Upload
zanthe
View
46
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Current Status and Development Plans for the Nuclear Power Sector in Russia: Generation Capacity, and Fuel-cycle Approaches. Map of Russian NPPs sites. 10 NPPs, 31 units, N уст. =23242 MWt. Russian NPPs generation in 1992-2005. The dynamic of failures of Russian NPPs in 1992-2005. - PowerPoint PPT Presentation
Citation preview
1
Current Status and Development Plans for
the Nuclear Power Sector in Russia:
Generation Capacity, and Fuel-cycle Approaches
Current Status and Development Plans for
the Nuclear Power Sector in Russia:
Generation Capacity, and Fuel-cycle Approaches
2
Map of Russian NPPs sites
Beloyarsk NPP
Balakovo NPP
Novovoronezh NPP
Kursk NPP
Kalinin NPP
Kola NPPLeningrad NPP
Smolensk NPP
Bilibino NPP
VVER-1000
VVER-440
BN-600
EGP-6
RBMK-1000
Rostov NPP
10 NPPs, 31 units, Nуст.=23242 MWt
3
Russian NPPs generation in 1992-2005
148,6
128,9
103,597,8
119,6
143,0147,6
139,8
134,9120,0
108,3108,8
119,2
99,3
169,8
159,3
157,7
155,7150,9
90
120
150
180
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
bln
. kW
.hr.
Fact Forecast
1 VLD connected to
the grid 4 BAL connected to
the grid
2004: physical start-up of Kalinin 3
2 VLD is scheduled to beconnected to the
grid
4 KLN, 5 BAL are scheduled to beconnected to the
grid
4
The dynamic of failures of Russian NPPs in 1992-2005
32 299 00210424324
4044
165
130
119
97
81 76
9886
65 67
3745
40444738
6769
88102
7983
101
128
159
197
0
20
40
60
80
100
120
140
160
180
200
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
0
20
40
60
80
100
120
140
160
180
200
Safety related Miscellaneous
Total The new regulations of failures recording were put into force
from 1998
5
Trend of reactor scrams in 1992-2005
32 33
1214
11 10 10
15
6
1513
10 11
6
0
5
10
15
20
25
30
35
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
6
Radiation and environmental safety at NPPs in 2006
• No incidents associated with radiological
consequences and environmental pollution.
• Radioactivity of gas-aerosol effluents and
liquid releases does not exceed the
permissible values.
• Main dose limits are met at all the NPPs.
7
Main issues in operation of Russian NPPs in 2004-2006
• Metal corrosion and erosion processes
• Faults in operation of electric
equipment
• Natural impacts
8
Examples of erosion-corrosion destructions
23.03.06 3SMO Damage of low-pressure steam lines at turbine generator 6 of Smolensk NPP
9
22.01.06 1KUR. Damaged equipment of the openswitchyard 330 kV
10
Volgodonsk NPP (January 29, 2005)
Intake channel covered with the ice
11
Natural impacts (birds)
7 failure of the open switchyard electric equipment occurred in the period 2001- 2006 due to the birds:Novovoronezh – 1 event;Leningrad – 2 events;Kursk - 4 events
12
Main areas of activities in 2004-2005
• Upgrading and LTE
• Improvement of the NPP effectiveness
• Improvement and ensuring of NPP equipment reliability
• Management of SNF and RW
• Preparations to decommissioning
• Emergency preparedness
• Human factor
13
Factors promoting the performance of NPP lifetime extension (LTE) activties
• ConservatismConservatism of the previously accepted design basis for justification of the 30-30-yearsyears life time for the operating NPPs
• Large scope of upgrading activitiesLarge scope of upgrading activities implemented during the design life time
• Specific costs for NPP lifetime extension are significantly lowersignificantly lower then the investments required for construction if new NPP units
UP
GR
AD
ING
AN
D L
TE
NPP operation experience allows to justify the revision of the previously accepted NPP lifetime durations
14
Radwaste management facilities taken into operation in 2004-2006
• Kursk NPP unit 1 solid radioactive waste storage;
• Kursk NPP radwaste accumulation and sorting
facility;
• Smolensk NPP liquid radwaste storage 2;
• Solid radwaste temporal storage facility in the
turbine hall of Smolensk NPP;
• Storage polygon for the waste containing
raidionuclides in permissible values at Balakovo
NPP.
RW
AN
D S
NF
MA
NA
GE
ME
NT
15
Improvement of the SNF managementMain pending issues – safety
ensuring in SNF storage and transportation from the NPP sites.
Ways of resolution:
• Implementation of the facilities for cask-type storage and transportation of the SNF from the RBMK NPPs;
• Construction of the centralized dry storage for SNF from RBMKs and VVERs at Krasnoyarsk;
• Establishment of the facilities ensuring removal of the SNF from the AMB reactors of Beloyarsk first stage;
• Construction of additional SNF pit at Bilibino.
RW
AN
D S
NF
MA
NA
GE
ME
NT
16
Forecast of electricity generation in Russia(Energy strategy of Russia for the period to 2020)
(approved by the Decree of the Russian Government dated 28.08.03 №1234-р)
160180
210230
200
300266
1070
1205
1365
11101205
1015930
2005 2010 2015 2020
In the European part of Russia:Growth of the NPP generation share to 30%;Growth coverage – to 50% in average
Optimistic
Medium
bln.kW.hr/yearbln.kW.hr/year
TOTAL
At NPPs
17
In particular before 2030 to implement 40 GWt of electric power in the country and almost the same amount abroad.
To achieve this it is necessary:
1. Uranium problem
2. The problem of SNF and radwaste
3. Machine-building base
4. Constructional base
5. Road-map
18
Construction policy
1. Units completion (from 3 to 5) which have already been started to be built
2. To prepare NPP project – 2006To take all the best which exists on PWR and to prepare and make a standard project. To ensue the construction velocity up 2 units to 2010.
3. By 2010 to realize the PWR project corresponding the best international models and to realize their serial production between 2010 and 2020
4. By 2020 dimensioned scientific and further nuclear energy development must be realized
19
In the version of experimental-industrial complex creation for next generation
nuclear fuel cycle processing:
- To finish reactor BN-800 construction at Beloyarsk NPP
- BN-800 is necessary for practical confirmation of new safety level, new fuel type, construction materials and closed fuel cycle. It’ll be implemented in 2012-2014
- Nowadays everything is restrained because of fuel production lack (the main question is where and how MOX fuel will be produced
20
In the version of dimensioned serial construction of commercially effective
units of generation with fuel production and SNF reprocessing
Fast reactor based on sodium technology: - Development of head licensed project of commercial
NPP-2014- Production of the first loading in the Complex – 300
– 2018- Creation of fuel production for serial NPPs – 2020- NPP putting into operation (building) – 2020- Creation of SNF reprocessing production - 2025
21
Specific indices:- Prime cost – 3 cents per 1 Kw/h
- Specific cost – 1000 per 1 Kw/h
- Annual delivery of electric power – 13500 Gw/h a year
- Lifetime – 60 years
- Staff coefficient – 0,35 pers/Mw
- Coefficient of reproduction – 1,3 with the possibility of increase to – 1,5
22
In Russia not less than 1,0 Gw a year
• Fast reactor with plumbum coolant (FRSC) – creation of commercial block with fuel production and SNF reprocessing is possible by 2030
• High-temperature graphite reactor for energotechnological use (hydrogen and etc) and electric energy production – prototypical unit by 2017 and the head four unit NPP with fuel production by 2025
• Regional NPPFloating NPPs on the basis of energy facilities from ice-breakers are viewed. The first NPP is being built in Murmansk
23
Desirable and expected composition and structure of reactor park of Russia:
- 2020 – 45 Gw TR
- 2030 – 50 Gw TR and 5 Gw FR
- 2040 – 55 Gw TR and 15 Gw FR
24
Level of readiness of Russian nuclear industry engineering base for realization of the next generation
nuclear fuel cycle creation project
In the version of experimental-industrial complex
- Technical project BN-800 is approved and there’s a license for building and construction has been started.
- Creation of BN-800 is a necessary step before creation of commercial reactor:
- Technology of MOX fuel production was elaborated and tested:
- There’s readiness for development of technical project for fuel production.
- In BN-800 commercial reactor fuel capacity should be proved;
- SNF reprocessing was tested in Research Institute and is ready for realization at RT-1 (variant without separation of uranium and plutonium is possible).
25
In the version of serial construction of commercially effective power units of next
generation with fast reactors.
• Initial phase, elaboration of commercial reactor conception.
• All the complex of activities with the sodium coolant technology confirms possibility of development of necessary technologies for the projects of commercial reactors and nuclear fuel cycle facilities.
• There aren’t constructional materials for deep fuel burn-out
• There’s no project for fuel production
26
Spent fuel management
Fuel of WWR-440 reactor type is reprocessed at the plant RT-1 at the Urals. Fuel of WWR-1000 and RBMK in Krasnoyarsk region.
Pond storage (“wet”) (Spent fuel storage-1)
SFS-1 capacity for SNF of WWR-1000 is 6000 tons (by uranium dioxide). SNF for storage is received from three Russian NPPs (Novovoronezh, Balakovo and Kalinin), four Ukranian NPPs (Southern-Ukranian, Zaporozhskaya, KHmelnitskaya, Rovenskaya) and one Bulgarian NPP (“Kozloduy”). SNF reception is foreseen at Volgodonsk NPP.
27
Design storage volume of RBMK-1000 SNF of launching complex is 5082 tons (U)
Design total volume is 37785 tons (U), including:
26510 tons (U) – РBМК-100011275 tons (U) – WWR-1000Real amount of SNF isn’t shown in tons
U, but in uranium dioxide tons (UО2), because this dioxide is nuclear fuel.
Thus real amount of SNF at a dry storage is:
37785 × UО2 / U = 37785/238 = 42865 tons UО2.