Project Update
April 11th , 2011
Roadway Projects
• Opened both Northbound lanes 2/22 • Street lighting conflict with CenterPoint
power lines scheduled for completion by the end of April
• Work continues on the project to complete outstanding items
Cullen Parkway
Cullen Parkway
Phase II – Mary’s Creek Bypass to SH35
• Opened to 4 lanes on 4/6 • Completed landscape and irrigation
installation; conducted substantial completion inspection with TxDOT
• Completed major sidewalk and brick paver installation
• Continued traffic signal installation network
Dixie Farm Road
• One lane closure between SH 35 and Veterans allowing only westbound traffic
• Brush cleared between Veterans and BNSF railroad tracks
• Began installing 10x4 RCB east of Veterans • Conflicts were identified with the relocation
of three CenterPoint Energy power poles and a resolution has been initiated.
• Utility relocation continues
Walnut Reconstruction
Construction Phase III – Morgan to Harkey and CR 89
• Contractor completed paving at the remediation areas east of FM 1128
• CenterPoint installed 2nd arm for Southfork streetlights; working on plan for Magnolia streetlights
• Initiated ditch re-grading, base and asphalt work on east side of FM 1128
• Late April/Early May opening
Magnolia Road
• Green Armor installation is scheduled to be
complete by mid-April • Final walk-through scheduled for the end of
April
Town Ditch Phase III
• Orange Street has been closed to westbound traffic between SH 35 and Mykawa to begin the installation of utilities and grading
• Began installation of inlets • Continued coordination with the utility
companies • AT&T has many conflicts that are affecting
the project
Orange Street
• Returned plan review of 100% plans with
drainage updates to the engineer for revisions • Traffic counts and noise measurements
completed for Noise Impact Analysis; Engineer working on draft report submission
• ROW acquisition underway – 61 of 65 parcels acquired, 4 in condemnation (May 16th)
Bailey Road (Veterans to FM1128)
• Irrigation and landscaping ongoing; working with HOA for upgrades
• Final clean-up in progress
McHard Road (Country Place to Cullen)
McHard Road (Soundwall Construction)
• CenterPoint installed new transmission lines
along north side of McHard in order to de-energize and remove lines on the south side.
• North side wall placement complete with the exception of Sound Fighter gate installation
• Majority of south side mow strip, column, and panel placement complete
• Two lanes of paving Flea Market to Walmart • Working with TxDOT to address local
business concerns • USACE issued permit for low water crossing
on Hickory Slough • All utilities have been relocated along SH35
with the exception of the contaminated soil area & water line on bridge
SH35 – BW8 to FM518
• Utility relocates and coordination ongoing • Initiated slip form from Kirby to Clear
Creek Bridge • Bridge deck at Clear Creek Bridge poured • Storm Sewer Completed
FM 2234 Widening
• Cabinet box, controller and signal heads delivered to contractor site
• Bollards installed and painted • CenterPoint pole adjustments and tree
clearing scheduled for completion this month
Interim Traffic Signal Installation – Mykawa Road at Brookside Road
Drainage Projects
Detention Pond • Pond B excavation complete; Pilot channel
installation in progress • Excavation of diversion channel from Pond A to
CR 143 complete • Hauling activities and fill placement at designated
fill sites continued • City staff finalized pump configuration • Waiting for engineer to complete plan revisions
for pump station
Cowart Creek Diversion
Diversion Ditch • Conoco Phillips issued NTP • CR100 closure thru next week • Veterans closure late April – 4-6 weeks • Awaiting re-submittal of 90% N/S Ditch
plans
Cowart Creek Diversion
Facility Projects
• Completed below slab utilities, water, sewer,
electrical, and data • 95% complete on Site Utilities, including internal
drainage, electrical and phone and prep’d for installation of fiber optic to PSB
• Poured slab with cut outs for tilt wall panels • Reviewing Building access control options and costs
Hillhouse Road Service Center
• Continuing work on Interview Room Recording System – New cameras & mics were installed in two rooms for a
three week test period – Audio, video, and playback of new equipments meets
needs – Contractor directed to install this setup in all interview
rooms • Performed Final Acceptance Walkthrough on
March 21st . The contractor is working to complete additional items
Public Safety Building
• Held final walk-through • Continued working through warranty items,
Fire Marshal’s issues, and Architectural Barrier issues resolved
• All furniture has arrived • Intercom system was installed
Fire Station #5
• Underground utilities complete • Began erection of pre-engineered building • Driveways and 50% of parking/paving has
been poured
Fire Station #6
• HGAC grant application has been submitted • Staff has reviewed 60% design plans and
specs • Working to advertise the project once the
HGAC grant is approved
Pearland Gateway – Project Stars
Parks
• Revised plans received from architect. Held pre-development meeting with Planning to clarify permitting issues with shade structures
• Plans submitted for review through development department and CIP review processes
Trail Connectivity
• Held progress meeting to review park amenities, type and cost of fields, and brought project in line with current budget and cost estimates
• Met with BDD4 to review pond function, H&H model, access, and property acquisition, and identified need for Interlocal Agreement
• CR403 Extension per SPA with MUD#16 • Set up coordination meeting with MUD #16
Engineer and developer
Sports Complex at Max Road
Utility Projects
30” Waterline Interconnect
• The sub-contractor has drilled the piers on the North side of Clear Creek for the aerial crossing
• The 30” waterline has been pressure tested from McHard to the Alice Street Water Plant
• Completed installation of 20” distribution waterline from Alice Street Water Plant along McHard to Old Alvin Rd.
• Fuqua line and meter station underway • CoH 72” line scheduled for completion in July 2011
City of Houston Interconnect
20” waterline with Gate Valve at Alice Street Water Plant
City of Houston Interconnect
Alice Street Water Plant • Industrial TX continued working on the pump
building and chemical facility • Preload completed the construction of the interior
of the ground storage tank • Upon completion of the 30” waterline, Preload
will test the ground storage tank • Poured the slab for the turbine facility
South SH 35 Interim Lift Station at Industrial Drive
• Plans were revised. Request for proposal submitted to the contractor
• Proposal received from contractor and is currently under review
• Revisions will result in a deductive Change Order
• Revised Design Services proposal to remove filter lift station & filter evaluation from design effort after filter evaluation letter report was completed
• Negotiated revised design contract • Prepared contract for presentation to
Council for award
Longwood WWTP Rehabilitation
• Plant personnel are cleaning out the old storage basin to be reconstructed as the new thickener, for surveyor work on topographic plant site
• Met with geotech engineer and structural engineer on site to discuss bridge design issues
• Structural design of bridge and thickener equipment is underway
Barry Rose WWTP Rehabilitation
• Negotiated design contract • Engineer prepared revised proposal • Presenting agreement and proposal to Council for
consideration
Hatfield Basin Trunk Sewer
• Held project kick-off meeting • PER phase underway
Twin Creek Regional Lift Station
Far Northwest Wastewater Treatment Plant Improvements
• Staff received and reviewed proposal for
equipment repairs and upgrades from decanter manufacturer
• Scheduling to meet with UV system manufacturer
Old Alvin 20” Waterline
• Contract for PER services awarded at Council • Held Kick-off meeting
Project Update
Questions/Comments
April 11th , 2011