LONG TERM PLANNING
8/13/2019 LONG TERM PLANNING.ppt
2/16
LONG TERM PLANNING
Coordinate long term maintenance planning activity at theplant like unit overhaul planning
Ensure cost efficiency and bring about cost reduction inthe plant through spare parts cost reduction, inventorycontrol and planning
Ensure adherence to safety, environment and regulatorynorms
Benchmark with other projects to find areas forimprovement
Ensure timely availability of materials, tools and tackles foroverhauling and breakdowns
Coordination meeting with all maintenance department forjob and material planning on daily basis for overhauling
Condition monitoring of plant equipment and maintaining
records thereof
8/13/2019 LONG TERM PLANNING.ppt
3/16
LONG TERM PLANNING
Prepare annual and 5 year rolling plan of overhaulsand pre overhauling preparations for material andcontracts
Monitoring of job progress and preparation of MIS onmajor equipment history, performance and failureanalysis
Financial Budgeting for O&M departments includingannual plans for contract jobs and material
-- Spare parts development
Record of documentation including drawings of theparts to be developed
Renewal of all statutory licenses,boiler, explosivesetc.
Condition monitoring of plant equipment and
maintaining records thereof
8/13/2019 LONG TERM PLANNING.ppt
4/16
ANNUAL O/H SCHEDULE
NTPC Ltd
Badarpur Thermal Power Station
AS ON
14.10.2011
Proposed BTPS STATIONS MAINTENANCE PROGRAM-2012-13
STATIONLICENSE
VALIDITY UNIT PLAN
NO. OF DAYS
REMARKS
BTPS
15-Sep-12 #-1 1-Aug-12 20-Aug-12 20 BoilerMaintenance
15-Apr-12 #-2 22-Aug-12 10-Sep-12 20 BoilerMaintenance
21-Jul-12 #-3 1-Apr-12 20-Apr-12 20 BoilerMaintenance+Con
denser tubes(4762
nos)
20-Aug-11 #-4 1-Oct-11 9-Nov-11 40 BoilerMaintenance+ ESP
R&M jobs*
17-Mar-11 #-5 11-Mar-13 19-Apr-13 40 BoilerMaintenance+ ESP
R&M jobs*+Boiler
panel Jobs
*Schdule depends upon-ESP R&M Package ,#4 S/D depends upon Agra canal closure
8/13/2019 LONG TERM PLANNING.ppt
5/16
8 YEAR ROLL PLAN
DOC NO: QSR-008/F-08
TENTATIVE EIGHT YEAR ROLLING PLAN FROM 2011-2012 TO 2018--2019 DATED- 4.7.2011 REV:00
UNIT NO Boiler
license
date
Ist Sync
Date
Details of Last O/H 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19
Last Capital
O/H Start
Date, End
Date ,
Durartion
Last O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
Planned O/H
Start Date,
End Date,
Duration
1
6.6.2011 26.07.1973
30.07.200
9
25.05.201
0 1-Sep-11 1-Sep-12 1-Sep-13 1-Sep-14 1-Sep-15 1-Sep-16 1-Sep-17 1-Sep-18
14.09.200
9
11.06.201
0 20-Sep-11 20-Sep-12 20-Sep-13 15-Oct-14 20-Sep-15 20-Sep-16 20-Sep-17 20-Sep-18
47 Days 18 Days 20 Days 20 Days 20 Days 45 Days 20 Days 20 Days 20 Days 20 Days
2
14.4.2012 05.08.1974
22.10.200
9 3.4.2011 1-Apr-11 1-Apr-12 1-Apr-13 1-Apr-14 1-Apr-15 1-Apr-16 1-Apr-17 1-Apr-18
28.12.200
9 20.4.2011 20-Apr-11 20-Apr-12 20-Apr-13 14-May-14 20-Apr-15 20-Apr-16 20-Apr-17 20-Apr-18
67 Days 18 Days 20 Days 20 Days 20 Days 45 Days 20 Days 20 Days 20 Days 20 Days
3
20.5.2011 29.03.1975
07.09.200
8
30.04.201
0 22-Sep-11 22-Sep-12 22-Sep-13 17-Oct-14 22-Sep-15 22-Sep-16 22-Sep-17 22-Sep-18
26.10.200
8
26.05.201
0 11-Oct-11 11-Oct-12 5-Nov-13 5-Nov-14 11-Oct-15 11-Oct-16 11-Oct-17 5-Nov-18
50 Days 27 Days 20 Days 20 Days 45 Days* 20 Days 20 Days 20 Days 20 Days 45 Days
4
8/13/2019 LONG TERM PLANNING.ppt
6/16
LONG TERM PLANNING-
PRACTICAL ENGINEERING DECLARATION
PREPARATION
OPI(Overhaul preparedness index)PREPATION AND MONITORING
MATERIAL/CONTRACTS -REQUIREMENT-STATUS
EXPEDITING OF MATERIAL/CONTRACTS.
PERMITS PLANNING IN PTW SYSTEM PLANNING&SCHDUKING OF ACTIVITIES
AND MONITORING OF SCHDULE.
O/H REPORT PREPARATION
8/13/2019 LONG TERM PLANNING.ppt
7/16
ENGINEERING DECLARATION
Freezing of jobs to be done in O/H
BTL-ROOT cause analysis
recommendation
Any recommendation of concerned
divisions
Before S/D Efficiency Cost of o/h
After S/D EfficiencyPay Back Period of
COST of O/H--Justification
8/13/2019 LONG TERM PLANNING.ppt
8/16
OPI MONITORING
Unit: 1: O/H Date:01.03.2011, O/H Type:AOH, FY of O/H: 2011-12
S.N Activity/Description
Max Months Before OH OPI-11Remarks
Marks 24 18 12 6 Score
1
Formation of Outage Committee
20 20
202 Engineering Declaration
Submission in required format
(Revision No: --) Overhaul Date
(Proposed)
30 R0
20
R1
5
R2
5
303 Outage period & duration:
Justification of outage duration &
time period
30 20
5
5
304 Identification of Equipments &
Scope of Work for Overhaul.
Standard Scope of Work
Boiler & Aux. Steam Turbine & Aux.
Turbo Generator & Electrical
100
8/13/2019 LONG TERM PLANNING.ppt
9/16
OPI
Unit: 3: O/H Date:08.08.2011, O/H Type:AOH,
FY of O/H: 2011-12
OPI(-04)
Sno Activity U/M Total Qnty
Expected/
Due for O/H
Cumulative
Target for this
OPI
Cumulative
Achieved
Shortfall, if
any
MAX. MARKS ACTUAL
SCORE
ACTUAL SCORE Cum
Sparesprocureme
nt
1 CRITICAL
SPARES
1.1Total No of
Spares
identified
No of Items 4 4 4 0
15.0 15.0 15.0
1.2 Purchase
Indents
Raised
No of Items 4 4 4 0
30.0 30.0 30.01.3 Purchase
Enquiry
Issued
No of Items 4 4 3 1
30.0 22.5 22.5
1.4 Purchase
Order
Placed
No of Items 4 4 3 1
75.0 56.3 56.3
1.5 Items recd
against PO
No of Items 4 4 0 4
150.0 0.0 0.0
Total 1.0
300 124 123.8
8/13/2019 LONG TERM PLANNING.ppt
10/16
ANNUAL BUDGET
PREPARTION
Presently Budget preparation is through
ABB(Activity Based Budgeting)
Activities to be defined and material and
services requirement to be projected
Required Activities has to be plannedaccordingly budget will be allocated after
review.
8/13/2019 LONG TERM PLANNING.ppt
11/16THANKYOU
8/13/2019 LONG TERM PLANNING.ppt
12/16
8/13/2019 LONG TERM PLANNING.ppt
13/16
LONG TERM PLANNING-REQ
Functional competence requirement Knowledge of NTPCs Maintenance Management System and modern
maintenance management practices
Knowledge of operation and maintenance systems
Knowledge of environment and safety requirements and statutoryguidelines
Awareness of suppliers of materials and services
Planning and organizing capability Computer proficiency to help in the planning work
Knowledge of statutory licenses.
Knowledge of project management
Awareness of shut down jobs. Record keeping from the last overhauling / documentation
Cross functional competence requirement
Awareness of Contracts and Materials
Knowledge of Finance, HR and IT
8/13/2019 LONG TERM PLANNING.ppt
14/16
HEAD MTP
Formulating plant maintenance policy and strategy to serve corporateobjectives
Coordinate maintenance planning activity at the plant
Ensure cost efficiency and bring about cost reduction in the plant
through spare parts cost reduction, inventory control and planningEnsure adherence to safety, environment, energy conservation,
efficiency and regulatory norms
Benchmark with other projects to find areas for improvement
Ensure timely availability of materials, tools and tackles for overhaulingand breakdowns
Coordination meeting with all maintenance departments for job andmaterial planning on daily basis for overhauling
Prepare annual and 5 year rolling plan of overhauls and pre-overhauling preparations for material and contracts
8/13/2019 LONG TERM PLANNING.ppt
15/16
HEAD MTP
Forced shutdown planning and coordination
Monitoring of job progress and preparation of MIS onmajor equipment history, performance and failureanalysis
Financial budgeting for O&M departments includingannual plans for contract jobs and material
Spare parts development
PTW system management
Maintain record of documentation including drawings
of the partsto be developed Condition monitoring of plant equipment and
maintaining records thereof
Renewal of all statutory licenses:boiler, explosivesetc.
8/13/2019 LONG TERM PLANNING.ppt
16/16
STP
Coordinate short term maintenance planning activity at the plantlikebacking down, short shutdown
Ensure adherence to safety, environment and regulatory norms
Benchmark with other projects to find areas for improvement
Ensure timely availability of materials, tools and tackles for Preventivemaintenance and breakdowns
Ensure daily planning meeting for coordination with all maintenancedepartment for job and material planning
Monitoring of job progress and preparation of MIS on major equipmenthistory, performance and failure analysis
Planning for preventive maintenance and breakdowns as well asmonitoring
Forced shutdown planning and coordination
PTW system management