Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
E-1WS Culvert ReplacementBid AwardProject # 19-10173L.01
Anthony LasCasas P.E.Director of Operations & Maintenance
Board Meeting – December 11, 2019
LWDD Board of Supervisors Meeting December 11, 2019Agenda Item #8
LWDD
E-1
WS
Cana
l
Remove Existing Triple 72” CMP Culverts Replace w/ twin 10ft x 8ft Concrete Box Culverts
TimelineBudgetIncluded in 5-Year Capital PlanJune 4, 2019 – Proposed Budget Working Draft included
$1,400,000 Budget line item for ConstructionJuly 17, 2019 – Approved as part of Preliminary BudgetDesign & PermittingDecember 3, 2018 –Higgins Engineering was Authorized
for Design, Permitting and Construction Phase ServicesMay 14, 2019 – SFWMD ROW Permit approvedBidding & ConstructionAugust 14, 2019 – Request Authorization to solicit bidOctober 2019 – Advertise Request for Bid December 11, 2019 – Award Bid January 2020 – Notice to Proceed May/June 2020 – Projected Completion
Bid Results
Contractor Bid Amount
Arbor Tree & Land, Inc. $979,500
Danz Contracting, LLC $1,324,000
Giannetti Contracting Corp. $1,488,750
Hinterland Group, Inc. $1,492,500
Murray Logan Construction, Inc. $738,550
Ric-Man Construction, Inc. $757,200
Zahlene Enterprise, Inc. $969,585
ZEP Construction, Inc. $1,067,714
Staff Recommendation
Approval to award bid to Murray LoganConstruction, Inc. for construction ofreplacement culverts for E-1WS at HillsboroCanal
Control Structure 9 ReplacementRFB 19-7170P.07
Anthony LasCasas P.E.Director of Operations & Maintenance
Board Meeting – December 11, 2019
LWDD Board of Supervisors Meeting December 10, 2019Agenda Item #9
Control Structure 9
Boynton Beach Blvd
CS 9
Military Trail
Congress Ave
Lawrence Rd
Gateway Blvd
Existing CS 9 (to be abandoned)
Proposed CS 9
C. Stanley Weaver Canal
Existing Control Structure 9Currently located on the C. Stanley Weaver Canal,west side of Lawrence Rd,north of Boynton Beach Blvd.
Proposed Control Structure 9Structure to be reconstructed to the east, on the C. Stanley Weaver Canal, ~350 ft east of Lawrence Rd,north of Boynton Beach Blvd.
Existing Structure
Initial structure was built in 1952; demolished and replaced in 1980 In early 2014, the energy dissipaters were removed to allow
additional pump flow Two-gate system does not allow for “hurricane” gate Only major structure without an Ogee spillway; absence reduces
efficiency and causes a hydraulic jump under bridge In 2014, dive inspection revealed significant lateral seepage under
the bridge and exposed/corroding rebar Temporary repairs for corrosion were made to radial gates in 2014 North Pump is currently inoperable Overhead powerlines restrict maintenance and emergency access
to the gate and pumps Manual weed removal required North radial gate structural repair in 2016 following hoist failure
Proposed Structure
Three-gate structure will provide more capability, reliability andoperational flexibility
Dual pumps will allow more capability and reliability Mechanical weed removal will improve operational efficiencies and
improved reliability Relocation will eliminate the conflict with overhead power lines Redesign and relocation will remove “hidden” hydraulic jump Change in surface water may cause increase in ground water,
warranting a seepage trench along the north bank to mitigateconcern
Relocation to east may cause concern for approximately 10 adjacentresidents; construction work and aesthetic changes to backyard view
Engineer’s Estimate of Probable Construction Cost - $6.7M
Timeline
December 11, 2019 – Request authorization to solicit Bids for construction January-September 2020 – Permitting January/February 2020 – Advertise Request for Bids March 2020 – Board approval to award Bid April 2020 – Notice to Proceed April-October 2020 – Contractor to perform preliminary site
work and order long lead items (FPL Service, Steel Sheeting, Pumps, Trash Rake, Gates & Control Panels) November 2020 – Begin Construction June 2021 – Projected Completion
Staff Recommendation
Approval to advertise a Request for Bids forconstruction of relocated Control Structure #9
Bank Street Partners, LLC – 7-Eleven #34785; Transfer and Convert the existing Piping, Paving, & Parking Agreement to a Right-of-Way PermitLWDD Project No. RW-19-0338
Nicole Smith, Right-of-Way Permit Coordinator December 11, 2019
LWDD Board of Supervisors Meeting December 10, 2019Agenda Item #11
Parcel is located on the SE Quad of Hypoluxo Road and Congress Ave; the L-18Canal is located along the north side of this parcel, adjacent to Hypoluxo Road.
June 12, 1991 - LWDD Board of Supervisors approved the Piping of the L-18 Canalfor the proposed Service Station for ~200’ east of Congress (Request made by H.P.Thompkins, Jr.)
August 12, 1992 - LWDD Board of Supervisors approved a 6-month extension forthe approvals granted in 1991 for the Piping of the L-18 Canal for the ServiceStation (Lennar Homes) & Boynton Lakes Plaza (Request made by Lennar Homes& Boynton Lakes Party in order to finalize the Tri-Party Agreements)
August 25, 1993 - Tri-Party Agreement was recorded (ORB 7855/1329) for the gasstation parcel between LWDD, Lennar Homes, and Palm Beach County
2019 – Bank Street Partners, LLC has requested the transfer of the Piping, Paving,Parking License Agreement to the current owners and convert to a Right-of-WayPermit
The two parcels to the east have current Tri-Party Agreements.
Background
Staff Recommendation
Approval to transfer existing responsibility of Tri-Party PipingLicense Agreement to current owner, Bank Street Partners,LLC, for a portion of the L-18 Canal; being within a portion ofSection 08, Township 45, Range 43. Subject to:
• Updated Signed & Sealed Pipe Inspection• Approval of Site Plan
• Including Lighting, Planting, and Irrigation Plans• LWDD Operating Policies Application Fee
• $9.00 x 160 LF = $1,440.00 (Paid) Use Fee
• $20.00 x 160 LF = $3,200.00 Annual Fee – (Commencing 2020)
• $4.00 x 160 LF = $640.00• Adjusted every five (5) years by the compounded CPI
Parcel is located on the SE Quad of Hypoluxo Road and Congress Ave; the L-18 Canal is located along the north side of this parcel, adjacent to Hypoluxo Road. December 12, 1984 - LWDD Board of Supervisors approved ~1,000’ of Piping for
the L-18 Canal from Congress Avenue eastward for the Boynton lakes Plaza(Richard Reikenis, P.E. representing Centure Design)• Construction had to be completed within one (1) Year
May 13, 1987 – Request to pipe the L-18 Canal was withdrawn (Request submittedand withdrawn by Burt Smith)
June 12, 1991 - LWDD Board of Supervisors approved the Piping of the L-18 Canalfor the proposed Service Station for ~200’ east of Congress (Request made by H.P.Thompkins, Jr.)
July 17, 1991 – LWDD Board of Supervisors approved the Piping of the L-18 Canalfor the Boynton Lakes Plaza (Request made by Maziar Keshavarz, P.E. & JoelWantman, P.E.)
Agreement was recorded August 25, 1993 (ORB 7855/1329) for the gas stationparcel, between LWDD, Lennar Homes, and Palm Beach County
Background
Edward Kloss – Dollar Tree; Request to install an emergency exit sidewalk within the north portion of the L-16 CanalLWDD Project No. RW-19-0356
Nicole Smith, Right-of-Way Permit Coordinator December 11, 2019
LWDD Board of Supervisors Meeting December 10, 2019Agenda Item #12
Parcel is located on the SW Quad of Lantana Road and Old CongressAvenue; the L-16 Canal is located along the south side of this parcel
LWDD had no previous ownership within parcel December 22, 1981 - At LWDD request, H&P Company conveyed a 40’
exclusive Easement Deed (ORB 3655/1972); north line of the easement isthe south side of the building
August 19, 1982 - LWDD issued a Drainage Permit; Plans show proposedbuilding at easement line
November 2019 - LWDD Inspector (J. Summers) stopped construction of aHVAC System within the L-16 Canal Right-of-Way without a permit fromLWDD; they do have a permit from PBC
November 2019 - Representatives from the Dollar Tree Store contacted theDistrict regarding the installation of an emergency exit sidewalk from theback of the building to the parking lot on the east side of the building
Dollar Store Representatives removed exiting A.C. Units from L-16 R/Wand installed on the roof
Representatives have reduced the proposed encroachment from ~9’ fromthe building to 4’ and utilizing the door closest to the parking lot; They arerequesting ~ 4’ x 25’ emergency exit sidewalk for egress only
Background
Staff Recommendation
Approval to construct a 4’ x ~25’ emergency exit sidewalk within the north 4’ of the L-16 Canal Right-of-Way Subject to:
• Approval of Site Plan• Proof of Liability Insurance adding LWDD as an Additional
Insured• LWDD Operating Policies Application Fee
• $500.00 (Requested) Use Fee
• $20.00 x 25 L.F. = Minimum $1,500.00 per Policy Annual Fee – (Commencing 1 year after issuance)
• $4.00 x 25 L.F. = Minimum $500.00 per Policy• Adjusted every five (5) years by the compounded CPI
Surplus and Disposal Karen Hoyt, Director of FinanceDecember 11, 2019
LWDD Board of Supervisors Meeting December 10, 2019Agenda Item #13
Surplus and Disposal
Pursuant to Chapter 274, Florida Statutes, theDistrict has the discretion to surplus property thatis obsolete or the continued use of which isuneconomical, unsafe, inefficient, or which servesno useful function Staff has identified items that meets this criteria
and requests that they be declared surplus, anddisposed of through the recommended disposalmethod
Listing of Items
Asset ID Description Original Cost Acquisition Date Recommended Disposal Method Comments Hours/Mileage
Buildings & Improvements
1 B61 A/C System, Lennox 2 Ton 6,392.00 7/31/2009 Recycling Program / Garbage
2 B61A EVAPORATOR COIL/DRAIN PAN-AHU 1,330.39 5/22/2012 Recycling Program / Garbage
3 B62 A/C - Air Handling Unit, Trane 2,321.00 3/13/2009 Recycling Program / Garbage
Machinery & Equipment
4 M-070 Tractor - John Deere, 6115M 22,282.00 9/5/2013 Online Auction Website/Trade-in Cost of repairs exceed unit value 6,273
5 T-100 2008 FORD F250 4X4 EXT CAB 30,067.00 2/1/2008 Online Auction Website/Trade-in Expected to meet criteria this year 194,773 +
6 T-101 2008 FORD F250 4X4 27,183.00 2/1/2008 Online Auction Website/Trade-in Expected to meet criteria this year 152,289 +
7 T-101A ROLL & LOCK BED COVER 1,195.00 2/11/2016 Online Auction Website/Trade-in
8 T-103 2008 FORD F250 4X4 27,183.00 2/1/2008 Online Auction Website/Trade-in Expected to meet criteria this year 171,549 +
9 T-110 2008 FORD F450 4X4 CAB&CHASSIS 34,620.00 4/4/2008 Online Auction Website/Trade-in Expected to meet criteria this year 62,713 +
10 T-112 2009 STERLING ACTERRA TRUCK 108,726.00 6/19/2008 Online Auction Website/Trade-in Expected to meet criteria this year 40,727 #
11 T-121 2011 FORD F150 4X4, PICK-UP 24,489.00 5/13/2011 Online Auction Website/Trade-in Expected to meet criteria this year 179,882 +
Office furniture, fixtures & equipment
12 07531 UHF Antenna w/ 1/2 Cable 5,948.75 10/5/2015 Damaged in Storm - Garbage
291,737.14
+ Criteria to replace: 12 years or 200,000 miles (Vehicles of 1.5 tons or less)
# Criteria to replace: 10 years and 200,000 miles (Vehicles of more than 1.5 tons)
Fiscal Year 2020 – Operating Budget
Capital Expenditures
VEHICLES:DEPARTMENT DESCRIPTION QTY COST TOTAL
Fleet / Structures Truck - Ford F150 (Replaces T-121) 1 30,000 30,000
Truck - Ford F250 (Replaces T-100, T101, T-103) 3 30,000 90,000
Truck - Ford F450 (Replaces T110) 1 40,000 40,000
Truck - Ford F450 w/custom bed (Replaces T-112) 1 60,000 60,000
6 220,000
Staff Recommendation
Declare listed items surplus and authorize disposal of items through the recommended disposal method.
Canal Rehabilitation Program Anthony LasCasas, PEDirector of Operations & MaintenanceDecember 11, 2019 – Board Meeting
LWDD Board of Supervisors Meeting December 10, 2019Agenda Item #14
In response to the hurricanes of 2004 & 2005, LWDD Board
of Supervisors authorized staff, under resolution 06-03,
“..to implement a plan of reclamation…”
Hurricane Francis
September 5, 2004; landfall on Hutchinson Island as Cat 2
Hurricane Jeanne
September 26, 2004; landfall on Hutchinson Island as Cat 2
Hurricane Wilma
October 24, 2005; landfall at Cape Romeo as Cat 3
Critical Path ProgramrenamedCanal Rehabilitation Program May 15, 2013
Critical Path Programrenamed Canal Rehabilitation Program May 15, 2013
2006 Initially estimated
27 projects / 25 miles 2015 Revised estimate to
196 projects / 150 miles 2018 Increased estimate to
224 projects / 180 miles0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
JAN
07
MA
Y-0
7SE
P-0
7JA
N-0
8M
AY
-08
SEP
-08
JAN
-09
MA
Y-0
9SE
P-0
9JA
N-1
0M
AY
-10
SEP
-10
JAN
-11
MA
Y-1
1SE
P-1
1JA
N-1
2M
AY
-12
SEP
-12
JAN
-13
MA
Y-1
3SE
P-1
3JA
N-1
4M
AY
-14
SEP
-14
JAN
-15
MA
Y-1
5SE
P-1
5JA
N-1
6M
AY
-16
SEP
-16
JAN
17
MA
Y 1
7SE
P 1
7JA
N 1
8M
AY
18
SEP
18
JAN
19
MA
Y 1
9SE
P 1
9
CRP Vegitation Removal (miles)3rd Party Contractor LWDD Crews
97.9 miles completed since October 2015 LWDD - 55.5 miles
Contractor Services - 37.3 miles
3RD Party (Developer/Govt.) - 5.1 miles
82.9 miles remaining Expected Completion of Tree Clearing Phase in early 2022
(excluding ~10 miles restricted ROW)
30.1 miles completed in past 12 months
Total Cost of Contract Services Expended or Encumbered FY20 $49,000 FY19 $1,268,906 FY18 $1,326,928 FY17 $630,785 FY16 $120,475
Canal Rehabilitation Update ‐ December 2018 –December 2019
97.9 mi 54%
0
10
20
30
40
50
60
70
80
90
100
Future Work Projected completion of tree clearing phase in 2022
Approximately 10 miles of ROW with restricted or poorly defined
access
Over 4,000 unpermitted encroachments identified
Complete survey mapping of all ROW
Complete modeling efforts
Regrade, realign and re-establish permanent access and design
sections
Goal to recover District ROW and implement a permanent and sustainable maintenance program