8
Market update London fit-out update summer 2016 making the difference Turner & Townsend 01

Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

Market

update

London fit-out update summer 2016

making the difference

Turner & Townsend 01

Page 2: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

Turner & Townsend 02

The London fit-out market remains busy despite uncertainty in

the global economy. An expected peak in lease expiries in

London in 2018 is driving demand, with occupiers seeking to

rationalise their property portfolio and make their space work

harder, particularly with rental prices steadily increasing. A

number of major fit-out projects are coming on line during 2017

which will absorb capacity and result in tier one fit-out

contractors and their supply chain being more selective in their

bidding.

We also see a trend in nearshoring among the major professional and legal

services practices, with support functions being relocated to the regions

where rents are lower, with London used as a central hub for attracting

talent.

In 2015 we saw tender price inflation levels on London fit-out projects at

around five percent due to the surge in demand in the fit-out market. In

2016 this has dipped to around four percent as market supply has caught

up with demand. We expect this to return to around five percent in 2017

as some of the planned major fit-out projects come on line. Some clients

are choosing to procure their main contractor team early on a two-stage

arrangement, often many months ahead of starting on site, in order to

secure resource from the best teams.

London fit-out update

Tender price inflation

5% London fit-out 2015

4% London fit-out 2016

5%

London fit-out 2017

Page 3: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

London fit-out update

Turner & Townsend 03

London fit-out market analysis

Turner & Townsend undertook a survey of tier one and tier two suppliers over the summer of 2016, testing market sentiment, expected tendering conditions and expected price rises.

Market outlook

During summer 2016 the general feeling in the fit-out market

has been one of waiting for the fallout of the Brexit vote,

effectively placing a pause on expectations. Notwithstanding

this, there was an expectation that input costs (labour, plant,

materials) would continue to increase after the ‘Brexit’ vote,

regardless of outcome, with few suppliers expecting the market

to cool (eight percent).

The market is buoyant and the short-term impact of Brexit has

led to price increases due to the weak pound, but it is unknown

what the effect of ‘Brexit’ will be in the medium term, and

whether or not market activity will increase or decrease. We

have seen little evidence of schemes being cancelled or put on

hold however, uncertainty in the economy may put off

investors.

Still, London is most active with big projects underway such as

Crossrail and Elephant and Castle redevelopments. However,

regions outside the capital are benefiting from the heat of the

London market, with developers starting to invest in areas

surrounding major cities such as Cardiff, Bristol, Watford,

Oxford etc.

Tendering conditions

▪ Cold:

intense competition, not much work, prices low.

▪ Lukewarm: strong competition, moderate tender prices.

▪ Warm:

moderate competition, moderate tender prices.

▪ Hot:

reduced competition, work easy to get, tender prices

high.

▪ Overheating:

Shortage of builders, minimal competition, prices very high.

The market has plenty of opportunities, but increased foreign competition in London is making work

harder to win, which places increased pressure on tendering conditions. An increasingly active market

place would tend to cause a reduction in pricing levels as firms bid competitively to secure work.

Warmer50%

Staying The

Same42%

Cooler8%

Tier one and two supplier survey: market conditions Turner & Townsend

Cold8%

Lukewarm8%

Warm59%

Hot8%

Overheating17%

Tier one and two supplier survey: tendering conditions Turner & Townsend

Page 4: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

London fit-out update

Turner & Townsend 04

The level of contractors and sub-contractor insolvencies has also been fairly subdued of late, lending

some assurance to the surety of fulfilment of works. Evidence suggests that cost increases have

occurred while there is more pressure from contractors to reduce prices. Programmes are getting

tighter and profit margins seem to be reducing, potentially impacting the level of future insolvencies if

this situation persists.

Inflation rates

According to our recent contractor survey undertaken in summer 2016, suspended ceiling systems are

expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by

carpenter/ bricklayers at 5.7 percent and ductwork at 5.3 percent. The smallest inflationary increase

appears to be sprinkler systems, appreciating by just 3.7 percent.

Tier two supplier survey: Inflation expectations +12 months Turner & Townsend

Page 5: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

London fit-out update

Turner & Townsend 05

Survey return commentary

Fabric systems

We are seeing our costs increase however, there is more pressure from contractors to reduce

prices. Programmes are getting tighter. There are a number of major office fit-outs coming to the

market shortly in London as well as Cambridge, Manchester and Birmingham.”

Audio Visual

We have found during the last quarter that tender activity has slowed and that the marketplace is

very competitive at the moment. We have received some feedback that customers in the City

maybe holding off on making key decisions until after the impact of the EU referendum is clearer

due to the uncertainty of the situation. Overall we have seen major blue chip companies

incorporating av/vc communications within their planning strategies and see the value of investing

in this technology. The technology for digital signage has advanced and we see this as an area of

growth in the future.”

MEP

Buoyant market within central London. Good levels of competition. 2017 and 2018 are forecast to

be very busy in the central London fit-out market. Principle contractors winning two stage work

however they are competitively tendering the M&E packages. Also our downstream sub-contractors

are very busy and are being selective in what projects they take.”

Joinery

There are currently many large projects and we believe there is a shortage of supply to meet the

expectations and high quality requirements of the clients/whole supply chain. In our opinion there

are danger signs in terms of potentially over stretching resource and commitments on jobs due to

pressure from the market and this is a high risk to up and coming projects namely delivery and

quality.”

Contractor

London remains a relatively buoyant market. Levels of opportunity are supporting growth. Sub-

contractors are getting selective as to which projects they target/support. Although there is a

strong level of opportunities, the market is still competitive and competition is high. The sub-

contract market is now overheating for certain trades such as joinery and M&E services. Getting

the market leaders in these trades is now very difficult.”

Key challenges

Lack of competition between supply chain driven by consultant’s preference and reliance on tier one

supply chain. Drives up costs and stifles development of competitive supply chain.

Lead times of specified fabrics are getting longer as stock levels decrease. Additionally, lead times

on VC equipment and supply of smartboards.

Design/client changes, approvals, labour shortages and commitment to place orders on projects.

Overall taking into account all the points raised we believe so much time is being lost which could be

used to benefit delivery and quality of job delivery.

Page 6: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

London fit-out update

Turner & Townsend 06

Indicative costs

Cat A

The table below shows indicative costs for a typical developer’s Cat A fit-out, together with benchmark

costs from some of our recent projects.

Item £/ft2

Powder coated perforated concealed grid suspended ceiling

5.5

Medium duty full access raised floor and floor sealer

(with under floor barriers and earthing)

3.5

Four pipe fan coil air conditioning (including units, pipework, ductwork, supply air grilles, power supplies, BMS outstations, wiring, insulation,

condensate drainage etc)

18.0

LG 7 compliant lighting installation (including sub circuits, LCM‟s,

controls and non-maintained emergency lights)

8.0

Under floor power network (from distribution boards , floor boxes at 1: 10 sq. metres)

4.5

Life safety systems (fire alarms, sprinklers)

2.5

Carpet (Heavy Duty Commercial

grade antistatic carpet tiles) on ‘Tackifier’

2.5

Blinds to windows (manually controlled roller blinds)

1.0

Basic Security system and wireways 1.0

Contractor’s preliminaries and OH&P

Prelims

7% OH&P 4%

Total 52.0

Currently a standard developer’s Cat A fit out is benchmarking at around £52/ft2. Price increases are

expected for suspended ceilings in particular, which when coupled with the weak pound is likely to push this figure upwards.

Based on some of our recently procured projects we are seeing Cat A costs ranging from £47/ft2 to £56/ft2,

although there are efficiencies to be had through large volume projects and utilisation of the Shell & Core contractor if already on site.

Cat A benchmarks (£/ft2), central London Turner & Townsend

42

44

46

48

50

52

54

56

58

Project

A

Project

B

Project

C

Project

D

Project

E

Page 7: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

London fit-out update

Turner & Townsend 07

All-in capital cost range Cat B

The graph below shows the typical range for fit-out from Cat A to Cat B. Fit outs at the lower end tend

to be more open plan with collaboration spaces and traditional AV solutions. Those at the upper end

have more cellular space, client meeting suites and/ or client dining, or higher end AV solutions.

Cat B fit-out benchmarks

The table below shows a selection of Cat B fit out costs from developer’s Cat A, together with the

overall duration on site. Costs are out-turn costs re-based at 2Q16 and exclude professional fees,

furniture, and data cabling/ client IT.

Project Ft2 £/ft2

(Cat B) Weeks on

site

Project A, Central London 86k £88 21

Project B, Central London 205k £103 34

Project C, Central London 60k £113 35

Project D, Central London 491k £118 61

Project E, Central London 400k £156 52

Project F, Central London 56k £158 22

Project G, Central London 45k £167 16

0 50 100 150 200 250 300

Low

High

Fit Out Fees Furniture Data Cabling E/O Dealer Floor

Page 8: Market update - Turner & Townsend · expected to increase the most in the coming 12 months, by 7.5 percent. This is closely followed by carpenter/ bricklayers at 5.7 percent and ductwork

Turner & Townsend 08

About Turner & Townsend

We are an independent professional services company

specialising in programme management, project

management, cost management and consulting across

the real estate, infrastructure and natural resources

sectors.

With 97 offices in 41 countries, we draw on our extensive

global and industry experience to manage risk while

maximising value and performance during the

construction and operation of our clients’ assets.

© Turner & Townsend Cost Management Limited. This content is for general information purposes only and does not

purport to constitute professional advice. We do not make any representation or give any warranty, express or

implied, and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained

in this document.

It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including

orally, to any other party without our express written permission and we accept no liability of whatsoever nature for

any use by any other party.

Our team

Colin Wood

Director

t: 44 (0) 20 7544 4136

[email protected]

Kristoffer Hudson

Economic Analyst

t: 44 (0) 113 205 4832

[email protected]