

during anti-

social hours

and falling

asleep whilst

driving.

Fatality,

Injury

Site

personnel

General

Public

5 3 15 H

Breaks to be taken during driving for

journeys greater than 2 hours in

length or when necessary. If

necessary, a break should be taken

between arriving on site and starting

work or completion of work and driving

back home.

5 1 5 L

4

Traveling to

meeting point

from vehicle or

other method

of

transportation

Unsafe

routes to

and from the

meeting

point.

Meeting

point is

within a

busy urban

area near

spots which

are very

quiet and

isolated at

night time.

Fatality,

Injury

Site

personnel 4 3 12 H

Normal caution in a city environment

should be exercised. Staff should only

take routes to the meeting point if

they feel safe to do so. If necessary,

contact should be made with the Site

Person in Charge and/or a

relative/personal acquaintance etc. to

notify them that they are on their way

to/from site. Team are advised not to

wait alone at the meeting point for

extended periods of time.

4 1 4 L

8

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

No Activity Hazard Consequence Who is

at risk

Degree of risk Controls Residual risk

O P R HML O P R HML

5

Working

during anti-

social hours.

Reduced

level of

alertness

and risk of

personal

injury.

Fatality,

Illness, Injury

Site

personnel 3 3 9 M

Breaks to be taken before and after

each shift. Staff should ensure they

have adequate rest before the shift

commences.

2 2 4 L

6 Needles and

sharps.

Infections

from bio-

hazardous

material in

area of

inspection.

Illness, Injury Site

personnel 4 4 16

An assessment of the site should be

undertaken upon arrival and before

commencing work.

If sharps are found, the Site Person in

Charge and Lead Inspector shall take a

view on work being suspended until

the hazard can be eliminated. Staff

should be careful handling items at

ground level and placing their hands in

areas which cannot be seen.

4 1 4 L

7

Working in

confined

spaces

Poisonous

gas or lack

of oxygen,

emergency

situations

including fire

/ explosions

Serious Injury Site

personnel 5 3 15 H

All staff entering sub vent tunnels will

be trained to work in confined spaces.

The staff will sign in with the Kier EM

Highways Security office before

entering the sub vent tunnel, ensure

the presence of Top man, availability

of escape breathing equipment sets

and gas monitor. All staff working

inside the sub vent tunnel must work

in pairs, remain within sighting

distance of each other, remain aware

of all available entry & exit points and

establish clear communication.

5 1 5 L

9

33235.KXC.S1.Condition Survey.Ramboll.G.RAMS.

No Activity Hazard Consequence Who is

at risk

Degree of risk Controls Residual risk

O P R HML O P R HML

8 Falling

objects

Falling

objects

striking staff

Fatality,

Injury

Site

personnel 5 2 10 M

Wear hard hat (BS EN 397) at all times

in all areas of the tunnels. Seek

immediate medical assistance if

injured. Ensure adequate lighting to

assess the area ahead.

No works should be being undertaken

above areas proposed to be inspected.

5 1 5 L

BuIlding S1 RISK ASSESSMENT & METHOD STATEMENT FOR THE CONDITION SURVEYS

Error! Reference source not found.

1-8-10

APPENDIX 1

NETWORK RAIL– CANAL TUNNELS SECURITY AND ACCESS

INFORMATION PACK

Canal Tunnels Information Pack –Security and Access Rev 6.1

Information Pack – Security and Access Arrangements at Canal Tunnels

Thameslink (Network Rail) Information Pack

1. Canal Tunnels Summary of Current Arrangements:

o All systems are commissioned and live but the Canal Tunnels are not operational or entered

into service, the points are clipped at either end and the routes are not signed over to the

signaller.

o The Overhead Line is live (25000Kv) and should always be treated as such; there are only

limited scenarios when access into the tunnel is permitted without an isolation being

granted (access arrangements with regards the overhead line further detailed within section

2).

o The connecting junctions from Canal Tunnels onto the Midland Mainline and the East

Coast Mainline are live railway infrastructure (Refer to section 3 and Appendix B for more

details). These lines cannot be accessed without the required safe system of work in place.

o There is no Principle contractor managing the site on a daily basis, The Network Rail project

team, ODM team and H&S team manage the access to this site (details within section 2

access arrangements).

o The track circuits are not strapped out throughout the tunnels therefore no machines or

trolleys can be brought into the tunnels unless under a possession environment as it will

drop track circuits on the live railway.

Canal Tunnels Information Pack –Security and Access Rev 6.1

2. Access Arrangements

Walkouts:

To undertake walkouts in the tunnel the following process shall be followed:

o Project manager Gareth Owen ([email protected]) and Senior ODM Manager

Mick Hilder ([email protected]) shall be informed of the walkout 1 week

before, detailing the date, time, timeframe and site contact for the walkout.

o A Work Activity Risk Assessment shall be produced based on the template in appendix A,

taking into consideration the Network Rail lifesaving rules and the Canal Tunnels site specific

health and safety considerations in section 3. This WARA needs to be sent to Gareth Owen

prior to the walkout ([email protected]).

o The walkout must only be undertaken in the tunnel 4ft or squeeze way and not on the

emergency walkway. If the walkout is required to be undertaken on the emergency walkway

then an isolation of the tunnels needs to be planned as per the normal isolation request

period and within the required timescales.

o The Duty ODM must be called before the party enters the tunnels and after they leave the

tunnels. The weekly ODM roster can be requested from Gareth Owen

([email protected]) or Mick Hilder ([email protected]).

o The attendees of the walkout must have the WARA briefed to them before accessing the

tunnels.

o No Materials or track trolleys can be brought in as part of a walkout; the walkout can only

constitute a visual low level inspection.

o No lone working is permitted within the tunnels; the minimum group size is two.

o No SSOWP is mandated to access the tunnels for a walkout (provided no isolation is

required), the access is fenced and segregated from the Midland Mainline end and all parties

can stay 10m away from the live railway on the ECML end by not going beyond the RRAP.

More details of this can be found in section 4 and Appendix B.

Canal Tunnels Information Pack –Security and Access Rev 6.1

Physical Works:

To undertake physical works within the tunnels the following process shall be followed:

o Project manager Gareth Owen ([email protected]) and Senior ODM Manager

Mick Hilder ([email protected]) shall be informed of the works 1 week before,

detailing the scope of works, date, time, timeframe and site supervisor for the works.

o The contractor shall amend their WPP and TB to reflect the site specific health and safety

considerations in section 3. This needs to be signed off by the relevant parties and a for

information copy forwarded to Gareth Owen ([email protected])

o An isolation is required to undertake any works within the tunnels.

o A SSOWP is required to undertake any works within the tunnels.

o The Duty ODM must be called before the party enters the tunnels and after they leave the

tunnels. The weekly ODM roster can be requested from Gareth Owen

([email protected]) or Mick Hilder ([email protected]).

o No track trolleys or Machines can be brought in as part of the work unless it is in conjunction

with a possession the East Coast Mainline/Midland Mainline.

o No lone working is permitted within the tunnels the minimum group size is two.

o The contractor becomes principle contractor of the tunnel they work in for the duration they

are working in it.

Canal Tunnels Information Pack –Security and Access Rev 6.1

3. Health and Safety considerations for all parties who need to access Canal Tunnels:

The list below details risks to consider when entering Canal Tunnels (this is not exhaustive and you

should always undertake a thorough task based and site based risk assessment when planning your

works).

Live overhead line (25000v) or OLE – no work can be undertaken without an Isolation and C

form, walkouts can be conducted within the 4ft or Squeezeway but not on the walkway.

Train movement on the East Coast Main Line (ref below picture)

Train movements at St Pancras Low Level Station (ref below picture)

Full Personal Protective Equipment is required by all parties entering Canal Tunnels

Canal Tunnels Information Pack –Security and Access Rev 6.1

Working at height if using the Emergency Walkway (no guard rails)

Slip / Trips

No one person is to enter Canal Tunnels on their own

Leptospirosis

Low level signals (personnel hitting their head)

All parties undertaking a walkout or survey access into the tunnel must complete a self-

assessed WARA (example in appendix A).

All parties undertaking work must prepare a Works Package Plan which references the risks

and access arrangements relating to Canal Tunnels. This WPP must be signed off by the

required signatories and sent to Gareth Owen for information prior to work.

All Parties MUST sign in and out with the Duty ODM security

Communication line to be established with Duty ODM prior to entering the tunnels

Duty ODM to be made aware of the general time frame of the site walkout

Sharps

Smoking is not permitted anywhere on site

Poor lighting at the lower level at St Pancras end.

Materials Stored towards St Pancras end (slip / trip)

Be aware that there is a HV 650v Signalling Power Supply

Be aware that there is a 415v M&E Power Supply

Flooding on the access walkway in the St Pancras Area to the Up Canal Tunnel (Slip Trip)

Canal Tunnels Information Pack –Security and Access Rev 6.1

Please ensure you also follow the Network Rail lifesaving rules:

Canal Tunnels Information Pack –Security and Access Rev 6.1

4. Entering and Exiting the Canal Tunnels

o There are four permitted access points into the Canal Tunnels (diagram in Appendix B):

1. Off St Pancras Low Level Platform A, following the segregated walkway into the Up Canal

Tunnels.

2. Off St Pancras Low Level Platform B, Following the segregated walkway into the Down

Canal Tunnels

3. Via the pedestrian access point off York Way (Standard East Coast Mainline Locks on the

access gate).

4. Via the vehicle access point off York Way and through Argent land (Standard East Coast

Mainline Locks on the access gate).

o The emergency lighting can be switched on manually with the emergency light switches located

at walkways on each entrance of each tunnel bore and located every 200m within the tunnel.

Access is permitted on the walkway to switch the lights on. The lights are on a 45 minute timer,

after 45 minutes half the lights turn off and after a further 15minutes the rest of the lights turn

off. To reset the timer just re-press one of the emergency light switches. Example of switch

below.

o Remember to contact the duty ODM before you enter the tunnels and once you leave the

tunnels.

Canal Tunnels Information Pack –Security and Access Rev 6.1

5. Security and Emergency and On Call Information

The previously installed security arrangement has been agreed to be removed as it did not provide

sufficient assurance or protection.

The duty night ODM will now undertake weekly inspections of the tunnel and include it in the ODM

report.

All incidents and accidents must be reported through the close call process (detailed in section 6)

and to the Duty ODM.

Duty ODM Generic Number: 0203 657 5755

For all week day and out of hours (including weekends) emergency’s the night shift ODM should be

contacted on the generic number above. An updated roster will also be issued by the Snr. ODM with

direct mobile numbers for the duty ODMs. This is available to any parties who plan to enter the

tunnels.

Where personnel deem it necessary to make contact with the British Transport Police (in the case of

an emergency) normal protocol should be applied.

Project On-Call staff shall take forward the management of the investigation of accidents and

incidents.

Canal Tunnels Information Pack –Security and Access Rev 6.1

6. Close Call Contact Information

All close calls should be reported via reported through the close call system (NSC) and the relevant

line manager.

7. Key Contact Information

o Three Bridges ROC Tel: 01293847754

o Kings Cross PSB Tel No Shift Signalling Manager: 02072782616

o York Electrical Control: 01904525836

o West Hampstead SSM: 01332442478

o Gareth Owen (Project Manager) - 07515628896

o Mick Hilder (Snr. ODM manager)- 07771672833

o Richard Elkin (Operations Interface Manager) – 07771668936

o H&M Security Cabin Canal Tunnels – 07917 241 706

BuIlding S1 RISK ASSESSMENT & METHOD STATEMENT FOR THE CONDITION SURVEYS

Error! Reference source not found.

2-8-11

APPENDIX 2

LOCATION OF BUIDLING S1 IN RELATION TO THE CANAL TUNNELS