53
PRELIMINARY ENGINE,ERING REPORT LOWER MAUUAIS COULEE IMPROVEMET,{TS swc No. 1614 DEVILS IAKE BASIN NORTH DAKOTA STATE WATER COMMISSION CALIO cor"tLEE DEVILS LAKE BASIN EDMOFE COULEE LAKE ALICE LAKE IBSEN LAKE IRVINE DRY LAKE CHANNEL A O DEVILS LA'(E END STUDY June 1994

LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

PRELIMINARY ENGINE,ERING REPORT

LOWER MAUUAIS COULEEIMPROVEMET,{TS

swc No. 1614DEVILS IAKE BASIN

NORTH DAKOTASTATE WATER COMMISSION

CALIOcor"tLEE

DEVILSLAKEBASIN

EDMOFECOULEE

LAKEALICE

LAKEIBSEN

LAKEIRVINE

DRYLAKE

CHANNEL A

O DEVILS LA'(E

ENDSTUDY

June 1994

Page 2: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

PRELIIIINÀRY ENGIT{EERIIIG REPORT

Lo¡rer l[auvais Coulee ImprovementsSTIC Project #1614

June L994

I{orth Dakota State ffater Comnission900 East Boulevard

Bismarck, North Dakota 58505-0850

Prepared by:

€C. Gregg ImanIÍater Resource Engineer

Sul¡mitted by:

DaTe L. Fr , P.E.Director of Tfater DeveloPment

Approved by:

David À.State

,

Page 3: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

TÀBLE OF CONTENTS

I. TNTRODUCTION.

Study Objectives.Project Location and Purpose.Historical Background

II. ITYDROLOGY

Page

1

7

89

10

11

13

131626

31

32

37

T2L4L71819202224

I13

Hydrolog-yHydrolog-yHydrology

IIT. HTDRÀI]LICS.

IV. ÀI,TERI{ÀTI\rES.

ÀIternativeÀIternativeÀlternativev.

vr.VII.

for CurrenÈ Lower Mauvais Cou1ee Study.from l-980 Lower Mauvais Coulee Study.from 1991 Chain Lakes Study

OneTwoThree

TabIeTabIelab1eTableTableTabIeTableTabIeTabl-e

1234567I9

PERlrrr REQUTREIÍENTS

SIII,ÍIT,ARY

RECOIIUENDÀTIONS

TÀBLES

Rating Cu::r¡e for 1993 Flood Conditions.Rating Curve for Àlternative One.Existing Structure Summary. .Cost Estimate to Replace Structure #9Cost Estimate to Replace Structure #8Cost Estimate to Replace Structure #6Cost Estimate to Replace Structure #fRating Curve for Àlternative Two.Rating Curve for Àlternative Two ¡uith Stop LogsRemoved from Control Structure,Rating Curve for ÀIternative Three. .Rating Curve for Àlternative Three with StopLogs Removed from Control StructureCost Estimate for Àlternative Three Channelfmprovements. .

2628Tabl-e

Table1011

30Table 12

-l-

30

Page 4: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

FigureFigureFigureFigure

FigureFigure

1-23-4

8-

TÀBLE OF CONTENTS (CONT. )

FIGI]RES

Location of Lower Mauvais CouleeStudy Àrea and Structure LocationsIsometric View of Structure #1Comparison of Water Surface Profiles of LowerMauvais Coulee for \979 Equivalent Flow. .Channel Profile of Lower Mauvais Coulee forExisting Conditions.Channel Profile of Lower Mauvais Cou1ee forAlternative Three.Comparison of Lake Irvine Rating Curves. .Comparison of Lake lrvine Rating Curvesfor Drawdown Capabilities. .

24

23

Page

25

27

2933

34

Figure 5

Figure 6 -

ÀPPENDICES

Appendix À - Copy of Agreement

Àppendix B - Recommendations of 1980 Lower MauvaisCoulee ÏÍater Surface Profile Study

Appendi-x C Synbols and Àbbreviations

-ll-

Page 5: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

I. INTRODUCTION

Study Objectives:In June of 1993, the North Dakota State l{ater Commission and

the Devils Lake Basin Joint lfater Management Board entered into an

agreement to conduct a hydraulic study of Lower lvlauvais Cou1ee

(also known as Big Coulee) from Lake Irvine to the l[est Bay ofDevils Lake. The agreement called for the State I{ater Commission

to conduct a field survey of the project area, including crosssections of the coulee; modify and update existing hydraulicstudies of Lower Ìfauvais Cou1ee; recommend potential road crossingand channel improvements; test the effects of the proposedímprovements using the hydraulic model; estimate the effects of theproposed improvements on the Chain of Lakes using informationderived from the 1991 Chain Lakes Improvement Study; preparepreliminary cost estimates for the various alternatives; and

prepare a written report documenting the findings of theinvestigation. A copy of the açJreement is contained in Àppendix A.

Project tocation and Purpose:Lower Mauvais Cou1ee is located in the Devils Lake Basin in

western Ramsey and eastern Benson Counties. The reach of thecoulee modelled for this study is approximately 21 miles long. Itoriginates at Lake Irvine, Iocated near the city of Churchs Ferry,and flows southeast to the !{est Bay of Devils Lake, approximately5 miles east of the city of Minnewaukan, North Dakota. Figure 1

shows the location of Lower Mauvais Coulee within the state of

-r-

Page 6: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

LOWER MAUVAI.S COLTLEEIMPROVEME¡IZ^S

swc # t6t4LOCATION MAP

Figure I - Locationof Lower Mauvais Coulee

LAKE ISBEN

SWÊElWATERLAKE

I¡*ETIA¡,YAFoot¡-E

LAKE BASIN

SnFlll¡

LAKE ALICE

LAKE IRV]NE

DEVLSLAKE

-2-

Page 7: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

North Dakota. Figure 2 shows the study area, including thestructure locations.

The channel slope of Lower Mauvais Coulee is relatively flat,particularly at the upper end of the couLee. Àny obstructions thatcause an increase in water level can increase flooding fartherupstream. The purpose of this study is to identify areas ofrestriction along Lower Mauvais Coulee and to propose correctivemeasures that will reduce flood.ing, both aloág the coulee and inthe Chain of Lakes area.

Ilistorical Background :

Several studies of the Devils Lake Basin have been compJ-eted

in recent years. In December 1980, a study titled Lower Mauvais

Coul-ee lilater Surface Profile Study \ras completed by the State Water

Commission. This study determined the effects of existing channel

conditions and road crossings on selected flows. The study alsorecommended improvements to the channel, culverts, and bridges.Àppendix B contains a summary of the recommendations of the 1980

study and their associated costs. The study recommended

improvements in two phases. The phase one improvements includedprojects that would provide the greatest benefits. The phase two

improvements would provide additional flood relief, but would

involve several projects and considerable cost.

-3-

Page 8: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

I

6

tlt L't

a 53 I5.

a

'l

!ìÍ:-l---l¿: -t-le

t';l+IìrlI jru. I

-lI

¡q

I unc nuxINAl.IONAL

¡2

ll t a t1 ll rl

a t/'"t.Y

¡

olt

I

29

t6

20

a

I

, JL 28,9

o

¡t,la IJ

BJ BEGIN STT'DY

END STI'DY

ture #1

ì2

,rì

OVER- ."

r¡rytI

lt rucI r\

llllllll.ll

[-esz Structure #16 ! j'fl'

ÊrHHPJ ts-(aØÉrthfioÉoN)rfÉlflo a')r|trÉoo,o<prdÞP. I-JorD5ÞIJ'

I,ÞI INNEWA

POn 40ô

ta

AN-.¡J

!,0

ãtNlol

fllr oJr lf,

r1

t^s

DEVlLS

llt

Þa

It

e.o

aJO o

[.1

L

Í\-t

ll/'l

____ J

u

¡WAUKAN¡EMENT

E

LA/(EA EA

;lII

,,tttt

þ

I

t

I

I

t,

FESERVATTO

a

lfi

tAMINDIAN

a

I

zlirln J.-

l0

JI

2t

¡

I

a ut2

2'

I

--Jl__-11

Il,

fclluRcHs

J2

¡ NILES a

l6 il. .¡a

292t(a

2'.¡2tII

)1

26

a

t 2J22'

rltillrtl

a

II

l92ao

2t

I

20

llt1

, GROAT:- 16

I

J

t,t I 9

+

lt

Lr-.

BENSON

R.65;

Page 9: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Since the 1980 study was compl-eted, few of its reconmendationshave been implemented, mainly due to a lack of funds. In one

instance, Structure #9, where an increase in the size of theroadway crossing was recommended, the existing bridge was replacedby two 1O-foot diameter corrugated metal pipe (CUP) culverts witha smaller flow area than the bridge they replaced.

In September 1991, a study titled Chain Lakes Improvement was

completed by the North Dakota State llater Commission. This studyevaluated the feasibility of certaj-n hydraulic improvements to thewatercourses in the vicinity of Mikes Lake, Chain Lake, Lake À1ice,and Lake lrvine to reduce flood damages. The study resulted fromrecommendations made by the Lake Alice Study Group.

The study recommended the instaLl-ation of a ne\r controlstructure at the downstream end of Lake Irvine. It alsorecommended that Lakes frvine, Àlice, and Chain be drawn down to an

el-evation of approximately 1439 mean sea level (msl) each fall.Ànother recommendation of the study was the construction of a

channel in the Duck Road area to improve flows out of Chain Lake

and Mikes Lake. Reconsideration of the improvements to Lower

Mauvais Coulee suggested in the 1980 study was also recommended.

The improvements evaluated in the 1991 Chain Lakes Study wouldreduce flooding during 5-year and 10-year floods. The improvements

would have little effect on flooding during larger events because

-5-

Page 10: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

during }arger events there is too much water in the area to move

downstream to Devils Lake without causÍng flooding problems" Àt

this tirne, nonê of the recoÍmrendatj.ons of the 1991 stud¡r'have been

implemented.

-6-

Page 11: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

IT. IITDROLOGY

The Devils Lake Basin covers a total of about 31814 square

miles invoJ-ving all or portions of eight counties. Devils Lake

itself has a drainage area of approximately 31320 square miles,with the remainder of the basin entering Sturnp Lake. About 2,01-0

square miles of the Devils Lake Basin drains into the Chain ofLakes system. Channel A has a drainage area of approximately 890

square miles. The remaining L,L20 square miles of drainage area

enters Devils Lake via Lower Mauvais Coulee. The three main

tributaries above Lower Ìlauvais Coulee are St. Joe, Calio, and

Mauvais Cou1ees.

Channel A was completed in 1978. It allows Sweetwater Lake,

Morrison Lake, and. Dry Lake to outlet directly to Six lvlile Bay ofDevils Lake. The flow from these lakes formerly exited thenorLhwest corner of Dry Lake and entered llikes Lake, eventuallyentering Devils Lake via Lower l"lauvais Coulee. Prior to theconstruction of Channel A, water flowed out the northwest corner ofDry Lake at elevation 1447.5 msl. Following the construction ofChannel A, the northwest outlet of Dry Lake was raised to elevation1449.5 msl. Channel À is operated so that Dry Lake is maintained

at elevation L447.5 msl during the summer. In the fall, the gates

on the Channel À control structure are opened and Dry Lake is drawn

down to elevation 1445 msl to allow flood storage for the upcoming

spring runoffr âs stipulated in the Channel À operating plan.

-7-

Page 12: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Hydroloqy for Current Lower Þlauvais Cou1ee Study:

This study evaluated the effects of potential road crossingand channel improvements on Lo$¡er Mauvais Coulee for a range off lows from Lake Irvine. The discharges from Lake Irvine that r,rere

evaluated ranged from 18 cubic feet per second (cfs) to 11080 cfs.The various improvements \üere modelled for this range of fLows and

rating curves at Lake Irvine were developed from this information.These rating curves are contained in the folJ-owing sections of thisreport.

The flows below the confluence of Lower Mauvais Cou1ee and

Little Coulee were increased to account for the added flow from

Little Coulee. Little Coulee has a drainage area of approximately400 square miles. Hydrographs from high flow events for Lower

Mauvais Coulee and Little Coulee Yrere compared to quantify thecontribution of Little Cou1ee to Lower Mauvais Coulee below theconfluence. The events that were compared occurred after theinstallation of Channel A. fhis comparison indicated that on

average, the peak flow on Litt1e Coulee occurs prior to the peak

flow on Lower Mauvais Coulee. For the events analyzed, when thepeak flow on the reach of Lower Mauvais Coulee below the confluence

with Little Coulee occurs, approximately 10 percent of the flow isbeing contributed by Little Coulee and 90 percent comes from Lake

Irvine. Considering this distribution, the flows on Lower Mauvais

Cou1ee that were modelled for the reach of channel below theconfluence with Litt1e Cou1ee ranged from 20 cfs to I,200 cfs

-8-

Page 13: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

corresponding to the range of flows of 18 cfs to 11080 cfs for theupper reach of coulee.

Hydrology from 1980 Lower llauvais Coulee Study:

The 1980 water surface profile study on Lower Mauvais Coulee

approximated the 1979 flood as a 100-year event. This was based on

the observation that at the time of the study, the L979 floodprovided the highest volume of inflow to Devils Lake since 1867.

In Lg7g, 2851000 acre-feet of water flowed into Devils Lake.

Of this, approximately 1?OrO0O acre-feet entered the lake through

Lower Mauvais Coulee. Channel- À carried an additional 561000

acre-feet of water. fn L979, the peak discharge from Lake lrvinewas 11030 cfs. Below the confluence with Little Coulee, the peak

flow on Lower Mauvais Coulee was L,400 cfs. Channel À was onlyoperated. for part of the year in 1979, and the northwest outlet ofDry Lake had not been raised to elevation L449.5 msI.

For the 1980 Lower Mauvais Coulee Study, a flood equaì- to 50

percent of the IgTg flood volume, adjusted for a fully operationalChannel À, \úas estimated to be a 25-yeat event. Based on thisassumption, a 2S-year flood would yield a peak discharge from Lake

Irvine of 700 cfs, and the flow below the confluence with LittleCou1ee would. be 900 cfs. The 25-year ftood was used to determine

the structure size needed for the stream crossings.

9

Page 14: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Hydrologrv from 1991 Chain Lakes Improvement Study:The 1991 Chain Lakes Improvement Study deterrnined inflows for

Mikes Lake, Chain Lake, Lake Àlice, and Lake Irvine using the USGS

stream gage on Mauvais Coulee near Cando, NorÈh Dakota. À Log

Pearson Type fII analysis was performed using the gage records todevelop S-year and lO-year peak flows and the runoff volume at thegage. The HEC-I computer model was used t'o develop S-year and

l0-year hydrographs for the basin above the gage and the model was

calibrated using the gage records. The HEC-1 computer model v¡as

also used to develop hydrographs for the confluence of Mauvais

Coulee and Lake Alice, âs well as the mouth of Ca1io and St. Joe

Cou1ees. The hydrographs rrere input into the National lÍeatherService's DIÍOPER model. The DWOPER model was used to analyze theeffects of various hydraulic improvements to the watercourses inthe vicinity of lvlikes Lake, Chain Lake, Lake ÀIice, and Lake

Irvine.

The D!ÍOPER model used for the 1991 Chain Lakes Study generated

flow and stage hydrographs for the outlet of Lake lrvine. À reviewof these hydrographs indicates that the flow from Lake Irvine intoLower Mauvais Cou1ee for a S-year precipitation event is 360 cfsfor existing conditions, and 390 cfs if the recommendations of the1980 Lower Mauvais Cou1ee Study are implemented. The flow for a

lQ-year precipitation event is 560 cfs for existing conditions, and

620 cfs if the reconmendations of the l-980 Lower Mauvais Coulee

Study are implemented.

-10-

Page 15: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

III. TTDRÀIJLICS

À hydraulic analysis of Lower Mauvais Coulee was performed

using the HEC-2 computer model, developed by the U.S. Àrmy Corps ofEngineers. HEC-2 computes water surface profiles for steady,gradually varied flow in natural or man-made channels for variousflows. The data needed to perform these computations include:flow regime, starting water surface elevation, discharge, losscoefficients, cross-section geometry, and reach lengths. The

computational procedure used by the model is based on the solutionof the one-dimensional energ-y equation with energ)¡ loss due tofriction evaluated with Manning's equation. This computation isgeneralty known as the Standard Step Method-

The HEC-2 computer model for Lower Mauvais Coulee was

developed using survey information obtained by the State T{ater

Commission's survey crew in the falt of 1993. This included cross

sectional data, bridge and culvert geometries, and water levelsalong the coulee. The HEC-2 computer model $¡as developed and

calibrated to the conditions experienced at the time of the survey.

This computer model \ilas used to develop a rating curve for Lower

Mauvais Coul-ee for the conditions experienced during the 1993

flood. Table 1 contains a rating curve for Lower Mauvais Coulee atLake lrvine for the 1993 flood conditions -

-11_-

Page 16: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Tab1e 1 - Rating Cunre for 1993 Flood Conditions

144r.. 5L442.41443.0v44.A1445.0r.446.0

0.081.0

148.0228. 0317.0415.0

-12-

Page 17: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

IV. ÀI,TERNÀTIVES

Several improvements to increase the capacity of Lower Mauvais

Coulee \rere evaluated. These improvements are summarized in threealternatives. Àlternative One involves reducing the amount ofvegetation in the channel of Lower Mauvais Coulee and maintaininga pilot path through the high cattail areas below Pelican Lake.

Alternative Two involves reducing the amount of vegetation in thechannel of Lower Mauvais Coulee and maintaining a pilot path

through the high cattail areas below Pelican Lake; installing new

bridges to replace Structures #9, #8, #6, and #1; and installing a

ne\f control structure at Lake Irvine. Àlternative Three isessentially the same as Alternative Two excePt that it also

involves excavating a 60-foot wide channel from Structure +4 (the

Highway 2 Bridge) to the confluence with Little Coulee. The

following sections describe these alternatives in detail.

Àlternative One:

This alternative involves reducing the amount of vegetation inLower Mauvais Coul-ee and maintaining a pilot path through the high

cattail areas below Pelican Lake. The flooding experienced duringthe summer of 1993 in the Devils Lake Basin was compounded by the

large amount of vegetation that existed in many of the waterways afthe tine of the flooding. À cattail cutter was used to remove some

of the vegetation from these waterways. The use of the cattailcutter hetped improve the channel conditions to some extentr butthe amount of vegetation in the channels was still high. The

-13-

Page 18: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

effect of the cattails was perhaps most evident along Lower Mauvais

Coulee due to its relatively ftat slope. TabÌe 2 shows a ratingcurve for Lower Mauvais Coulee at Lake lrvine for Àlternative One.

Table 2 - Rating Curve for ÀIternative One

Lake In¡ine Level (msl) Discharge (cfs)L44L .61442.01443.0L444.01445. 01446.0

0.0101.0240.0369.0558.0756.0

The current high 1evels in Devils Lake will help control thevegetation in some areas, such as bet'ow Pelican Lake. This area isnorrr essentially part of Devils Lake and the high water may kiltmost of the cattails. Às the lake rises and recedes this highvegetation area wiII move upstream and downstream, respectively.It is important, however, to always maintain a pilot path throughthe vegetation in this area.

Reducing the amount of vegetation in Lower Mauvais Coulee and

maintaining a pilot path through the high cattail areas belowpel-ican Lake will have a significant effect on \tater levels in thecoulee and the takes above it. During the summer of 1993, the peak

fl-ow on Lower Mauvais Coulee below the confluence with LittleCoul-ee was 347 cfs on Àug-ust 31. Of this flow, approximately 31

cfs came from Litt1e Coulee and 3f6 cfs came from Lake lrvine.This corresponds to a level of approximately L445 msl at Lake

-L4-

Page 19: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Irvine. Based on the results of the HEC-2 model, if the amount ofvegetation $¡ere reduced in Lower Mauvais Coulee and a pilot path

\fere maintained below Pelican Lake, the coulee woul-d have been

capable of passing a flow of 316 cfs with Lake lrvine at a leve1 ofapproximately 1443.6 msI.

The most effective method of reducing the amount of vegetationin Lower Mauvais Coulee is to develop a regular maintenance

program. When the channel is dry, the vegetation can be controlledby mowing. I{hen there is water in the channel, it may be necessary

to control the vegetation using an herbicide such aS Rodeo

(registered trademark of Monsanto Company, St. Louis, MO), or insome cases a cattail cutter. The annual cost to control thevegetation in Lower Mauvais Coulee is estimated to be approximately

$10,000.

In addition to improved channel maintenancer a 75-foot wide

pilot path should be maintained through any cattail area in theupper reaches of Devil-s Lake. In 1993, the area below Pelican Lake

\ras overgro\ún with cattails. Higher lake leve1s will move theproblem area farther upstream. If Devil-s Lake recedes, it isJ-ike1y that the area below Pelican Lake will again develop a

cattail problem.

Maintaining the pilot path witl require that the vegetation be

dredged, cutr ot sprayed. Dredging wiII be difficult and costly

-15-

Page 20: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

due to the wet conditions that occur through this area. À cattailcuÈter could be used to develop the pitot path, but this would al-so

be very costly. À simpler solution may be to spray the cattailswith an herbicide such as Rodeo using an aerial sPrayer.

ÀIternative Two:

This alternative involves reducing the amount of vegetation inthe channel of Lower Mauvais Coulee and maintaining a piloL paththrough the high cattail areas below Pelican Laker âs recommended

in ÀIternative One. It also involves replacing four roadway

crossings with new bridges and installing a control structure atLake lrvine.

The portion of Lower Mauvais Coulee above the confluence withLittle Coulee has a flat sIope. On average, the slope in thisreach is approximately 9 inches per mile. Any obstructions thatcause an increase in water level wiII cause the water level toincrease in the coulee through Lake frvine. Several structuresIocated along this reach of the coulee are undersized and cause an

increase in water level. Table 3 shows the existing crossingsalong Lower Mauvais Coulee and the net flow area associated witheach of them.

-16-

Page 21: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Table 3 - Existing Structure Summary

1615L413L2

Section 10 BridgeHighway L9 BridgePelican Lake BridgeSoo Line RailroadNew BridgeSouth Highway 281 BridgeBrinsmade Road BridgeTwo 10-foot Diameter CMPNormania School CrossingNorth Highway 281 BridgeStraabe BridgeBridge South of Churchs FerrYEastbound Highway 2 BridgeWestbound Highway 2 BridgeChurchs Ferry Railroad BridgeOld Highway 2 BridgeLake Irvine

300310295

3L76s0310L572284702L5500s555426s0s30492

11r_0

9I7654e4w321

Structures #9 , #8, and #6 are undersized and cause water levelincreases during high flows. Structure #1 is deteriorated and

should be replaced for structural reasons. The replacement ofStructure #1 will also a1low a new control structure for Lake

Irvine to be installed. The design of the replacement structuresis based, on the size of the other structures on Lower Mauvais

Coulee and the ability of the new bridges to pass flow withoutcausing a significant water level increase.

Structure +9 currently consists of two lO-foot diameter ClfP

culverts. The culverts wiII cause a water level increase ofapproximately L.2O feet during a L979 equivalent flow in Lower

Mauvais Coulee. The culverts should be replaced by a bridge. The

bridge wiII have a 30-foot bottom width and 2:1 (2 Horizontal to I

-Lt-

Page 22: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Vertical) side slopes. The width across the underdeck of. thebridge will be approximately 65 feet, resulting in a net flow area

of approximately 432 square feet. The channel invert below thebridge will be at an elevation of 1434.0 msl and the bridge 1ow

chord elevation wiII be 1443.0 msl. The cost to install a nevr

bridge at Structure #9 is estimated to be $1401000. Table 4

contains a preliminary cost estimate to replace Structure #9.

Table 4 - Cost Estirnate to Replace Stmcture #9

MobilizationRemove CulvertsConcrete BridgeFiIlGravelTraffic ControlSeeding

1I1,9802 ,000

200I1

SubtotalContingencies (+Contract Àdministration (+Engineering (+TOTÀL

LSLSSFCYCYLSAc

$5,000.003,000. 00

45.00L.20

15.005,000.00

300.00

$ 5,0003,000

89,1002 ,4003,0005,000

300

$107,80010,73310,73310 -734

108 )108 )10t )

$140,000

Structure #8 currently consists of five 54-inch x 72-i-nch CMP'

one 48-inch x 72-inch CMP, one 60-inch diameter CMP, and one

120-inch diameter ClfP. The culverts will cause a water levelincrease of approximately 1.2 feet during a 1979 equivalent flow inLower Mauvais Cou1ee. The culverts should be replaced by a bridge.The bridge will- have a 30-foot bottom width and 2¿I side slopes.The width across the underdeck of the bridge will be approximately70 feet, resulting in a net flow area of approximately 500 sguare

-18-

Page 23: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

feet. The channel invert below the bridge will be at an elevationof L434.5 msl and the bridge low chord elevation will be 1444.5

ms1. The cost to install a new bridge at Structure #8 is estimated

to be $1481000. Table 5 contains a preliminary cost estimate toreplace Structure #8.

TaI¡Ie 5 - Cost Estimate to Replace Structure #8

MobilizationRemove CulvertsConcrete BridgeFilIGravelTraffic ControlSeeding

11

2,L002 t200

1001I

LSLSSFCYCYLSÀc

s5,000.00 $5,000.00

4s.00r.20

15. 005,000.00

300.00

,000,000,500,640,500,000300

$ 113 ,94011,35311,35311-354

55

942I5

SubtotalContingencies (+Contract Administration (+Engineering (+TOTAL

'/-10810t10t

)))

$148,000

Structure #6 currently consists of a 26-fooE long bridge.I{ith the existing Structures #8 and #9 in place, Structure #6 wiIIbe overtopped d.uring a L979 equivalent flow in Lower Mauvais

Coulee. If Structures #8 and #9 are replaced, Structure #6 willcause a water level increase of approximately 0-25 feet during a

IgTg equivalent flow. Structure #6 should be repJ-aced by a ne\Ù

bridge. The new bridge will have a 3O-foot bottom width and 2zL

side slopes. The width across the underdeck of the bridge will be

approximately 72 feet, resuJ-ting in a net flow area ofapproximately 536 square feet. The channel invert below the bridge

-l_9-

Page 24: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

will be at an elevation of 1435.0 msl and the bridge low chord

elevation will be 1445.5 ms1. The cost to install a new bridge atStructure #6 is estimated to be $153r000. Table 6 contains a

preliminary cost estimate to replace Structure #6.

Table 6 - Cost Esti¡rate to Replace Structure #6

lvlobilizationRemove Existing BridgeConcrete BridgeFiTIGravelTraffic ControlSeeding

1I2,L601r500

22011

LSLSSFCYCYLSÀc

$5,000.005,000.00

4s.001.20

15.005,000 . 00

300.00

10t )10t )

$ 5,0005r000

97 ,2001r8003,3005r000

?00

s117,60011,80011,80011.800

SubtotalContingencies (+Contract Administration (+Engineering (+TOTÀL $153,000

Structure #1 cunently consists of an eight barrel timber box

culvert with sluice gates (approximately S-foot x S-foot) ' a

2g-foot long bridge, and a 20.5-foot x 13.O-foot structural platearch pipe. Structure #1 is large enough to pass flow withoutcausing a significant water leve1 increase; however, the conditionof the 2Q-foot long bridge is deteriorated and the sluice gates on

the timber box culverts are inoperable. In addition, the sluicegates on the control structure and the earthen weir that controlLake lrvine at an elevation of L44L.6 msl, which the State Engineer

has determined to be the normal elevation of Lake lrvine, lúere

removed during the 1993 flood.

-20-

Page 25: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

The existing Structure #1 should be replaced by a new bridgeand controÌ structure. The new bridge will have a 4O-foot bottom

width and 2:1 side slopes. The width across the underdeck of thebridge wil-I be approximately 70 feet, resulting in a net flow area

of approximately 547 square feet. The channel invert below thebridge will be at an elevation of L437.6 msl and the bridge low

chord elevation will be L447.0 ms1. fn conjunction with the bridgereplacement, the road south of Lake Irvine should be raised toelevation 1448.0 msl to prevent overtopping during a L979

equivalent flow. This will involve raising approximately 5r500

feet of road.

À new control structure will be incorporated into Structure #1

directly upstream from the bridge. The control sÈructure will be

a 7o-foot wide concrete weir. The crest of the weir will be set atelevation L44I.6 msI. The weir will be located approximately 10

feet upstream of the bridge and wiII tie into the wingwalls. Three

6-fooÈ wide stop log bays will be incorporated into the weir t'o

allow the drawdown of Lake lrvine to elevation L437.6 msl. The

proposed drawdown structure r.¡i1l allow Lake Irvine to be drawn down

to elevation L439.0 msl- in approximately 142 days. Three stop 1og

bays \ilere installed since the capacity of the three bays is near

the capacity of Lower Mauvais Coulee for both existing conditionsand conditions involving the channel- improvements evaluated inÀIternative Three.

-2L-

Page 26: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

The cost to install a new bridge and control structure atStructure #1 is estimated to be $265r000. Table 7 contains a

prelirninary cost estimate to replace Structure #1. Figure 3 shows

an isometric view of the proposed Structure #1.

Tab1e 7 - Cost Estimate to Replace Structure #1

MobilizationRemove Existing StructuresBridge Replacement(a) ConcreÈe Bridge

(b) FiIl(c) Gravel(d) Rock Riprap(e) Filter Material

Control Structure(a) Excavation(b) Concrete(c) Reinforcing Steel(d) Sheet Piling(e) Rock R5-prap(f) Filter Material(g) Misc. Materials

Traffic ControlSeeding

11

LSLS

SFCYCYCYCY

$5,000.008,000 . o0

45.00L.20

15.0025 .0015.002.50

300.000.50

25.0025.0015.00

2,000.005r000.00

300 .00

$ 5,0008,000

94,50018,0003o,000

3 t]-25675

L,25015,6003r640

13,2501,500

3002,0005,0001,900

$203,64020 | 45320 | 453)o _4q4

2,10015,0002,000

]-2545

s0052

7 ,280s30

6020I

16

CYCYLbs.LFCYCYLSLSÀc.

SubtotalContingenciesContract ÀdministrationEngineeringTOTÀL

(+/- 10t)(+/- 108)(+/- 10?)s265,000

the total cost to perform the structural improvements

evaluated in Alternative Two is estimated to be $706r000. Fundingof approximately S500r000 is currently available from the Office ofIntergovernmental Àssistance through the Federal Flood DisasterÀssistance Program for the bridge and control structureinstallation. The North Dakota Department of Transportation has

-22-

Page 27: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

ì!'i.ì:J!çì!'i.ì:J!ç

Figure 3 - fsometricView of Structure #1

Page 28: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

agreed to fund 80 percent of the cost to replace Structure #6,

contingent on Structures #8 and #9 being replaced at the same time.

ÀIternative Two wil-I increase the capacity of Lower Mauvais

Coulee, particularly during high flows. Figure 4 shows acomparison of the viater surface profiles of Lower Mauvais Coulee

for ÀIternative One and ÀIternative Two for a I979 equivalent flow.It should be noted that the effectiveness of the structurereplacernent will be reduced if the vegetation is not reduced in thechannel as recofltmended. in Àlternative One. Tab1e I shows a ratingcurve for Àlternative Two.

Table I - Rating Curse for ÀIternative Two

744L.6L442.01443.0L444.01445.0L446.0

0.047 .0

234 .0383.0s88.0848.0

Removing the stop logs from the control structure on Lake

Irvine will allow the lake to be drawn down and will also increasethe capacity of the coulee during low flows. Tab1e 9 shows a

rating curve for Alternative Two with the stop logs removed from

the control structure.

-24-

Page 29: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Figure 4 - Water Surface Profiles ofLower Mauvais Coul-ee fot L979 Equivalent Ffow

LOWER MAUVAIS COULEESìYC ProJcct l:101,+

WATER SURFACE PROFILEFOR 1979 EQUIVELENT FLOW

-199J

SWC SUR\€Y 0A'IA...... '. wsEL oPltoN 1. -.. WSEL OPTON 2

ÉFØ:õFU

E!+ntsØ

IA trØts

@

U

lH.,--

t -J-

I 448

1444

1 440

1 4f,6

1432

1 428

1424

1420

zotr5U

E

1440

1 4J6

14J2

1428

1424

1420

INJL¡

I

640+00 720+OO 800+00 880+O0 960+00 1040+00 I 1 20+00560+O0

orsrANcE (ít)

zotrU)U

E

1440

1 4J6

1432

1428

1424

1420

I 416

1412

1 408

I 404

'1400

tsø

;)----

1440

1 436

1432

14?A

1424

1420

141ô

1412

LEDOENO

0+00 80+00 160+00 240+00DTSTANCE (rt)

J20+00 400+o0 480+00

Page 30: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Table 9 - Rating Curve for ÀIternative Two withStop Logs Removed from Control Structure

L437.61438.01439.01440.01441.0L442.01443.0L444.0L445.01446.0

0.03.0

11.02L.068.0

134 .0246.0391.0597.08s9 .0

Àlternatiwe Three:This alternative involves reducing the amount of vegetation in

the channel of Lower Mauvais Cou1ee and maintaining a pilot path

through the high cattail areas below Pelican Laker ês recommended

in Àlternative One; installing' nel'r bridges at Structures #9, #8'

and #6, an¿ installing a nevr bridge and control structure atStructure #L, as recommended in ÀIternative Two; and excavating a

6g-foot wide channel with 3:1 side slopes from Structure #4 to theconfluence with Little Coulee.

Figure 5 shows a channel bottom profile of Lower Mauvais

Coulee for existing conditions. Performing the proposed channel

improvements wiLt remove several high spots from the channel and

increase the capacity of Lower Mauvais Coulee.

The proposed. improvements to Lower Mauvais Cou1ee will extend

from Structure #4 (the Highway 2 Bridge) downstream to the

-26-

Page 31: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Figure 5 - ChanneL Profile ofLower Mauvais Coul-ee for Existing Conditions

LOWER MAUVAIS COULEE

gÍC Prol.ct #: l6t¿PROI'II,E

-logJ

sìlc stRlEY 0AT

Æ_J_\4-¡-

.-------E-

o o+nN +*h 6

1 440

1 4J6

1 440

1 4J6

1432

1428

1424

1420

zotr3ul

lt+sz1428

1424

1420

IN-)\)I

560+00 640+00 720+OO 800+00 880+00 960+00 1 040+00 1 1 20+00

DrsrANcE (ít)

zoFUJU

E

1440

1 4J6

14J2

1+28

1424

1420

1 416

1412

1 408

I 40+

1 400

1440

1 4J6

1432

1428

1424

1420

1416

14',12

LEOCEND

ì'--Ã-ll)-

0+00 80+00 1 60+00 240+00DrsrANcE (ít)

J20+00 400+00 480+00

Page 32: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

confluence vrith Litt1e Coulee. This reach of coulee \úas selecteddue to its flat sIope. The channel slope bel-ow the confluence withLittte Coulee increases, resulting in a higher channel capacity.The channel slope upstream of Structure #4 is currently at themaximum achievable slope, timited by the invert elevations ofStructures #3 a¡d #2. The sJ-ope of the improved channeL will tiein to the invert elevations of the existing structures and proposed

new structures. Figure 6 shovrs a channel bottom profile of Lower

Ivlauvais Coulee after the improvements in Alternative Three are

implemented. Table 10 shows a rating curve for Alternative Three.

Table 10 - Rating Curse for ÀIternative Three

L44L.6L442.01443.01444.01445.01446.0

0.047 .O

297 .0s06.07L4.0984.0

Table 11 contains a rating curve for Alternative Three withthe stop logs removed from the Lake lrvine control structure.

-28-

Page 33: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Figure 6 - Channel Profile of LowerMauvais Coulee for Alternative Three

LOWER MAUVAIS COULEE

src ProlooL #: 1614

PROt'll,E

-19eJ

S$C SJRIEY----cHAt¡NE-

rO o+nN*+ @

zoE^<q>E5"U

1 440

1 456

1432

1428

1424

1420

1440

1 4J6

14J2

1428

142+

1420

IN)\0

I

720+OO 800+00 880+00 960+00 1040+00 1 1 20+00560+00 640+00

DrsrANcE (ft)

zotrUJU

ñE

'1440

r 456

1+32

1428

1424

1420

1 416

1412

1 408

1404

I 400

- -r{É

---- _-.\l- 1_U

E-úl-

1440

1 4J6

1432

1424

1424

1420

141 6

1412

LEDGEND

-JNUtszzzu-><þJoðl-Éfr o_

Ø

-lT--l

fo tnt-z.UIoÉ.L

)UzzIo

_l -\¡4-

-L=-trt

==-¡¡¡:,-Ê-F------ç- þ)-& "1 d------EË

Éf

-L

---------------.E---------:- d---TI-¿

-=---¡L-- --È-È-----_{JÈ-_t)--{

tsFt

--------E-¡u-O

0+00 80+00 '160+00 240+00DTSTANCE (ft)

J20+00 400+00 480+00

Page 34: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Table 11 - Rating Cu:r¡e for ÀIternative Three withStop Logs Removed Fron Control Structure

MobilizationExcavationSeeding

1272 t000

85

0.03.0

L2.031.099.0

2L2.0345.0519.0725.0999.0

$10,000.002.50

300.00$ 10,000

580 r 00025 - 500

$715,50071r50071r50071 -500

$930,000

L437.61438.01439.01440.01441.0L442.01443.01444.0144s.01446.0

The cost to perform the channel improvements eval-uated inÀlternative Three is estimated to be $930r000. Table 1,2 containsa preliminary cost estimate for the Alternative Three channelimprovements.

Table L2 - Cost EstÍmate for AlternativeThree Channel fmprovements

Ttem Ouantitrr Ilnit Tlnit Price TotalLSCYAc.

SubtotalContingencies (+Contract Àdministration (+Engineering (+TOTÀL

10t )10t )108)

-30-

Page 35: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

V. PER¡{IT REQUIREI{ENTS

No permits should be required for Àlternative One, although,if the vegetation is removed from the channel through mechanicalmeans and sediment is removed aJ-ong with it, a Section 404 Permitmay be required from the U.S. Army Corps of Engineers. Once thevegetation is removed from the channel, it should be removed fromthe wetland and deposited so that it cannot reenter the waterway.If the vegetation is controlled through the use of chemicals, theNorth Dakota State Health Department must be notified prior to theapplication of the chemicals.

The bridge replacements evaluated in ÀIternative Two willrequire a Section 404 Permit from the U.S. Àrmy Corps of Engineers.The instal-Iation of the control structure on Lake Irvine inconjunction with the replacement of Structure #1 will also requirea Section 404 Permit. The installation of the control structurewilL also reguire a dam permit and a sovereign lands permit, bothissued by the State Engineer. Àn operating plan for the drawdown

structure must be included with the state permit applications.

The channel irnprovements evaluated in Àlternative Three willrequire a Section 404 Permit from the U.S. Àrmy Corps of Engineers.State permits nay also be required from the State Engineertdepending upon the scope of the channel improvements that arepursued.

-3 1-

Page 36: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

VI. SU}IUÀRY

Lower Mauvais Coulee is located in the Devils Lake Basin inwestern Ramsey and eastern Benson Counties. It originates at Lake

Irvine, located near the city of Churchs Ferry, and flows southeast

to the TÍest Bay of Devils Lake. The purpose of this study was toidentify areas of restriction along Lower Mauvais Coulee and topropose corrective measures that will reduce flooding, both along

the coulee and in the chain of lakes.

Other recent studies of the Devils Lake Basin relative toLower Mauvais Coulee include a December 1980, study titled Lower

Mauvais Coulee Tlater Surface Profile Study, and a September 1991,

study titled Chain Lakes Improvement. Both of these studies \rere

completed by the North Dakota state I,Iater commission.

This study evaluated the effects of poËential road crossingand channel improvements on Lower Mauvais Coulee. These

i-mprovements were evaluated for a range of flows using the HEC-2

computer model, developed by the U.S. Àrmy Corps of Engineers. The

computer model was used to develop rating curves for the outlet toLake frvine and these rating curves were used to evaluate theeffectiveness of the various improvements. Figure 7 shows agraphical comparison of the rating curves for the 1993 floodconditions (existing) and for the three alternatives that were

evaluated. Figure 8 shows a graphical comparison of the ratingcurves for the 1993 fl-ood conditions (existing), for ÀIternative

-32-

Page 37: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

LAKE IRVI]VE RATI]VG CUR,VES

î t 44s.oo

1447 .OO

1 446.OO

1444.OO

1 443.OO

EXISTING

400.00 600.00DIScHARGE (cfs)

Figure 7 - GraphicalComparison of Lake Irvine Rating Curves

ALT. 1 ALT. 2 ALT. 5

It,(,I

E

z.oF

|JJJL¡l

1442.OO

1 441 .000.00 200.00 800.00 1000.00

Page 38: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

LAKE IRVI]VE R,ATIIVG CUR,VESFOR DRAWDOWIV CAPABILITIE S

I(,ÞI

1448.00

1446.00

1 t 444.oo

1438.00

1 436.00

E

z.o=UJ_llJI

1442.OO

1440.00

EXISTING

400.00

ALT. 2 ALT. 3

Figure I - GraPhical ComParison ofLake Irvine Rating curves for Drawdown Capabilities

600.000.00 200.00DISCHARGE (cfs)

900.00 1000.00

Page 39: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Two with the stop logs removed from the control structure, and forÀIternative Three with the stop logs removed from the controlstructure.

The improvements that s¡ere evaluated are summarized in threealternatives. Alternative One involves reducing the amount ofvegetation in the channel of Lower Mauvais Coulee and maintaininga pilot path through the high cattail areas below Pelican Lake.

The most effective vray of reducing the vegetation in the channel isthrough the development of a regular maintenance program. This can

be done through mowing when the channel is dry or through the use

of chemical-s during wet years. The annual cost to control thevegetation in Lower lvlauvais Cou1ee is estimated to be $10r000 peryear.

Alternative Two involves reducing the amount of vegetation inthe channel of Lower Mauvais Coulee and maintaining a pilot path

through the high cattail areas below Pelícan Lake¡ âs recommended

in Alternative One. It also involves installing ne\t bridges atStructures #9, #8, and #6, and installing a newbridge and controlstructure at Structure #f. The nell bridge at Structure #9 willhave a net flow area of approximately 432 square feet and isestimated to cost $1401000. The new bridge at Structure #8 willhave a net flow area of approximately 500 square feet and isestimated to cost $148,000. The new bridge at Structure #6 willhave a net flow area of approximately 536 square feet and is

-35-

Page 40: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

estimated to cost $l-53r000. The new bridge at Structure #1 willhave a net flow area of approximately 547 square feet. The controlstructure consists of a 7O-foot wide weir located directly upstream

from the bridge. The control structure will control Lake Irvine atan elevation of L44L.6 msI with drawdown capabilities to elevationL437.6 msl. The cost to construct the new bridge and controlstructure at Structure #1 is estimated to be $265r000.

Àlternative Three involves reducing the amount of vegetationin the channel of Lower Mauvais Coulee and maintaining a pilot paththrough the high cattail areas below Pelican Laker âs recommended

in Àlternative One; installing nevr bridges at Structures #9, #8,

and #6, and installing a ne\ü bridge and control structure atStructure #L, as reconmended in Alternative Two; and excavating a

60-foot wide channel with 3:1 side slopes from Structure #4 to theconfluence with Litt1e Coulee. The slope of the excavated channel

will tie in to the invert elevations of the existing structures and

proposed nen structures. The cost to perform these channel

improvements is estimated to be $930r000.

-36-

Page 41: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

VII. RECO}I}ÍENDÀTIONS

Several improvements to increase the capacity of Lower lvlauvais

coulee vrere analyzed during this study. ÀIternative one, which

involves reducing the amount of vegetation in the channel of Lower

Mauvais Coulee and maintaining a pitot path through the high

cattail areas below Pelican Lake, wiII provide the greatest floodreduction benefits. Therefore, it is recommended that a reg-ular

channel maintenance program be developed for Lower Mauvais Coulee.

The bridge replacements and control- structure installationevaluated in ÀIternative Two will provide flood reduction benefitsduring high flows. Funding of approximately $500r000 is currentlyavailable from the Office of Intergovernmental- Assistance through

the Fed,eral Flood Disaster Assistance Program for the bridge and

control structure installation. The North Dakota Department ofTransportation has agreed to fund 80 percent of the cost to replace

Structure #6, contingent on Structures #8 and #9 being replaced atthe s¿ìme time. Therefore, it is reconmended that new bridges be

instal-Ied at Structures #9 , #8, and #6 , and a ne\ü bridge and

control structure be installed at Structure #1'

The channel improvements evaluated in ÀIternative Three willalso provide flood red.uction benefits along Lower Mauvais Coulee

and. in the Chain Lakes. The cost to perform these improvements ishigh and it may be difficult to obtain the permits necessary toperform the channel improvements. The decision to proceed with any

-37-

Page 42: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

of these improvements is the responsibility of the Devils Lake

Basin Joint l{ater Resource Board.

- 38-

Page 43: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

ÀPPENDIX À - COPY OF ÀGREEI{EIüT

Page 44: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

swcMay

t6 tIProjsst 4!'fff.13, 1993

ÀGREEI.IENTInvestigation

oftower l{auvais Cou1ee Improvements

I. PÀRTIES

ÏHIS ÀGREEMENT is between the North Dakota State WaterCommission, here-i-nafter Conrm-ission, through its Secretary, David À.

Sprynczynatyk; and the DeviÌs Lake Basin Join-' I{ater Management

Board, hereinafter Joint Board, through its Chair, Benhart À.

Varnson.

rI.,. PRoJECT, PIJR*DOSE, ÀND LOCÀÎION

The Joint Board has reques-"ed the Commission to conduct a

hydraulic study of the Lower l{auvais Cou1ee from Lake frvine to theWest Bay of Devil-s Lake. The study will identify areas ofrestriction along the Coulee, and propose corrective measures toreduce flooding, both along the coul-ee and in the chain of Lakes

area.

IIT. PRELII'ÍINÀRY INYESTIGÀTION

Th; parties agree that further informa-,-ion is necessaryconcerning the proposed project. The study wilL primariJ-y updateinformation in the 1980 Lower Mauvais Coulee investigation.Therefore, the Commission wiII:

-1-

Page 45: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

1

2

3

4

5

6

Conduct a f ield surrey of the pro ject area,including: cross sections of the coulee.-Modify and update existing hydraulic studies of theLower Mauvais Coulee.Recommend potential roadimprovements. crossing and channel

Test the effects of the proposed improvements usingthe hydrauJ-ic model_.

EstimaLe the effects of the proposed improvementson the chain of Lakes using iñformatiðn derivedfrom the 1991 Chain Lakes Improvemen-u Study.Prepare preliminary cost estimates for the wariousalternatives; and

Prepare a r+ritten reportof the investigation. documenting the findings7

The Joint Board shaLl_

Commission to heJ-p def rayinvestigation.

vr. cosrsdeposit a total of 52r900 with the

the field costs associated with this

V. RIGHTS-OF-ENIRY

The Joint Board agrees to obtain written permission from anyaffected landowners for fieLd investigations by the Commission,which are required for the preliminary investigation.

VI. TNDEUNTFTCÀTION

The Joint Board agrees to indemnify and hotd harmless thestate of North Dakota, the commission, and any empl-oyees or agentsof those entities, from all claims for damages to property, rightsor Persons, as a result of any act or omission by the Joint Board..

-2-

Page 46: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

its agents, contractorsr or employees. fn the event a suit isinitiated or judgment entered against the State of North Dakota,the Commission, or any of their employees or agents, the JointBoard shall indemnify them for all costs and expenses, includinglegaI fees, and any judgment arrived at or satisfied or settlemententered, to the extent that such cost and expenses are caused by orresulting from any act or omission by the Joint Board, its agents,contractors or employees.

VII. I'ÍERGER CI,AUSE ,This agreement constitutes the entire ag,reement between the

parties. No waiver, consent, ¡nodification nor change of terms ofthis agreement shall bind either party unless in writing, signed by

the parties, and attached hereto. Such waiver, consent,modification or change, if made, shal-l be effective only in thespecific instance and for the specific purpose given. There are no

understandings, ag'reementsr or representations, oral or writtentnot specified herein regarding this agreement.

NORTH DÀXOTÀ ST.â.TE WÀTERcot'fltrssroN

DÀVID À.SecretaWITNESS:

-\

DEVILS I,ÀKE BÀSTN JOINT WÀTERUÀNÀGE}I.ENT BOÀRDBy

BENHÀRÎ À VÀRNSONChairI{ITNESS:

I

7DÀTE

a/tç/q 3

-3-

DÀTE:

ê -z-7J

Page 47: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

ÀPPENDIX B - RECO}ITENDÀTIONS OF 1980 LOWER }IÀUVÀISCOI'LEE IIATER SIIRTÀCE PROFILE STTIDY

Page 48: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

RecomÍrendations from 1980 Lower llauvais Coulee Study

1. Replace the culverts with a bridge on theNoimania School Road (Structure #8)

1À. Install a lO-foot diameter culvert fromChannel À at' the Normania School RoadCrossing (Structure #8)

2. Snag and clear 3 miles of coulee betweenStructure #7 and the confluence withLittle Coulee

3. Devetop a pilot path bel-ow Pelican Lake '

Phase One ImBrovements:ftem

Phase Two ImProvements:

1. Perform Phase One imProvements

2

5A.

58.

7

1980 Cost

s149,000

12 r 500

12,00012,300

$173,000155,00010,000

151,00010,000

22L,00010,000

51,000230 r 000

114,000

182,000182,000

12 r 000

182,000

3

4

5

Replace Structure +6Removal only of Structure #6

Replace Structure #9Removat onlY of Structure #9

Replace Structure #14neiroval onIY of Structure +L4

Install a 7S-foot wide control structureat Lake lrvineReplace Structure #1 and raise the road

Remove structure #L, install a control structure,and raise the road as a dikeRaise the dikes between Lake lrvineand Highway 2

Replace the old Highway-2- bridge (Structure #2)Reirove the old Higñway- 2 bridge (Structure +2)

Replace Structure #10 (Low Priority)

6

8.

Page 49: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

Phase Ttro InProvements (Cont- )

g. Widen the channeL between Structure #11and Pelican Lake

10. Remove the culverts and install a bridgeon tlre Minnevraukan Flats Road (Low Prio-rity)

11. Raise Highway 19 and raise Structure #l-5(Low PrioritY)

L2. Raise llighway 19 and replace Struct'ure #15(Low PrioritY)

13. Remove Structure #16

s 50,000

182,000

208,000

325, 0oo

6r500

Page 50: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

.APPENDIX C - SYIIBOLS ÀI{D ÀBBREVIÀTIONS

Page 51: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

SYI{BOI,S À}ID ÀBBR-EVIATIOI{S

Cl4P - Corrugated Metal PiPe

msl - mean sea leve1cfs - cubic feet per second

USGS - United States Geological Survey

HEC - The HydroloEic Engineering CenterDWOPER - Dlrnanic Tlave Operational Mode1

LS - Lump Sum

Àc. - AcresSF - Sguare FeetCY - Cubic YardsSI{C - State lÍater Commission

Page 52: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

L.

2,

3.

4

BIBTIOGRÀPHY

U.S. Àrmy Corps of Engineers, HEC-2 Water Surface Profiles'September L982.

North Dakota State l{ater Commission, Lower Mauvais CouleeWater Surface Prof ile Study, Decer.nber 1980 'North Dakota State Þlat"er Cornmission, ChaÍn I-,akes ImProvementtSeptember 1991.

O}son-Kaufman, fnc., Hydraulic Analysis and Structure'Sel-ectíon - Bridge No. 102.18.1.

Page 53: LOWER MAUUAIS COULEE IMPROVEMET,{TS · 2015-12-03 · T2 L4 L7 18 19 20 22 24 I 1 3 Hydrolog-y Hydrolog-y Hydrology IIT. HTDRÀI]LICS. IV. ÀI,TERI{ÀTI\rES. ÀIternative ÀIternative

2t

l6

30(ru

qftrn

ó

LrN( -,1\--*

u

¡o

Þ

¡2irr. l-'I

COULEE

29

Il{¡

ItMAOE

It

2t

t-- ¡ !'o--' t

t6

. LAIGa.c

2t

(

,,\L'-'ì.

a

\!

]J

zlirl

f,

A

. 16\¡rHuÉ

"]

_5jL+

Structure #7AtufrtE

l5

, Structure #8

StrucÈure #9iJ

l1

L

ù-

Strrrcture #10t¡

-_ a

¡ta

ll

t.o

.l

SILVERLAKE¡r.

NATIONALWILDLIFEREFUGE

IINAI.IoNALll g

rlil

tlllrl

5

I---l t-I LAc ^ux

zuo

oture #11

MORTE

EFVGWILDL

l?

-t-4 -t-r_

n

ll

t,

lu':ot ¡J

t-

--t-

=ll,l

-- -'i;:'-1.

t______t.ld,vIsr r]^Y

END STT'DY

I

?t

JO

illl

I

ta IJ

,\=

22

Structure #13 /7< 4o*,,>

(

Structure #1 r)

POR ¡10ô

20

t(I\-\\

I,I

I

I

I

(

INN

I ILULN

I

I

I_T_l-r-_r.l_._t_-_ 6 -

JI

tôr'ril

(

Ii ,

ovER- '' ¡

I

lr

Èr0Iat5qt

!ì¿

.tr¡6

Jl' .

Structure #2s

BEGIN STI'DY

2J

;,l^ll^il

FEN RY

J

!I

0

^sH

JI

I r^" rõl

,qo

fIAMSEY

vl_ ____L- -;-rr

rl¡? ll

J6

o

t

rt'l r

ltllil

I l-

tr-. "'ll

-l -5

l)

GROAT:.. l6

o

(r20

lo

ll ì2

2l :è:1

^t il<F5

iL 28

l.l

l2

2,' ?8ttil

llrltl

.,1

,l

IE

li

E

{J

a

Lt:l

l2

ïi al¡il

ItL

1_i tó

ÞOr P'

'amÉrrBBOþO t\)crÉlBo(/.l

atFÉoo,o<ÊJrtÞP. F.Ioo5Pra

IÈI

ãt3lrl 1.O

JO o

frÂ-Fnì

t,

____-J

29

ll

tWAUKAN;EMENT AREA

f:'(f

;lII

tl

il----l-I t_t | 6l I

)'\

IStructure #76 .'.'!

ll .\ûì

IIÞll-f-

OEVlLS

LAKEF

_l_l"

¡t

[.1

BENSON