    LONG TERM PLANNING

  • 8/13/2019 LONG TERM PLANNING.ppt

    2/16

    LONG TERM PLANNING

    Coordinate long term maintenance planning activity at theplant like unit overhaul planning

    Ensure cost efficiency and bring about cost reduction inthe plant through spare parts cost reduction, inventorycontrol and planning

    Ensure adherence to safety, environment and regulatorynorms

    Benchmark with other projects to find areas forimprovement

    Ensure timely availability of materials, tools and tackles foroverhauling and breakdowns

    Coordination meeting with all maintenance department forjob and material planning on daily basis for overhauling

    Condition monitoring of plant equipment and maintaining

    records thereof

  • 8/13/2019 LONG TERM PLANNING.ppt

    3/16

    LONG TERM PLANNING

    Prepare annual and 5 year rolling plan of overhaulsand pre overhauling preparations for material andcontracts

    Monitoring of job progress and preparation of MIS onmajor equipment history, performance and failureanalysis

    Financial Budgeting for O&M departments includingannual plans for contract jobs and material

    -- Spare parts development

    Record of documentation including drawings of theparts to be developed

    Renewal of all statutory licenses,boiler, explosivesetc.

    Condition monitoring of plant equipment and

    maintaining records thereof

  • 8/13/2019 LONG TERM PLANNING.ppt

    4/16

    ANNUAL O/H SCHEDULE

    NTPC Ltd

    Badarpur Thermal Power Station

    AS ON

    14.10.2011

    Proposed BTPS STATIONS MAINTENANCE PROGRAM-2012-13

    STATIONLICENSE

    VALIDITY UNIT PLAN

    NO. OF DAYS

    REMARKS

    BTPS

    15-Sep-12 #-1 1-Aug-12 20-Aug-12 20 BoilerMaintenance

    15-Apr-12 #-2 22-Aug-12 10-Sep-12 20 BoilerMaintenance

    21-Jul-12 #-3 1-Apr-12 20-Apr-12 20 BoilerMaintenance+Con

    denser tubes(4762

    nos)

    20-Aug-11 #-4 1-Oct-11 9-Nov-11 40 BoilerMaintenance+ ESP

    R&M jobs*

    17-Mar-11 #-5 11-Mar-13 19-Apr-13 40 BoilerMaintenance+ ESP

    R&M jobs*+Boiler

    panel Jobs

    *Schdule depends upon-ESP R&M Package ,#4 S/D depends upon Agra canal closure

  • 8/13/2019 LONG TERM PLANNING.ppt

    5/16

    8 YEAR ROLL PLAN

    DOC NO: QSR-008/F-08

    TENTATIVE EIGHT YEAR ROLLING PLAN FROM 2011-2012 TO 2018--2019 DATED- 4.7.2011 REV:00

    UNIT NO Boiler

    license

    date

    Ist Sync

    Date

    Details of Last O/H 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

    Last Capital

    O/H Start

    Date, End

    Date ,

    Durartion

    Last O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    Planned O/H

    Start Date,

    End Date,

    Duration

    1

    6.6.2011 26.07.1973

    30.07.200

    9

    25.05.201

    0 1-Sep-11 1-Sep-12 1-Sep-13 1-Sep-14 1-Sep-15 1-Sep-16 1-Sep-17 1-Sep-18

    14.09.200

    9

    11.06.201

    0 20-Sep-11 20-Sep-12 20-Sep-13 15-Oct-14 20-Sep-15 20-Sep-16 20-Sep-17 20-Sep-18

    47 Days 18 Days 20 Days 20 Days 20 Days 45 Days 20 Days 20 Days 20 Days 20 Days

    2

    14.4.2012 05.08.1974

    22.10.200

    9 3.4.2011 1-Apr-11 1-Apr-12 1-Apr-13 1-Apr-14 1-Apr-15 1-Apr-16 1-Apr-17 1-Apr-18

    28.12.200

    9 20.4.2011 20-Apr-11 20-Apr-12 20-Apr-13 14-May-14 20-Apr-15 20-Apr-16 20-Apr-17 20-Apr-18

    67 Days 18 Days 20 Days 20 Days 20 Days 45 Days 20 Days 20 Days 20 Days 20 Days

    3

    20.5.2011 29.03.1975

    07.09.200

    8

    30.04.201

    0 22-Sep-11 22-Sep-12 22-Sep-13 17-Oct-14 22-Sep-15 22-Sep-16 22-Sep-17 22-Sep-18

    26.10.200

    8

    26.05.201

    0 11-Oct-11 11-Oct-12 5-Nov-13 5-Nov-14 11-Oct-15 11-Oct-16 11-Oct-17 5-Nov-18

    50 Days 27 Days 20 Days 20 Days 45 Days* 20 Days 20 Days 20 Days 20 Days 45 Days

    4

  • 8/13/2019 LONG TERM PLANNING.ppt

    6/16

    LONG TERM PLANNING-

    PRACTICAL ENGINEERING DECLARATION

    PREPARATION

    OPI(Overhaul preparedness index)PREPATION AND MONITORING

    MATERIAL/CONTRACTS -REQUIREMENT-STATUS

    EXPEDITING OF MATERIAL/CONTRACTS.

    PERMITS PLANNING IN PTW SYSTEM PLANNING&SCHDUKING OF ACTIVITIES

    AND MONITORING OF SCHDULE.

    O/H REPORT PREPARATION

  • 8/13/2019 LONG TERM PLANNING.ppt

    7/16

    ENGINEERING DECLARATION

    Freezing of jobs to be done in O/H

    BTL-ROOT cause analysis

    recommendation

    Any recommendation of concerned

    divisions

    Before S/D Efficiency Cost of o/h

    After S/D EfficiencyPay Back Period of

    COST of O/H--Justification

  • 8/13/2019 LONG TERM PLANNING.ppt

    8/16

    OPI MONITORING

    Unit: 1: O/H Date:01.03.2011, O/H Type:AOH, FY of O/H: 2011-12

    S.N Activity/Description

    Max Months Before OH OPI-11Remarks

    Marks 24 18 12 6 Score

    1

    Formation of Outage Committee

    20 20

    202 Engineering Declaration

    Submission in required format

    (Revision No: --) Overhaul Date

    (Proposed)

    30 R0

    20

    R1

    5

    R2

    5

    303 Outage period & duration:

    Justification of outage duration &

    time period

    30 20

    5

    5

    304 Identification of Equipments &

    Scope of Work for Overhaul.

    Standard Scope of Work

    Boiler & Aux. Steam Turbine & Aux.

    Turbo Generator & Electrical

    100

  • 8/13/2019 LONG TERM PLANNING.ppt

    9/16

    OPI

    Unit: 3: O/H Date:08.08.2011, O/H Type:AOH,

    FY of O/H: 2011-12

    OPI(-04)

    Sno Activity U/M Total Qnty

    Expected/

    Due for O/H

    Cumulative

    Target for this

    OPI

    Cumulative

    Achieved

    Shortfall, if

    any

    MAX. MARKS ACTUAL

    SCORE

    ACTUAL SCORE Cum

    Sparesprocureme

    nt

    1 CRITICAL

    SPARES

    1.1Total No of

    Spares

    identified

    No of Items 4 4 4 0

    15.0 15.0 15.0

    1.2 Purchase

    Indents

    Raised

    No of Items 4 4 4 0

    30.0 30.0 30.01.3 Purchase

    Enquiry

    Issued

    No of Items 4 4 3 1

    30.0 22.5 22.5

    1.4 Purchase

    Order

    Placed

    No of Items 4 4 3 1

    75.0 56.3 56.3

    1.5 Items recd

    against PO

    No of Items 4 4 0 4

    150.0 0.0 0.0

    Total 1.0

    300 124 123.8

  • 8/13/2019 LONG TERM PLANNING.ppt

    10/16

    ANNUAL BUDGET

    PREPARTION

    Presently Budget preparation is through

    ABB(Activity Based Budgeting)

    Activities to be defined and material and

    services requirement to be projected

    Required Activities has to be plannedaccordingly budget will be allocated after

    review.

  • 8/13/2019 LONG TERM PLANNING.ppt

    11/16THANKYOU

  • 8/13/2019 LONG TERM PLANNING.ppt

    12/16

  • 8/13/2019 LONG TERM PLANNING.ppt

    13/16

    LONG TERM PLANNING-REQ

    Functional competence requirement Knowledge of NTPCs Maintenance Management System and modern

    maintenance management practices

    Knowledge of operation and maintenance systems

    Knowledge of environment and safety requirements and statutoryguidelines

    Awareness of suppliers of materials and services

    Planning and organizing capability Computer proficiency to help in the planning work

    Knowledge of statutory licenses.

    Knowledge of project management

    Awareness of shut down jobs. Record keeping from the last overhauling / documentation

    Cross functional competence requirement

    Awareness of Contracts and Materials

    Knowledge of Finance, HR and IT

  • 8/13/2019 LONG TERM PLANNING.ppt

    14/16

    HEAD MTP

    Formulating plant maintenance policy and strategy to serve corporateobjectives

    Coordinate maintenance planning activity at the plant

    Ensure cost efficiency and bring about cost reduction in the plant

    through spare parts cost reduction, inventory control and planningEnsure adherence to safety, environment, energy conservation,

    efficiency and regulatory norms

    Benchmark with other projects to find areas for improvement

    Ensure timely availability of materials, tools and tackles for overhaulingand breakdowns

    Coordination meeting with all maintenance departments for job andmaterial planning on daily basis for overhauling

    Prepare annual and 5 year rolling plan of overhauls and pre-overhauling preparations for material and contracts

  • 8/13/2019 LONG TERM PLANNING.ppt

    15/16

    HEAD MTP

    Forced shutdown planning and coordination

    Monitoring of job progress and preparation of MIS onmajor equipment history, performance and failureanalysis

    Financial budgeting for O&M departments includingannual plans for contract jobs and material

    Spare parts development

    PTW system management

    Maintain record of documentation including drawings

    of the partsto be developed Condition monitoring of plant equipment and

    maintaining records thereof

    Renewal of all statutory licenses:boiler, explosivesetc.

  • 8/13/2019 LONG TERM PLANNING.ppt

    16/16

    STP

    Coordinate short term maintenance planning activity at the plantlikebacking down, short shutdown

    Ensure adherence to safety, environment and regulatory norms

    Benchmark with other projects to find areas for improvement

    Ensure timely availability of materials, tools and tackles for Preventivemaintenance and breakdowns

    Ensure daily planning meeting for coordination with all maintenancedepartment for job and material planning

    Monitoring of job progress and preparation of MIS on major equipmenthistory, performance and failure analysis

    Planning for preventive maintenance and breakdowns as well asmonitoring

    Forced shutdown planning and coordination

    PTW system management