33
Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim Ir. Herwin Rubijono 19 September 2016 Manajemen Proyek Hotel Ambhara

Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir [email protected] WA/SMS : 0812-98920067 Background

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Ir. Herwin Rubijono

19 September 2016

Manajemen Proyek

Hotel Ambhara

Page 2: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Resume :M.A. Herwin Rubijono, [email protected]/SMS : 0812-98920067

Background :

Education :S1 Teknik Komputer

Port folio :- IT Consultant;- Project Management- SOP

Working Experience :- PT Prosys Bangun Nusantara;- PT Alcatel Indonesia;- PT EB Connection;- PT HP Indonesia;- PT Multi Media Arto Sentosa (now)…Projects:- Grand Indonesia;- Chevron Oil Company;- PT Telkom (SDP Project);- PT Telkom (Seat Management);- PT TGI;- PT PGN- Others……

Trainer/Instructor:- Prosys Bangun Nusantara- PLN- VICO- PT. Aneka Tambang- PT. Pakuwon Jati- PT. Adaro- ESDM- PT. Medco- PT. ANJ- PT. Pertamina- PT. Djarum- PII- Others……

Page 3: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Time Management

Project Cost Management

Project Risk Management

Project Claim Management

Subject :

Page 4: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Time Management

Page 5: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Time Management

Project Time Management

The processes required to manage the timely completion of the project, asfollows :

Plan Schedule Management Define Activities Sequences Activities Estimate Activity Resources Estimate Activity Duration Develop Schedule Control Schedule

Page 6: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Define Activities, Milestone, Activity Sequence Activity List A comprehensive list of all schedule activities that are planned to be performed

on the project. Helps project team members to understand what work is to be performed.

Milestone A significant point or event in the project. An event that is possibly restraining future work or marking the completion of

a major deliverable. A schedule milestone has zero duration. Sometimes called a milestone activity.

Activity Sequence Identifying and documenting dependencies among schedule activities.

Precedence Diagram Method, is a technique used for constructing a schedule modelin a which activities represented by node and linked by one or more logicalrelationship.

Conceptual and Methodologies-time

Project Time Management

Page 7: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Conceptual and Methodologies-time

Project Time Management

Page 8: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Estimate Activity Resource Resource requirements: What resources (persons, equipment, or materials)

What quantities of each resource will be used

When each resource will be available to perform project activities

Conceptual and Methodologies-time

Page 9: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Identifies the scheduling method and tools used to create theschedule, and how the schedule is to be calculated. Critical Path Method (CPM) – Precedence Diagram Baseline Project Schedule Actual Project Schedule Schedule Compression Scheduling Tools

Develop ScheduleConceptual and Methodologies-time

Project Time Management

Page 10: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Forward calculation

Backward calculation

A10

2 days

A20

3 days

A40

4 days

A30

1 day

A50

2 days

A60

5 days

3 6

9

7 9

8

3 7

5

1

8

84

2

Critical Path and Float Identification

2

1 2

7 8

13

9 136

3 6

8

7 8

5 6

Conceptual and Methodologies-time

Project Time Management

Page 11: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Forward calculation

Backward calculation

A10

2 days

A20

3 days

A40

4 days

A30

1 day

A50

2 days

A60

5 days

3 6

9

7 9

8

3 7

5

1

8

84

2

Critical Path and Float Identification

2

1 2

7 8

13

9 136

3 6

8

7 8

5 6

critical path

Conceptual and Methodologies-time

Project Time Management

Page 12: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Time Management

Page 13: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Time Scheduling – Gantt Chart

Conceptual and Methodologies-time

Project Time Management

Page 14: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Critical Path

Critical Path Generally - not always - the sequence of schedule activities that determines

the duration of the project. Generally, it is the longest path through theproject.

Critical Path Method Used to determine the amount of scheduling flexibility (the amount of float)

on various logical network paths in the project schedule network, and todetermine the minimum total project duration.

Conceptual and Methodologies-time

Project Time Management

Page 15: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

CPM (Critical Path Method)

Conceptual and Methodologies-time

Project Time Management

Page 16: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Cost Management

Page 17: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Cost Estimating :Developing an estimate (approximation) of the costs of the resourcesneeded to complete project activities.

Cost Budgeting :Allocating the overall cost estimates to the individual work items inorder to establish a cost baseline for measuring project performance.

Conceptual and Methodologies-cost

Cost Management

Project Cost Management

Page 18: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Conceptual and Methodologies-cost

Cost Management

Page 19: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

19

Cost Baseline, Expenditures, and Funding Requirements

Conceptual and Methodologies-cost

Project Cost Management

Page 20: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Earned Value, Planned Value, and Actual Costs

Project Cost Management

Conceptual and Methodologies-cost

Earned Value Management (EVM) is a methodology that combines scopeschedule, and resource measurement to assess project performance andprogress. Planned Value (PV) Earned Value (EV) Actual Cost (AC)

Variance from the approval baseline will also be monitored : Schedule Variance (SV) = EV – PV Cost Variance (CV) = EV – AC Schedule performance index (SPI) = EV/PV;

SPI <1 : behind schedule; SPI=1 : on schedule SPI>1 : Ahead Schedule

Cost Performance index (CPI)=EV/AC CPI <1 : over planned cost; CPI=1 : on planned cost; CPI > 1 : Under Planned cost

Page 21: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Earned Value, Planned Value, and Actual Costs

EV

Conceptual and Methodologies-cost

Project Cost Management

Page 22: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Risk Management

Page 23: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Conceptual and Methodologies-risk

Risk Management in the projects involves: Identify risk Assessing and analyzing the likelihood and impacts of risks Trying to reduce the uncertainties (by gathering more information

or making different decisions) Trying to lessen the impacts of risks Developing contingency plans for critical risks Monitoring risks as the project progresses

Project Risk Management

Project Risk Management“Project Risk is an uncertain event or condition that, if it occurs, has aneffect on at least one project objective”.

A1

Page 24: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Slide 23

A1 Author, 9/15/2016

Page 25: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Origin of Project Risk

• Project risk has its origins in the uncertainty present in all projects:

Known risks are those that have been identified and analyzed, making itpossible to plan responses for those risks. Known risks that cannot bemanaged proactively, should be assigned a contingency reserve.

Unknown risks cannot be managed proactively and therefore may beassigned a management reserve.

• A negative project risk that has occurred is considered an issue.

Conceptual and Methodologies-risk

Project Risk Management

Page 26: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Type of Risk :

Risk Avoidance: changing the project plan to eliminate the risk or conditionor to protect the project objectives from its impact.

Risk Acceptance: accepting the consequences should a risk occur. Plan fordealing with it when it occurs, but do nothing to lessen its probability orimpact.

Risk Transfer or Deflection: assign the risk to a 3rd party. (e.g. Insurance,Outsourcing)

Risk Mitigation: reducing the impact of a risk event by reducing theprobability of its occurrence. (e.g. contract experts)

Project Risk Management

Conceptual and Methodologies-risk

Page 27: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Threshold of Risk LevelsPROBABILITY

5. AlmostCertain

4. Likely

3. Possible

2. Unlikely

1. Rare

IMPACT 1.Insigni-ficant

2. Minor 3. Mode- 4. Major 5. Catas-rate trophic

High HighHigh

High High

High

Med

Med Med

Med Med

Med Med

Med

Low

Low

Low Low Low

LowLow

Low

Low

Low

Low

Conceptual and Methodologies-risk

Project Risk Management

Page 28: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Claim Management

Project Claim Management

Conceptual and Methodologies-claim

Page 29: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Claims management describes the processes required to prevent project claim,to mitigate the effect of those that do occur, and to handle claims quickly andeffectively.

Project Claim Management

Conceptual and Methodologies-claim

Claims could be come from project owner or project contractor

Claim processes :- Negotiation- Mediator- Arbitration board- Legal judgment

Page 30: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Project Claim Management covered :o Claim Identification;o Claim Quantification;o Claim Prevention;o Claim Resolution

Page 31: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

1. Claim IdentificationIdentifying from scope knowledge and contract term/condition changes of some activity.Determine claim extra workDetermine extra time

2. Claim quantificationDetermine statement of claimDetermine of claim activity

3. Claim preventionCreate project plan and term/condition of contract & risk management plan

4. Claim ResolutionContribution on statement of work and claim quantification definition;Contribution on contract preparation

Page 32: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

Claim Causes :o Changes in subsurface conditions;

o Discrepancies and ambiguities in plans and specifications;

o Neglect or delay;

o Sending other contractors onto the site;

o Delays and Changes in the work

Page 33: Manajemen Proyek - herbycalvinpascal.files.wordpress.com€¦ · Manajemen Proyek Hotel Ambhara. Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS : 0812-98920067 Background

End of SlideQ & A