ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SITE PLAN & EXISTING BUILDINGPHOTO
M170504
LPC-01
SITE PLAN1 SCALE: 1/16" = 1'-0"
N
271 CENTRAL PARK WEST13-STORY MASONRYBLOCK: 1201 LOT: 29
7 WEST 87TH STREET5-STORY MASONRY
275 CENTRAL PARK WEST19-STORY MASONRY
AREA OFWORK
PHOTO 1 - UPPER WEST SIDE/CENTRAL PARK WEST HISTORIC DISTRICT MAP. 271 CENTRAL PARK WEST IS SHOWN IN RED.
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXISTING BUILDING PHOTOS
M170504
LPC-02
PHOTO 3 - CURRENT PHOTO OF THE PROPERTY SHOWING THE SOUTH (WEST 87TH STREET) FACING PRIMARY ELEVATION.NOTE: EXISTING SERVICE ELEVATOR BULKHEAD IS NOT VISIBLE.
PHOTO 2 - CURRENT PHOTO OF THE PROPERTY SHOWING THE EAST (CENTRAL PARK WEST) FACING PRIMARY ELEVATION.NOTE: EXISTING SERVICE ELEVATOR BULKHEAD IS NOT VISIBLE.
CEN
TRAL
PAR
K W
EST
WEST 87TH STREET
WEST 88TH STREET
CEN
TRAL
PAR
K
2A 2C
WEST DRIVE
2B
1A
1B
3A
3B
16'-8" 52'-5" 20'-0"89'-1"
CENTRAL PARK WEST1B1A
D001
NEW SKYLIGHTASSEMBLY
EXG WATERTANK TOREMAIN
ELEVATORBULKHEADTO REMAIN
NEWDOOR
NEW MASONRYWALL W/ FACEBRICK
NEW ROOF
NEW WALL W/ METAL CLADDING
2A
16'-8" 52'-5" 20'-0"89'-1"
• • • • ••• •••••••••
WEST DRIVECENTRAL PARK WEST
CENTRAL PARK
NEW PASSENGER ELEVATOR BULKHEAD &STANDPIPE VALVE ENCLOSURE CLEARSTHE SIGHT LINES FROM THE STREET LEVEL.THE NEW BULKHEADS ARE SLIGHTLYVISIBLE FROM THE WEST DRIVE ASDIRECTED BY LPC.
6'-0"2B 2C
D001
NEW ROOF
NEW WALL W/ METAL CLADDING
15'-4" 30'-0" 15'-4"60'-11"
WEST 87TH STREET3A3B
D002
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SIGHT LINE STUDY
M170504
LPC-03SIGHT LINE ELEVATION: NORTH2 SCALE: 1/32" = 1'-0"
SITE PLAN4 SCALE: 1/32" = 1'-0"
SIGHT LINE ELEVATION: NORTHWEST1 SCALE: 1/32" = 1'-0"
SIGHT LINE ELEVATION: WEST3 SCALE: 1/32" = 1'-0"
N
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SIGHT LINE STUDYPHOTOGRAPHS
M170504
LPC-04
PHOTO 4 - FACING SOUTH-WEST LEVEL ALONG WEST 87TH/ STREET SHOWING THE EXISTING CONDITIONS AT THE PENTHOUSE ROOF. PHOTO 5 - FACING SOUTH-WEST ALONG WEST 87TH/ STREET SHOWING THE MOCK-UP CONSTRUCTED FOR ONE (1) OF TWO (2) OF THE PROPOSED BULKHEADS AT THE PENTHOUSE ROOF.
PHOTO 6 - FACING NORTH ALONG CENTRAL PARK WEST SHOWING THE EXISTING CONDITIONS AT THE PENTHOUSE ROOF. PHOTO 7 - FACING NORTH ALONG CENTRAL PARK WEST SHOWING THE MOCK-UP CONSTRUCTED FOR ONE (1) OF TWO (2) OF THE PROPOSED BULKHEADS AT THE PENTHOUSE ROOF.
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SIGHT LINE STUDYPHOTOGRAPHS
M170504
LPC-05
PHOTO 8 - FACING NORTHWEST ALONG THE ROOF LEVEL SHOWING THE PROPOSED MOCKUPS. PHOTO 9 - FACING NORTH ALONG THE ROOF LEVEL SHOWING THE PROPOSED ELEVATOR BULKHEAD MOCKUP. THE RED OUTLINE DEPICTS THE CURRENT ACCESS DOOR TO THE PASSENGERELEVATOR MACHINE ROOM. THIS ACCESS DOOR IS CURRENTLY IN THE PENTHOUSE APARTMENT AND WOULD BE RELOCATED TO THE PROPOSED ELEVATOR BULKHEAD.
LOCATION OF BULKHEADMOCKUPS
PHOTO 10 - FACING NORTHWEST ALONG WEST DRIVE IN CENTRAL PARK SHOWING THE EXISTING CONDITIONS. PHOTO 11 - FACING WEST ALONG WEST DRIVE IN CENTRAL PARK SHOWING THE VISIBILITY OF THE CONSTRUCTED MOCK-UPS ALONG THE PENTHOUSE ROOF LEVEL.
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SIGHT LINE STUDYPHOTOGRAPHS
M170504
LPC-06
PHOTO 12 - FACING WEST ALONG A FOOT PATH IN CENTRAL PARK. PHOTO 13 - ZOOMED IN FACING WEST ALONG A FOOT PATH IN CENTRAL PARK.
PHOTO 14 - FACING WEST ALONG THE SOUND END OF THE JACQUELINE KENNEDY ONASSIS RESERVOIR IN CENTRAL PARK PHOTO 15 - ZOOMED IN FACING WEST ALONG THE SOUND END OF THE JACQUELINE KENNEDY ONASSIS RESERVOIR IN CENTRAL PARK
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
SIGHT LINE STUDYPHOTOGRAPHS
M170504
LPC-07
PHOTO 16- FACING SOUTH ALONG THE ROOF LEVEL SHOWING THE SIMILAR ELEVATOR BULKHEADS AT NEIGHBORING BUILDING 267 CENTRAL PARK WEST PHOTO 17-FACING WEST ALONG WEST DRIVE IN CENTRAL PARK SHOWING THE VISIBILITY OF THE ELEVATOR BULKHEADS AT NEIGHBORING BUILDING 267 CENTRAL PARK WEST
W D
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
W D
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
WEST 87TH STREET
CEN
TRAL
PAR
K W
EST
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
W D
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
W D
EXG ELEVATOREQUIP TO REMAIN
EXG MILLWORKDOOR TO REMAIN
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
REMOVE EXGACCESS DOOR
EXG O.S. & Y. STANDPIPE CONTROLVALVE TO BE REMOVED.
CONTRACTOR TO VIF EXISTENCE OFOTHER STANDPIPE VALVES/CHECK
VALVES
EXG METALGRATINGPLATFORM TOREMAIN
WEST 87TH STREET
CEN
TRAL
PAR
K W
EST
EXG ELEVATOREQUIP TO REMAIN
EXG ACCESS PANEL @ CLG TO BECLOSED
EXG STANDPIPE DOWN FROM ROOFTANK ABOVE CLG TO REMAIN
NEW STANDPIPE SECTION TOCONNECT TO EXG
EXG METALGRATINGPLATFORM TOREMAIN
EXG MILLWORKDOOR TO REMAIN
REPLACE EXGACCESS DOORW/ NEW RATEDWALL ASSEMBLY
A
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXISTING/REMOVAL &PROPOSED PLAN: PENTHOUSE
M170504
LPC-08
1LPC-08
1LPC-11
5LPC-13
7LPC-14
3LPC-12
EXISTING/REMOVAL PLAN: PENTHOUSE1 SCALE: 1/4" = 1'-0"
EXISTING/REMOVAL KEY PLAN: PENTHOUSE2 SCALE: 1/16" = 1'-0"
3LPC-08
2LPC-11
6LPC-13
8LPC-14
4LPC-12
CONSTRUCTION PLAN: PENTHOUSE3 SCALE: 1/4" = 1'-0"
CONSTRUCTION KEY PLAN: PENTHOUSE4 SCALE: 1/16" = 1'-0"
D002
PENTHOUSE ROOF
SERVICE ELEVATORBULKHEAD
5'-11
"
3'-0"
NEW METAL GRATINGPLATFORM
D001
EXG ELEVATOR EQUIPBELOW TO REMAIN
NEW WALL W/ METALCLADDING
6"3'-
0"2'-
5"
6'-0"
9'-8"
B
5'-8"2'-8"
B
3'-0"
3"
C
C
3'-0"3'-3"6'-6"
4'-8"
B
C
RELOCATE EXG STANDPIPE VALVEFROM PENTHOUSE LEVEL TO
PENTHOUSE ROOF
MAXIMIZE CEILING HEIGHT
NEW WALL W/ METAL CLADDING
NEW DOOR
NEW DOOR
NEW METAL LADDER
C
4'-6"
6'-9"
13'-9"
D002
PENTHOUSE ROOF
TERRACE
TERRACE
SERVICE ELEVATORBULKHEAD
5'-11
"
3'-0"
NEW METAL GRATINGPLATFORM
D001
EXG ELEVATOR EQUIPBELOW TO REMAIN
NEW WALL W/ METALCLADDING
6"3'-
0"2'-
5"
6'-0"
9'-8"
B
5'-8"2'-8"
B
3'-0"
3"
C
C
3'-0"3'-3"6'-6"
4'-8"
B
C
RELOCATE EXG STANDPIPE VALVEFROM PENTHOUSE LEVEL TO
PENTHOUSE ROOF
MAXIMIZE CEILING HEIGHT
NEW WALL W/ METAL CLADDING
NEW DOOR
NEW DOOR
NEW METAL LADDER
C
4'-6"
6'-9"
13'-9"
WEST 87TH STREET
CEN
TRAL
PAR
K W
EST
TERRACE
TERRACE
PENTHOUSE ROOF
SERVICE ELEVATORBULKHEAD
REMOVE EXG SKYLIGHT
6'-0"
7'-2"
5'-0"
2'-11
"
RELOCATE EXG STANDPIPE VALVEFROM PENTHOUSE LEVEL TO
PENTHOUSE ROOF
WEST 87TH STREET
CEN
TRAL
PAR
K W
EST
PENTHOUSE ROOF
SERVICE ELEVATORBULKHEAD
REMOVE EXG SKYLIGHT
6'-0"
7'-2"
5'-0"2'-
11"
RELOCATE EXG STANDPIPE VALVEFROM PENTHOUSE LEVEL TO
PENTHOUSE ROOF
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXISTING/REMOVAL &CONSTRUCTION PLAN:PENTHOUSE ROOF
M170504
LPC-09
3LPC-09
5LPC-15
7LPC-15
6LPC-15
8LPC-15
CONSTRUCTION PLAN: PENTHOUSE ROOF3 SCALE: 1/4" = 1'-0"
CONSTRUCTION KEY PLAN: PENTHOUSE ROOF4 SCALE: 1/16" = 1'-0"
1LPC-04
1LPC-15
3LPC-15
2LPC-15
4LPC-15
EXG/REMOVAL PLAN: PENTHOUSE ROOF1 SCALE: 1/4" = 1'-0"
EXISTING/REMOVAL KEY PLAN: PENTHOUSE ROOF2 SCALE: 1/16" = 1'-0"
1LPC-11
5LPC-13
7LPC-14
3LPC-12
2LPC-11
6LPC-13
8LPC-14
4LPC-12
5LPC-16
7LPC-16
6LPC-16
8LPC-16
1LPC-16
3LPC-16
2LPC-16
4LPC-16
WEST 87TH STREET WEST 88TH STREET271 CENTRAL PARK WEST 275 CENTRAL PARK WEST 279 CENTRAL PARK WEST262 CENTRAL PARK WEST
CENTRAL PARK WEST
••••••••••••••••••••••••
••••••••••••••••
••••••••••••••••••
••••••••••••••••
NEW SKYLIGHT ASSEMBLY
EXG SERVICE ELEVATORBULKHEAD TO REMAIN
NEW MASONRY WALL W/ FACE BRICK
NEW ROOF
NEW WALL W/ METAL CLADDING
D002NEW DOOR
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
PROPOSED BLOCK ELEVATION
M170504
LPC-10PROPOSED BLOCK ELEVATION1 SCALE: 1/16" = 1'-0"
REMOVE EXGSKYLIGHTASSEMBLY
EXG WATERTANK TOREMAIN
EXG SERVICEELEVATORBULKHEADTO REMAIN
PENTHOUSE ROOF LEVEL
PENTHOUSE
D001
NEW SKYLIGHTASSEMBLY
EXG WATERTANK TOREMAIN
EXG SERVICEELEVATORBULKHEADTO REMAIN
NEWDOOR
NEW MASONRYWALL W/ FACEBRICK
NEW ROOF
NEW WALL W/ METAL CLADDING
PENTHOUSE ROOF LEVEL
PENTHOUSE
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXg/REMOVALS & PROPOSEDEXTERIOR ELEVATION: NORTH
M170504
LPC-11
EXISTING EXTERIOR ELEVATION: NORTH1 SCALE: 1/4" = 1'-0"
PROPOSED EXTERIOR ELEVATION: NORTH2 SCALE: 1/4" = 1'-0"
NEW SKYLIGHT ASSEMBLY
EXG SERVICE ELEVATORBULKHEAD TO REMAIN
NEW MASONRY WALL W/ FACE BRICK
NEW ROOF
NEW WALL W/ METAL CLADDING
D002NEW DOOR
PENTHOUSE ROOF LEVEL
PENTHOUSE
REMOVE EXGSKYLIGHT ASSEMBLY
EXG WATERTANK TOREMAIN
EXG SERVICEELEVATORBULKHEADTO REMAIN
PENTHOUSE ROOF LEVEL
PENTHOUSE
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXG/REMOVALS & PROPOSEDEXTERIOR ELEVATION: WEST
M170504
LPC-12PROPOSED EXTERIOR ELEVATION: WEST4 SCALE: 1/4" = 1'-0"
EXISTING EXTERIOR ELEVATION: WEST3 SCALE: 1/4" = 1'-0"
EXG WATER TANKTO REMAIN
NEW ROOF
NEW WALL W/ METALCLADDING
EXG SERVICE ELEVATORBULKHEAD TO REMAIN
NEW SKYLIGHTASSEMBLY
PENTHOUSE ROOF LEVEL
PENTHOUSE
NEW MASONRY WALLW/ FACE BRICK
EXG WATERTANK TOREMAIN
EXG SERVICEELEVATORBULKHEADTO REMAIN
REMOVE EXGSKYLIGHTASSEMBLY
PENTHOUSE ROOF LEVEL
PENTHOUSE
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXG/REMOVALS & PROPOSEDEXTERIOR ELEVATION: SOUTH
M170504
LPC-13PROPOSED EXTERIOR ELEVATION: SOUTH6 SCALE: 1/4" = 1'-0"
EXISTING EXTERIOR ELEVATION: SOUTH5 SCALE: 1/4" = 1'-0"
EXG WATERTANK TOREMAIN
EXG SERVICEELEVATORBULKHEADTO REMAIN
PENTHOUSE ROOF LEVEL
PENTHOUSE
EXG WATER TANKTO REMAIN
NEW ROOF
NEW WALL W/ METALCLADDING
PENTHOUSE ROOF LEVEL
PENTHOUSE
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXG/REMOVALS & PROPOSED:EXTERIOR ELEVATION: EAST
M170504
LPC-14
EXISTING EXTERIOR ELEVATION: EAST7 SCALE: 1/4" = 1'-0"
PROPOSED EXTERIOR ELEVATION: EAST8 SCALE: 1/4" = 1'-0"
REMOVE EXG SKYLIGHTASSEMBLY
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
EXG WALL TO REMAIN
6'-6"
PENTHOUSE
3'-8"
PENTHOUSE ROOF LEVEL
PENTHOUSE
EXG METAL GRATINGPLATFORM TO REMAIN
REMOVE EXG ACCESSDOOR
EXG MILLWORK DOORTO REMAIN
REMOVE SKYLIGHTASSEMBLY
4'-8"
2'-8" 2'-0"
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
EXG WALL TO REMAIN
REMOVE EXG SKYLIGHTASSEMBLY
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
REMOVE EXG SKYLIGHTASSEMBLY
REMOVE EXG ACCESS DOOR
EXG MILLWORK DOORTO REMAIN
EXG WALL TO REMAIN
NEW METAL GRATINGPLATFORM
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
NEW LADDER
NEW MASONRY WALLW/ FACE BRICK
NEW SKYLIGHT ASSEMBLY
NEW CURB (6" MIN)
NEW HOIST BEAM (W 8x10)
NEW DOOR
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
EXG WALL TO REMAIN
NEW LADDER
NEW MASONRY WALLW/ FACE BRICK
NEW SKYLIGHT ASSEMBLY
NEW HOIST BEAM (W 8x10)
EXG METAL GRATINGPLATFORM TO REMAIN
REPLACE EXG ACCESS DOORW/ NEW RATED WALL ASSEMBLY
NEW METAL GRATINGPLATFORM
NEW LADDER
EXG MILLWORK DOORTO REMAIN
NEW DOOR
NEW SKYLIGHT ASSEMBLY
4'-8"
2'-8"
NEW MASONRY WALLW/ FACE BRICK
EXG ELEVATOR EQUIPTO REMAIN
NEW CURB (6" MIN)
NEW HOIST BEAM (W 8x10)
EXG METAL GRATINGPLATFORM TO REMAIN
EXG ELEVATOR EQUIPTO REMAIN
EXG WALL TO REMAIN
NEW METAL GRATINGPLATFORM
3'-6"
6'-6"
NEW LADDER
NEW MASONRY WALLW/ FACE BRICK
NEW SKYLIGHT ASSEMBLY
8'-0"10
'-91 2"
3'-0"
PENTHOUSE ROOF LEVEL
PENTHOUSE
NEW HOIST BEAM (W 8x10)
2'-91 2"
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXISTING & PROPOSEDPASSENGER ELEVATORBULKHEAD SECTIONS
M170504
LPC-15
EXG PASSENGER ELEVATOR SECTION: NORTH1 SCALE: 1/4" = 1'-0"EXG PASSENGER ELEVATOR SECTION: EAST2 SCALE: 1/4" = 1'-0"
EXG PASSENGER ELEVATOR SECTION: SOUTH3 SCALE: 1/4" = 1'-0"EXG PASSENGER ELEVATOR SECTION: WEST4 SCALE: 1/4" = 1'-0"
PROPOSED PASSENGER ELEVATORBULKHEAD: NORTH5 SCALE: 1/4" = 1'-0"
PROPOSED PASSENGER ELEVATORBULKHEAD: EAST6 SCALE: 1/4" = 1'-0"
PROPOSED PASSENGER ELEVATORBULKHEAD: SOUTH7 SCALE: 1/4" = 1'-0"
PROPOSED PASSENGER ELEVATORBULKHEAD: WEST8 SCALE: 1/4" = 1'-0"
6'-7"
EXG WATER TANKTO REMAIN
PENTHOUSE ROOF LEVEL
EXG STANDPIPETO REMAIN
EXG BEAMS TO REMAIN
EXG WATER TANKTO REMAIN
EXG STANDPIPETO REMAIN
EXG BEAMS TO REMAIN
EXG WATER TANKTO REMAIN
EXG STANDPIPETO REMAIN
EXG BEAMS TO REMAIN
EXG WATER TANKTO REMAIN
EXG STANDPIPETO REMAIN
EXG BEAMS TO REMAIN
NEW WALL W/ METALCLADDING
EXG WATER TANKTO REMAIN
RELOCATE EXGSTANDPIPE VALVEFROM PENTHOUSE LEVELTO PENTHOUSE ROOFREFER TO STANDPIPEDRAWINGS
EXG BEAMS TO REMAIN
NEW ROOF
EXG WATER TANKTO REMAIN
RELOCATE EXGSTANDPIPE VALVEFROM PENTHOUSE LEVELTO PENTHOUSE ROOFREFER TO STANDPIPEDRAWINGS
EXG BEAMS TO REMAIN
NEW WALL W/ METALCLADDING
NEW ROOF
NEW DOORNEW WALL W/ METALCLADDING
EXG WATER TANKTO REMAIN
RELOCATE EXGSTANDPIPE VALVEFROM PENTHOUSE LEVELTO PENTHOUSE ROOFREFER TO STANDPIPEDRAWINGS
EXG BEAMS TO REMAIN
NEW ROOF
6'-7"
NEW WALL W/ METALCLADDING
NEW DOOR
6'-0"
6'-4"
PENTHOUSE ROOF LEVEL
EXG WATER TANKTO REMAIN
RELOCATE EXGSTANDPIPE VALVEFROM PENTHOUSE LEVELTO PENTHOUSE ROOFREFER TO STANDPIPEDRAWINGS
EXG BEAMS TO REMAIN
NEW ROOF
ENGINEERING & ARCHITECTURE, DPC
TEL. (212) 675-8844 / FAX (212) 691-7972
159 WEST 25TH STREETNEW YORK, NY 10001
BUILDING INFORMATION
BLOCK: 1201
LOT: 29
MAP: 5D
ZONING DISTRICT: R10A
LANDMARK: YES
SITE PLAN
LIMITED PENTHOUSE ALTERATIONS,ACCESS DOOR RELOCATION
271 CENTRAL PARK WESTNEW YORK, NYDOCKET #: 19-19956
UPPER WEST SIDE/CENTRALPARK WEST HISTORIC DISTRICT
LANDMARK PRESERVATIONCOMMISSIONSEPTEMBER 4, 2018PUBLIC HEARING
N
CEN
TRAL
PAR
K W
EST
CO
LUM
BUS A
VENU
E
12B
100'
75.5
'27
1
CEN
TRAL
PAR
K
WEST 87TH STREET
WEST 88TH STREET
700 FEETTO LAKE
EXISTING & PROPOSEDSTANDPIPE VALVE ENCLOSURESECTIONS
M170504
LPC-16
EXG STANDPIPE: NORTH1 SCALE: 1/4" = 1'-0"EXG STANDPIPE: EAST2 SCALE: 1/4" = 1'-0"
EXG STANDPIPE: SOUTH3 SCALE: 1/4" = 1'-0"EXG STANDPIPE: WEST4 SCALE: 1/4" = 1'-0"
PROPOSED STANDPIPE: NORTH5 SCALE: 1/4" = 1'-0"PROPOSED STANDPIPE: EAST6 SCALE: 1/4" = 1'-0"
PROPOSED STANDPIPE: SOUTH7 SCALE: 1/4" = 1'-0"PROPOSED STANDPIPE: WEST8 SCALE: 1/4" = 1'-0"