- 1 -
Eliminates capital cost, costly parts
inventory, maintenance cost/problems
Fixed Cost/Tonne
Includes all operating cost such as manpower, fuel & lubricants, Maintenance parts and supplies
Services to clients
Mine Engineering, Pit Planning and Design
Open Pit Mining and Quarrying
Drilling and Blasting
Tailings Dam Construction
Environmental mitigating measures (drainage, silt ponds & dikes)
Progressive rehabilitation of mined out areas
Equipment leasing
Main Office: Manila Address: M. Selma Road, Lower, Calajo-an RSTI Compound
Minglanilla, Cebu Pamplona, Las Piñas City (63-32) 272-3232 Fax (63-32) 272-6337 (02) 872-9347
- 2 -
1. VISION – MISSION – CORE VALUES
2. GENERAL INFORMATION
Name of Firm : ANSECA DEVELOPMENT CORPORATION
Business address : M. Selma Road, Lower Calajo-an, Minglanilla, Cebu
Contact No. : +6332 2723232
Fax No. : +6332 2726337
Email add : [email protected]
BUSINESS OBJECTIVES:
The company caters to the various needs of different business sectors/activities that are involved in
Earthmoving, quarrying, waste and ore mining, equipment leasing land development, etc.
Legal status of the firm : Corporation
Date of Incorporation : September 28, 1990
CAPITAL STRUCTURE
Authorized Capital Stock : PhP 100,000,000
Subscribed Capital Stock : 100,000,000
Paid-in Capital Stock : 100,000,000
VISION
“TO BE THE BYWORD IN MINING AND EARTHMOVING, GLOBALLY COMPARABLE, BY USING MODERN EQUIPMENT
AND TECHNOLOGY, PROVIDING THE MOST ECONOMIC AND EFFICIENT SERVICE TO THE FULL SATISFACTION OF
THE CLIENTS, COMMITTED TO THE HIGHEST STANDARDS OF SAFETY, HEALTH AND ENVIRONMENT.”
MISSION
“WE PROVIDE THE BEST QUALITY SERVICE IN MINING AND EARTHMOVING TO OUR CLIENTS AT THE MOST
EFFICIENT COST.”
CORE VALUES
HONESTY – INTEGRITY – COMMITMENT PROFESSIONALISM – DEVELOPMENT – CONSISTENCY
- 3 -
3. MAJOR PROJECTS COMPLETED
1.
Toledo City, Cebu
Handling of copper concentrates from the mill to pier
Underground mine subsidence backfilling contract
Equipment leasing (bulldozer, loaders, trucks)
2.
MASBATE GOLD PROJECT Aroroy, Masbate 1985 to 1993
Equipment Leasing (Heap leaching Ore operations)
3.
DIZON COPPER GOLD MINE Zambales – 1990 to 1992
Tailings dam construction and equipment leasing
4.
ANTAMOK GOLD OPERATION Antamok, Benguet – 1991 to 1003
Open Pit Gold Mining
5.
Mainit Surigao del Norte – 1990 to 1992
Open Pit Gold Mining
6.
PHILEX GOLD PHILIPPINES Bulawan Gold Project – 1995 to 2000
Open Pit Gold Mining, Heap Leach Pad and Tailings Dam Construction
7.
PHILEX GOLD PHILIPPINES Sibutad Gold Project – 1997 to 1998
Open Pit Gold Mining, Heap leach Pad Construction
8. MANILA MINING CORPORATION
Placer Surigao del Norte
Involves 8,000 TPD open pit gold mine. Five (5) years contract on ore and waste stripping at 936,000 MT per year.
9. FORMERLY : BACNOTAN STEEL INDUSTRIES, INC. (BSII)
A 5-year contract was signed January 10, 2000 between Kawatetsu PAC -Atlantic Transport, Inc. (K-PAC) and ANSECA to handle the in-site logistics of the Bacnotan Steel Industries, Inc. (BSII) in Calaca Batangas.
10. APO CEMENT CORPORATION Tina-an, Naga, Cebu
A 10-year contract of quarrying limestone and cement grade materials at 4.0 MMT per year with environmental enhancement and pollution abatement measures such as tree planting, drainage system maintenance with silt ponds and dikes, dust and noise suppression. ANSECA has also participated in the ISO 9001 and ISO 14001 accreditation of APO Cement.
11. MOLDEX REALTY INC. Meycauayan, Bulacan – 1993 to 1994
Land Development
12. ANTIPOLO PROPERTIES, INC. / RSBS Village East III, Binangonan, Rizal – 1992 to 1993
Land Development
13. ARABELLA REAL ESTATE Consolacion, Cebu – 1994
Land Development
14. TIERRA GRANDE ESTATE Lawaan, Talisay City Cebu
850,000 cubic meter contract for 9 months for real estate development. Scope of work : dozing, spreading and compaction
15. MIRAMONTE PHASE II Talamban Cebu City
Dozing, loading, hauling, spreading and compaction. Average material movement is about 2,000 cu.m. per day.
16. GUADALUPE PROJECT Guadalupe, Cebu City
Dozing spreading and compaction. Project has just started, and materials movement is about 2,000 per day.
17. LA BUENA VIDA PROJECT Cagayan de Oro, City
Involves 300,000 cubic meters of earth moving Job. Average daily volume is at 3,000 cubic meters per day.
18.
CITY SPORTS CLUB, Cebu Business Park
Site Preparation and Extraction
- 4 -
19. CORONA DEL MAR
Talisay City, Cebu
Site Preparation / Land Development
20. STA. LUCIA REALTY & DEV’T. INC.
1. GLENN ROSE RESIDENTIAL ESTATE
Carcar City, Cebu
2. GREENVILLE HEIGHTS
Consolacion, Cebu
3. VISTA GRANDE SUBDIVISION
Compostela, Cebu
4. SUMMER HILLS SUBDIVISION
Compostela, Cebu
Site Preparation / Land Development
21. LAPANDAY DIVERSIFIED PRODUCTS CORPORATION
Bukidnon
Site Preparation / Clearing and Grubbing
22. DEL MONTE PHILIPPINES
Davao City
Site Preparation / Clearing and Grubbing
23. PNOC-EC
Naga City, Cebu
PNOC COAL ANCHORAGE AND TERMINALLING SERVICES
Anchorage operation of un-loading imported coal from mother vessel to barges and subsequent terminalling / blending services.
24. PNOC-Geothermal
Tongonan, Leyte
Clear and grubbing operations
Site preparation for the geothermal
25.
Padcal Tuba, Benguet
TAILINGS POND #3 AND DIKES
a.1 Spillway Excavation – Clearing, stripping, excavation, stockpiling, construction and maintenance of ramps/access/haulage roads, drilling/blasting (if required) and provision of silt/sediment traps.
a.2 Quarry G – Clearing, stripping, construction and maintenance of ramp/access/haulage road/extraction/stockpiling and if required, drilling/blasting.
TAILINGS DAM #2 – Toe Dam Buttressing with Drain Blanket
Development of Quarry Source/Borrows Area
Construction of Access Ramp from Riverbed to the Upper Benche
OPEN PIT/SUBSIDENCE BACKFILLING
Quarry Development and Subsidence Backfilling Operations with an average daily volume of 5,800 MT per day or 2.0 million MT per year
26.
PHILIPPINE MINING SERVICES CORP.
Alcoy, Cebu
PMSC is a subsidiary of Kawatetsu Steel Corporation of Tokyo, Japan. PMSC is engaged in mining the huge dolomite deposit of Alcoy and Dalaguete, Cebu, programmed at 900,000 tons/year. Dolomite is used in steel and glass making, refractory, construction & others. Recently, PMSC has awarded the operation of the dolomite quarry with a 5 year contract to ANSECA. ANSECA played a vital role in the accreditation process of PMSC ISO 9001.
- 5 -
4. PROJECTS IN PROGRESS
1. HOLCIM PHILIPPINES, INC. – LUGAIT PLANT
Lugait Misamis Oriental
- 10-year contract with the following scope of works:
Mine planning and design, quarrying and delivery of limestone, shale and pozzolan at 3.0 Million MT annually, materials handling and rehabilitation pollution abatement measures and environmental protection i.e. dust and noise suppression and reforestation. ANSECA participated actively in the accreditation process of HOLCIM Cement ISO 9001 Management Quality System and ISO 14001 Environmental Management System, and OHSAS-18001.
2. HOLCIM PHILIPPINES, INC. – DAVAO PLANT
Barrio Ilang, Davao City - 10-year contract with the following scope of work:
Engage the services for the delivery of Limestone at 2.1 Million MT annually, Quarry Development and Production Project, Silica Material Handling and Feeding Project, Process Materials Handling and Rehabilitation Project.
- 6 -
3. HOLCIM PHILIPPINES, INC. – BULACAN PLANT
Bayabas, Doña Remedios Trinidad, Bulacan - 10-year contract with the following scope of works:
Mine planning and design, quarrying and delivery of limestone, shale and pozzolan at 3.0 Million MT annually, materials handling and rehabilitation pollution abatement measures and environmental protection i.e. dust and noise suppression and reforestation.
- 7 -
4. HOLCIM PHILIPPINES, INC. – LA-UNION PLANT
Quirino, Bacnotan, LaUnion - 11-year contract with the following scope of work:
Engage the services for the delivery of Limestone at 1.3 Million MT annually, Quarry Development and Production Project, Silica Material Handling and Feeding Project, Process Materials Handling and Rehabilitation Project.
6.
Dahican, Carrascal Surigao del Sur
A 5-year contract project, renewable upon mutual consent. ADC started the project on June 04, 2010 which responsibility is to mine and deliver Nickel ore and waste materials to the designated area in Dahican, Carrascal, Surigao del Sur. The major activities are as follows:
Mine Development – Waste stripping, extraction of the ore, benching as per mine engineering plans, hauling and dumping to ore stockyards/designated areas.
Construction and maintenance of haul roads dust suppression, silt ponds and silt traps.
Construction and maintenance of designated ore stockyards.
- 8 -
7. ADNAMA MINING RESOURCES, INC. Urbiztondo, Nickel Project Bgy. Urbiztondo, Claver, Surigao del Norte
A 5-year mining contract project, renewable upon mutual consent. ADC started the project on June 01, 2012 with the responsibility to mine and deliver Nickel ore and waste materials to the designated area in Bgy. Urbiztondo, Claver Surigao del Sur. The major activities are as follows:
Developing mining areas, Stripping of waste/overburden materials, Bench forming and pit drainage.
Ore extraction from designated mining area
Transport of nickel ore to designated stockpile areas
Breaking of saprolite material, Stockpile maintenance and pre-piling activities.
Loading of ores to barges/LCT, trimming of loaded or on board the barges/LCT
Construction and maintenance of mine access roads.
- 9 -
5. TECHNICAL CAPABILITIES
The company has a team of high caliber, competent, experienced and highly trained professionals composed of geologist, geodetic, mining, civil and mechanical engineers, certified public accountant, management, financial and legal consultants. The team sees to deliver high quality of services and observe professional decorum in and out of the work place.
LIST OF ENGINEERS:
NAME PROFESSION
1. LIMOSNERO, ALEX MINING ENGINEER
2. QUITORAS, ROSALITO MINING ENGINEER
3. MONTESA, LESLIE MINING ENGINEER
4. CHING, ALLAN MINING ENGINEER
5. OMAY, RICHARD CIVIL ENGINEER
6. SOMERA, ALLAN CIVIL ENGINEER
7. GIRAY, CHERYL CIVIL ENGINEER
8. SIMBAJON, CHRISTIAN CIVIL ENGINEER
9. JAVIER, JASPER CIVIL ENGINEER
10. SELMA, SEGUNDINO III INDUSTRIAL ENGINEER
11. LLABAN, ANGELIQUE INDUSTRIAL ENGINEER
12. BADAYOS, RHEA MAE INDUSTRIAL ENGINEER
13. CABSAG, MARVIN CHEMICAL ENGINEER
14. BUSTAMANTE, VINCENT MECHANICAL ENGINEER
15. CRUZ, ALEX MECHANICAL ENGINEER
16. DELA CRUZ, ROBERTO MECHANICAL ENGINEER
17. GUINITA, REYNALDO MECHANICAL ENGINEER
18. JAYAG, JERMAINE MECHANICAL ENGINEER
19. MORENO, OSCAR MECHANICAL ENGINEER
20. TABORNAL, ERWIN MECHANICAL ENGINEER
21. MEJARO, ROMMEL MECHANICAL ENGINEER
22. HERUELA, REYNANTE MECHANICAL ENGINEER
23. LUZANO, IVAN MECHANICAL ENGINEER
24. YRAT JAYSON MARK MECHANICAL ENGINEER
25. MARQUEZ, ROMMEL ELECTRICAL ENGINEER
26. HOLLANES, VERGELIO ELECTRICAL ENGINEER
- 10 -
6. EQUIPMENT FLEET
- 11 -
- 12 -
7. SUBSIDIARY/AFFILIATE COMPANIES
We have subsidiaries/affiliates which give ready support for our manpower and logistic requirements.
Anseca-Acelco Ventures, Inc.(AAVI) - An expanded venture company of ADC and ACELCO
Mach Asia Manufacturing Corp. (MAMCOR) - ADC’s maintenance arm which provides services such as track rebuilding, equipment reconditioning, undercarriage repair, engine overhauling, o-ring and hose fabrication and machining jobs.
Mach Asia Trading Corporation (MATCO) - A direct importer of second hand heavy equipment which could be tapped anytime should ADC require additional units for new and existing projects.
SFAG MC - A subsidiary that provides additional manpower requirements of ADC and affiliate companies.
ADC Property Ventures, Inc. - A real estate arm of ADC. Acquired Properties:
1. New Reclamation Area, Mandaue City Lot Area: 20,328 sq.m
2. A. S. Fortuna, Mandaue City Lot Area:.3,815 sq. m.
3. Bgy. Maguikay, Mandaue City Lot Area:.2,800 sq. m.
4. Bgy. Sasa, Buhangin District Davao City Lot Area:.13,917 sq. m.
5. Muelle Loney St., Poblacion, Ilo-ilo City Lot Area:.5,340 sq. m.
FILPRO Ventures, Inc - Engaged in acquiring, developing, leasing out real estate properties.
MEGA Assets Inc. – A real estate lessor.
8. THE HUMAN RESOURCE DEPARTMENT
The company has a Human Resource Department whose foremost goal is to accomplish the designated objectives through the productive utilization of its work force. The HRD staff who heads this department are educationally equipped and qualified and are deeply work oriented. There expertise in the area of human resources shall enable them to take an active and enlightened participation towards accomplishing these goals and realize its personnel programs. In achieving these ends, the staff place focus in the maintenance of a harmonious working environment between management and the personnel engaged. The HR Department performs both managerial and operative functions. Thus, it takes care in the planning, organizing, directing and controlling its human resources. Stated differently, both functions involve the procurement, development, compensation, integration, maintenance and separation of personnel. Embraced therein are the pre-employment testing, recruiting and hiring, skills training, disciplinary procedures and counseling, performance evaluation, promotions and transfers and employee / labor relations.
Aside from the aforementioned activities, HRD also takes responsibility in the keeping of personal records and reports, research, insurance benefits, compliance to government circulars, wage/salary administration, health and medical services, retirement programs, attitude surveys, relocation services, supervisory training, community relations, security/plant protection, public relations, administrative services, payroll processing, travel and transportation, maintenance and janitorial services. Finally, the HR Department coordinates with the designated personnel assigned in the various projects the company undertakes with clients in the different areas of the country.
- 13 -
9. SAFETY AND HEALTH PROGRAM
The company’s Safety and Health Program is in place as approved by the Mines and Geosciences Bureau, Department of Environment and Natural Resources, Region VII. It is a continuing program. The mission of the company’s safety management is to achieve a risk-free operation through the establishment and maintenance of a company-wide system for identifying, measuring and controlling performance problems that produce accident loss. These include but not limited to, unsafe work practices, unacceptable working environments, property malfunctions, managerial oversights, and the like. It is the objective of the company to fully incorporate safety into the operational system so that its employees, equipment and environment are amply protected from accidents and that company officials in all levels of supervision take a direct hand pursuing accident prevention activities in accordance with the following standards:
Personal Injury Prevention
Property Damage Control
Environmental Protection
Occupational Safety and Health Standards.
9.a. SAFETY AND HEALTH PROGRAM AWARD
- 14 -
10. ISO 9001 QUALITY MANAGEMENT SYSTEM, ISO 14001
ENVIRONMENTAL MANAGEMENT SYSTEM AND OHSAS
OCCUPATIONAL HEALTH, SAFETY ASSESSMENT SYSTEM.
Participated actively in the International Standard Organization (ISO) systems accreditation for the foreign –owned cement plants of HOLCIM Lugait (ALSONS Cement Corporation), CEMEX – APO Cement Corporation, LA Farge – FORTUNE Cement Corporation, Iligan Cement Corporation (ICC), Philippine Mining Service Corporation (PMSC) and Philex Mining Corporation where ANSECA has long term quarrying contracts.
11. ACCREDITATION BY DENR
The company is an Accredited Service Contractor pursuant to Section 143 of Department of Environment and Natural Resources Administrative Order No 96-40 series of 1999. This requirement is a must for all services contractor that has something to do with environmental protection. A service contractor, particularly a foreigner, cannot operate as such in the country without this.
12. MAJOR SUPPLIERS
PARTICULARS ITEM SUPPLIED
Komatsu Ltd. 2-3-6 Akasaka Minato-ku, Tokyo, 170 Japan Phone : 81-3-5561-2790; Fax : 81-3-5561-4767
Heavy Equipment
Komatsu Used Equipment Corporation Shuwa Tameike Bldg., No. 4-2, Nagatacho 2-Chome, Chiyoda-ku Tokyo 100, Japan Phone : 81-3-3292-7621; Fax : 81-3-3592-7622
Heavy Equipment
Monark Equipment Corporation A. C. Cortes Avenue, Ext. Mandaue City, Cebu Phone : 3465534; Fax : 3461267
Heavy Equipment
APAC Pte. Ltd. 221 Henderson Road #06-12 Henderson Bldg. Singapore 159557 Phone : (65)-2763667; Fax : (65)-2763670
Heavy Equipment
Maxima Equipment Company, Inc. 202 E. Rodriguez Sr. Blvd. Quezon City Metro Manila Phone : 721-1071; Fax : 721-1075
Parts
Maxima Equipment Company, Inc. 212 Subangdaku, Mandaue City Cebu, Philippines Phone : 344-0658; Fax : 344-0659
Parts
CIVIC Merchandising, Inc. FF Cruz Avenue North Reclamation Area Subangdaku, Mandaue City Cebu, Philippines Phone : (032)344-5572, (032)344-5573; Fax: (032) 346-1545
Heavy Equipment/Parts