Upload
unbeatable171
View
219
Download
0
Embed Size (px)
Citation preview
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
1/36
PROJECT COST
MANAGEMENT
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
2/36
PROJECT COST MANAGEMENT
Processes involved in planning,estimating, budgeting, financing,
funding, managing and controlling costsso that the project can be completed
within the approved budget
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
3/36
Plan Cost Management Processes that establishes the policies, procedures and
documentation for planning, managing, expending and controllingproject costs
Estimate Costs Process of developing an approximation of the monetary resources
needed to complete the project activities
Determine Budget The process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline
Control Costs The process of monitoring the status of the project to update the
project costs and managing changes to the cost baseline
PROJECT COST MANAGEMENT
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
4/36
Plan Cost Management Processes that establishes the policies, procedures and
documentation for planning, managing, expending andcontrolling project costs
Provides guidance and direction on how the project costs willbe managed throughout the project
Plan Cost Management
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
5/36
Project Management Plan
Scope Baseline project scope statement, WBS detail
Schedule Baseline defines when the project costs will beincurred
Other Information Cost related scheduling, risk,communications decisions
Project Charter Provides summary budget from which detailed
project costs are developed EEF Culture, structure, market conditions, exchange rates,
published commercial information i.e resource cost rates
OPA Financial control procedures, historical info, financial
databases, policies, procedures & guidelines
Plan Cost Management I/Ps
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
6/36
Expert Judgment
Analytic Techniques
Developing the project plan may include choosing
strategic options such as self funding, funding withequity, or funding with debt
May also detail ways to finance project resources suchas making, purchasing, renting or leasing
May affect project schedule and/or risk
Payback period, return on investment, IRR, NPV,discounted cash flows
Meetings
Plan Cost Management T/Ts
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
7/36
Cost Management Plan Can establish the following
Units of Measure Staff hours, staff days, weeks for time measure
Meter, liters, tons, kilometers or cubic yards for quantity
Lump sum in currency form
Level of Precision degree to which activity costestimates will be rounded up (US$100.49 to US$100 orUS$995.59 to US$1000)
Level of Accuracy the acceptable range (e.g., + 10%) usedin determining realistic activity cost estimates
Plan Cost Management O/Ps
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
8/36
Cost Management Plan Can establish the following Organizational Procedures Links WBS provides the
framework for cost management plan
WBS component used for the project cost accounting is called
control account; assigned a unique code or account numberthat links directly to the performing organizations accountingsystem
Control Thresholds Variance thresholds for monitoring
cost performance may be specified to indicate an agreed-uponamount of variation to be allowed before some action needs tobe taken
Plan Cost Management O/Ps
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
9/36
Cost Management Plan Can establish the following Rules of performance Measurement EVM rules of
performance measurement are set. The plan may
Define the points in the WBS at which measurements of controlaccount will be performed
Establish the EVM techniques (e.g, weighted mile stones, fixedformula, percent complete)
Specify tracking methodologies and the EVM computationequations for calculating projected estimate at Completion (EAC)forecasts to provide a validity check on the bottom-up EAC
Plan Cost Management O/Ps
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
10/36
Cost Management Plan Can establish the following Reporting formats Formats, Frequency
Process descriptions Descriptions of each of the other cost
management processes are documented
Additional Details strategic funding choices, procedures toaccount for fluctuations in currency exchange rates, procedure forproject cost recording
Plan Cost Management O/Ps
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
11/36
Process of developing an approximation of themonetary resources needed to complete projectactivities
Generally expresses in units of some currency ($, etc)
Estimate Costs
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
12/36
Estimate Costs I/Ps
Cost Management Plan Defines how project cost will be managedand controlled. Includes methods used and level of accuracy required toestimate activity cost
Human Resource Management Plan provides project staffingattributes, personnel rates and related rewards/recognition
Scope base line
Project Scope Statement Provide product description,acceptance criteria, key deliverables, project boundaries,
assumptions and constraints
Work breakdown structure
WBS dictionary
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
13/36
Estimate Costs I/Ps
Project Schedule The type and quantity of resources andthe amount of time which those resources are applied to complete thework of the project
Risk Register Risk response costs
Enterprise Environmental Factors Market Conditions What products, services and results are
available in market, from whom, and under what terms and conditions.Regional and/or global supply and demand conditions greatly influenceresource costs
Published Commercial Information Provide standard cost formaterial and equipment
Organizational Process Assets Cost estimating policies,
templates, historical information, lessons learned
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
14/36
Estimate Costs T/Ts
Expert Judgment Analogous Estimating
Uses the values such as scope, cost, budget and duration or measures ofscale such as size, weight and complexity from a previous, similar projectas the basis for estimating the same parameter or measurement for acurrent project
Generally less costly and less time consuming but also less accurate
Parametric Estimating Uses and statistical relationship betweenrelevant historical data and other variables (e.g square footage in
construction) to calculate a cost estimate for project work.
Bottom-up Estimating Method of estimating a component of work. Thecost of individual work packages or activities is estimated to the greatestlevel of specified detail. The detailed cost is then summarized or rolled up tohigher levels for subsequent reporting and tracking purposes.
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
15/36
Estimate Costs T/Ts
Three-Point Estimating Most Likely (cM)
Optimistic (cO)
Pessimistic (cP)
Triangular Distribution cE= (cM + cO + cP)/3
Beta Distribution cE= (cO + 4cM + cP)/6
Reserve Analysis May include contingency reserves to account for costuncertainty. Contingency reserves are the budget within the cost baseline that isallocated for identified risks, which are accepted and for which contingent ormitigating responses are developed
Cost of Quality Assumptions about COQ may be used to prepare theestimates
Project Management Software
Vendor Bid Analysis
Group Decision Making Techniques Brainstorming, NGT, Delphi
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
16/36
Estimate Costs O/Ps
Activity Cost Estimates Quantitative assessments of the probable costs required to complete project
work. Presented in summary form or in detail.Costs are estimated for allresources that are applied to the activity cost estimate. This includes, but isnot limited to, direct labour, materials, equipment, services, facilities,information technology and special categories such as cost of financing
(including interest charges, an inflation allowance, exchange rates or a costcontingency reserve)
Basis of Estimate
The supporting documentation providing a clear and complete understandingof how the cost estimate was derived
Documentation of the basis of the estimates Documentation of all assumptions made
Documentation of any known constraints
Indication of the range of possible estimates (e.g $10,000( + 10%) toindicate that the item is expected to cost between a range of values), and
Indication of the confidence level of the final estimates
Project Documents Updates
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
17/36
Process of aggregating the estimated cost ofindividual activities or work packages to establish anauthorized cost baseline
Determines the cost baseline against which projectsperformance can be monitored and controlled
Determine Budget
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
18/36
Determine Budget I/Ps
Cost Management Plan How project costs will be managed & controlled Scope Baseline
Project Scope Statement Formal limitations by period for theexpenditure of the project funds can be mandated by the organization, byagreement or by other entities such as Govt agencies. These fundingconstraints are reflected in the project scope statement
Work breakdown structure
WBS dictionary
Activity Cost Estimates
Project Schedule Used to aggregate costs to the calendar periods in which
the costs are planned to be incurred Resource Calendars
Risk Register To aggregate the risk response costs
Agreements
Organizational Process Assets
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
19/36
Determine Budget T/Ts
Cost Aggregation Cost estimates are aggregated by work packages in accordance with the WBS.
The work package cost estimates are then aggregated for the highercomponent levels of the WBS (such as control accounts) and ultimately for the
entire project
Reserve Analysis Contingency reserves and the management reserves
Expert Judgment
Historical Relationships
Funding Limits Reconciliation
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
20/36
Determine Budget O/Ps
Cost Baseline Approved version of the time phased project budget
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
21/36
Determine Budget O/Ps
Project Funding Requirements Total funding requirements and periodic funding requirements
(quarterly, annually) derived from the cost baseline
Project Document Updates Activity cost estimates
Project schedule
Risk register
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
22/36
Process of monitoring the status of the project to update the projectcost and managing changes to the cost baseline
Provides the means to recognize variance from the plan in order to takecorrective action and minimize risk.
Includes Influencing the factors that create changes to the authorized cost base line
Ensuring that all change requests are acted on in a timely manner
Managing the actual changes when and as they occur
Ensuring that cost expenditures do not exceed the authorized funding, by period, byWBS components, by activity and in total for the project
Monitoring cost performance to isolate and understand variances from the approvedcost baseline
Monitoring work performance against funds expended
Preventing un approved changes from being included in the reported cost or resourceusage
Informing appropriate stake holders of all approved changes and associated costs
Bringing expected cost overruns within acceptable limits
Control Costs
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
23/36
Control Costs I/Ps
Project Management Plan Cost Baseline Cost baseline is compared with actual results to
determine if a change, corrective action or preventive action is necessary
Cost Management Plan How the project costs will be managed andcontrolled
Project Funding Requirements Projected expenditures plus anticipatedliabilities
Work Performance Data Includes information about project progress,such as which activity have started, and which deliverable have finished.Information also includes costs that have been authorized and incurred
Organizational Process Assets
Existing formal and informal cost control related policies procedures andguidelines
Cost control tools
Monitoring and reporting methods to be used
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
24/36
Control Costs T/Ts
Earned Value Management (EVM)
Methodology that combines scope, schedule and resourcemeasurement to access the project performance and progress
Develops and monitors three key dimensions for each work packageand control account
Planned Value
Earned Value
Actual Cost
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
25/36
Control Costs T/Ts
Earned Value Management (EVM) Planned Value (PV)
Authorized budget assigned to scheduled work
To be accomplished for an activity or WBS component
Total of the PV is also performance measurement baseline (PMB)
Total planned value is also known as budget at completion (BAC)
Earned Value (EV) Measure of work performed, expressed in terms of the budget
authorized for the work
EV measured cannot be greater than the authorized PV budgetfor a component
Often used to calculate the percent complete of a project
EV is monitored both incrementally to determine current statusand cumulatively to determine the long term performance trends
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
26/36
Control Costs T/Ts
Earned Value Management (EVM)
Actual Cost (AC)
Is the realized cost incurred for the work performed on an
activity during the specified time period
It is the total cost incurred in accomplishing the work that theEV measured
Will have no upper limit; what ever is spent to achieve the EV willbe measured
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
27/36
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
28/36
Control Costs T/Ts
Earned Value Management (EVM) Schedule Variance
Measure of schedule performance expressed as the differencebetween EV and PV
Amount by which the project is ahead of behind the planneddelivery date at a given point in time
Measure of schedule performance on a project
EVM schedule variance will ultimately equal zero when theproject is completed because all of the planned values will havebeen earned
SV=EV-PV
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
29/36
Control Costs T/Ts
Earned Value Management (EVM)
Cost Variance
Amount of budget deficit or surplus at a given point in time,
expressed as the difference between EV and AV
Measure of cost performance on a project
CV = EV-AC
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
30/36
Control Costs T/Ts
Earned Value Management (EVM)
Schedule Performance Index (SPI)
Measure of schedule efficiency expressed as the ratio of EV to
PV
Measures how efficiently the project team is using its time
SPI = EV/PV
SPI > 1.0 indicates more work was completed than was planned
SPI < 1.0 indicates less work was completed than was planned
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
31/36
Control Costs T/Ts
Earned Value Management (EVM)
Cost Performance Index (CPI)
Measure of the cost efficiency of budgeted resources,
expressed as a ratio of EV to AC
CPI = EV/AC
CPI > 1.0 indicates a cost underrun of performance to date
CPI < 1.0 indicates a cost overrun of performance for workcompleted
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
32/36
Control Costs T/Ts
Forecasting
Project team may develop a forecast for the estimate at completion(EAC) that may differ from the budget at completion (BAC)
If it becomes obvious that the BAC is no longer viable, the PM shouldconsider the forecasted EAC
Involves making projections of conditions and events in the projectsfuture based on current performance information and otherknowledge available at the time of the forecast
EACs are based on the actual cost incurred for work completed, plusan estimate to complete (ETC the remaining work)
EAC = AC + Bottom-up ETC
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
33/36
Control Costs T/Ts
Forecasting EAC Forecast for ETC work performed at the budget rate
It accepts the actual project performance todate as represented by theactual cost and predicts that all future ETC work will be accomplished atthe budgeted rate
EAC = AC + (BAC EV)
EAC Forecast for ETC work performed at the present CPI It assumes what the project has experienced todate can be accepted to
continue in the future
EAC = BAC/CPI
EAC Forecast for ETC work considering both SPI and CPI factors In this the ETC work will be performed at an efficiency rate that
considers both the cost and schedule performance indices
EAC = AC + [(BAC EV)/(CPI x SPI)]
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
34/36
Control Costs T/Ts
To-Complete Performance Index (TCPI) It is a measure of the costperformance that is required to be achieved with the remaining resources in orderto meet a specified management goal, expressed as the ratio of the cost to finishthe outstanding work to the remaining budget
TCPI = Work remaining (BAC EV)/Funds remaining (BAC AC) or (EAC AC)
Performance Reviews
Variance Analysis It is the explanation (cause, impact andcorrective actions) for
Cost CV = EV AC
Schedule SV = EV PV Variance at completion VAC = BAC EAC
Trend Analysis It examine project performance overtime to determine ifperformance is improving or deteriorating. Graphical analysis techniques areused
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
35/36
Control Costs T/Ts
Performance Reviews
Earned Value Performance It compares the performance measurementbaseline to actual schedule and cost performance. If EVM is not used thenthe analysis of the cost baseline against actual costs for the work performedis used for cost performance comparison
Project Management Software
Reserve Analysis
7/30/2019 Lecture - 6 Pcm ( PMBOK)I
36/36
Control Costs O/Ps
Work Performance Information CV, SV, CPI, SPI, TCPI, VAC Cost Forecasts EAC or a bottom-up EAC
Change Requests
Project Management Plan Updates
Cost Baseline Cost Management Plan
Project Documents Updates Cost estimates
Basis of estimates
Organizational Process Assets Updates Causes of variances
Corrective action chosen and the reasons
Financial data basis
L ss s l