99
THE GOVERNMENT OF THE UNITED STATES OF AMERICA MILLENNIUM CHALLENGE CORPORATION Compact Program for the Government of the Republic of Malawi (2011 2016) Concept Paper for the Energy Sector Millennium Challenge Account Malawi Country Office Secretariat P. O. Box 31513 Lilongwe Malawi “Poverty Reduction through Economic Growth”

Malawi Energy Concept Paper

Embed Size (px)

DESCRIPTION

Energy Initiatives in Malawi

Citation preview

Page 1: Malawi Energy Concept Paper

THE GOVERNMENT OF

THE UNITED STATES OF AMERICA

MILLENNIUM CHALLENGE CORPORATION

Compact Program for the Government of the

Republic of Malawi

(2011 – 2016)

Concept Paper for the Energy Sector

Millennium Challenge Account – Malawi Country Office Secretariat

P. O. Box 31513

Lilongwe

Malawi

“Poverty Reduction through Economic Growth”

Page 2: Malawi Energy Concept Paper

i

TABLE OF CONTENTS

ABBREVIATIONS AND ACRONYMS ............................................................................................................... iii

UNITS OF MEASURE ..................................................................................................................................... iv

CURRENCY EQUIVALENTS ............................................................................................................................. v

LIST OF FIGURES ........................................................................................................................................... vi

LIST OF TABLES ............................................................................................................................................ vii

LIST OF ANNEXES ....................................................................................................................................... viii

1 SUMMARY OF THE INVESTMENT CASE ................................................................................................ 1

1.1 Electricity Demand and Supply Projections ................................................................................. 2

2 INVESTMENT OBJECTIVE AND OUTCOMES .......................................................................................... 4

2.1 Program Logic for the Investment Program ................................................................................ 4

2.2 Investment Outcome 1 – Increased Availability of Quality and Reliable Power ......................... 5

2.3 Investment Outcome 2 – Increased access to power for Un-served users ................................. 7

2.4 Investment Outcome 3 – Improved and Effectively Managed Power Sector for Improved Service Delivery ........................................................................................................................................ 8

2.5 Investment Outcome 4 - Improved National Resource Management in Priority Catchments to Sustain Power Sector Investments ......................................................................................................... 10

3 USE OF INVESTMENT FUNDS .............................................................................................................. 13

4 PROJECT BENEFITS AND BENEFICIARIES ............................................................................................ 15

4.1 Beneficiary Analysis ................................................................................................................... 15

4.2 Key Assumptions Underlying Estimates of Incremental Costs and Benefits ............................. 16

4.3 Summary of Overall ENPV and EIRR for Energy Investments .................................................... 17

4.4 Target beneficiaries ................................................................................................................... 17

5 SUPPORTING TECHNICAL INFORMATION .......................................................................................... 27

Page 3: Malawi Energy Concept Paper

ii

5.1 Sector Description ..................................................................................................................... 27

5.2 Recent, On-Going or Expected Investments ............................................................................. 29

6 ENVIRONMENTAL, SOCIAL & INVESTMENT SUSTAINABILITY RISKS .................................................. 33

6.1 Environmental Impact Assessment Regulatory Framework ..................................................... 33

6.2 Environmental and Social Risks ................................................................................................. 33

6.3 Risks to Investment Sustainability ............................................................................................. 35

7 IMPLEMENTATION PLANS, MONITORING & EVALUATION ................................................................ 41

7.1 Implementation Plan ................................................................................................................. 41

7.2 Monitoring & Evaluation ........................................................................................................... 42

8 BIBLIOGRAPHY .................................................................................................................................... 44

9 ANNEXES ............................................................................................................................................ 45

Page 4: Malawi Energy Concept Paper

iii

ABBREVIATIONS AND ACRONYMS

ADB African Development Bank AICD Africa Infrastructure Country Diagnostic study CFL Compact Fluorescent Light-Bulb COUE Cost Of Un-Served Energy DFID Department for International Development (UK Government) DoEA Department of Energy Affairs DRRM Diagnostic Review of Revenue Management project DSM Demand-Side Management EAPP East African Power Pool EIRR Economic Internal Rate of Return ENPV Economic Net Present Value ESCOM Electricity Supply Corporation of Malawi EIA Environmental Impact Assessment ESIA Environmental and Social Impact Assessment ESMAP Energy Sector Management Assistance Program GDP Gross Domestic Product GoM Government of Malawi HH Household HV High voltage IPP Independent Power Producer JICA Japanese International Cooperation Agency LRMC Long-Run Marginal Cost MAREP Malawi Rural Electrification Program MGDS Malawi Growth and Development Strategy MCA Millennium Challenge Account MCA-M Millennium Challenge Account - Malawi MCC Millennium Challenge Corporation MERA Malawi Energy Regulatory Authority MV&LV Medium-Voltage and Low-Voltage NECO National Electricity Council NGO Non Governmental Organization NRM Natural Resources Management NSO National Statistical Office PCC Project Coordination Committee PMU Project Management Unit PPIAF Public-Private Infrastructure Advisory Facility PPP Public Private Partnership PV Photovoltaic PwC PriceWaterhouseCoopers SADC Southern Africa Development Community SAPP Southern African Power Pool SCADA Supervisory Control and Data Acquisition T&D Transmission and Distribution TC Trading Center WTP Willingness-To-Pay

Page 5: Malawi Energy Concept Paper

iv

UNITS OF MEASURE

GWh Gigawatt hour (1 million kWh) kWh Kilowatt hour kW Kilowatt km Kilometer kV Kilovolt

kVA Kilovolt ampere Klh Kilolumens hour MJ Megajoule

MWh Megawatt hour (1 thousand kWh) MW Megawatt (1 thousand kW)

Page 6: Malawi Energy Concept Paper

v

CURRENCY EQUIVALENTS

US$1.00 = 140 Malawi Kwacha (MK) (January 2009)

Page 7: Malawi Energy Concept Paper

vi

LIST OF FIGURES

Figure 1: Energy Sector Program Logic Diagram ............................................................................ 5

Figure 2: MCA-M Implementation Structure for the Energy Project ........................................... 41

Figure 3: MCA – Malawi Energy Sector Program Logic................................................................. 43

Page 8: Malawi Energy Concept Paper

vii

LIST OF TABLES

Table 1: Summary of Total Estimated Costs for Project Outcomes ............................................... 3

Table 2: Preliminary Cost Estimates for Priority Investments in Malawi’s Energy Sector ........... 13

Table 3: Calculated ENPV and EIRR for Energy Sector Projects .................................................... 17

Table 4: Increase in Income of Households Being Electrified ....................................................... 19

Page 9: Malawi Energy Concept Paper

viii

LIST OF ANNEXES

Annex 1: Output of the Stakeholder Problem Tree Analysis ...................................................................... 45

Annex 2: Map of Malawi Showing Existing ESCOM Grid ............................................................................ 47

Annex 3: Transmission Projects .................................................................................................................. 48

Annex 4: Enabling Frameworks, Sustainability and Capacity Building ....................................................... 49

Annex 5: Inventory of Existing Preparatory Work ...................................................................................... 51

Annex 6: Assumptions and Parameters used in the Evaluations ................................................................ 59

Annex 7: Description of Economic Rate of Return Calculation ................................................................... 61

Annex 8: Poverty Rates by District .............................................................................................................. 66

Annex 9: Principle Beneficiaries and Benefit Impact Areas ........................................................................ 67

Annex 10: Proportion of Income generating tasks and average weekly hours worked ............................. 68

Annex 11: Gender and Rural Electrification: A Case from Bangladesh ....................................................... 69

Annex 12: Distribution of Households by Main Fuel Source Used for Cooking and Lighting ..................... 70

Annex 13: Sectors and Sub-Sectors in Malawi and Income Distribution .................................................... 71

Annex 14: Land and Population Distribution across Regions and Farm Households ................................. 73

Annex 15: Main Public Facilities and Business Entities in Trading Centers ................................................ 74

Annex 16: Electricity Rate of Entities in Electrified Trading Centers in 2003 ............................................. 75

Annex 17: Assumptions Environmental Savings on Charcoal ..................................................................... 76

Annex 18: Supporting Data for Benefits of Electrification .......................................................................... 77

Annex 19: Income Generating Benefits of Electrification ........................................................................... 79

Annex 20: Regions Affected per Project ..................................................................................................... 80

Annex 21: Map of regions affected by Energy and Transport Projects ...................................................... 81

Annex 22: Scope of Assignment ESCOM Creditworthiness Improvement ................................................. 83

Annex 23: Line Route for the 220kV and 132kV Lines ................................................................................ 85

Annex 24: Extract from ESCOM’s Draft Integrated Strategic Plan for 2009-2013 ...................................... 86

Annex 25: Implementation Timeline .......................................................................................................... 88

Annex 26: Generation Indicators and Targets ............................................................................................ 89

Annex 27: Transmission and Distribution Indicators and Targets .............................................................. 90

Page 10: Malawi Energy Concept Paper

1

1 SUMMARY OF THE INVESTMENT CASE

In December 2007 having met a number of economic, social and political indicators, Malawi

became eligible to apply for a substantial one-off investment from the Millennium Challenge

Corporation (MCC). The MCC’s overarching requirement of the Government of Malawi to be

awarded this investment is that it must be used to unlock economic growth and therefore

reduce poverty in the most effective and efficient way available, delivering demonstrable

results. Faced with this unique opportunity, the Millennium Challenge Account – Malawi (MCA-

M) has followed a rigorous process of analyzing the underlying constraints to economic growth

and in extensive consultation with stakeholders MCA-M has identified two key sectors

warranting this investment; energy and transport.

The conclusion of the constraints analysis conducted by the MCA-M team is that the key to

unlocking Malawi’s economic growth is to improve the competitiveness of Malawi’s exports,

namely agricultural and manufactured products. This conclusion is widely supported by the

Government of Malawi’s Growth and Development Strategy (MDGS) and other development

partners such as the World Bank, African Development Bank and Department for International

Development.

Whilst there are many underlying constraints to enhancing the competitiveness of Malawi’s

exports, the investment case for the energy sector is compelling because poor power

infrastructure is substantially limiting diversification of non-traditional exports and investments

in manufacturing. Malawi’s insufficient, unreliable and poor quality power supply has a

substantial effect on return on investment1, adding cost and operational risk onto producers of

exports which places Malawi as the country with the highest sales losses due to power outages

and requires more than 40% of businesses to rely on costly-generators. This is a burden to

existing businesses, compounding other disadvantages2 of doing business in Malawi but also

reduces the attractiveness of Malawi to external, new sources of investment.

Low generation capacity, unreliable transmission and distribution network coverage, lack of

investment capacity and natural resources degradation are all to blame for the high frequency

of power outages in Malawi and for the very low levels of coverage3. Without significant

investment, poor performance within the power sector is set to deteriorate further as

forecasted peak demand from 2010 continues to outstrip current installed generation capacity.

1 Economic losses relating to power outages are likely to be equivalent to 2-3% of Malawi‟s GDP

2 Such as the geographical disadvantage of being land-locked, macro-economic challenges such as currency

fluctuations, cost and accessibility of finance, poor transport infrastructure and lack of skills for industry 3 Currently at 7.6% of the entire population

Page 11: Malawi Energy Concept Paper

2

1.1 Electricity Demand and Supply Projections

Since 2001, energy demand in Malawi has increased rapidly. The number of consumers has

increased by 41% with an average increase in total energy consumption of 18.5%. The actual

installed capacity for the power system in 2007 was 285 MW of which 255 MW was available to

its customers. According to the base scenario of the power demand forecast carried out in

January 2007, generation capacity is expected to increase to 347.6 MW by 2010 due to

increased supply from Kapichira II and major rehabilitation works. On the other hand, the

projected demand indicates that Malawi will require 324.8 MW by 2010; 478 MW by 2015; and

757.4 MW by 2020.

Malawi is planning considerable investments in generation capacity in order to increase current

supply. Firstly, the Malawi Government is increasing power generation by adding 64MW of

installed capacity through the Kapichira II project which is expected to be completed by

2013/14. The Government of Malawi is yet to pass the Interconnection Bill which will allow

Malawi to tap about 300MW of power from Cabora - Bassa Dam which is expected to be part of

the grid system by 2011. In addition, the Government of Malawi in collaboration with the

African Development Bank and the government of Tanzania on plans to construct multipurpose

dams along the Songwe River Basin including hydropower plants with an installed capacity of

342MW. The project will be financed by the African Development Bank and is a ten (10) year

project between the Government of Malawi and the Government of Tanzania.

Finally, the ADB has agreed to fund the feasibility studies on Lower Fufu falls and the

implementation of the project, which is expected to be implemented in 2016, would add an

installed capacity of 144MW. In total, Malawi is expecting, between 2011 and 2021, about

850MW of installed capacity from all these investments.

More reliable transmission and distribution systems are required alongside such investments in

generation in order to efficiently use the potential installed investments that Malawi is

anticipating. In conclusion it is proposed that the request for investment from the MCC is used

to increase access to more reliable power in Malawi for economic use. A total investment

requirement of US$246.8 million has been proposed in the power sector that will target the

following outcomes:

Page 12: Malawi Energy Concept Paper

3

Table 1: Summary of Total Estimated Costs for Project Outcomes

Outcome 1: Improved Availability of Reliable & Quality Power $99,200,000

Outcome 2: Increased Access to Power for Un-served Users $63,440,000

Outcome 3: Improved and Effectively Managed Power Sector for Improved Service Delivery $23,200,000

Outcome 4: Improved Natural Resources Management of Catchment Areas around Energy Projects $4,000,000

Sub Total $189,840,000

Physical Contingency (20%) $37,968,000

Price Contingency (5%) $9,492,000

Engineering and Construction Supervision Costs (5%) $9,492,000

Total Project Costs $246,792,000

The proposed overall investment has an attractive ERR of 18.1% and demonstrable positive

impacts on both the poor and businesses of US$75.0 million, with beneficiaries ranging from

smallholder farmers, to small business owners, and users of social infrastructure (such as

schools and hospitals). Crucially, existing businesses will benefit from improved access to power

that will enhance their competitiveness on the global market by reducing generator costs and

improving their operational performance. In addition, new investment opportunities from

existing and new sources will become more attractive encouraging private sector growth that in

turn will drive new economic growth, increase incomes and ultimately reduce poverty in the

country.

Page 13: Malawi Energy Concept Paper

4

2 INVESTMENT OBJECTIVE AND OUTCOMES

2.1 Program Logic for the Investment Program

The long-term compact goal for Malawi is to promote economic growth and reduce poverty

through increasing competitiveness of agricultural and manufactured products. This goal is in

line with the Malawi Growth and Development Strategy (MGDS) and the Millennium Challenge

Corporation (MCC) goals.

The constraints to economic growth were systematically analyzed by the MCA-M team using

the HRV approach and are documented in the accompanying Malawi Constraints Analysis to

Economic Growth report. The MCA-M’s report also compliments other reports4 analyzing the

energy sector in Malawi. This constraints analysis was followed up with sector-specific

stakeholder consultations to identify a mutually exclusive, collectively exhaustive list of

problems5 that together are the root cause of insufficient and poor quality power in Malawi.

These underlying problems were then grouped in a logical framework against which desired

high level sector outcomes were defined to overcome each of these problems, supported by a

series of project-driven outputs. The result of this preparatory work helped to establish the

Compact Goal for Malawi and to set the energy sector objective for the MCC investment.

The sector objective is to ensure increased access to more reliable power for producers and

consumers for economic use. The impact of such interventions will reduce energy costs for

users as well as the number of outages and load-shedding.

At the microeconomic level, increased access to reliable power is expected to increase

productivity of farming, mining and tourism due to increased reliability, quality and connectivity

especially for farmers and businesses. These improvements in power supply will in turn reduce

poverty by increasing the productivity of rural farming, agro-processing and other economic

activities thereby increasing returns to farmers and businesses and increasing disposal incomes

and hence improving livelihoods and food security.

The improved returns in farming and businesses will also promote investments in new

businesses allowing diversification of agricultural and manufacturing exports leading to job

creation. As a result, the macro effect of the MCC investment in the energy sector will be an

increase in the value and volume of production contributing to an increased GDP/ capita.

4 The Energy Constraints Chapter of the Malawi Country Economic Memorandum (draft) prepared by DFID and the

Energy Constraints Chapter of the World Bank Country Economic Memorandum (draft) 5 See Energy Problem Tree in Annex 1

Page 14: Malawi Energy Concept Paper

5

Figure 1: Energy Sector Program Logic Diagram

Source: MCA-M

The total investment is expected to deliver four key outcomes (described below). The

individual projects that will deliver each outcome are described in Section 3, and the

beneficiaries are described in detail in Section 0. Additional background information describing

the energy sector in Malawi is provided in Section 5.

2.2 Investment Outcome 1 – Increased Availability of Quality and Reliable

Power

The largest part of the investment fund requested for the energy sector is to be used to address

the core problem of unreliable, insufficient and poor quality power. The other outcomes

address the long-term sustainability of the sector and the extension of power to un-served

areas. The investment to increase availability of quality and reliable power will deliver the

following outputs: -

COMPACT GOAL

Economic growth through increased competitiveness of agricultural and manufactured products

OUTCOME 1

Increased availability of quality and reliable power

supply

OUTPUTS

- Rehabilitated power station

- Rehabilitated transmission and distribution

systems

- Improved weed and siltation management

- Demand-side management activities

OUTCOME 2

Increased access to quality and reliable power supply to

unserved users

OUTPUTS

- Rehabitated distribution system in the southern,

central and northern regions of Malawi

- Electrification for rural and peri-urban areas in Malawi

OUTCOME 3

Improved and effectively managed power sector for improved service delivery

OUTPUT

- Strengthened capacity for MERA and Department of

Energy

- Creating an enabling environment for the

establishement of PPPs

- Improved financial sustainability and

operational efficiency of ESCOM

OUTCOME 4

Improved Natural Resources Management in priority

catchmens to sustain power sector investiments

OUTPUT

-Strengthened capacity to formulate and enforce NRM

legislation.

- Revised and harmonised NRM policies.

- improved weed and silt management systems.

-improved livelihoods through sustainable NRM business

enterprises

ENERGY COMPONENT OBJECTIVE

Increased accessiblity to more reliable and quality power supply

Page 15: Malawi Energy Concept Paper

6

a). Rehabilitated power stations – US$17.4 million;

b). Demand-side management activities to reduce peak demand growth – US$1.9

million;

c). Rehabilitated Transmission system – US$67.8 million;

d). Weed and siltation management (linking to Outcome 4) – US$7.1 million; and

e). Improvement in protection, control and data acquisition – US$4.7 million.

2.2.1 Rehabilitated Power Stations

A shortage of funds caused by low end-user tariffs for electricity and dependence on central

budgets or international financing institutions has prevented ESCOM investing adequate funds

into the refurbishment and preventive maintenance needed to reduce the poor performance of

the existing hydropower plants such as Nkula ‘A’ hydropower plant which is now over 40 years

old and is overdue for refurbishment. Refurbishment of the existing power stations has been

further hampered by the insufficient reserve capacity at these power stations, which prevents

the power plants being taken out of service. The lack of generation capacity will be relieved to

some extent by the planned investment in Kapichira-II hydropower plant (64MW) financed by

the Government of Malawi, the interconnection of Malawi’s electricity grid with Mozambique

funded by the WB (300MW), the Songwe River Basin project (342MW) and the Lower Fufu Falls

HPP project (144MW). However demand is growing rapidly and is projected to reach 325 MW,

478 MW and 757 MW for years 2010, 2015 and 2020 respectively. Given the expected load

growth, Malawi will be better equipped to meet growing demand requirements for energy.

2.2.2 Demand Side Management

A gap between the demand for and supply of electricity at peak times will be inevitable until

Kapichira-II and the Mozambique interconnector are commissioned which is unlikely to be

earlier than the end of 2012 or early 2013. Demand-side management measures could be

introduced that would delay the need for investment in new generation and transmission

capacity - this would be valuable even after Kapichira-II and the interconnector are

commissioned. Such measures would include the installation of maximum demand meters as

well as implementation of feeder metering.

2.2.3 Rehabilitated Transmission and Distribution System

Overloaded transmission and distribution networks result in unreliable electricity supply

leading to regular interruptions and voltage fluctuations that damage consumers’ (households

and businesses) electricity equipment. In order to reduce forced power outages and meet

reasonable standards for quality of supply that will encourage investment, ESCOM needs to

upgrade transmission substations that are currently or will soon become overloaded. This will

Page 16: Malawi Energy Concept Paper

7

also prepare the system for future increases in generation capacity which is projected to

increase significantly to over 800MW in the next five to ten years due to upgrading of the

existing power plants or the building of new ones. In addition to improving power system

reliability and reduce losses, improvements are urgently required in protection and supervisory

control and data acquisition systems (SCADA) for the electricity transmission network. The

SCADA system will also facilitate speedy system switching operations.

Furthermore the northern part of Malawi is currently served by a single 132 kV transmission

line that leads to poor supply reliability and cannot supply all of the existing demand in the

region. The capacity of the transmission network to the north needs to be increased in order to

increase supply reliability, which will also facilitate the transfer of power to the south via load

centers at Lilongwe and Blantyre when the hydropower plants in the north are developed6 and

from a joint hydropower project at Songwe on the border with Tanzania.

2.2.4 Weed and Siltation Management

Inadequate funds for preventative maintenance at the existing hydropower plants have been

exacerbated by the build up of siltation, weed infestation and debris in the Shire River that can

damage the turbines if allowed to pass the screens. These issues raise the need for a more

holistic approach to natural resource management to tackle the root causes of the resource

degradation (described in Outcome 4) as well as short to medium term measures to improve

operational effectiveness of the current plants.

The above outputs for Outcome 1 are expected to cost a total of US$99.2 million and success

will be measured against reducing power outages that result from generation deficits and

reducing transmission and distribution outages.

2.3 Investment Outcome 2 – Increased access to power for Un-served users

According to the Integrated Household Survey (2004-2005), less than 6% of households were

supplied with electricity and inevitably most of these were in urban centers7. For the 85% of

people who live in rural areas, only 2% of households were electrified. The Government of

Malawi has set a goal to increase the electrification rate to 10% by 2010; 20% by 2015 and 30%

by 2020. Currently, ESCOM does not have sufficient funds to extend the network to supply un-

served areas with economic potential of electricity, which also rules out neighboring areas with

small businesses or smallholder farmers that could benefit from electricity. In order to increase

access to power for un-served users, investment is required to deliver the following outcomes: -

6 Particularly the Lower Fufu hydropower plant

7 National Statistical Office, Integrated Household Survey 2004-05.

Page 17: Malawi Energy Concept Paper

8

a). Rehabilitated northern, central and southern distribution system - US$42.0 million;

and

b). Electrification for rural and peri-urban areas – US$21.4 million.

2.3.1 Rehabilitated Northern, Central and Southern Distribution System

ESCOM urgently needs to rehabilitate the distribution networks to improve distribution system

reliability and to accommodate electricity demand growth and increased access in the short,

medium and long term.

2.3.2 Electrification for Rural and Peri-Urban Areas

Transmission line extensions or strengthening works are proposed to supply areas with existing

or proposed large consumers as well as other consumers. The extension of the transmission

lines will prepare for extending the distribution networks so that access to the electricity grid

can be extended to new users. These projects will benefit the macro-and local economy, create

local employment and reduce the use of diesel generation by the large consumers.

The above outputs for Outcome 2 are expected to cost a total of US$63.4 million and success

will be measured in terms of providing electricity to an additional 20% of households by 2025

(i.e., bringing the total to 30% by 2025) including a 5.7% increase in access by rural households.

2.4 Investment Outcome 3 – Improved and Effectively Managed Power Sector

for Improved Service Delivery

Shortages of funds to finance new investment and maintain the power sector assets have

arisen partly from inadequate tariff levels and partly from ESCOM’s high losses, poor revenue

collection and high debt servicing costs. Whilst a new sustainable tariff is in the process of being

introduced, public sector funds to invest in new power generation are limited and will continue

to be limited. In order to protect and sustain MCC, GOM and other donor investments in the

sector as well as to encourage new sources of investment to build longer term generation

capacity, the project is required to deliver the following outcomes: -

a). MERA and Department of Energy Affairs (DoEA) capacity strengthened - US$3.2 million;

b). Enabling environment for PPPs - US$12.0 million;

c). Improved financial sustainability of ESCOM - US$4.0 million; and

d). Improved operational efficiency of ESCOM - US$4.0 million.

Page 18: Malawi Energy Concept Paper

9

2.4.1 MERA and DoEA Capacity Strengthened

The legal, regulatory, and policy frameworks are important to attracting future investment in

power generation in order to avoid a recurrence of load shedding. The relevant primary laws

(covering electricity, energy and rural electrification) came into force in 2008 and secondary

legislation has been drafted with technical assistance provided to the former National

Electricity Council (NECO)8. However, the DoEA needs to complete the legal framework

governing coal and renewable energy supply.

In addition to further strengthen the capacity of these organizations, both MERA and DoEA

require investment in IT-systems to improve efficiency in storing and sharing regulations, codes,

guidelines, decisions and general sector information. Furthermore, websites are required for

both organizations to share general sector information with all key stakeholders such as

potential IPPs, ESCOM and private users. In particular, the DoEA website will require

information on renewable energy and coal.

MERA has recently recruited staff and depending on the skills and experience of the new

recruits, training will be required9. DoEA staff will also require new training on implementation

of the new legislation.

2.4.2 Enabling Environment for PPPs Created

Government has begun to implement a framework that advocates the financing of future

power generating capacity by the private sector either alone or in partnership with the public

sector. Such investment is necessary to avoid power shortages re-emerging in the future. In

fact, the next major hydropower project at Lower Fufu is planned to be developed using, in

part, private finance.

A legal and regulatory framework to enable private participation efficiency has been created

but the framework is not yet adequate to attract private investment.

2.4.3 Improved Financial Sustainability and Operational Efficiency of ESCOM

ESCOM needs to be placed on a financially sustainable footing to allow it to self-finance and to

borrow to invest in on-going maintenance and improvement measures. This will allow ESCOM

to be creditworthy as a signatory for new power purchase agreements with IPPs or power

8 Regulations, codes and model licenses and agreements were developed by consultants to MERA‟s predecessor

organization, the National Electricity Council. 9 Training will be required in: 1) regulatory oversight (economic, technical and legal), 2) financial regulation, and 3)

environmental management

Page 19: Malawi Energy Concept Paper

10

plants funded and operated under public-private partnership arrangements. In recent years,

ESCOM has been able to cover its operating and interest costs only as a result of loans from

international financing institutions being written off or deferred10. ESCOM has also been

hampered by poor collection performance that has resulted in inadequate cash flows to meet

debt service obligations11. At the current tariffs which are about US$0.043, ESCOM is unable to

finance new investment or service debts relating to new investment.

As a corrective measure, ESCOM has submitted an application for a tariff increase to MERA

which will allow ESCOM to become sustainable and fund future investments. Pending MERA’s

formal approval the increase in tariffs should become effective on 1st July 200912. The MCC

investment is intended to be used to fund the large-scale installation of prepayment meters,

substantially reducing commercial losses and improving cash flow. It is proposed that

consumers with prepayment meters will be charged a lower tariff.

The above outputs designed to achieve Outcome 3 are expected to cost a total of US$23.2

million. It should be noted that the sustainability of ESCOM and the long-term sustainability of

the MCC investment requested depends on the new tariff increases being implemented. It is

also assumed that these tariffs are sufficient and that MERA has the ability to approve further

increases if necessary.

2.5 Investment Outcome 4 - Improved National Resource Management in

Priority Catchments to Sustain Power Sector Investments

Many catchment areas in Malawi are experiencing varying levels of environmental degradation

problems which are contributing considerably to diminished hydro-generation capacity

resulting in unreliable and poor quality power supply in the country. Annex 1 outlines (see NRM

problem tree for the energy sector) some of these problems and key to them is inappropriate

land use and management practices in catchment areas, particularly in the Shire river

catchment where ESCOM hydro-power generation facilities are located. Other problems

include weak enforcement of NRM legislation, conflicting NRM policies, lack of alternative and

affordable sources of energy, population pressure and lack of coherence in the institutional

arrangements to effectively coordinate and implement NRM programs. All these problems

promote deforestation, soil erosion and sedimentation resulting in unreliable and poor power

generation.

10

Part of the Highly Indebted Poor Countries debt forgiveness initiative. 11

In FY06 ESCOM was unable to meet its debt service obligations on 21% of its direct loans nor to the Government

for on-lent loans. 12

Consult Annex 6 for more in detailed information

Page 20: Malawi Energy Concept Paper

11

Although specific interventions shall be determined after the catchment management study, it

is envisaged that required investment should include the following:

2.5.1 Revised and Harmonized NRM Policies

A number of Natural Resources Management (NRM) sector policies have been developed and

are being implemented in Malawi to promote sustainable development through the sound

management of the country’s natural resources. These include the forestry, fisheries, water,

land use and management, national parks and wildlife and energy policies. However, it has now

been realized that there are significant gaps, duplications, errors and omissions, conflicts and

inconsistencies between some of these policies. These irregularities make implementation and

enforcement efforts on the policies very difficult necessitating regular reviews and

harmonization.

2.5.2 Strengthened Capacity to Formulate and Enforce NRM Legislation

Weak enforcement of NRM legislation is leading to unsustainable use and management of

natural resources in many areas in Malawi. For example, degradation of many catchment areas

and river banks could be attributed to weak enforcement of relevant sections of the forestry,

land use and water legislations.

2.5.3 Improved Weed and Silt Management Systems

The increasing amount of weed infestation and siltation being experienced in many streams

and rivers in Malawi is associated with the inappropriate land use and management practices in

catchment areas. ESCOM spends large amounts of money to dredge silt from its reservoirs and

repair damages to turbines in the power plants caused by siltation.

2.5.4 Improved Livelihoods through Sustainable NRM Business Enterprise

Over dependence on natural resources as a source of income is linked to the rapid degradation

of environment and natural resources base in Malawi. Promotion of sustainable economic

diversification through income generation activities and public-private sector partnership

technologies will reduce pressure on natural resources.

2.5.5 Improved Institutional Coordination and Extension Services for NRM

Due to ineffective institutional capacity, there are conflicting objectives and lack of coherence

in the institutional arrangements to effectively coordinate natural resources management

programs among government institutions that impact on natural resources management. These

Page 21: Malawi Energy Concept Paper

12

include Agriculture, Lands and Natural Resources, Energy and Mines, Irrigation and Water

Development and National Parks and Wildlife. There is an urgent need for government to

facilitate the establishment of a key institution to take the lead in the management and

enforcement of environment and natural resources management programs including.

The outputs designed to achieve outcome 4 are expected to cost a large sum of money and will

require the contribution of many development partners. MCC contribution to this amount will

initially be US$4.0 million.

Page 22: Malawi Energy Concept Paper

13

3 USE OF INVESTMENT FUNDS

The list of projects required to achieve each of the sector outcomes described above and

deliver the overall sector objective of “increasing access to reliable power for economic use”

are listed below. To provide an overview of the investment case we have provided a cost

estimate per project and have also provided a snapshot of the economic viability of the projects

by outcome. Preliminary cost estimates for priority investments in the energy sector amount to

US$246.8 million for all project outcomes.

A description of the assumptions used to calculate the economic rate of return and other

supporting justification is contained in Section 0 and the relevant Annexes. Section 0 also

contains a detailed description of the wider benefits and beneficiaries. Background information

on the sector concerning each of the projects is described in Section 5 and the relevant

Annexes.

Table 2: Preliminary Cost Estimates for Priority Investments in Malawi’s Energy Sector Cost Item Estimated Cost (US$)

Outcome 1: Improved Availability of Reliable & Quality Power

Output 1: Rehabilitated Power Stations

Rehabilitation of Nkula 'A' and 'B' power plants $17,360,000

Sub Total $17,360,000

Output 2: Demand Side Management Activities to Reduce Peak Demand Growth

Installation of Maximum Demand Meters $160,000

Implementation of Feeder Metering $1,760,000

Sub Total $1,920,000

Output 3: Rehabilitated Transmission and Distribution Systems

Fundi's Cross Substation in Mulanje - 12.5 MVA transformer $400,000

Area 48 Substation in Lilongwe - second 12MVA transformer $400,000

Chigumula Substation in Blantyre-second 15 MVA transformer $480,000

Chinyama Substation in Kasungu - 15 MVA transformer $480,000

Upgrade Chintheche - Mzuzu (Luwinga) line from 66kv to 132 kV - 87km (including transformation: 132/33kV) $8,240,000

Lilongwe - Mzuzu 220 kV line – 400 km $52,000,000

Luwinga - Bwengu 132kV line - 80km $5,840,000

Sub Total $67,840,000

Output 4: Weed and Siltation Management

Additional Harvester for Liwonde Barrage $320,000

Dredger for silt Management at Kapichira Power Station $3,600,000

Dredger for silt Management at Tedzani Power Station $2,400,000

Trash diversion for Nkula, Tedzani and Kapichira Head ponds $800,000

Sub Total $7,120,000

Output 5: Improvement in protection, control and data acquisition

Upgrade the protection system $1,920,000

Upgrade the transmission SCADA System $2,720,000

Procurement and Installation of distribution SCADA system $320,000

Sub Total $4,960,000

Page 23: Malawi Energy Concept Paper

14

Cost Item Estimated Cost (US$)

Total on Outcome 1 $99,200,000

Outcome 2: Increased Access to Power for Un-served Users

Output 1: Rehabilitated Distribution System

Rehabilitation of the southern electricity supply system $12,960,000

Rehabilitation of the central electricity supply system $13,280,000

Rehabilitation of the northern electricity supply system $15,040,000

Computer based mapping of distribution network assets $720,000

Sub Total $42,000,000

Output 2: Electrification for Rural & Peri-Urban Areas

Network Extension in Peri Urban Areas $7,840,000

Network Extension in Rural Areas - Implementation of MAREP Phase VII $13,600,000

Sub Total $21,440,000

Total on Outcome 2 $63,440,000

Outcome 3: Improved and Effectively Managed Power Sector for Improved Service Delivery

Strengthening of MERA's regulatory capacity $2,000,000

Strengthening of DoEA's technical capacity $1,200,000

Updating the (1998) Power System Development Plan, feasibility studies and alternative source identification $12,000,000

Implementation of Financial Sustainability Plan for ESCOM $4,000,000

Improving ESCOM's operational efficiency $4,000,000

Sub Total $23,200,000

Total on Outcome 3 $23,200,000

Outcome 4: Improved Natural Resources Management of Catchment Areas around Energy Projects

Site specific outputs shall be determined after the Catchment Management Study $4,000,000

Total on Outcome 4 $4,000,000

Subtotal on Outcome 1, 2, 3 & 4 $189,840,000

Physical Contingency (20%) $37,968,000

Price Contingency (5%) $9,492,000

Engineering and Construction Supervision Costs (5%) $9,492,000

Total Project Estimated Costs $246,792,000

Page 24: Malawi Energy Concept Paper

15

4 PROJECT BENEFITS AND BENEFICIARIES

4.1 Beneficiary Analysis

This section provides a summary of the intended beneficiaries for the power projects largely

from distribution projects. The power project will extend connections to new peri-urban and

rural trading centers which were identified by the Malawi Rural Electrification Program

(MAREP). The MAREP investment plan being proposed under the MCC targets fifty four (54)

trading centers to be electrified out of the twenty seven (27) districts in Malawi13. In total, the

target is to increase access to electricity from the current 7.6% to 30% by 2025 and to 45% by

2040 (the expected project investment return period)14.

The lack of reliable electricity available for businesses has resulted in a number of firms and

some households using generators to substitute for the unreliable power supply from ESCOM.

The MCA-M constraint analysis found that about 50% of Malawian firms use generators and the

average sales losses from power outages is now around 10% of total sales. In addition,

unreliable energy and connections to rural areas impacts largely on the environment as people

substitute electricity for charcoal use, fuelwood and use of kerosene for lighting and cooking.

This has created a devastating problem in Malawi from deforestation that is heavily affecting

catchment areas to large environmental problems resulting in loss of good arable land for

cultivation.

Recent visits by both MCC and MCA Malawi staff have found that the streams of benefits even

from off-grid energy solutions have resulted in significant reduction in the use of alternative

sources of energy such as charcoal, fuelwood and kerosene. It is currently estimated that of the

total energy consumption levels in Malawi, about 89% is through biomass consumption

(charcoal and fuelwood), 7% through petroleum, 2% through coal and 2% through electricity15.

Currently, household energy consumption makes about 80% of ESCOM’s customer base

seconded by the industrial sector with 19%16.

The beneficiary streams will, therefore, assess benefits based on the following:

a). Environmental benefits;

b). Business impacts;

13

The MAREP VII targets three (3) trading centers per district. 14

For detailed analysis of beneficiary projections see beneficiary calculations for Energy developed by MCA-M. 15

See Malawi energy consumption by source and sector (figure 1.1), p.10, in Dean Girdis and Mangesh Hoskote,

2005 16

See ESCOM website customer database on www.escommw.mw

Page 25: Malawi Energy Concept Paper

16

c). Annual gross power benefits; and

d). Annual costs of operation savings.

4.2 Key Assumptions Underlying Estimates of Incremental Costs and Benefits

4.2.1 ENVIRONMENTAL BENEFITS

The lack of reliable electricity in Malawi proliferate the use of charcoal, fuelwood and kerosene

which have significant environmental and social effects. Hydro power generation is globally

recognized as the cheapest form of energy and has an assumed efficiency of 65%. Arpaillange

(1996) estimates the assumed energy efficiency of fuelwood, charcoal and kerosene to be 15%,

25% and 35%, respectively. This shows that a lot of energy is lost when the three sources of

energy are used. Furthermore, the price paid by individuals on the three energy alternatives is

higher than the price paid for hydro powered electricity.

MCA Malawi updated Arpaillange (1996) cost estimates on the price of useful energy for

fuelwood, charcoal and kerosene which have been used to quantify both social and

environmental benefits accrued to the project. The key assumptions employed are as follows:

(a) Using Arpaillange (1996) methodology, the assumed market price for useful energy for

fuelwood, charcoal and kerosene are US$0.16/kWh, US$0.11/kWh, and US$0.35/kWh,

respectively. He also assumes that the average annual energy consumption by urban

households for fuelwood, charcoal and kerosene are 2,115 kg/year, 393 kg/year and 30

liters/year, respectively.

(b) Given information in (a) above, annual quantities consumed given assumed efficiencies

for each household are 1,410 kWh/year for fuelwood, 983 kWh/year for charcoal and

105 kWh/year for kerosene.

(c) The distribution of households by main fuel source used for cooking and lighting are

given in annex 12.

4.2.2 ANNUAL GROSS POWER BENEFITS AND BUSINESS IMPACTS

The poor state of power infrastructure in Malawi poses a major constraint on returns to

investments. This has resulted into limited diversification of non-traditional exports and

manufacturing output and investment. Median sales losses due to power outages in Malawi on

average are 10% of total sales. Furthermore, as a result of unreliable electricity, about 50% of

firms have generators which are a major cost contributor to each firm’s operations expenses.

At the national level, MCA Malawi assumes the following:

Page 26: Malawi Energy Concept Paper

17

(a) The accrued benefits once the project is initiated will increase value added on all

manufacturing products by approximately the loss in sales of 10%.

(b) There will be a decreased consumption of diesel for generators based on current market

prices.

4.2.3 ANNUAL COST OF OPERATION SAVINGS

Transmission losses, operations and maintenance costs are significantly high in the electricity

sector and the cost for producing electricity is currently at MK11/kWh (or US$0.08/kWh)

compared to the current market sales price for electricity at US$0.043/kWh. It is expected that

the revenue diagnostic study and the financial plan and least cost expansion study will

recommend ways of improving operations at ESCOM and reduce the cost of supply. Though the

actual savings will be calculated once the studies are completed, MCA Malawi assumes that the

cost of supply will be reduced by 50% over the project period.

4.3 Summary of Overall ENPV and EIRR for Energy Investments

The calculation of economic returns based on economic net present value (ENPV) and

economic internal rate of return (EIRR) are assessed using a 12.5% hurdle rate for Malawi. The

table below shows a summary of the ENPV and EIRR for the energy interventions:

Table 3: Calculated ENPV and EIRR for Energy Sector Projects

Project Type

Certainty Equivalent

100% 90% 85% 75%

Energy Calculated ENPV (12.5%) $75,038,749 $55,292,060 $45,418,716 $25,672,027

EIRR 18.1% 16.8% 16.1% 14.6%

The overall investments show that the ENPV will be US$75.0 million with an EIRR of 18.1%.

Additional details regarding the particular impact on the specific groups of beneficiaries are

described below where we have also provided preliminary estimates on the impact of the MCC

investments on domestic households and non-domestic users of electricity.

4.4 Target beneficiaries

4.4.1 Benefits to Domestic Users

The principle beneficiaries and respective benefits of the Concept Project are divided into

domestic and non-domestic users of electricity. The backlog of benefits is through the

environmental impacts such as the use of charcoal and fuelwood which pose a threat to

Malawi’s natural resources. About 89% of Malawi’s population use charcoal and fuelwood for

cooking and kerosene and candles for lighting. It is expected that the increase in electricity use

will reduce the use of biomass energy for household use. In addition, less power outages and

Page 27: Malawi Energy Concept Paper

18

less voltage fluctuations will enable electricity use to become more reliable for business use

thereby reducing the dependence on generators and use of petrol or diesel as the prices of

such commodities is becoming unpredictable and expensive on the global market.

The projects to be implemented will increase the number of electrified households and the

income of households affected by the implementation, but this differs by region. Other benefits

are more indirect and therefore less measurable17. By implementing the concept projects

potentially more than 52,600 households will be electrified due to the increased capacity in

generation, transmission and distribution of electricity. This would be an increase of more than

45% with regard to the number of domestic connections in 2007. Possible risks include

untimely installation of additional generation capacity, technical capacity of ESCOM and the

cost of connection for households.

All regions in Malawi will be affected by implementation of the projects. In each region an

additional 4 to 5% of the households can be supplied by the ESCOM grid that is fairly evenly

spread. The urban areas will notice the immediate impact of the project since most of the

beneficiaries are already connected to the grid. Through implementation of the project the

electrification rate of Malawi can potentially be increased to 45% of the population by the end

of the estimated project period on assumption that new hydropower plants are installed when

appropriate.

Within a residence electricity is mostly used for lighting, television, ironing, refrigeration,

household appliances and cooking. Radios in non-electrified households mostly run on

batteries. Outside the dwelling, households could benefit from using electricity in business and

public entities connected to the grid.

It is expected that income of households will increase by generating more income from existing

activities (see table 4) and by generating income from new activities due to an increased ability

to expand their businesses. The increase in income based on a ‘customer surplus’ calculation is

19-22%, and based on an ‘electricity attribution to income’ calculation 5-15% (See table 4 for

the impact on income of households, Annex 6 for explanation of the calculation and Annex 14

for a table of the base income generation data used by region).18

17

See Annex 7 for household characteristics and population and Annex 8 for poverty rates 18

According to the study “Household Energy Use in Malawi” in 2006 the consumer surplus for electrification of a

rural household is US$0.17-0.21/kWh (44-45 US$ per year at a consumption of 260 kWh/year) on the conservative

assumption that the area under the lighting demand curve is only 5% of the area under a straight-line approximation

Page 28: Malawi Energy Concept Paper

19

Table 4: Increase in Income of Households Being Electrified

Rural Household

(US$)

Peri-Urban Household

(US$)

Urban Household (US$)

Actual

Consumption Costs per year 17 114 211

Connection Costs 175 175 175

Willingness to Pay

Consumption per year 154 325 496

Connection and In-House Wiring 53 112 660

Surplus

Consumption per year 137 211 285

Connection and In-House Wiring -122 -63 485

Annual Income

Actual 281 593 905

Customer surplus per year 62 103 174

Increase in income per year 43 31 48

Customer surplus (%actual income) 22% 17% 19%

Electricity attribution to income (%actual income) 15% 5% 5%

As the connection costs are equal for the poor and non-poor, the poor face an impediment to

connect to the electricity grid to a greater extent than the non-poor. It is therefore proposed

that additional connection should be accompanied with a cost reduction of electricity

connection to the poor. In this case the subsidy should be made explicit, in both the

Government of Malawi and ESCOM’s books, it should be well-targeted; performance based,

and should not impact on ESCOM’s sustainability or creditworthiness.

4.4.2 Benefits to Non-Domestic Users

As already-connected business and public entities will experience fewer power outages, shorter

power outages and less voltage fluctuations, they will be more efficient in their use of

electricity and will avoid using generators. On average this will result in 10% increase in total

sales value both for formal and informal firms.19 Firms with a generator are 60% more

productive than those without and 50% of the enterprises in Malawi have generators. A

company will also run a lower risk of withdrawing from the sector in Malawi due to power

outages and poor power quality. The number of medium and small enterprises withdrawn can

be decreased by 0.12% if reliable electricity can be provided for those enterprises at risk.20

Improving the availability and reliability of power supply will also attract more investors in

Malawi who operate energy-intensive processes such as uranium diggers, heavy sand

extractors, textile manufacturers and dairies. With more reliable and low-cost electricity,

19 The median estimate for losses in production due to power outages and surges from the public grid in 2004 was

10 percent of the total sales value (both for formal and informal firms). Among firms with generators, the average

firm loses 0.5% of the median sales per year. 20

Malawi Medium and Small Enterprise Survey, 2000

Page 29: Malawi Energy Concept Paper

20

manufacturing costs are reduced which in turn should reduce the pressure on salaries and

wages and hence should also positively benefit staff income levels.

Below we have explored the impact of the MCC investment on certain key business sectors in

Malawi. Special attention is given to trading centers since they afford the rural population

easiest access to the national grid.21

4.4.2.1 Agriculture

More than 5% of the Malawian population live on an urban farm of which 30% are poor and

almost 85% live on a rural farm of which almost 44% are poor (Welfare Monitoring Survey,

2007). Knowing that more than 90% of the urban population and less than 1% of the rural

people have access to electricity we might assume that more people on urban farms would

immediately benefit from reliable electricity than people on rural farms.

Contemporary irrigation methods use electricity to transport the water. Malawi has an

irrigation22 potential of about 162,000 hectares, but only a little over 2% of the total arable land

is presently under irrigation23. Almost none of the agricultural households use modern methods

of irrigation24. The government has the plan of rehabilitating existing schemes and developing

new ones, for a projected irrigated area of 70,000 hectares by 201125.

Large-scale farms are in general highly dependent on the supply of electricity as they are often

engaged in high-value crop production, most notably that of tobacco, tea, coffee and

sugarcane. The poverty rate at a large-scale farm is 30.6% and the per capita expenditure

US$204, whereas the poverty rate is 61.0% and the per capita expenditure US$122 for small-

scale rural farmers. Large-scale farms could benefit by increased reliability of the power supply

and so avoiding use of generators26.

21

See Annex 15 for an overview of (sub-) sectors and income distribution for small and medium enterprises 22

The GoM has recognized that irrigation and water development is key to the country‟s future success, due to its

direct linkages with agriculture and energy. Irrigation will contribute towards reducing overdependence on rain-fed

agriculture, while proper conservation of water will also contribute towards the generation of electricity. 23

FAO (Food and Agriculture Organization of the United Nations), 2007 24

Integrated Household Survey 2004-2005 25

In China a 1% increase in irrigation is associated with a 0.41% rise in agricultural output per worker, resulting in a

1.13% drop in poverty incidence. (Growth, Inequality, and Poverty in Rural China: The Role of Public Investments,

S. Fan et al., 2002) 26

A sugar estate indicated that it needs to irrigate 24 hours a day in order to get the desired crop quality and a tea

estate in Malawi indicated losses of almost US$20 million a year due to power interruptions.

Page 30: Malawi Energy Concept Paper

21

4.4.2.2 Industry

The mining, textile and dairy industries are important sub-sectors with electricity sensitive

processes. The country has known mineral deposits of apatite, aquamarine, bauxite, corundum,

glass sand, granite, graphite, kaolin, kyanite, monzanite, phosphate, pyrite, salt, tourmaline,

uranium, and vermiculite. Resources of oil or natural gas are not known.27 Currently 3,246

formal employers are working in this sector and two important mining projects are starting

developing: the multi-million dollar Kayelekera Uranium Project28 and the Tengani Heavy

Mineral Sands Project. Although industrial minerals deposits are generally not of immediate

interest to international companies, local companies should seriously consider developing these

mineral deposits, which are mostly suitable for exploitation through small-scale mining for local

industries. Reliable electricity supply is an important requirement to attract investors and the

concept paper lays the foundations for this.

The current level of investment in the clothing and textile sector in Malawi is estimated to be in

the region of around US$5 million. For the textile sub-sector in particular, the investment levels

are so low that it is not possible for this sector to produce all the fabric types demanded by the

garment sub-sector. The informal garment sector provides employment to around 30,000

people country-wide. The formal garment and textile sector employs between 10,000 and

11,000 people.

The dairy industry faces a limited return due to among other things low productivity. Since the

milk processing requires a constant temperature for its storage facilities, reliable electricity

supply is critical to this industry. Five dairy processing plants, situated in the major cities of

Blantyre, Lilongwe and Mzuzu, dominate the sector. In the formal sector, there are some 4,000

dairy farmers producing around 6,500 tons of milk. The sector is mainly reliant upon

smallholders with just a few large-scale farms.

4.4.2.3 Trading Centers

An electrified trading center is mostly impacted by power outages and poor power quality. By

implementing the concept project 94% of the maize mills, 54% of the business centers and 43%

27

Ministry of Energy and Mining, 1997 28

Investor Paladin Africa requested 100% reliable electricity supply of ESCOM, which ESCOM could not

guarantee, and is using now diesel generators. Besides, there is no country in the world that can supply 100%

reliable electricity.

Page 31: Malawi Energy Concept Paper

22

of the public facilities in the electrified trading centers will benefit from having more reliable

electricity supply from the national grid, but this differs per region (see Annex 15 and 16).29

4.4.3 Other Secondary Benefits

4.4.3.1 Health Benefits

Because of the complex relations between health, lifestyle, environment and infrastructure, it is

difficult to quantify the impact of the concept project on the health of the individuals affected.

A study on electrification in Bangladesh30 reported that the average annual healthcare

expenditure by the electrified households was 44% higher than their non-electrified

counterparts. The annual health care expenses for the females of electrified villages were 85%

higher than those in the households of the non-electrified villages and 104% higher than those

in the non-electrified households of electrified villages.31 It is not known whether this can be

attributed to the fact that the households already have higher incomes as evidenced by the

ability to afford electricity or whether it is due to increased media awareness through TV and

radio access.

Reliable availability of electricity could also benefit the quality of health services and lower

costs by extending opening hours and significantly strengthening the cold chain for vaccines32.

In addition, worker absenteeism in both health clinics and schools can be reduced by improving

living conditions and morale. However, no study has been undertaken in Malawi to quantify the

impact.

4.4.3.2 Supporting Education

Educational benefits associated with electrification have also been documented. Reading is in

general easier with electricity compared to paraffin lamps.33 Television might take reading time

away, but electrification increases the reading time of both adults and children in the

household once the adult and/or child decides to read. Once individuals chose to read or study,

electricity was also found to increase the time the children spent studying by 77 minutes and

29

See Annex 15 for an overview of the main public facilities and business entities (including maize mills) in

Trading Centers 30

Economic and Social Impact Evaluation Study of the Rural Electrification Program in Bangladesh, 2002,

NRECA International Ltd. Partners with the Rural Electrification Board of Bangladesh and USAID for the Rural

Power for Poverty Reduction (RPPR) Program 31

The previous MAREP programs were not accompanied by impact evaluations 32

In the medical field, "paraffin refrigerators" (fuelled with kerosene) are used for storing vaccine. However,

kerosene is sold for high prices in the market, and several clinics have been installed with independent power

sources to preserve vaccine. 33 Kerosene lamps provide 10-50 times less light than an incandescent lamp, depending on the type of bulb.

Page 32: Malawi Energy Concept Paper

23

the time adults spent reading by 27 minutes per electrified household per day, compared with

non-electrified households.34

Electrification of a secondary school in Malawi could increase the rate for passage of qualifying

examinations for advance to higher grades and graduation from on average 30% to 80%.35,36

Primary schools are less dependent on electricity as secondary schools assuming that primary

schools are using fewer electric appliances and most of them are closed during the afternoon

and evenings.37 Assuming that schools offering higher education already use electricity they will

benefit from increased reliability of electricity supply and if using own generators during a

power outage from avoided use of alternative energy sources. In areas where there are off grid

energy solutions such as the solar-hybrid energy systems, students in secondary schools nearby

are able to read for two to three hours in the evening and able to offer other subjects such as

basic computer applications.

4.4.3.3 Improving Women’s Socio-Economic Status

Electrification can also contribute to the positive development on women’s socio-economic

status. Possible benefits of having electricity are the women’s mobility, more free time from

chores, knowledge about gender inequality issues, household work plan according to

convenience, changes in attitude in terms of reducing healthcare disparities, increase in overall

years of schooling for both boys and girls, preference to send girls to schools, and awareness of

legal issues. Women in electrified households are involved more in household level income-

generation activities and tend to reallocate time to remunerative employment. These

qualitative assumptions are supported by a quantitative analysis of the impact of rural

electrification on the changing socio-economic status of women in Bangladesh (see Annex 11).

4.4.3.4 Reducing Environmental Harm

4.4.3.4.1 Charcoal, Fuelwood and Kerosene Use

Almost half the charcoal in Malawi comes from forest reserves, 10% from national parks and

almost 40% from customary land. Households mainly use firewood and charcoal for cooking,

and paraffin for lighting as alternative energy source for electricity.38 About 98% of rural

households, 64% of households in Lilongwe and 42% in other cities use firewood for cooking.

34

Based on data from Demographic and Health Survey for 11 countries, Independent Evaluation Group, World

Bank 35

Master Plan Study on Rural Electrification in Malawi, 2003 36

This most certainly cannot be attributed to electric lights alone. Obviously, those schools with lights are better in

lots of dimensions, including probably the preparedness of students attending them. 37

On the other hand, 25% of the pupils in primary school experience facilities at school in bad condition (source:

Welfare Monitoring Survey 2007, National Statistical Office) 38

See Annex 12 for percentage distribution of households by main source of fuels used for cooking and lighting

Page 33: Malawi Energy Concept Paper

24

With the MCC investment implemented and if people use electric stoves when connected we

expect a 3% decrease on charcoal equivalent forest area cleared.39 At a consumer-level, urban

consumers with access and means can be expected to substitute the more convenient and

modern electricity for fuelwood and charcoal as a primary cooking fuel.40

Assuming a household without electricity uses 2,115kg of fuelwood and a household with

electricity uses 393kg of charcoal per annum41 then the consumption of charcoal can be

reduced significantly once a household gets connected to the grid.42 On average, urban

households using paraffin for lighting and not for other purposes saves 30 liters of paraffin

(kerosene) per year once it uses electricity for lighting, and a rural household 14 liters per year.

If a household would use electricity instead of firewood it could save about US$105 a year for

charcoal use and US$226 a year for fuelwood43. On the other hand a household needs to

purchase a small electric stove if it starts using electricity for cooking, estimated at a cost of

US$18-36 per stove with a warranty of one year.

On the negative side, since the number of charcoal producers will be decreased the self-

employment will be impacted negatively, equivalent to a reduction of 0.48% of the number of

small-scale producers, 0.8% of the medium-scale producers or 0.6% of the large-scale

producers. These producers will need to find alternative sources of income; however with

increased access to electricity the opportunities to engage in other activities are expected to

increase.

Selling of charcoal has increased significantly in recent years, estimated at an average of 230

thousand tons/year, up from 140 thousand tons/year in the 1990s. Charcoal production is

wasteful as traditional kilns are only 10% efficient and therefore a large volume of wood is

required to make a small quantity charcoal. Only a small percentage (20-30%) of the economic

chain benefits the producer, the rest enters the informal economy of middlemen and retailers,

and as a result, government loses out on tax earnings. There is need to promote alternative and

affordable sources of energy in order to reduce the increasing environmental damage caused

by charcoal making and trading.

39

See Annex 17 for assumptions 40

Household Energy Use in Malawi, 2006 41

Based on data from the study “Charcoal: The Reality; A Study of Charcoal Consumption, Trade and Production

in Malawi” submitted to the Forest Governance Learning Group, 2007 42

At a price of US$ 0.17 per kg equivalent to a yearly saving of more than US$10. According to the study

“Household Energy Use in Malawi, 2006” a household spends approximately US$105 per year on charcoal. 43

Calculations are based on Arpaillange (1996) base consumption estimates.

Page 34: Malawi Energy Concept Paper

25

4.4.3.4.2 Weed Infestation

Malawi is spending considerable amount of money to address the problem of weed infestation

in many rivers and other water bodies. The problem has seriously affected hydro-power

generation plans where ESCOM is spending approximately US$550,000 annually to manage the

weeds. There is inadequate information on the nature and dynamics of the weeds and

therefore Government has initiated a comprehensive national study to allow for realistic,

practical and long term solution to the problem.

Through the study, an integrated weed management plan will be produced for all the

catchments in the country and this will be a framework for future national programs to address

the weed problems. However, it will probably take many years before the study is completed as

government has not yet identified funds for the study. The catchment management study to be

supported by MCC includes a weed study component at micro catchment level which will come

up with urgent solutions affecting the power generation. The results of the study will be

incorporated in the proposed national study when it is completed.

4.4.3.4.3 Siltation

In 1994, the cost of environmental degradation in Malawi was approximately USD 245 million,

an estimated 11.5 % of GDP. Today, given that environmental conditions have deteriorated

further, the cost is probably higher. Siltation from cultivated areas is compounded by

inappropriate farming practices and inadequate extension messages. This calls for extensive

reform in the protection and management of land use systems and improvement in the

enforcement of environment and natural resources management laws and extension services in

some parts of the country particularly in environmentally sensitive catchment areas to address

the problem of rapid environmental degradation.

4.4.3.4.4 Public Awareness

This is an important element in the promotion of sustainable land use and management

practices in catchment areas to reduce environmental damage. Special training in Community

Based Natural Resources Management and other conservation technical skills should be

provided, through academic institutions and NGOs, to farmers and other service providers.

There is also need to sensitize the general public on available alternative energy sources

(energy efficient stoves, solar panels, briquettes, etc).

Page 35: Malawi Energy Concept Paper

26

4.4.4 Rural Areas

Investments in the energy sector will immediately have an impact on the existing customers in

the rural area already having connection to the national grid as well as new customers which

will benefit from having electricity for the first time. Most connections in rural areas are

residential. These customers will experience fewer power outages and improved power quality,

resulting in fewer interruptions in using lighting and electric devices and less burn-outs of

electric devices.

Page 36: Malawi Energy Concept Paper

27

5 SUPPORTING TECHNICAL INFORMATION

5.1 Sector Description

An inventory of the existing studies from which this paper has drawn for background

information is listed in Annex 5. In the following section key information about Malawi’s energy

sector is summarized so that the request for investment from the MCC can be put into context

within the wider energy sector in Malawi and more broadly within Southern Africa.

ESCOM is a state-owned national power company that currently owns and operates Malawi’s

major power plants, the national transmission grid and distribution network, and supplies

electricity to final consumers. Currently ESCOM has an installed generating capacity of 285 MW

connected to the national transmission grid. The interconnected grid, comprising of 132 kV and

66 kV transmission lines, is supplied from three main hydropower plants at Tedzani (93 MW,

commissioned in 1972 with an extension in 1995), Nkula A and B (124 MW, commissioned in

1966 with an extension in 1981) and Kapichira Falls I (64 MW, commissioned in 2000). A 15 MW

gas turbine in Blantyre, commissioned in 1972, was designed for back-up but is no longer

available and will be retired shortly. The main hydropower schemes are all located on the Shire

River whose source is Lake Malawi.

ESCOM’s transmission network is currently isolated from neighboring countries (other than

small cross-border distribution) but is a member of the Southern Africa Power Pool (SAPP).

Because of its physical isolation, it is not currently able to trade electricity. However, when the

planned 220 kV interconnector with Mozambique having a potential capacity of distributing

300MW is commissioned (see below), Malawi will become an operating member of SAPP and

will initially purchase 100MW of power from its neighbor from the Hydro Cabora-Bassa (HCB)

power complex to meet the existing demand. In the longer term, connection to SAPP allows the

possibility of both exports as well as imports under long-term contracts or short-term trading to

fill immediate shortages. Importantly, the possibility of imports (without necessarily the

imports themselves) helps reduce the risks associated with dependence on a single river – the

Shire – as the source of almost all of Malawi’s power generation.

To the north, Malawi’s power grid is isolated from that of Tanzania, but the proposed Songwe

multi-purpose dams with an installed capacity of 342MW hydropower plant offers the

possibility of a second interconnection with Tanzania and later the East Africa Power Pool

(EAPP) when Tanzania joins EAPP44.

44

It is currently estimated that the installed capacity on the EAPP along the Congo River is approximately

3,000MW.

Page 37: Malawi Energy Concept Paper

28

In 2003, the Government of Malawi approved a Power Sector Reform Strategy (PSRS) and

subsequently enacted three legislative documents (relevant to this Concept Project) that were

approved by Parliament in 2004 vis-à-vis: the Energy Regulation Act, the Electricity Act and the

Rural Electrification Act.

The legislation required the creation and licensing of a transmission company, one or more

generation companies, and one or more distribution companies. The transmission company

was also to be the single buyer of electricity from the generators and the seller of electricity to

the distribution companies. The legislation also created the Malawi Energy Regulatory

Authority (MERA) to replace the existing National Electricity Council (NECO). There was some

delay in taking the step required to bring the legislation into force but this step was finally

taken in 2008 though the Electricity Act was not fully enacted45.

In preparation for the new law, ESCOM has created generation, transmission and distribution

business units under a holding company structure (though not established as companies). The

company is divided into the three business units, two holding company divisions and the office

of the Chief Executive Officer.

The PSRS envisioned that new power generation capacity would be developed by the private

sector as independent power producers (IPPs) contracted by the transmission company. The

new law requires that tendering for the capacity required by the transmission company be

supervised by MERA.

PriceWaterhouseCoopers (PwC), on behalf of the Privatization Commission46 reviewed the PSRS

in 2007 and recommended the creation of an ESCOM holding company with three separate

generation, transmission and distribution subsidiaries, and with the transmission company

initially responsible for the buying and selling function. PwC also made recommendations

relating to private participation in ESCOM.

The role of policy making in the energy sector is the responsibility of the Ministry of Energy

through the Department of Energy Affairs (DoEA). DoEA is also responsible for implementing

Malawi’s rural electrification program and off-grid renewable energy programs. Several

components of the Concept Project are designed to assist in implementing the policy approved

in the PSRS and enshrined in the legislation, including:

a). Developing the framework that will attract private investors in IPPs;

45

The captioned sections are Part II, section 4 and all of Parts IV and V 46

ESI: ESCOM PSP Review and Validation Report, PwC for the Privatisation Commission, November 2007.

Page 38: Malawi Energy Concept Paper

29

b). Developing the framework to regulate the power sector, including private generators

and public-private partnerships (PPPs); and

c). Preparing a least-cost investment plan to identify which power plants should be

developed and contracted by the transmission company as well as identifying

necessary transmission investments.

5.2 Recent, On-Going or Expected Investments

As part of its day-to-day activities, ESCOM routinely undertakes investments in transmission

and distribution and connection of households in both urban and peri-urban areas. Rural

electrification is the responsibility of the Ministry of Energy and Mines. The investments listed

below are larger scale projects undertaken by ESCOM or projects undertaken by DoEA or other

Government bodies.

5.2.1 Refurbishment of Hydro-Power Plants

ESCOM has undertaken the rehabilitation of three units at Nkula B and this was self-financed by

ESCOM. Rehabilitation of Nkula A and further work on the other two units at Nkula B is planned

when there is sufficient spare capacity on the system (i.e., when Kapichira-II is commissioned)

to allow the plant to be taken out of service. This rehabilitation is included in the Concept

Project.

The Tedzani I & II hydropower stations have been out of operation since December 2001 and

are currently undergoing complete refurbishment including rewinding of the stators, the

reconditioning the turbines and auxiliary equipment, rehabilitation of intake structures and

introduction of a SCADA system. Most of the work is completed and this is expected to be fully

complete by around the end of February 2009. The refurbishment will have restored to service

the 40 MW of capacity that was not available since 2001. This project costs US$16.5 million and

was undertaken on a trade-financed basis that took several years to arrange, and encountered

a number of challenges along the way.

Further investment is required in trash screens, dredging and weed-control equipment in order

to prevent future damage of the type that led to the refurbishment of the existing hydropower

plants and led to capacity deficits. These additional investments are included in the Concept

Project.

5.2.2 Kapichira-II

The Kapichira-I hydropower plant, commissioned in 2000, currently has 2 x 32 MW units but the

civil works were designed to allow an additional 2 x 32 MW units to give a total capacity for the

Page 39: Malawi Energy Concept Paper

30

four machines of 128 MW. Kapichira-II is expected to cost US$52.8 million including the

associated construction of 30km of 132kV transmission line from Kapichira to Blantyre West

Substation and substation equipment to evacuate the additional power47. Funding for

Kapichira-II was approved by the Government of Malawi from the Development Fund.

Completion of Kapichira-II is crucial to the strategy of relieving the constraints described in

Section 1, but it is not sufficient by itself to relieve constraints on the supply of reliable

electricity to existing consumers and to widen access to new consumers. Investments in

generation must be combined with the investments in transmission and distribution that are

included in the Concept Project in order to achieve the intended goals. As discussed in Section

6, we note that failure to complete Kapichira-II would jeopardize the success of the Concept

Project in improving the reliability and availability of electricity in Malawi.

Consideration was given by the Government of Malawi to the involvement of the private sector

in developing Kapichira-II but given the physical characteristics of the Kapichira site and the

many facilities used in common by Kapichira I and II, private sector participation was not

considered feasible or necessary.

5.2.3 Interconnection with Mozambique

A 220 kV interconnector with Mozambique is planned with financing by the World Bank. This

will run from the existing Matambo substation in the Tete Province of northern Mozambique to

a new substation at Phombeya located in Malawi’s Balaka District, north of Blantyre. The line

will have a maximum capacity of approximately 300 MW but initially it is expected to provide

an initial minimum capacity of 50 MW when it is commissioned in 2012 and will allow exports

when Malawi has excess capacity. The total capital cost of the interconnector is estimated at

US$109 million of which approximately US$60 million is for the Malawian portion of the line

including associated investments to improve infrastructure to support electricity trading, as

well as technical support. The World Bank’s Board approved the loan in 2007. An

Interconnection Bill to approve the project is currently before Parliament and is expected to be

approved before 31 August 2009.

We note that, as with Kapichira-I, the additional capacity provided by the Mozambique

interconnector by 2012 will be crucial to the success of the Concept Project in improving the

reliability and availability of electricity in Malawi. Despite investments in transmission and

distribution, if there is insufficient generating capacity then power supply will be inadequate

and load shedding will continue.

47

World Bank estimates US$60-65 million.

Page 40: Malawi Energy Concept Paper

31

5.2.4 Rural Electrification - MAREP

MAREP - Malawi Rural Electrification Program - started in 1980 and since 1995 has been

implemented by DoEA. Four phases of MAREP have been fully implemented and, as of January

2009, a fifth is almost complete. The program involves extensions to transmission and

distribution lines to administrative centers, trading centers and tobacco growing areas.

MAREP IV was completed in May 2007 and extended grid access to 97 trading centers

countrywide (more than originally targeted). The total cost was MK 680 million (US$4.8 million),

of which MK 188 million (US$1.3 million) was provided by the Japanese Government under

debt relief grant aid. The balance was financed from local resources through a levy on

petroleum product sales (the fuel levy).

MAREP V benefits 27 trading centers at a cost of MK899 million (US$6.3 million). The Malawi

Government provided MK84 million from the Development Fund, MK404 million from the fuel

levy and MK215 million from a MERA establishment fund. The Japanese Government is

providing the balance of MK196 million through the Japanese Non-Project Counter Value funds.

MAREP V was expected to be completed in October 2008 but has been delayed by the heavy

rains. At the time of preparing the Concept Paper in January 2009, it had almost been

completed.

MAREP VI will electrify a further 54 trading centers. The trading centers to be electrified have

been identified based on the 2003 Rural Electrification Master plan study (see Section 3) and

field teams were sent out in January 2009 to prepare feasibility studies and design the schemes.

These studies are expected to be completed within two months. MAREP VI will be funded in

part from the fuel levy and, it is hoped, continued support from the Japanese Government. The

cost will be estimated after the feasibility and design studies have been completed but this

phase is expected to cost approximately MK 2,400 million (US$16.5 million). The cost per

trading center for MAREP VI (and for MAREP VII below) is considerably higher than previous

phases because the earlier phases had targeted the easier-to-reach trading centers.

A MAREP VII project will continue the program of electrification described in the 2003 Master

plan and targets to electrify 81 trading centers.

5.2.5 NRM Projects

The projects listed below are at different levels of formulation or implementation and will

contribute significantly to poverty reduction and environment and natural resources

protection.

Page 41: Malawi Energy Concept Paper

32

Agriculture Sector Program: Supported by the World Bank and others, includes

Sustainable Land Management and agriculture policy reforms in food security

Mainstreaming Sustainable Land Management and Climate Change Adaptation in the

Shire River Basin: supported by UNDP, focuses on integrated watershed management

and community based natural resources management to reduce land degradation.

Community Based SLM for small holders; a World Bank supported initiative in the

Agriculture Sector Program (under CAADP) to improve land management

Nyika Plateau Community Conservation-UNDP/GEF; targets sustainable management of

the Nyika Plateau ecosystem.

Mulanje Mountain Conservation Trust (MMCT)-an endowment fund looking after the

conservation of the biodiversity of mount Mulanje.

Malawi Environmental Endowment Trust (MEET)-offers grants for community project in

environment and natural resources.

COMPASS - A USAID financed civil society and local government initiative promoting

environment as economic goods for community based natural resources management

and development.

Promotion of alternative sources of Energy-supported by the Malawi Government aims

at promoting the utilization of various market ready viable alternative sources of

energy to substitute firewood and charcoal.

Community Environmental Micro-projects-supported by USAID under the NATURE

program and implemented by the Ministry of Local Government through the

department of Environmental Affairs, promoted community based environment and

natural resources projects.

Page 42: Malawi Energy Concept Paper

33

6 ENVIRONMENTAL, SOCIAL & INVESTMENT

SUSTAINABILITY RISKS

6.1 Environmental Impact Assessment Regulatory Framework

The Malawi government adopted both the Environmental Policy and Environmental

Management act in 1996 to provide guidance and set standards for the development of sector

policies in environment and to promote the sustainable use and management of the

environment and the conservation of natural resources.

Among other provisions, the Act established the Department of Environmental Affairs as the

government watchdog to coordinate implementation of environment and natural resources

programs in Malawi through the National Council for the Environment (NCE) and the Technical

Committee on the Environment (TCE). The Council is composed of sector representatives and

acts as the advisory body to the Minister while the Technical Committee gives technical advice

and information to enable the NCE to give informed advice to the responsible Minister.

The Act also provided for the EIA process which requires that potential environmental

consequences of major development projects be identified and considered before project

activities are undertaken. To facilitate this process, EIA guidelines were prepared and adopted

in Malawi in 1997.

The Environmental Policy was revised in 2004 and provides for the establishment of an

autonomous Environmental Protection Agency (EPA) because there are limitations for the

Department of Environmental Affairs to compel fellow departments to comply with relevant

NRM policies and legislation. The EPA will have adequate political visibility and authority to

compel compliance and enforcement with applicable NRM laws and policies. The

Environmental Management Act has been revised and provides a legal framework for the

establishment of the Environmental Protection Agency. It is now awaiting parliamentary

approval.

6.2 Environmental and Social Risks

With one or two exceptions, the Concept Projects do not have significant detrimental

environmental or social impacts. All the projects in the power sector were thoroughly screened

to determine if environmental and social impact assessments were conducted or required for

new projects. The outcome of this screening process was as follows:

Page 43: Malawi Energy Concept Paper

34

6.2.1 Generation Systems Improvement Projects

The procurement of the additional weed harvester for the Liwonde Barrage will require the

identification and acquisition of suitable sites for the disposal and sustainable management of

harvested weeds. An Environmental Management Plan will be required to provide guidelines

for this and the development of the guidelines will be part of the Catchment management

Study

The procurement of the dredgers for siltation management will also require the development

of an Environmental Management Plan, which will provide guidelines for the disposal and

sustainable management of the silt.

6.2.2 Transmission Projects

The development of the new substations and looping of existing lines at new sites in Blantyre

and Lilongwe will not require Environmental and Social Impact studies as these will be

established in existing ESCOM sites. Issues to do with any possible encroachments will be

resolved using the existing mechanisms and responsible authorities.

The construction of new transmission lines and upgrading of existing lines will require

environmental impact assessments as the lines will pass through ecosystems with varying

biodiversity and land use practices. All the proposed lines pass through uninhabited areas and

will not involve the resettlement of people.

6.2.3 Distribution Projects

Peri-urban electricity access will involve the installation and retrofitting of equipment on

existing distribution substations and overhead lines within existing servitudes. No adverse

environmental and social impacts are expected.

6.2.4 Projects Requiring Environmental Impact Assessments

a). The Lilongwe – Mzuzu 220 kV transmission line extension that may potentially pass

through ecologically sensitive areas and human settlements requiring resettlement

action plans.

b). Relatively short 132 kV and 66 kV transmission line extensions may also potentially pass

through forested areas and environmental impact assessments may be required.

c). Whilst weed management, siltation management and trash diversion works on the

Shire River are relatively small-scale activities, may have environmental impacts and

environmental assessments should be undertaken.

Page 44: Malawi Energy Concept Paper

35

d). Rehabilitated Transmission and Distribution Systems projects will require

Environmental and Social Impact Assessments

e). Some of the projects covering Electrification for Rural and Peri-Urban Areas will require

Environmental and Social Impact Assessments.

6.3 Risks to Investment Sustainability

This section identifies risks to the sustainability of the MCC investment and describes measures

planned or needed to ensure that the benefits from the Concept Project can be sustained

beyond the period of MCC financing.

6.3.1 Complementary Measures to Increase Generation Capacity

The success of the Concept Project depends crucially on the completion of Kapichira-II to

increase Malawi’s available capacity by 64 MW and the commissioning of the interconnector

with Mozambique to allow the import of a further 300 MW of power. The Ministry of Finance

has approved funding for Kapichira-II and the plant is expected to be completed within two

years by the end of 2011. Work on the Mozambique interconnector is pending formal approval

by Parliament of the Interconnector Bill and once approved is expected to be completed by

2012.

Furthermore, the Government of Malawi financed the preparation of preliminary feasibility

studies and designs for some of the projects on the Songwe River in the 2008/09 financial year

which is currently being implemented under the Ministry of Irrigation and Water Development.

The river has a potential of constructing a hydropower plant with an installed capacity of

342MW which will benefit Malawi and Tanzania in the longer term. It is expected that the

source of funds for this project could be committed from the African Development Bank. The

African Development Bank will also finance the full feasibility studies for the Lower Fufu Hydro

Power Plant which has a design capacity of 144MW. This HPP is expected to be installed within

the MCC impact period.

In addition, the project will depend on other investments being promoted by the MCC project

through the construction of mini-hydro power plants of 5MW of installed capacity and

promoting existing energy initiatives by local private companies such as the molasses-power

plant developed by the two Sugar companies in Malawi which have an installed capacity of

14MW each.

Page 45: Malawi Energy Concept Paper

36

6.3.2 Sector Reforms

In 2003, the Government of Malawi approved a power sector reform strategy (PSRS) and

subsequently enacted legislation that was approved by Parliament in 2004 and which came into

force in 2008. This required the creation and licensing of a transmission company, one or more

generation companies, and one or more distribution companies. The transmission company

was also to be the single buyer of electricity from the generators and the seller of electricity to

the distribution companies. The legislation also created the independent regulator – the

Malawi Energy Regulatory Authority (MERA) to replace the existing National Electricity Council

(NECO).

The PSRS envisioned that new power generation capacity would be developed by the private

sector as independent power producers (IPPs) contracted by the transmission company. The

new law requires that tendering for the capacity required by the transmission company be

supervised by MERA.

ESCOM is currently operating as a holding division with three separate generation, transmission

and distribution divisions, and with the transmission division initially responsible for the buying

and selling function. A study prepared for the Privatization Commission by

PriceWaterhouseCoopers recommended that private sector be invited for participation in

ESCOM as a holding company with subsidiary generation (existing power plants), transmission

and distribution companies, and with new power plants being developed by independent

power producers. Continuation of Government’s reform strategies is important for the

sustainability of the Concept Project.

6.3.3 Watershed Management

The problems of siltation and weed infestation affecting ESCOM’s existing hydropower plants

on the Shire River, have potentially have arisen from poor protection of the catchment areas

in the Lake Malawi and Shire river systems, resulting in poor and unsustainable power

availability. These problems are widely linked to changing land use and management practices

in the catchment areas (see annex 21: map of Malawi showing major catchment areas).

It should, however, be noted that improved catchment management policy entails recognizing

that environment and natural resources protection requires political will, stakeholder

commitment and adequate resources. In addition, it must be recognized that the desired

poverty impacts may not be achieved in the shortest possible time. This investment will,

therefore, need to be complimented by activities that enable the establishment of

demand/productive uses, rural uptake and ability to pay. Catchment protection and improved

land use management practices will thus have major benefits to hydropower plants in Malawi

Page 46: Malawi Energy Concept Paper

37

and will improve generation capacity, power availability and reduce the need for dredging and

other river management practices that are currently necessary to ensure the continuous

operations of the power generation plants.

6.3.4 Operations & Maintenance – Financial

Financial resources have, in the past, been inadequate to ensure proper maintenance of

generation and transmission assets and this has led to problems of poor generation availability

and reliability that the Concept Project is seeking to address through investment in

rehabilitation of hydropower plants and control of sedimentation, weed growth and debris in

the river. Inadequate financial resources have also led to low levels of investment in

transmission and distribution, leading to overloaded equipment, low supply reliability and poor

quality supply.

Plans are underway to improve the financial viability and sustainability of ESCOM through the

Financial Sustainability Study and the Diagnostic Review of Revenue Management Study48. The

recommendations of these studies will be implemented through the Concept Project and will

help ensure ESCOM’s viability and the financial sustainability of the power sector. Issues

affecting the company’s financial position that will be addressed by the two studies include:

a). High losses in transmitting and distributing electricity (losses of over 19%);

b). Devaluation of local currency;

c). High leverage;

d). Inadequate capital investment;

e). Poor collection performance (average debtor days ratio of 184, representing a value of

about US$30.5 million); and

f). Poor business culture.

While ESCOM’s accounts for the past four years show that ESCOM has covered its operating

costs, including depreciation, bad debt provision and interest costs, from its tariff revenue, this

has partly been achieved because debts on-lent from Government have been deferred49 or

converted to equity. This will be unsustainable. At the current tariffs, ESCOM would be unable

to finance new investment or service debts relating to new investment.

To ensure operation and maintenance of the projects can be sustained after implementation,

ESCOM needs to cover its operating costs and attract financing. This in turn requires that tariff

levels be regulated to ensure financial viability while, at the same time, ensuring that costs are

48

Request for Proposals for Consultancy Services for Development and Monitoring of ESCOM Financial

Sustainability Plan, final version March 2008 49

Relating to the Highly Indebted Poor Countries initiative.

Page 47: Malawi Energy Concept Paper

38

kept to the minimum necessary level. The newly established independent regulatory authority

– MERA – has an important role to play in this regard50. ESCOM has also taken short term cost

cutting and administrative measures including, among others, employees’ expenses, hiring of

vehicles, revenue collection and procurement.

ESCOM submitted an application for a tariff increase in January 2009 and public hearings were

held in early February. A decision is expected to be taken on the application in July. The tariff

application proposed a multi-year tariff formula covering the years 2009 to 2013 thereby

helping secure adequate levels of revenues for ESCOM over that period.

6.3.5 Operation & Maintenance - Institutional

Staff in ESCOM’s generation business unit have long experience of operating hydropower plants

but have been hampered by problems in financing measures to reduce the risks to turbines and

generators caused by trash and sediment. The measures in the Concept Project should relieve

these problems. Improved revenues when the new regulatory framework becomes operational,

combined with the financial improvements described in Section 6.1, should ensure that

financial constraints do not hamper proper maintenance practices in future so that operational

improvements will be sustainable.

Similarly, financial improvements will facilitate investments in the transmission network,

reducing overloading transformers and lines and ensuring a transmission network that

maintains a reasonable level of reliability and reduces technical losses. MERA is currently

drawing up licenses for generation, transmission, distribution, import and export. The licenses

follow the by-laws of the electricity act and aim at setting standards for the various

performance areas51. In case a licensee fails to meet the performance standards, MERA may

levy penalties on the licensee or terminate the license.

6.3.6 Tariffs and User Fees

ESCOM is a vertically integrated power company though generation will be open to private

sector participation for all future power plants after Kapichira-II. The services provided by

ESCOM are financed through regulated tariffs charged to electricity consumers. Both the level

of the tariffs and the tariff structure are, under the Energy Regulation Act which came into force

in 2008, regulated by MERA.

50

ESCOM‟s application for a new, cost-reflective tariff is being processed by MERA and a decision on approval

will be made by 1st July 2009. See ESCOM‟s website (www.escommw.com) for ESCOM‟s tariff application.

51 Performance areas identified include installation permits, supply and quality of service, safety code rules, wiring,

customer service and tariffs and charges

Page 48: Malawi Energy Concept Paper

39

Over the past four years to fiscal year 2007, ESCOM covered its operating costs (including

depreciation and bad debts) and interest costs from its tariff which is currently about

US$0.043/kWh but this was achieved largely because loans from international financing

institutions were written off or deferred. At the current tariffs, ESCOM would be unable to

finance new investment or service debts relating to new investment. In the fiscal year 2006,

ESCOM was able to pay only 79% of debt service obligations to lenders that had extended

direct loans to the company, but it has been unable to meet its debt service obligations on the

remainder of direct loans and to the Government for on-lent loans.

ESCOM submitted an application for a tariff increase to MERA in January 2009 and public

hearings were held in February 2009. The application requested an average tariff increase of

54% over a period between 2009 and 2013. This level of increase is consistent with an

assessment conducted by PwC for the Privatization Commission52 which suggested that tariffs

needed to increase to approximately US$0.065/kWh in order to allow ESCOM to attract

financing of future investments.

An increase in tariffs is considered crucial to avoid a recurrence of load shedding when the

Concept Project investments end. This increase will prepare ESCOM to add more generation

capacity including the Lower Fufu HPP.

6.3.7 Legal and Regulatory Issues

The energy sector laws passed by Parliament in 2004 were ‘gazetted’ by the Ministry of Energy

and Mines in 2007, thereby making part of these laws effective. The legislation, and the Power

Sector Reform Strategy that preceded it, were intended to create a framework that would:

a). Improve technical and economic efficiency (including improvement in the reliability

of electricity supply and reduction in load shedding, improvement in the

maintenance of power plants, and reduction in waiting lists for new connections).

b). Improve commercial performance. This includes placing ESCOM in a position where it

can finance substantially more investments from its own balance sheet and

improvements in commercial (non-technical) losses and reductions in outstanding

debtors.

c). Take advantage of power trading opportunities under SAPP allowing Malawi to be

either an exporter or importer of electricity.

d). Make electricity accessible to a large proportion of the population.

e). Protect the environment.

52

ESCOM PSP Strategy Review and Validation, February 2008.

Page 49: Malawi Energy Concept Paper

40

The independent sector regulator (MERA) was formally established in 2008 and has recently

recruited staff. MERA will provide important comfort to potential investors in power generation

(e.g., Lower Fufu hydropower scheme) that tariffs to end users will be sufficient to ensure that

the buyer (ESCOM’s transmission business) will be financially viable and able to make

payments. MERA will also ensure that electricity tariffs allow sufficient revenues for ESCOM’s

business units to adequately maintain, refurbish, and reinforce their equipment in order to

avoid problems of load shedding and poor electricity supply quality.

While the MAREP program is funded by grants and rural grids are transferred to ESCOM on

completion, the costs to ESCOM are similar to (or lower than) those of households in urban or

peri-urban areas. But if ESCOM is to seriously expand access to the national grid then additional

costs will be incurred. The regulatory framework would also allow ESCOM to recover the costs

associated with such a program.

Page 50: Malawi Energy Concept Paper

41

7 IMPLEMENTATION PLANS, MONITORING &

EVALUATION

7.1 Implementation Plan

The implementation arrangements for the Concept Project are described in this section,

including the project implementation structure, an assessment of the capacity of relevant

implementing entities, relevant experience of the implementing entities, the implementation

timeline, and plans for longer-term project activities53.

Figure 2: MCA-M Implementation Structure for the Energy Project

The implementation of the project shall follow guidelines set by the MCC. The project has made

provision for the procurement of Consultancy Servicers to undertake studies to finalize the

project details and prepare tender documents. The project implementation units of ESCOM and

53

See Annex 27 for timelines at the project level.

Page 51: Malawi Energy Concept Paper

42

MCA-M shall work hand-in-hand under a joint Project Steering Committee during construction.

ESCOM has expressed its wish to supervise the construction and commissioning of the project.

ESCOM shall appoint a Project Director with approval from MCC to supervise the construction

of the project. The Environmental Specialists from MCA-M and ESCOM shall oversee the

management of the Environmental and Social impacts identified during the study phase.

A Procurement specialist shall be appointed by MCC and seconded to MCA-M to verify that

materials supplied for the project are of expected quality and comply with the bill of quantities

and specifications. A Financial Specialist shall also be appointed by MCC and seconded to MCA-

M. The Financial Specialist shall verify all invoices submitted by contractors and authorize them

for payment before submission to MCA-M. MCA-M shall transmit the original to MCC with copy

to Government for payment. The Contractors will be paid directly from the Bank chosen by

MCC for disbursements.

7.2 Monitoring & Evaluation

The impact of the program on the beneficiaries will be monitored during, and at the end of, the

program. This section describes the outcomes and outputs of the projects and how these will

be measured. During the phase of due diligence and program refinement a full monitoring and

evaluation plan will be developed.

As described in Section 2, the program logic describes how the individual projects and outputs

relate to the sector outcomes, the sector objective and the overall compact goal. In order to

measure and evaluate the impact of the MCC investment indicators will be identified and base-

lined in the next phase. The indicators are derived from the Program Logic diagram and the

targets from impact analysis on beneficiaries.54 In Annex 26 the definitions, units of

measurement, the entity responsible for providing indicator data, the data collection

instrument, and the baseline and target values are shown for generation and, in Annex 27, for

transmission and distribution.

MCA-M shall work hand in hand under a joint Project Steering Committee during construction.

Supervision of construction and commissioning will be carried out by ESCOM. ESCOM shall

appoint a Project Director with approval from MCC to supervise the construction of the project.

Monitoring and evaluation (M&E) information is contained in a quarterly progress report and in

indicator tracking tables. The progress report includes information on both M&E management

issues and program results, including implementation issues such as setting up necessary

databases, hiring of M&E staff, as well as key program results and milestones. The indicator

54

See Annex 26 and 27 for the indicators applying to the generation, transmission and distribution projects

Page 52: Malawi Energy Concept Paper

43

tracking table reports specific results against projected targets, explaining significant deviations

from the targets. In addition to the reports, MCA-M will submit an annual supplement to the

quarterly report due at the end of each US Fiscal Year (September 30). The report should

provide a comprehensive overview of progress toward achieving compact goals and objectives

over the preceding year. As needed, the M&E plan outlines the process and timing for

contributing monitoring and evaluation content to these reports. All reports will be publicly

available.

Input for the reports will be given by ESCOM and NSO, whereas the quality of the data will be

overseen by an M&E specialist operating independently of ESCOM and NSO.

Figure 3: MCA – Malawi Energy Sector Program Logic

Source: MCA-M

COMPACT GOAL

Economic growth through increased competitiveness of agricultural and manufactured products

OUTCOME 1

Increased availability of quality and reliable power

supply

OUTPUTS

- Rehabilitated power station

- Rehabilitated transmission and

distribution systems

- Improved weed and siltation management

- Demand-side management activities

OUTCOME 2

Increased access to quality and reliable power supply

to unserved users

OUTPUTS

- Rehabitated distribution system in the southern,

central and northern regions of Malawi

- Electrification for rural and peri-urban areas in

Malawi

OUTCOME 3

Improved and effectively managed power sector for improved service delivery

OUTPUT

- Strengthened capacity for MERA and Department

of Energy

- Creating an enabling environment for the

establishement of PPPs

- Improved financial sustainability and

operational efficiency of ESCOM

OUTCOME 4

Improved Natural Resources Management in

priority catchmens to sustain power sector

investiments

OUTPUT

-Strengthened capacity to formulate and enforce NRM

legislation.

- Revised and harmonised NRM policies.

- improved weed and silt management systems.

-improved livelihoods through sustainable NRM

business enterprises

ENERGY COMPONENT OBJECTIVE

Increased accessiblity to more reliable and quality power supply

Page 53: Malawi Energy Concept Paper

44

8 BIBLIOGRAPHY

Girdis, D. and Hoskote, M. (2005), ‘Malawi: Rural Energy and Institutional Development,’

Washington D. C.: The International Bank for Reconstruction and Development

Malawi Government, „Electricity Act’, National Assembly, 2001

Malawi Government, „Energy Regulation Act, National Assembly, 2004

Malawi Government, „Establishment and Implementation of Multi-Sector Regulatory

Authorities: Draft Final Report,‟ submitted to the Privatization Commission, September

2006

Malawi Government (2005), ‘Integrated Household Survey 2004-2005,’ Zomba: National

Statistical Office

Malawi Government, „Malawi Growth and Development Strategy: From Poverty to Prosperity,

2006-2011,‟

Malawi Government, „National Energy Policy’, 2001

Malawi Government (2007), ‘Welfare Monitoring Survey,’ Zomba: National Statistical Office

Malawi Government (2008), ‘2008 Population and Housing Census: Preliminary Report,’ Zomba:

National Statistical Office

PriceWaterhouseCoopers, PB Power, Sacranie Gow and Company, DentonWildeSapte, and

Economic Consulting Associates (2007), ‘ESI: ESCOM PSP Strategy Review and

Validation,’ submitted to the Privatization Commission of Malawi

Page 54: Malawi Energy Concept Paper

9 ANNEXES

Annex 1: Output of the Stakeholder Problem Tree Analysis

Power Problem Tree - Summary Level

Strengthen T&D network in priority areasA B C

Feasibility study on new sources of power e.g. Lower FuFu

Rehabilitate Kapichira

Insufficient, unreliable and poor quality power supply

Low generation capacity

Unreliable transmission & distribution

network coverage

Unexploited new power sources

Current generation is

capacity constrained

Lack of investment capacity

Executed private sector investment in

IPPs

Gov approves PPP bill & PPP

strategy implemented

Projects prep’d & promoted

incl. feasibility studies

Reform tariff structure to reflect full

cost recovery

Investment environment is

stable and consistent

Public funding secured for

new generation capacity

Fully explore alternative

power sources e.g. hydro

Connect to SAPP

Enforce sust. land & resource use to reduce

siltation

Replace equipment at end of life &

stock reserves

Undertake preventative maintenance

Equipment replaced at end of useful life

Upgraded technology

Incentives aligned with performance

Independently operating

entity

T&D run with commercial orientation

Procurement capacity improved

Updated and implemented power sector master plan

Diversified geographic locations of power supply

Improved mgt capacity

Insufficient transmission & distribution

Implement methods to

reduce vandalism

Invest in additional gen. capacity e.g. Kapichera

A

B

C C

C

Reform tariff structure to reflect full

cost recovery

Page 55: Malawi Energy Concept Paper

Natural Resources Management Problem Tree for the Energy Sector – Summary Level

Hydro-Generation Capacity Diminished

Reduced Water flow

Excessive Siltation in Waterways, Dams,

Rivers, etc.

Intensive & damaging landuse pattern

Lack of enforcement of regulations

Increasing settlements

Population pressure

Conflicting policies Poor farming practices

Inadequate extensin services

Deforestation

Expansion of agric. land and settlement

Charcoal production

Lack of alternative livelihoods (cash)

Increasing energy needs especially charcoal and

firewood

Urbanization & lack of alternative energy

sources

Water resevoir capacity sevely diminished

Excessive aquatic weeds/trash

Lack of efficient harvesting equipment

tbdOther Chemical, Biological, Mechanical

measures tbd measures

Page 56: Malawi Energy Concept Paper

Annex 2: Map of Malawi Showing Existing ESCOM Grid

Page 57: Malawi Energy Concept Paper

48

Annex 3: Transmission Projects

The following transmission investments are identified as urgent:

a). Procurement and installation of switchgear for second 25MVA 132/66kV transformer at

Blantyre West Substation (US$ 0.4M: supply and installation of equipment)

b). Procurement and installation of a 20MVA 66/33kV transformer for Chichiri Substation in

Blantyre (US$ 0.6M: supply and installation of equipment),

c). Procurement and installation of a 12.5MVA 66/33kV transformer for Fundi’s Cross

Substation in Mulanje (US$ 0.5M: civil works and supply of equipment),

d). Construction of a new 220kV line from Lilongwe to Bwengu substation (US$65.0 million)

e). Construction of a new 220/132/66/33kV substation in Lilongwe (US$ 3.5M),

f). Procurement and installation of a second 12.5MVA 66/11kV transformer for Area 48

Substation in Lilongwe (US$ 0.5M: civil works, supply and installation of equipment),

g). Procurement and installation of a second 12.5MVA 66/33kV transformer for Telegraph Hill

Substation in Mzuzu (US$ 0.5M: civil works, supply and installation of equipment),

h). Construction of a new 132/66/33kV Substation in Blantyre (US$ 3.8 M),

i). Procurement and installation of a second 7.5MVA 66/33kV transformer for Chinyama

Substation in Kasungu (US$ 0.5M: civil works, supply and installation of equipment).

j). Upgrade Chintheche - Mzuzu line from 66kV to 132kV (US$7.28 M: civil works, supply and

Installation of equipment)

k). Upgrade Telegraph Hill – Bwengu line from 66kV to 132kV (US$3.04 M: civil works, supply

and Installation of equipment)

Page 58: Malawi Energy Concept Paper

49

Annex 4: Enabling Frameworks, Sustainability and Capacity Building

The sub-component targeting the creation of a framework that will attract private participation

in generation and that will, in turn, help ensure the sustainability of the improvements brought

about by the Concept Project are described below.

Develop an IPP Framework

Develop guidelines and procedures, to be followed for the selection and evaluation of IPP

projects. These could include for example, the development of competitive bidding process for

each request for IPPs. The procedures could include:

a). Bidding vs. negotiated contracts;

b). Details on the exact process and timing; -

c). Reporting requirements;

d). Selection Process; and/or Requirements related to the environmental impact and the

social consequences of proposed project.

e). Develop key model agreements for IPPs based on existing documents in use in other

countries including:

i) Power Purchase Agreement;

ii) Fuel Supply Agreement;

iii) Construction Agreement;

iv) Implementation Agreement; and

v) Operation and Maintenance Agreement

Feasibility Studies on Potential Hydropower Sites in Malawi

Malawi has a hydropower generation potential of 1, 000 MW. The total developed capacity is

only 285 MW. Most of the potential sites have not been developed to feasibility and bankable

stage. It has therefore been difficult if not impossible to sell such projects to prospective private

investors as many investors do not want to invest their money in feasibility studies. MERA has

been given the responsibility of facilitating the development of the potential sites to full

feasibility and bankable stage and to package them for immediate implementation. To fulfill

this mandate MERA will need support in the following areas:

General Regulatory Training

Regulation is a relatively new concept and therefore capacity building and development is

cardinal to enable the regulatory staff to discharge their mandate effectively. MERA will require

Page 59: Malawi Energy Concept Paper

50

financial support to develop and implement a systematic capacity building and training

program. In addition to the training program, more practical means of capacity building are

envisaged such as partnerships, exchange / study visits, and staff attachments.

Establish a Regulatory Information System and Procurement of Relevant Software

Availability of quality information to facilitate the regulation of the energy sector in Malawi is

very essential. Lack of information on energy matters prevents informed decision making by

various stakeholders and potential investors. The Licensees are also required to provide the

Authority with the necessary information based on the provision of their licenses. This

information enables the regulator to monitor the licensees’ compliance with the license

conditions. The information provided through licensee reporting systems will also be used by

MERA to generate public information to be used by consumers and other stakeholders.

MERA will need support to develop an Information Management System for regulatory

purposes cutting across different sectors of regulation. This will involve the development of the

following;

a). Electronic form/formats and templates in excel spread sheets for licensing data for

Electricity, Petroleum, Coal, Gas and Renewable Energy;

b). Electronic form/formats and templates for calculating unit energy prices for Electricity,

Petroleum, Coal, Gas and Renewable Energy;

c). Reports and form/formats for sending and receiving information to and from the energy

users, energy producers, other stakeholders and the general public; and

d). Staff training on the operation and management of the information system will be

necessary and there will also be need to procure the requisite software that will support

the Information Management System.

Procurement of Regulatory Tools

MERA is also mandated to carry out inspections and compliance monitoring to make sure that

operators are complying with the required quality and supply standards in the energy sector.

MERA is also mandated to investigate accidents and quality of supply complaints. MERA will

therefore need to procure the necessary tools to carry out this function without having to rely

on the industry to provide such tools as this would compromise MERA position on the matters

under investigation.

Page 60: Malawi Energy Concept Paper

51

Annex 5: Inventory of Existing Preparatory Work

The following Section provides an inventory of existing studies already undertaken and gives a

brief summary of each.

1. SECTOR STUDIES AND PLANS

The Malawi Country Economic Memorandum: Energy Constraints Chapter is under preparation

by the UK Government’s Department for International Development (DFID) and the World

Bank. The report considers the extent to which energy is a constraint to growth in Malawi and

analyses a series of options for tackling Malawi’s energy constraints and recommends 15

specific measures covering policy, investment and programs. Most of these measures are

incorporated into the Concept Project.

The Power Sector Reform Strategy (PSRS) described in Section 2.1 was prepared by a committee

chaired by the Department of Energy Affairs and approved by the Government of Malawi in

2003. This recommended the unbundling of ESCOM, private sector participation in new

generation projects and the creation of a new regulator – MERA.

Supporting the implementation of the PSRS and the subsequent legislation, a series of projects

were undertaken on behalf of the National Electricity Council (NECO, the forerunner of MERA),

the Privatization Commission and ESCOM:

Asset Revaluation Study (ESCOM), for the Privatization Commission, by Scott Wilson, May 2004

& Regulatory Advisory Services, for NECO, by Shaw Group, February 2004

The above projects were to prepare for the formal establishment of MERA and included the

development of model contracts, regulations, licenses, codes and organization charts for the

regulatory authority.

Though only indirectly related to the energy sector, the Privatization Commission also engaged

consultants to prepare a study on the Development of Policy, Legal, and Institutional

Framework for the Public-Private Partnership Program in Malawi. This was prepared by the

Institute for Public-Private Partnerships in March 2007. This, together with related work by the

World Bank, identified constraints to investor interest in Malawi and other southern African

countries and found that more businesses regarded Malawi’s poor electricity supply as a major

constraint to investment than in any other country in the region.

Page 61: Malawi Energy Concept Paper

52

In relation to rural electrification, a Master plan Study on Rural Electrification in Malawi was

prepared on behalf of the Ministry of Natural Resources and Environmental Affairs and DoEA

with funding by the Japanese International Cooperation Agency (JICA) in 2003. The Master plan

proposed the electrification of 249 trading centers in 11 more phases (beginning with Phase IV)

at a cost of US$49 million. A Follow-up Study for the Master plan Study on Rural Electrification

in Malawi was issued in 2004. The follow-up made institutional and organizational

recommendations and made recommendations on demand forecasting and prioritization of

trading centers to be electrified.

A study entitled Malawi: Rural Energy and Institutional Development was prepared by the

World Bank’s ESMAP55 in April 2005 which focused particularly on the institutional

arrangements for rural electrification and recommended among other things: the creation of a

regulatory and institutional framework within which private sector initiatives and large-scale

rural electrification could proceed in a financially viable manner; the establishment of a

mechanism for the provision of technical assistance, promotion, and support in cases where

off-grid rural electrification is to be executed by the private sector; and the creation of a

mechanism for the co-financing of rural electrification by which funds are channeled to the

beneficiaries through local, private sector banks.

2. ECONOMIC STUDIES

Economic studies to estimate the cost and benefits of the projects are summarized below.

Within this sub-section we also include least-cost analyses that demonstrate that the proposed

investments are the least-cost means of providing a service (in this case one of electricity

generation, transmission and distribution). We also mention below other related studies that

do not estimate economic costs and benefits but have some bearing on the project.

a. Economic Analyses of Proposed Investments

Analyses have been undertaken by ESCOM, with support from the MCA-M team, to estimate

the economic return on some of the individual components of the generation, transmission and

distribution projects included in the Concept Project. These are described in Section 4 of this

Concept Paper and reproduced in Annex 6. These analyses implicitly identify the current

baseline (i.e. demand that would not be met without the project). The analyses do not

specifically identify beneficiaries, but information on potential beneficiaries is supplied in

Section 4 of this Concept Paper. The ERRs for other projects are as much as 17.7%. The analysis

is examined further in Section 4 of this Concept Paper.

55

Energy Sector Management Assistance Program

Page 62: Malawi Energy Concept Paper

53

b. Least-Cost Power System Development Plans

A Power System Development and Operation study was completed by Consultants to ESCOM

(Lahmeyer/Knight Piesold) in December 1998 and is the most recent comprehensive analysis of

Malawi’s least-cost generation and transmission investment needs. This verified that Kapichira-

II and the interconnector with Mozambique are the least-cost supply options to meet demand

growth. This study is, however, now dated and a new least-cost investment plan is required to

verify the most appropriate investment in generation to supply the interconnected grid and to

extend or reinforce the national grid56.

In 2004, Stone & Webster completed an Integrated Resource Planning study on behalf of NECO.

This provided a partial update of the 1998 Power System Development and Operation study

(Lahmeyer/Knight Piesold) and considered demand-side measures as well as generation

investments. It also considered the impact of uncertainties when making investment decisions.

The report did not consider transmission investments, other than the interconnection with

Mozambique, and, while hydropower plants were considered, the recommended investment

plan did not identify the sequence of least-cost hydropower plants (other than Kapichira-II and

upgrades to the existing hydropower plants).

c. Other Economic Studies

In January 2009, ESCOM submitted an application to MERA for a tariff adjustment covering the

period June 2009 to July 2013 and this documents their revenue requirements and proposed

revisions to tariffs.

An Electricity Tariff Study was prepared for ESCOM by PB Power and completed in January

2005. The analysis was based on marginal costs and the report recommended an increase in

tariffs for residential consumers and a decrease in tariffs for other users (but the

recommendations were not implemented). The marginal cost values identified in this study

have been used in the economic analysis of the Concept Project.

3. SUPPORTING TECHNICAL DATA

Technical data on generation and transmission is contained in the 1998 Lahmeyer/Knight

Piesold Power System Development and Operation study described above. More up to date

data on generation is provided in the 2004 Integrated Resource Planning Study prepared for

NECO, also described above.

56

Such a study is proposed to be undertaken for MERA/ESCOM as part of the Concept Project. Though MERA is

responsible for verifying the need for generation capacity, ESCOM continues to be responsible for transmission

investment.

Page 63: Malawi Energy Concept Paper

54

A brief assessment of the failures of the hydropower plants, including problems relating to

sedimentation and inundation of the power plants, is contained in a report prepared by

PriceWaterhouseCoopers for the Privatization Commission - ESCOM PSP Strategy Review and

Validation, February 2008.

4. PRELIMINARY STUDIES

a. Studies of Generation, Transmission and Distribution

Preliminary assessments of the technical and economic viability of the Concept Project

components that relate to ESCOM were prepared by ESCOM for MCA-M in December 2008 (see

Section 3.2).

A Pre-feasibility study for the Lower Fufu hydropower project was prepared for ESCOM by

Norconsult in March 1996. Full feasibility studies and designs will be financed by the African

Development Bank.

A Generation Rehabilitation Project Proposal was prepared by ESCOM for the ESCOM Board in

December 2005. This identified the requirements for rehabilitation of its hydropower plants

and measures to reduce sediment, trash and weeds reaching the power station intakes.

Transmission investment requirements are evaluated by ESCOM’s system studies team based

on demand projections and load flow and other studies conducted using PSS/E software to

estimate the utilization of transmission lines and substation transformers. ESCOM’s technical

staff identifies existing or predicted overloading of equipment and submits proposals for critical

upgrades to ESCOM management who, in turn, submit their recommendations and detailed

budgets annually to be approved by the ESCOM Board. The studies are not formally published

but are documented.

5. CAPACITY BUILDING IN ESCOM

The requirements for capacity building in ESCOM will be determined by the Financial

Sustainability Study and the Diagnostic Review of Revenue Management (DRRM) Study (See

Section 12).

Page 64: Malawi Energy Concept Paper

55

6. FULL FEASIBILITY STUDIES

Songwe River Multi-Purpose Dam Project

Feasibility Study for the Stabilization of the Course of the Songwe River - This was a joint project

between Malawi and Tanzania. The study was prepared in November 2003 by NORPLAN in

association with COWI, DHI and WPES. Though the Songwe flood control, irrigation and

hydropower scheme is not part of the Concept Project, it impacts on the Concept Project to the

extent that the Lilongwe-Mzuzu transmission line reinforcement is designed, in part, to allow

power from the Songwe power plant to flow to the load centers in Lilongwe and Blantyre. In

the 2008/09 financial year, the Government of Malawi, through the Ministry of Irrigation and

Water Development, financed pre-feasibility studies and it is expected that the full feasibility

studies and construction activities will be financed by the African Development Bank.

Concept Project

The preliminary studies prepared by ESCOM and described in Section 4 will be adequate for the

smaller transmission and generation projects. A feasibility study is proposed for the Lower Fufu

hydropower project (see Section 12). A full feasibility study will be required for the proposed

220 kV Lilongwe-Kasungu-Mzuzu transmission line. More detailed design studies and project

descriptions will need to be prepared for the mid-size transmission projects and the large scale

distribution projects.

7. DETAILED BUDGETS

The budget for the components of the Concept Project is provided in Section 1.4 with an initial

20% physical contingency and 5% price contingency. A more detailed breakdown is not

available at the present time.

8. ENVIRONMENTAL AND SOCIAL IMPACT ANALYSIS

Kapichira Hydropower Scheme

A full environmental impact assessment (EIA) was undertaken for Kapichira covering the

potential impacts of both Phase I of the project (commissioned in 2000) and Phase II which is to

be developed under separate funding. At the request of the European Investment Bank, who

was considering lending funds for Kapichira-II, an Environmental Audit (rather than a full EIA)

was prepared.

Page 65: Malawi Energy Concept Paper

56

Lower Fufu Hydropower Project

We understand that the feasibility study for the Lower Fufu hydropower project will include an

environmental and social impact assessment (ESIA) to address physical, ecological and other

relevant problems.

Concept Project

We understand that ESIAs have not been undertaken for the components of the Concept

Project. ESIAs will be required the 220 kV Lilongwe-Kasungu-Mzuzu transmission line which

may pass through a forested area in the Northern Region. ESIAs may also be required for the

generation projects on the Shire River to control weed infestation and siltation; though the size

of the projects is small, the environmental impact may need to be reviewed.

Lower level ESIAs may be required for new transmission substations which will involve the use

of land for transmission lines. These lines may run through environmentally sensitive areas and

could require clearance of vegetation in a corridor along the route of the line.

9. RESETTLEMENT ACTION PLANS

Transmission lines are likely to need at least a Resettlement Action Plans to be developed to

determine any need for resettlement.

10. GENDER ANALYSIS

The Government of Malawi through the MGDS recognizes the role gender plays in the

development of a country. The current policy is to ensure that the participation of women in

key decision making positions increases to an average of 50%. The Department of Human

Resources Management and Development (DHRMD) has developed guidelines on gender

mainstreaming that will facilitate gender activities in the public sector. The aim of the

guidelines is to accelerate the process of mainstreaming gender in human resources

considering its crucial role in Malawi’s development process. However, no studies have been

undertaken to assess the extent of gender participation. A gender analysis study will need to be

carried. The GoM will submit a request for MCC funding under 609(g) for a study on the impact

of the concept projects on gender issues.

11. PUBLIC CONSULTATIONS

During the stakeholder consultations, over 1000 people were reached through various means.

The MCA-M Core team held meetings and consultations across all three regions of the country,

Page 66: Malawi Energy Concept Paper

57

targeting a cross section of stakeholders, including women, civil society, private sector, religious

leaders, rural communities and public sector officials.

During these consultations, the Core Team described the work that has been undertaken,

including the constraints analysis, and engaged stakeholders in discussions to identify their

perceived constraints to economic growth and poverty reduction in the country. Invariably, the

following were identified as the major constraints:

a) Lack of access to power – communities, particularly rural women, were able to make the

connection between access to reliable power and access to economic empowerment

opportunities

b) Access to adequate and sufficient education infrastructure

c) Access to reliable water for domestic and industrial use

d) Access to reliable transport networks to increase their access to markets.

With respect to power, rural communities, particularly women, were quick to point out that

their economic development would be enhanced as they would be able to among other things

access services such as electrified maize mills, mechanized irrigated agriculture, improved

health services, and for the youth, electricity would enable them to access educational

opportunities.

12. PLANS FOR ADDITIONAL STUDIES TO DEVELOP THE CONCEPT PROJECT

The requirements for capacity building in ESCOM will be determined by the Financial

Sustainability Study and the Diagnostic Review of Revenue Management (DRRM) Study. The

former is to be undertaken with funding from the Public Private Infrastructure Advisory Facility

(PPIAF), which was approved in January 2009.

A feasibility study for the Lower Fufu hydropower plant is to be undertaken by MERA. Funding

from the African Development Bank has been agreed but not formally confirmed. The Terms of

Reference for the feasibility study for this scheme include the associated transmission

connection to the existing grid and this will provide useful information on the future

transmission network in the North and the justification for reinforcing the transmission network

to the North.

An update of the least-cost power sector Master plan study is required. A Terms of Reference

has been drafted for the updated study57 and the GoM has asked MCC for funding under

57

The TORs for the Least Costs Power Sector Study are attached in annex XX

Page 67: Malawi Energy Concept Paper

58

609(g). ESCOM will need to prepare additional load flow studies taking into account the

additional generation capacity and transmission and distribution project components.

Catchment Study

Improved natural resources management of priority micro-catchments offers the best practical

option to sustain power sector investments in areas where power projects are located in

Malawi. Realizing the dynamic nature of the catchments, this could best be achieved through a

comprehensive study and analysis of biophysical baseline data, social-economic and human

influences in the catchment areas. This will allow for an integrated and more holistic approach

to the NRM problems leading to the development and implementation of site specific

interventions in the priority catchments.

One or two micro-catchments shall be selected in the Shire river catchment area and drivers,

problems, effects and impacts of unsustainable management practices shall be determined.

The final recommendations and conclusions of the study shall be the basis for restoration,

monitoring and sustainable management of natural resources in the shire river catchment area

in which projects supported by MCC shall be implemented.

Page 68: Malawi Energy Concept Paper

59

Annex 6: Assumptions and Parameters used in the Evaluations

1. Discount Rate

The analyses use constant 2008 prices and, for net present value calculations, a real economic

discount rate of 12.5% is employed. The latter is consistent with the calculations made by MCC.

Sensitivity analyses consider discount rates of 12% and 15%. The net-present value of the

energy project at a 12.5% discount rate is estimated at $75.0 million with an EIRR of 18.1%.

2. Electricity Tariffs and Connection Charges

ESCOM’s electricity tariff currently averages US$0.043/kWh. The revenues provided by this

tariff, after adjustment for losses, cover ESCOM’s operating costs and service some of its debts

but is inadequate to provide surpluses to self-finance a portion of future investments or to

satisfy lenders that it can cover future debt service obligations. ESCOM submitted an

application for a tariff increase to MERA in January 2009 and public hearings were held in 9-11

February 2009. The application requested an average tariff increase of 54% over a period

between 2009 and 2013. This level of increase is consistent with an assessment conducted by

PwC for the Privatization Commission58 which suggested that tariffs needed to increase to

approximately US$0.065/kWh in order to allow ESCOM to attract financing of future

investments and this value is used in the analysis below. Standard charges levied by ESCOM for

connection of households were raised in September 2008 from MK 9,900 (US$69) to MK 25,000

(US$175).

3. Willingness-to-Pay and Consumer Surplus

The projects that widen access to electricity in rural or peri-urban areas consider consumer

surplus (willingness-to-pay (WTP) for electricity less the cost of electricity) as well as possible

impacts on income and economic development (see below). However, consistent with MCC

guidelines which do not recommend the use of consumer surplus, the analyses show net

present values (NPVs) and economic rates of return (ERRs) both with and without consumer

surplus.

WTP for electricity was estimated based on a survey of rural households and the results

presented in background reports produced for the 2003 Master plan Study on Rural

Electrification in Malawi by JICA. This analysis showed a WTP of MK 1,838/month or

US$12.9/month (once connection had been made)59 or US$154.2/year. With average

58

ESCOM PSP Strategy Review and Validation, February 2008. 59

Equivalent to MK 85/kWh or US$0.59/kWh at today‟s exchange rates.

Page 69: Malawi Energy Concept Paper

60

consumption of 260 kWh per year and the current tariff of US$0.043/kWh, this implies a cost of

US$11.2 per year and consumption surplus of US$143 per year. If the tariff increases to

US$0.065/kWh, as discussed above, then the consumption surplus falls slightly to US$137 per

year (though willingness-to-pay is unaffected).

The 2003 survey also asked households to indicate their willingness to pay for a connection and

wiring costs necessary to receive electricity. This revealed a WTP value of MK 7,577

(US$53/connection or equivalent of US$6 per year60) which is below the current standard cost

of connection charged by ESCOM of MK 25,000 (US$175), equivalent to US$18.5 per year at a

10% discount rate61. If the true connection cost does indeed average MK 25,000 then this

would easily be recovered by consumers through the consumption surplus at the current tariff

of US$0.043/kWh and the combined net consumption and connection surplus would be US$130

per new customer per year. If the tariff is increased to US$0.065/kWh, as appears to be

necessary, then the combined net consumption and connection surplus would be US$124 per

new customer per year. Similar calculations of WTP for consumption of businesses were

estimated in the 2003 survey, at MK 3,110 (equivalent to US$ 22 at today’s exchange rate) per

month.

To our knowledge, no recent studies have been undertaken of WTP for peri-urban or urban

households in Malawi. The analysis below assumes that WTP in peri-urban households is

proportional to average household income in peri-urban households relative to income in rural

households (peri-urban average income is not known but is assumed to be intermediate

between incomes in urban and rural households62). Similarly, the WTP for connection in peri-

urban households is assumed to be proportional to income. These assumptions, combined with

a tariff of US$0.065/kWh give a net consumption and connection surplus for peri-urban

households of US$198 per new customer per year.

60

Assumed 30 year life of the connection. 61

Assumed 30 year life of the connection. 62

Average rural income is MK 40,241/year and average urban income is MK 129,407/year.

Page 70: Malawi Energy Concept Paper

61

Annex 7: Description of Economic Rate of Return Calculation

1. Impact on Income

The electrification of households should give the more resourceful households increased

opportunities for income earning through a range of activities including, for example, retailing

chilled foods or drinks, entertainment and processing agricultural products. Examples of income

generating activities resulting from electrification are provided in Annex 21. This direct and

immediate impact of electrification on connected households should be captured in the WTP

calculations described above63. However, there will also be indirect impacts on the local

economy and income earning potential of households in the electrified trading center whether

or not the households are connected, and there will even be economic development benefits to

villages in the district to the extent that there is increased trade, employment opportunities

and income in the trading centers. These impacts on non-electrified households will not be

captured in the WTP values.

There are no estimates of the economic development impacts of rural electrification in Malawi

but econometric studies have been undertaken in Bangladesh64. Households in the electrified

villages were found to have higher average incomes than households in non-electrified villages

but this cannot be interpreted as electrification causing the higher average income (because

villages with higher incomes will tend to be electrified first). However, the authors estimate the

percentage of annual income that can be “attributed” to electricity or, in other words, the

impact of electrification on average income. The results are:

Group Impact on income

Electrified households 16.4%

Non-electrified households in electrified villages 12.0%

Households in non-electrified villages 3.6%

These values were used in the analysis of rural electrification benefits for Malawi. The analysis

assumes that half of electricity sold to rural communities is to residential consumers. The

analysis further assumes that for every household in the electrified community there are a

further five households in neighboring villages that benefit indirectly through economic

development generated by the electrification (i.e., benefit from a 3.6% increase in average

income).

63

i.e., the benefits of electrification will be “internalized”. 64

Economic and Social Impact Evaluation Study of the Rural Electrification Program in Bangladesh, 2002,

NRECA International Ltd. Partners with the Rural Electrification Board of Bangladesh and USAID for the Rural

Power for Poverty Reduction (RPPR) Program.

Page 71: Malawi Energy Concept Paper

62

Peri-urban households without electricity are, by definition, already in the vicinity of areas that

are electrified and they will already have benefited to some extent from the indirect benefits of

electrification. We assume that these households benefit to the same extent as an electrified

household compared with a non-electrified household in a rural village. The impact on income

of electrifying peri-urban households is therefore (16.4% - 12.5%) = 4.4%.

2. Marginal Costs

When estimating the benefits of increased supply of electricity derived from investment in

generation, transmission or distribution, the costs or cost savings associated with the other

components of the supply chain must be captured. Thus, an investment in transmission that

reduces transmission losses will avoid generation costs (i.e., will avoid costs upstream of the

transmission line). Similarly, an investment to supply on-grid rural households will incur not

only the direct distribution investment costs but also costs of generation and transmission to

supply electricity to those rural households.

Marginal costs used in this Concept Paper have been based on those calculated in the 2005

Electricity Tariff Study prepared for ESCOM by PB Power. This gives marginal costs of generation

at US$0.013/kWh and marginal costs of transmission at US$0.012/kWh. Marginal costs of

distribution are not provided but, based on typical ratios of generation, transmission and

distribution costs; the analysis has assumed a value of US$0.04/kWh.

3. Cost of Un-served Energy (Value of Improved Reliability)

The benefits of improving reliability of electricity supply are measured in terms of the cost of

un-served energy (COUE) or the value of lost load. The cost of interrupting electricity supply (or

the value of avoiding interruptions) is high because it causes disruptions to normal business and

in some circumstances can lead to the loss of a complete batch of production or to damage to

equipment. A COUE value of US$0.2 per kWh not supplied was used in ESCOM’s 1998 Power

System Development and Operation study but the 2004 Electricity Tariff Study proposed instead

a value of US$0.83/kWh. The same value was used in the 2004 Integrated Resource Planning

study.

A background paper65 to the Africa Infrastructure Country Diagnostic (AICD) study noted that

the economic cost of interruptions to power supply in Africa averages 2.1% of GDP but in

Uganda and Tanzania, which are similar to Malawi, though with more reliable power supply,

the economic costs are 3.3% and 4.0% of GDP respectively. If the lost output in Malawi were

65

Background Paper 6, May 2008, Underpowered: The State of the Power Sector in Sub-Saharan Africa

Page 72: Malawi Energy Concept Paper

63

only 2.5% of GDP and load shedding is between 5% and 10% of energy sold then the economic

cost would be equivalent to between US$0.6/kWh and US$1.2/kWh.

The World Bank’s 2007 Project Appraisal Document for the Mozambique-Malawi Transmission

Interconnection Project suggested, however, that because load shedding had become acute in

Malawi and most electricity users had adopted back-up generation to provide power during

ESCOM outages, a cap on the COUE should be the cost of generation from diesel power plants.

While the cost to industry of an unpredicted power outage could be US$1.45/kWh, the cost of

back-up generation would be only US$0.16/kWh and the World Bank suggested a weighted

average COUE of US$0.22/kWh. This value has been used in the analysis.

4. Generation

Investments in generation are designed to improve the reliability and availability of the power

plants and extend the life of the plants. These investments include weed management, silt

management and trash diversion barriers at all of the hydropower plants and rehabilitation of

Nkula ‘A’ and ‘B’. Nkula ‘A’ was commissioned in 1966/67 and is now over forty years old but,

with rehabilitation, particularly of the electro-mechanical equipment, has the potential to last

another 25-30 years or more. The benefits of improved availability are captured initially in

reduced load shedding (and the reduced cost of un-served energy) and, later, when Kapichira-II

and the Mozambique interconnector are commissioned, in terms of avoided costs of new

generation (measured as the long-run marginal cost of generation). The benefits of life

extension are similarly captured in terms of avoided costs of new generation.

5. Transmission Reliability Improvements

A number of sub-components of the Concept Project are aimed at transmission reliability

improvements including investments in transformer upgrades, switchgear, protection systems,

new substations, and a SCADA system for the transmission network. The investment cost totals

US$16.2 million. These investments are designed to increase system reliability but the benefit is

measured in the economic analysis as the electricity supply that could not otherwise be

supplied and valued at the assumed electricity tariff (US$0.065/kWh). This undervalues the

benefits of the investments (i.e., the benefit of reliability could be measured based on the cost

of un-served energy which has a much higher value) but the ERRs are large even without taking

account of the cost of un-served energy.

The economic analysis is based on a typical investment in this group – a 20MVA 66/33kV

transformer for a substation at Chichiri in Blantyre and costing US$600,000.

Page 73: Malawi Energy Concept Paper

64

Transmission Extensions

Three sub-components of the Concept Project will extend the 66 kV transmission network or

upgrade from a 66 kV line to a 132 kV line in order to serve areas with large new loads as well

as existing, smaller, businesses that currently use diesel generators. The extensions will also

allow supply to the residential communities in these areas. The total cost of these investments

is US$12.9 million. The economic benefits in this analysis are the revenues to ESCOM and,

additionally, the avoided diesel fuel costs.

Further, the 220 kV Lilongwe-Kasungu-Mzuzu transmission line would, as with the above

transmission line extensions improve the reliability of supply and allow ESCOM to serve large

new and existing loads in the Northern Region (displacing diesel generation).

The benefits of this transmission line do not lie simply in the increased and improved supply to

the north. The transmission line is necessary to allow the power from the proposed 144 MW

Lower Fufu hydropower scheme to flow south to the load centers in Lilongwe and Blantyre.

Load in the north is relatively low and it is currently served by plants in the south. When the

Lower Fufu plant and the transmission line are built, the direction of flow of power will be from

north to the south. The north will export the surplus to the south emphasizing the importance

of the 220 kV Lilongwe-Mzuzu line. It is also necessary to allow power from the Songwe

multipurpose dam, including the 144 MW hydropower plants, to flow south. It would also allow

the possibility of trade between Malawi and Tanzania and connect a member of the Southern

Africa Power Pool to a potential member of the East Africa Power Pool (EAPP).

The benefits of building the 220 kV transmission line to allow the development of Lower Fufu

hydropower plant should be calculated as the total power system costs over a 20 or 25 year

planning horizon of a scenario with Lower Fufu less the total power system costs over a similar

horizon of a scenario without Lower Fufu but with the cost of the next best hydropower

alternative (including the associated transmission costs of that alternative). Information that

would allow this calculation will be available from the proposed update to the Power System

Development Plan (see Section 4.2.1). The study may require 12 months once it begins.

6. Distribution Reliability Improvement

Distribution rehabilitation has been divided into three sub-components each focusing on

Malawi’s three regions – North, Central and South. The total cost of these sub-components is

US$42.0 million (excluding physical and price contingency and Construction supervision costs).

The benefits are estimated as the incremental sales that the investments allow and effectively

assume that without the distribution refurbishments, supply to consumers could not be

expanded above the current levels. This is, perhaps, a pessimistic assumption in the short term

Page 74: Malawi Energy Concept Paper

65

but in the mid- to long-term, without these investments, the ability to supply consumers would

probably fall (rather than remain constant) and the assumption is then perhaps conservative.

No additional allowance has been made in the analysis for consumer surplus.

7. Pre-Payment Meters

The widespread introduction of pre-payment meters is intended to improve ESCOM’s revenue

collection performance and cash flow. This is a financial benefit to ESCOM and means that

consumers must pay for electricity in advance rather than, as at present, in arrears (up to 11

months after consumption). This investment is not amenable to economic analysis66 but is

nevertheless justified in order to allow improvements in revenue collection and ensure the

sustainability of the improvements introduced through the Concept Project.

8. Demand-Side Measures

Demand-side measures are particularly valuable in the short-term until Kapichira II and the

Mozambique interconnector are commissioned and while there continues to be load shedding,

but will also be important in the medium- and long-term to delay investment in generation and

transmission capacity. The investment cost in DSM measures is estimated at US$1.92 million

including the installation of maximum demand meters and implementation of feeder metering.

ESCOM estimates that the introduction of time-of-use tariffs will reduce peak demand by

19 MW in 2009. The investment in meters to allow time-of-use tariffs is only US$160,000 and is

therefore also clearly justified in economic terms.

66

It transfers the cost of credit from ESCOM to the consumer. To the extent that the cost of borrowing is higher for

the consumer than for ESCOM, it could be argued that the measure has a negative net economic impact, but this is a

relatively trivial impact.

Page 75: Malawi Energy Concept Paper

66

Annex 8: Poverty Rates by District67

Total (%) Urban (%) Rural (%)

Poor Ultra-poor Poor Ultra-poor Poor Ultra-poor

District of residence*

Chitipa 57 25 57 25

Karonga 47 19 47 19

Nkhata Bay 54 23 54 23

Rumphi 42 16 42 16

Mzimba/Mzuzu City 37 13 15 4 40 14

Kasungu 26 7 26 7

Nkhotakota 31 9 31 9

Ntchisi 29 7 29 7

Dowa 44 15 44 15

Salima 39 12 39 12

Lilongwe/Lilongwe City 23 6 10 2 31 8

Mchinji 41 13 41 13

Dedza 44 14 44 14

Ntcheu 42 14 42 14

Mangochi 48 19 48 19

Machinga 62 30 62 30

Zomba/Zomba City 47 19 23 8 50 20

Chiradzulu 49 20 49 20

Blantyre/Blantyre City 21 8 9 2 43 18

Mwanza 39 14 39 14

Thyolo 48 19 48 19

Mulanje 58 28 58 28

Phalombe 46 18 46 18

Chikwawa 51 23 51 23

Nsanje 60 27 60 27

Balaka 49 21 49 21

Source: Welfare Monitoring Survey 2007, National statistical office

* Likoma Island was not included in the IHS2, which serves as the basis for the poverty estimates

67

See Annex 2 for location of districts on map of Malawi

Page 76: Malawi Energy Concept Paper

67

Annex 9: Principle Beneficiaries and Benefit Impact Areas68

68

This list is not necessarily exhaustive

Page 77: Malawi Energy Concept Paper

68

Annex 10: Proportion of Income generating tasks and average weekly hours

worked Proportion of persons aged 15 years and above doing income generating tasks and average weekly hours worked

among these persons (Integrated Households Survey 2004-2005)

hours/week Urban Rural Northern Central Southern

HH agricultural or fishing activities 2.5 14.9 15.9 14.5 12.0

Non-agricultural and non-fishing HH business 7.1 3.1 2.6 3.1 4.1

Casual, part time or piece work 1.8 2.0 1.3 2.2 2.0

Wage, salary commission or any payment in kind 13.0 2.9 2.0 2.5 5.7

Total average hours worked 24.3 22.9 21.8 22.3 23.8

.

Page 78: Malawi Energy Concept Paper

69

Annex 11: Gender and Rural Electrification: A Case from Bangladesh69

Indicator(s) HE WE-EV WE-NEV

a) Percentage of women’s involvement in handicraft and sewing work at night Poor Rich b)Average number of women involved in IGA Poor Reported All households Rich Reported All households c) Percentage of women's reporting about decision making independence (freedom) to spend their earnings d) Percentage of women who reported wage discrimination e) Credit facilities Average amount of credit taken by women (in taka) Percentage of women taken credit more than taka 20, f) Savings of women Percentage of women’s reporting about own savings Percentage of women can enjoy independence in using savings g) Women’s mobility Overall women’s mobility score Gap to achieve full freedom in mobility h) Percentage of women reported always consultation on major family decisions i) Participation in decision-making process Overall decision-making participation score Gap between ideal and actual situation j) Percentage reporting about treatment by quack Boys Girls k) Knowledge of gender equality issues Women's knowledge score of gender equality issues Knowledge Gap of gender equality issues l) Empowerment score Overall women’s empowerment score 0.662 0.533 0.499 Gap between ideal and actual situation 0.338

13.8 14.6

1.19 0.3

1

0.12 22.8

29.8

21,863

21.5

39.8 79

0.488 0.512

50

0.72 0.28

38 42

0.80 0.20

0.662 0.338

- -

- -

- -

20.9

57.7

16,343 20

38.0

62

0.459 0.541

34

0.58 0.42

49 39

0.56 0.44

0.533 0.467

8.8 4.2

1.18 0.34

1.75 0.58 14.8

51.4

15,070

18

36.1 68

0.419 0.581

38

0.58 0.42

50 53

0.48 0.52

0.499 0.501

Note: HE = household with electricity; WE = Women Empowerment; EV = Electrified; NEV = Non-Electrified

69

Gender and Rural Electrification: A Case from Bangladesh, S. Halim, 2005

Page 79: Malawi Energy Concept Paper

70

Annex 12: Distribution of Households by Main Fuel Source Used for Cooking

and Lighting70

Cooking (%)

Place of residence

Proportion using

solid fuel Firewood Paraffin Electricity Charcoal

Crop residue, saw dust

Other Total

Urban 87.3 37.9 1.2 11.5 48.2 0.5 0.7 100 Rural 99.6 97.0 0.0 0.4 1.2 1.2 0.2 100

Lighting (%)

Place of residence

Firewood Grass Paraffin Electricity Candles Other Total

Urban 1.2 0.7 56.0 32.7 9.2 0.2 100 Rural 4.2 4.5 88.3 1.9 0.6 0.5 100

70

Integrated Household Survey 2004-2005, National Statistical Office

Page 80: Malawi Energy Concept Paper

71

Annex 13: Sectors and Sub-Sectors in Malawi71

and Income Distribution72

Agricultural sub-sectors Industrial sub-sectors Service sub-sectors

Cereals

1 Maize

1 Rice

2 Other cereals73

3 Root crops74

Pulses & nuts

4 Pulses & oils75

5 Groundnuts

Horticulture

7 Vegetables

8 Fruits

High-value export

oriented crops

9 Tobacco

10 Cotton

11 Sugarcane

12 Tea

13 Other crops76

Livestock

14 Poultry

15 Other livestock77

16 Fisheries

17 Forestry

18 Mining

19 Food processing

20 Beverages & tobacco

21 Textiles & clothing

22 Wood & paper products78

23 Chemicals & rubber products

24 Machinery, equipment and other

manufacturing79

25 Construction

26 Electricity & water

27 Agricultural trade and

transport services

28 Non-agricultural trade

and transport services

29 Hotels & catering

30 Communication

services

31 Financial & business

services

32 Real estate services

33 Community & other

private services

34 Government

administration

35 Health services

36 Education services

71

Source: A 2004 Social Accounting Matrix for Malawi, IFPRI, Washington D.C., 2008, Thurlow 72 Malawi Micro and Small Enterprises Survey, 2000 73

inclusive sorghum, millet 74

inclusive cassava, sweet potatoes, Irish potatoes 75

inclusive mixed beans, soybeans 76

inclusive sunflower seeds, paprika 77

inclusive cattle, goats, sheep and pigs 78

inclusive furniture 79

inclusive vehicles

Page 81: Malawi Energy Concept Paper

Less than MK2,000

MK2,000-MK5,000

MK5,000-MK10,000

MK10,000-MK20,000

MK20,000-MK50,000

Over MK50000

Crops 25.6 24.4 25.7 18.1 6.1

Livestock 45.4 8.2 16.4 14.7 15.3

Forestry 16.8 14.9 32.0 21.4 10.3 4.5

Fishing 27.9 1.2 1.6 8.8 14.0 46.6

Mining 32.7 19.5 19.5 28.4

Manufacturing 23.4 8.2 15.5 16.6 20.4 16.0

Construction 33.1 11.2 9.2 9.2 37.3

Commerce and Trade, Hotels

32.7 3.9 7.1 11.4 15.6 29.5

Transport 35.0 6.4 8.0 6.1 44.5

Services 30.5 8.7 11.4 15.0 20.4 13.0

Total 28.5 4.7 12.99 15.63 17.39 20.76

Page 82: Malawi Energy Concept Paper

Annex 14: Land and Population Distribution across Regions and Farm Households80

National Urban Rural

Small (<0.75

ha)

Med. (0.75-3 ha)

Large (>3 ha)

Farm Non- farm

Rural farm households in each region Non- farm Karonga Mzuzu Kasungu Salima Lilongwe Machinga Blantyre Ngabu

Population (1000) 12,173 654 727 358 814 1,282 661 2,523 2,033 1,972 693 458 3,731 6,240 363

Number households 2,694 133 189 71 163 246 143 537 465 474 137 134 942 1,241 54

Small-scale (<0.75ha) 30 44 69 72 203 237 217 70

Household size 4.5 4.9 3.8 5 5 5.2 4.6 4.7 4.4 4.2 5 3.4 4 5 6.7

Per capita exp. (US$) 150.8 286.2 308.6 116.7 132 152.8 130.9 145.4 110.3 125.3 101 185.8 121.6 130.1 203.7

Poverty rate (%) 52.4 30 21.2 62.8 55 43 56.3 47 67.7 61.4 70.6 37.5 61 55.6 30.6

Share of poor (%) 100 3.1 2.4 3.5 7 8.7 5.8 18.6 21.6 19 7.7 2.7 35.7 54.4 1.7

Harvest area (1000 ha) 3,050 174 - 81 295 525 128 591 482 599 175 - 647 1,792 437

Average farm land (ha) 1.13 1.31 - 1.13 1.8 2.13 0.89 1.1 1.04 1.26 1.28 - 0.69 1.44 8.02

Maize 0.57 0.99 - 0.54 0.8 1.08 0.41 0.59 0.58 0.5 0.66 - 0.36 0.7 3.67

Other cereals 0.05 0.01 - 0.1 0.06 0.01 0.04 0.03 0.06 0.09 0.22 - 0.04 0.08 0.09

Root 0.12 - - 0.28 0.36 0.2 0.18 0.09 0.1 0.17 - - 0.09 0.18 0.36

Pulses & nuts 0.26 0.23 - 0.12 0.34 0.56 0.05 0.29 0.2 0.4 0.17 - 0.16 0.36 1.17

Horticulture 0.03 0.03 - 0.05 0.07 0.06 0.02 0.04 0.03 0.03 0.03 - 0.02 0.05 0.13

Tobacco 0.05 0.04 - - 0.17 0.22 - 0.05 0.03 0.01 - - - 0.03 1.79

Other export crops 0.04 0.02 - 0.04 0.01 0.01 0.2 0.01 0.04 0.05 0.2 - 0.01 0.05 0.81

Crop yields (mt/ha)

Maize 1.13 1.00 - 1.17 1.3 1.37 1.33 1.24 0.96 0.93 0.79 - 1.07 1.14 1.27

Rice 1.17 1.24 - 1.64 1.83 1.09 1.51 1.86 0.76 0.74 1.09 - 1.12 1.17 1.61

Sorghum & millet 0.58 - - 0.77 0.57 0.57 0.68 0.64 0.44 - 0.59 0.58 0.59

Cassava 5.50 - - 5.64 6.8 5.46 5.41 6.83 3.55 4.89 - - 5.25 5.54 6.07

Groundnuts 0.75 0.75 - - 0.75 0.81 1.03 0.88 0.57 0.49 - - 0.68 0.76 0.78

80

Agricultural Growth and Investment Options for Poverty Reduction in Malawi, 2008

Page 83: Malawi Energy Concept Paper

Annex 15: Main Public Facilities and Business Entities in Trading Centers81

Public Facilities Business Entities

a) Secondary School

b) Primary School

c) Hospital

d) Health Center

e) Under Five Clinic

f) Maternity

g) Orphanage

h) Police Station

i) Police Unit

j) Immigration Office/ Border Post

k) Post Office/Post Agency

l) Radio Station

m) Church

n) Mosque

o) Community Halls/Recreation Centre

p) Court

q) Government Offices

r) Local Community/Cooperative Offices

s) Non-Government Organization Offices

a) Markets

b) Retail Shops-Grocery

c) Retails-Others

d) Wholesale Shops

e) Maize Mills

f) Furniture Workshops

g) Tinsmiths

h) Restaurants

i) Rest Houses

j) Bottle Stores/ Bars

k) Workshops for Car Repairs/ Garages

l) Battery Charge Stations

m) Barber Shops/ Beauty Shops

n) Banks

81

Source: Master Plan Study on Rural Electrification in Malawi, 2003

Page 84: Malawi Energy Concept Paper

75

Annex 16: Electricity Rate of Entities in Electrified Trading Centers in 200382

Public Facility Business Entity Maize Mill

Region Exi

stin

g in

TC

Ele

ctri

fied

Ele

c. R

ate

Exi

stin

g in

TC

Ele

ctri

fied

Ele

c. R

ate

Exi

stin

g in

TC

Ele

ctri

fied

Ele

c. R

ate

Northern 88 31 35% 261 124 48% 14 13 93%

Central 47 22 47% 125 62 50% 12 11 92%

Southern 102 50 49% 483 283 59% 42 40 95%

Total 237 103 43% 869 469 54% 68 64 94%

82

Source: Master Plan Study on Rural Electrification in Malawi, 2003

Page 85: Malawi Energy Concept Paper

76

Annex 17: Assumptions Environmental Savings on Charcoal83

Assumption Average

Household expenditure without electricity (tons/year) 0.18

Household expenditure with electricity (tons/year) 0.12

Household saving if electrified (kg) 58.9

Household saving if electrified (US$) 10.3

Saving on expenditure with concept project (tons/year) 7,125

Current number of small scale producers 7,041

Current number of medium scale producers 1,950

Current number of large scale producers 338

Production small scale producers (tons/year) 96,000

Production medium scale producers (tons/year) 58,000

Production large scale producers (tons/year) 77,000

Size of standard bag (kg) 38

Cost per standard bag (MK) 950

Price per kg (MK) 25

Current charcoal equivalent forest area cleared (ha/year) 15,088

Savings on charcoal equivalent forest area cleared with concept project (ha) 3%

Charcoal contribution to deforestation 33%

Malawi’s annual deforestation rate (ha) 52,000

Malawi's decrease in annual deforestation rate with concept project (ha) 465

Decrease number of small scale producers 0.48%

Decrease number of medium scale producers 0.80%

Decrease number of large scale producers 0.60%

83

Based on data from the study “Charcoal: The Reality; A Study of Charcoal Consumption, Trade and Production

in Malawi” submitted to the Forest Governance Learning Group, 2007

Page 86: Malawi Energy Concept Paper

77

Annex 18: Supporting Data for Benefits of Electrification84

Some findings of a study of Barnes (1988) support the fact that households benefit from getting

connection to the electricity grid.

o In Colombia electrification led to increased use of appliances, leading to increased

productive hours, resulting in staying up later at night (20 minutes more than non-

electrified households)

o In India electrification led to increased working hours (because cooking was delayed to

the evening), increased productivity of women (making handicrafts using night light),

increased reading time for children and adults and increased fan use

o In India electrification led to replacement of traditional methods of irrigation by

electrical pump sets in electrified villages, resulting in increased agricultural

productivity

o In India electrification led to the setting up of a larger number of shops in the village

and engendered a structural shift in employment to the tertiary sector. In individual

establishments, electrification seems to lead to larger firm size, more items sold, longer

working hours, higher income, and higher incomes per employee

In addition, lighting can lead to more leisure for men and children but also longer workdays,

especially for woman.

FUNDAP carried out promotion activities on benefits of electrification and uses of electrical

machinery and gave loans to small businesses supported by technical assistance, targeting

those that would not otherwise have access to credit (creating a likely downward bias

compared to control). The results suggest higher electricity usage among loan beneficiaries and

a consequent positive impact on income (Shonder and Wilbanks 1996).

According Chaudhury and Hammer (2003) in Bangladesh the proportion of households in the

community with electricity has a strong positive impact on the likelihood of living in the

community, which in turn reduces absenteeism.

Econometric modeling indicates that the availability of electricity had a positive impact on rural-

urban migration, though not on the crude birth rate at village level, couples’ income, female

labor force participation, fertility, mortality, and migration at the household level (Piampiti and

others 1982). 84

The Welfare Impact of Rural Electrification: A Reassessment of the Costs and Benefits – An IEG Impact

Evaluation, The World Bank, 2008

Page 87: Malawi Energy Concept Paper

78

Kiosk owners in Indonesia reported sales increases as a result of getting electricity, as they

could extend their product ranges to include wiring material, light bulbs, and kerosene cookers

(some electricity consumers have substituted firewood for kerosene previously used for

lighting). The most prevalent productive use of electricity was ice production in freezers used

for ice lollies and ice cubes (Meier 2001).

Productive uses of electricity were found within various sectors, with the largest percentage in

the services sector. At the household level 26 percent of households with home enterprise

increased income following electrification, as opposed to 4 percent without electrification

(Brodman 1982).

Staffing of doctors and nurses was better at the electrified health stations than unelectrified

(12:0.1) (Piampiti and others, 1982).

In Botswana electrification has meant decreased water supply interruptions and there has been

significant growth in small-scale activities such as dairy farming, horticulture, and pig raising

over 10 years. Besides, there are new education centres and schools and suitable

accommodation for staff who teach agricultural skills, hygiene by medical staff, and other

education staff. (Ramasedi 1992).

In most areas with electrification in Kenya, diesel motors have been replaced by electric ones,

which are cheaper and more efficient. Besides, there are new and improved health and

education centres operated on cheaper and more efficient electricity, rather than diesel

(Walubengo and Onyango 1992).

In Zambia the range of electrically operated coffee processing equipment has increased Bebeka

Coffee Plantation’s production by 35–40 percent over 10 years (Mariam 1992).

Street lighting led to fewer attacks at night in Peru (Valencia and others 1990)

Page 88: Malawi Energy Concept Paper

79

Annex 19: Income Generating Benefits of Electrification

The following diagram indicates the indirect impacts of rural electrification on income

generating activities. This is taken from maximizing the Productive Uses of Electricity to

Increase the Impact of Rural Electrification Programs (ESMAP, April 2008).

Page 89: Malawi Energy Concept Paper

80

Annex 20: Regions Affected per Project

Page 90: Malawi Energy Concept Paper

81

Annex 21: Map of regions affected by Energy and Transport Projects

x{

%[

%[

%[

%[

%[

%[

%[

%[

x{

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

x{

%[

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

%[

#Y

%[

x{

#Y#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

MPAMA

Lake Chilwa

Lake Chiuta

Lake

Malombe

Chilumba

Nsanje

Chiromo bridge

Nkula

Mwanza

Blantyre

MachingaBalaka

Ntcheu

DedzaMangochi

Cape Maclea

Monkey BayChipoka

Salima

Mponela

Kasungu

Lilongwe

Nkhotakota

Mzimba

Nkhata Bay

Mzuzu

Rumphi

Chitipa

Karonga

Chintheche

Tedzani

Kayerekere

Bwengu

Lobi

Linthipe

Phombeya

Lirangwe

NkayaNayuchi

Zomba

Ngara

Karonga - Kayelekera

Bwengu - Rumphi

To Nakala

To Beira

To Lusaka <<

<

Kapichira

Tedzani

Nkhula

Lirangwe - Machinga road

Monkey Bay - Cape McLear road

Mchinji

MALAWI: LOCATION OF PTENTIAL PROJECTS IN THE TRANSPORT AND ENERGY SECTOR

50 0 50 100 150 Kilometers

N

Power transmission lines

Power generation plants

Lakes

Energy Projects

Towns

Cityx{District Headquart%[

Main Centre#Y

Road rehabilitation

Railway line

Transportation Projects

Page 91: Malawi Energy Concept Paper

82

Map Showing NRM Catchment Areas in Malawi

x{

%[

%[

%[

%[

%[

%[

%[

%[

x{

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

%[

x{

%[

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

%[

#Y

%[

x{

#Y#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

#Y

Lake Chilwa

Lake Chiuta

Lake

Malombe

Lake Malawi

Nsanje

Chiromo

Mwanza

Blantyre

Ntcheu

DedzaMangochi

Cape Maclea

Monkey BayChipoka

Salima

Mponela

Kasungu

Lilongwe

Nkhotakota

Mchinji

Mzimba

Nkhata Bay

Mzuzu

Rumphi

Chitipa

Karonga

Chintheche

Kayerekere

Bwengu

Lobi

Linthipe

Phombeya

Lirangwe

NkayaNayuchi

Zomba

Liwonde

1

3

4

2

To Nakala

To Beira

To Lusaka <<

<

Catchments

Lake Malawi

Lake Chiuta

Lake Chilwa

Sire River

Lakes

Rivers

Railway line

Roads

Towns

x{ City

%[ District Headquart

#Y Main Centre

N

MALAWI: MAJOR CATCHMENT AREAS

Chipoka

Ngara

Nkhata Bay

Chilumba

Chiromo

50 0 50 100 150 Kilometers

Page 92: Malawi Energy Concept Paper

83

Annex 22: Scope of Assignment ESCOM Creditworthiness Improvement

1. Review ESCOM financial model, investment plan, previous ESCOM Financial Action Plan,

recent audit reports, analysis of accounts receivable and other information available on the

commercial, financial and technical performance of ESCOM.

2. Review with ESCOM the work done to date on analysis of accounts receivable and the

effectiveness of the actions currently underway, to identify the key issues underlying the

problem. Undertake an “age analysis” of the main receivables in terms of groups of

customers such as government, residential customers, etc. As a result:-

a). Discuss appropriate next steps on revenue improvement (prior to commencement of

the revenue improvement study).

b). Review the accounting policy for bad and doubtful debts and propose any necessary

revisions.

c). To the extent that non-payment by residential consumers is contributing to the

problem, the consultant should discuss the extent to which non-payment is an

affordability issue and discuss any possible improvements to make the lifeline tariff for

basic electricity needs more effective.

d). To the extent that non- or late-payment by Government entities is contributing to the

problem, the consultant should propose actions to address this issue.

3. Analyze and review the ESCOM the ‘technical and non-technical losses’ problem and

identify the key sources of the problem. The analysis shall include recommendation of

measures that can be realistically be implemented by ESCOM in the short, medium and long

term to bring its total losses to acceptable levels for utilities similar to that of ESCOM. In

this regard reference to previous loss reduction study conducted by Kennedy & Donkin early

1990 and subsequent work by ESCOM, is essential.

4. Undertake an analysis of “key operational policies” which impact on ESCOM`s overall

Operational and Capital Budget and use this information as input into house-keeping

measures that would reduce Budgetary waste.

5. Review the situation in terms of overdue debt servicing on loans to ESCOM from the

Government. Lay out the steps required to conclude the restructuring that has been agreed

between ESCOM and the Ministry of Finance and proposed any further actions that may be

necessary. Also review the situation on overdue debt service on direct loans to ESCOM, and

if appropriate prepare a plan for rescheduling the payment of this overdue debt service

6. Analyze the issue of exchange rate shocks and propose a mechanism such that if any

limitations are imposed on the automatic adjustment mechanism to avoid tariff shocks,

ESCOM would be financially compensated by the Government

7. Assess the effectiveness of the automatic tariff adjustment mechanism, aimed at adjusting

tariffs to account for exchange rate and inflation. Propose measures to increase the

effectiveness.

Page 93: Malawi Energy Concept Paper

84

8. In close collaboration with ESCOM, prepare a detailed financial model and Financial

Sustainability Plan, including consideration of efficiency improvements (e.g. loss reduction,

reduced accounts receivables), and the factors noted above, and tariff adjustments as

appropriate that will enable ESCOM to meet the Government’s financial sustainability

objectives for ESCOM. The plan should include sensitivity analysis and contingency

measures in case some aspects are not implemented as planned. In developing the plan,

the consultant should solicit input from key stakeholders, including donors and IFIs active in

Malawi’s energy sector.

9. Develop an implementation schedule with numerical targets and clear mechanisms and

responsibilities for reporting and monitoring implementation of the agreed plan.

10. Assist in building ownership and buy-in for the plan through active participation in one or

more workshops, organized by Ministry of Finance, and including key stakeholders, at which

the plan will be presented.

Page 94: Malawi Energy Concept Paper

85

Annex 23: Line Route for the 220kV and 132kV Lines

Page 95: Malawi Energy Concept Paper

86

Annex 24: Extract from ESCOM’s Draft Integrated Strategic Plan for 2009-2013

CORPORATE ISSUES AND GOALS

1) Poor Customer Service & Delivery

o Improved effectiveness in service delivery

o Improved reliability, security & restoration of supply

No contingency or backup

2) Poor Commercial and Financial Performance

o Improved revenue management

o Improved cash-flow management

o Improved business culture

o Implementation of Capital Management Process

o Reduced exchange rate risks

o Cost reflective tariffs

o Improved expenditure control

o Reduced back-log

o Appropriate technologies applied

o Provide supply contracts and tailor-made tariffs

3) Low Energy Market Share

o Improved customer relations

o Application of appropriate technologies.

o Increased industrial customer base

o More flexible new connection conditions

4) Inadequate Business Focus

o Full ownership of business

o Established Business Information System

o Fully implemented performance management process(PMP) and related rewards

o Compliance with Legislation

5) Weak Management of Human Resources

o Improved management skills

o Improved human resource capacity

o Plan for the effect of HIV/AIDS maintained

o Increased Environmental Risks

o Formulation of Contingency plans for adverse weather conditions

o Improved and enhanced management of aquatic weeds and trash/debris

o Acquisition and enforcement of way leaves

o Improved management of siltation

o Management of trash and aquatic weed

Page 96: Malawi Energy Concept Paper

87

o Increased Security Risks

o Reduced vandalism and thefts

o Eliminate unauthorized connections

o Inadequate Communication and Networking with Stakeholders

o Improved communication and networking

o Poor Safety Record

o Improved safety record

o Compliance with appropriate legislation

o Compliance with procedures

o Increased safety awareness

o Enforced safety code

6) Poor Business Culture

7) Improved business culture

o ESCOM Perceived as Corrupt

o Compliance with the Anti-Corruption Act

o Improved transparency

o Improved resource management

o Improved remuneration

8) Improved information flow

Page 97: Malawi Energy Concept Paper

88

Annex 25: Implementation Timeline

Page 98: Malawi Energy Concept Paper

89

Annex 26: Generation Indicators and Targets

Indicator Definition Unit of

Measurement

Source/ Responsible

Entity

Data Collection Instrument

Year 5 Target Value

General generation performance increased

Defines the performance increase of all current power generation stations due to weed, silt, dredger and trash management

(MWbefore / MWafter *100%) /

[generation station]

ESCOM Generation selling contracts

10%

Nkula A and B generation performance increased

Defines the performance of Nkula A and B power generation performance due to rehabilitation and modernization, and weed, silt, dredger and trash management

MWgenerated / MWinstalled * 100%

ESCOM Generation selling contracts

95%

Page 99: Malawi Energy Concept Paper

90

Annex 27: Transmission and Distribution Indicators and Targets

Indicator Definition Unit of

Measurement

Source/ Responsible

Entity

Data Collection Instrument

Year 5 Target Value

Peak demand decreased

Defines the decrease of the peak consumption

ΔMWpeak ESCOM SCADA System

-47.9

Load factor increased Defines the increase in ratio of average consumption per hour to the peak consumption

ΔMWhconsumption / ΔMWpeak

ESCOM SCADA System

1.7%

Energy unserved decreased

Defines the energy unserved due to load shedding and forced outages

ΔGWhunserved / year ESCOM SCADA System

-5.616

Line faults decreased (permanent)

Defines the number of line faults >3 minutes per 100 km per month for each line affected by the concept project

#[line faults]>3min / 100 km / month /

line ESCOM

SCADA System

0.5

Line faults decreased (all)

Defines the number of all line faults per 100 km per month for each line affected by the concept project

#[line faults]<3min / 100 km / month /

line ESCOM

SCADA System

10.0

Transformer outages decreased

Defines the number of transformer outages per month for each transformer affected by the concept project

#outages / month / transformer

ESCOM SCADA System

10.0

Line forced outage duration decreased

Defines the duration of line forced outage per 100 km per month for each line affected by the concept project

hours / 100 km / month /line /outageforced

ESCOM SCADA System

1.0

Transformer forced outage duration decreased

Defines the duration of a transformer outage per month for each transformer affected by the concept project

hours / 100 km / month / transformer

/outageforced ESCOM

SCADA System

0.5

SCADA system availability

Defines the part of the time all functions of the SCADA system are working

hoursavailable / hoursyear * 100%

ESCOM SCADA System

99%

Technical losses

Defines the decrease in technical losses of the energy purchased from generation per year

(ΔGWh[technical loss] / GWhpurchased /year) *

100% ESCOM

SCADA System

-5%

Power quality improved

Defines the improvement in power quality supplied due to strengthening the transmission network

Δ(#[devices burnt-out] /

customer)*100% NSO

Region-specific survey

-50%

Number of new connections per annum increased

Defines the increase in number of new connections per annum due to extending the transmission network

#[new connections] / year

NSO Region-specific survey

20,000