Lecture - 6 Pcm ( PMBOK)I

Embed Size (px)

Citation preview

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    1/36

    PROJECT COST

    MANAGEMENT

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    2/36

    PROJECT COST MANAGEMENT

    Processes involved in planning,estimating, budgeting, financing,

    funding, managing and controlling costsso that the project can be completed

    within the approved budget

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    3/36

    Plan Cost Management Processes that establishes the policies, procedures and

    documentation for planning, managing, expending and controllingproject costs

    Estimate Costs Process of developing an approximation of the monetary resources

    needed to complete the project activities

    Determine Budget The process of aggregating the estimated costs of individual

    activities or work packages to establish an authorized cost baseline

    Control Costs The process of monitoring the status of the project to update the

    project costs and managing changes to the cost baseline

    PROJECT COST MANAGEMENT

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    4/36

    Plan Cost Management Processes that establishes the policies, procedures and

    documentation for planning, managing, expending andcontrolling project costs

    Provides guidance and direction on how the project costs willbe managed throughout the project

    Plan Cost Management

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    5/36

    Project Management Plan

    Scope Baseline project scope statement, WBS detail

    Schedule Baseline defines when the project costs will beincurred

    Other Information Cost related scheduling, risk,communications decisions

    Project Charter Provides summary budget from which detailed

    project costs are developed EEF Culture, structure, market conditions, exchange rates,

    published commercial information i.e resource cost rates

    OPA Financial control procedures, historical info, financial

    databases, policies, procedures & guidelines

    Plan Cost Management I/Ps

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    6/36

    Expert Judgment

    Analytic Techniques

    Developing the project plan may include choosing

    strategic options such as self funding, funding withequity, or funding with debt

    May also detail ways to finance project resources suchas making, purchasing, renting or leasing

    May affect project schedule and/or risk

    Payback period, return on investment, IRR, NPV,discounted cash flows

    Meetings

    Plan Cost Management T/Ts

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    7/36

    Cost Management Plan Can establish the following

    Units of Measure Staff hours, staff days, weeks for time measure

    Meter, liters, tons, kilometers or cubic yards for quantity

    Lump sum in currency form

    Level of Precision degree to which activity costestimates will be rounded up (US$100.49 to US$100 orUS$995.59 to US$1000)

    Level of Accuracy the acceptable range (e.g., + 10%) usedin determining realistic activity cost estimates

    Plan Cost Management O/Ps

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    8/36

    Cost Management Plan Can establish the following Organizational Procedures Links WBS provides the

    framework for cost management plan

    WBS component used for the project cost accounting is called

    control account; assigned a unique code or account numberthat links directly to the performing organizations accountingsystem

    Control Thresholds Variance thresholds for monitoring

    cost performance may be specified to indicate an agreed-uponamount of variation to be allowed before some action needs tobe taken

    Plan Cost Management O/Ps

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    9/36

    Cost Management Plan Can establish the following Rules of performance Measurement EVM rules of

    performance measurement are set. The plan may

    Define the points in the WBS at which measurements of controlaccount will be performed

    Establish the EVM techniques (e.g, weighted mile stones, fixedformula, percent complete)

    Specify tracking methodologies and the EVM computationequations for calculating projected estimate at Completion (EAC)forecasts to provide a validity check on the bottom-up EAC

    Plan Cost Management O/Ps

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    10/36

    Cost Management Plan Can establish the following Reporting formats Formats, Frequency

    Process descriptions Descriptions of each of the other cost

    management processes are documented

    Additional Details strategic funding choices, procedures toaccount for fluctuations in currency exchange rates, procedure forproject cost recording

    Plan Cost Management O/Ps

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    11/36

    Process of developing an approximation of themonetary resources needed to complete projectactivities

    Generally expresses in units of some currency ($, etc)

    Estimate Costs

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    12/36

    Estimate Costs I/Ps

    Cost Management Plan Defines how project cost will be managedand controlled. Includes methods used and level of accuracy required toestimate activity cost

    Human Resource Management Plan provides project staffingattributes, personnel rates and related rewards/recognition

    Scope base line

    Project Scope Statement Provide product description,acceptance criteria, key deliverables, project boundaries,

    assumptions and constraints

    Work breakdown structure

    WBS dictionary

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    13/36

    Estimate Costs I/Ps

    Project Schedule The type and quantity of resources andthe amount of time which those resources are applied to complete thework of the project

    Risk Register Risk response costs

    Enterprise Environmental Factors Market Conditions What products, services and results are

    available in market, from whom, and under what terms and conditions.Regional and/or global supply and demand conditions greatly influenceresource costs

    Published Commercial Information Provide standard cost formaterial and equipment

    Organizational Process Assets Cost estimating policies,

    templates, historical information, lessons learned

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    14/36

    Estimate Costs T/Ts

    Expert Judgment Analogous Estimating

    Uses the values such as scope, cost, budget and duration or measures ofscale such as size, weight and complexity from a previous, similar projectas the basis for estimating the same parameter or measurement for acurrent project

    Generally less costly and less time consuming but also less accurate

    Parametric Estimating Uses and statistical relationship betweenrelevant historical data and other variables (e.g square footage in

    construction) to calculate a cost estimate for project work.

    Bottom-up Estimating Method of estimating a component of work. Thecost of individual work packages or activities is estimated to the greatestlevel of specified detail. The detailed cost is then summarized or rolled up tohigher levels for subsequent reporting and tracking purposes.

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    15/36

    Estimate Costs T/Ts

    Three-Point Estimating Most Likely (cM)

    Optimistic (cO)

    Pessimistic (cP)

    Triangular Distribution cE= (cM + cO + cP)/3

    Beta Distribution cE= (cO + 4cM + cP)/6

    Reserve Analysis May include contingency reserves to account for costuncertainty. Contingency reserves are the budget within the cost baseline that isallocated for identified risks, which are accepted and for which contingent ormitigating responses are developed

    Cost of Quality Assumptions about COQ may be used to prepare theestimates

    Project Management Software

    Vendor Bid Analysis

    Group Decision Making Techniques Brainstorming, NGT, Delphi

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    16/36

    Estimate Costs O/Ps

    Activity Cost Estimates Quantitative assessments of the probable costs required to complete project

    work. Presented in summary form or in detail.Costs are estimated for allresources that are applied to the activity cost estimate. This includes, but isnot limited to, direct labour, materials, equipment, services, facilities,information technology and special categories such as cost of financing

    (including interest charges, an inflation allowance, exchange rates or a costcontingency reserve)

    Basis of Estimate

    The supporting documentation providing a clear and complete understandingof how the cost estimate was derived

    Documentation of the basis of the estimates Documentation of all assumptions made

    Documentation of any known constraints

    Indication of the range of possible estimates (e.g $10,000( + 10%) toindicate that the item is expected to cost between a range of values), and

    Indication of the confidence level of the final estimates

    Project Documents Updates

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    17/36

    Process of aggregating the estimated cost ofindividual activities or work packages to establish anauthorized cost baseline

    Determines the cost baseline against which projectsperformance can be monitored and controlled

    Determine Budget

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    18/36

    Determine Budget I/Ps

    Cost Management Plan How project costs will be managed & controlled Scope Baseline

    Project Scope Statement Formal limitations by period for theexpenditure of the project funds can be mandated by the organization, byagreement or by other entities such as Govt agencies. These fundingconstraints are reflected in the project scope statement

    Work breakdown structure

    WBS dictionary

    Activity Cost Estimates

    Project Schedule Used to aggregate costs to the calendar periods in which

    the costs are planned to be incurred Resource Calendars

    Risk Register To aggregate the risk response costs

    Agreements

    Organizational Process Assets

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    19/36

    Determine Budget T/Ts

    Cost Aggregation Cost estimates are aggregated by work packages in accordance with the WBS.

    The work package cost estimates are then aggregated for the highercomponent levels of the WBS (such as control accounts) and ultimately for the

    entire project

    Reserve Analysis Contingency reserves and the management reserves

    Expert Judgment

    Historical Relationships

    Funding Limits Reconciliation

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    20/36

    Determine Budget O/Ps

    Cost Baseline Approved version of the time phased project budget

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    21/36

    Determine Budget O/Ps

    Project Funding Requirements Total funding requirements and periodic funding requirements

    (quarterly, annually) derived from the cost baseline

    Project Document Updates Activity cost estimates

    Project schedule

    Risk register

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    22/36

    Process of monitoring the status of the project to update the projectcost and managing changes to the cost baseline

    Provides the means to recognize variance from the plan in order to takecorrective action and minimize risk.

    Includes Influencing the factors that create changes to the authorized cost base line

    Ensuring that all change requests are acted on in a timely manner

    Managing the actual changes when and as they occur

    Ensuring that cost expenditures do not exceed the authorized funding, by period, byWBS components, by activity and in total for the project

    Monitoring cost performance to isolate and understand variances from the approvedcost baseline

    Monitoring work performance against funds expended

    Preventing un approved changes from being included in the reported cost or resourceusage

    Informing appropriate stake holders of all approved changes and associated costs

    Bringing expected cost overruns within acceptable limits

    Control Costs

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    23/36

    Control Costs I/Ps

    Project Management Plan Cost Baseline Cost baseline is compared with actual results to

    determine if a change, corrective action or preventive action is necessary

    Cost Management Plan How the project costs will be managed andcontrolled

    Project Funding Requirements Projected expenditures plus anticipatedliabilities

    Work Performance Data Includes information about project progress,such as which activity have started, and which deliverable have finished.Information also includes costs that have been authorized and incurred

    Organizational Process Assets

    Existing formal and informal cost control related policies procedures andguidelines

    Cost control tools

    Monitoring and reporting methods to be used

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    24/36

    Control Costs T/Ts

    Earned Value Management (EVM)

    Methodology that combines scope, schedule and resourcemeasurement to access the project performance and progress

    Develops and monitors three key dimensions for each work packageand control account

    Planned Value

    Earned Value

    Actual Cost

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    25/36

    Control Costs T/Ts

    Earned Value Management (EVM) Planned Value (PV)

    Authorized budget assigned to scheduled work

    To be accomplished for an activity or WBS component

    Total of the PV is also performance measurement baseline (PMB)

    Total planned value is also known as budget at completion (BAC)

    Earned Value (EV) Measure of work performed, expressed in terms of the budget

    authorized for the work

    EV measured cannot be greater than the authorized PV budgetfor a component

    Often used to calculate the percent complete of a project

    EV is monitored both incrementally to determine current statusand cumulatively to determine the long term performance trends

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    26/36

    Control Costs T/Ts

    Earned Value Management (EVM)

    Actual Cost (AC)

    Is the realized cost incurred for the work performed on an

    activity during the specified time period

    It is the total cost incurred in accomplishing the work that theEV measured

    Will have no upper limit; what ever is spent to achieve the EV willbe measured

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    27/36

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    28/36

    Control Costs T/Ts

    Earned Value Management (EVM) Schedule Variance

    Measure of schedule performance expressed as the differencebetween EV and PV

    Amount by which the project is ahead of behind the planneddelivery date at a given point in time

    Measure of schedule performance on a project

    EVM schedule variance will ultimately equal zero when theproject is completed because all of the planned values will havebeen earned

    SV=EV-PV

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    29/36

    Control Costs T/Ts

    Earned Value Management (EVM)

    Cost Variance

    Amount of budget deficit or surplus at a given point in time,

    expressed as the difference between EV and AV

    Measure of cost performance on a project

    CV = EV-AC

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    30/36

    Control Costs T/Ts

    Earned Value Management (EVM)

    Schedule Performance Index (SPI)

    Measure of schedule efficiency expressed as the ratio of EV to

    PV

    Measures how efficiently the project team is using its time

    SPI = EV/PV

    SPI > 1.0 indicates more work was completed than was planned

    SPI < 1.0 indicates less work was completed than was planned

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    31/36

    Control Costs T/Ts

    Earned Value Management (EVM)

    Cost Performance Index (CPI)

    Measure of the cost efficiency of budgeted resources,

    expressed as a ratio of EV to AC

    CPI = EV/AC

    CPI > 1.0 indicates a cost underrun of performance to date

    CPI < 1.0 indicates a cost overrun of performance for workcompleted

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    32/36

    Control Costs T/Ts

    Forecasting

    Project team may develop a forecast for the estimate at completion(EAC) that may differ from the budget at completion (BAC)

    If it becomes obvious that the BAC is no longer viable, the PM shouldconsider the forecasted EAC

    Involves making projections of conditions and events in the projectsfuture based on current performance information and otherknowledge available at the time of the forecast

    EACs are based on the actual cost incurred for work completed, plusan estimate to complete (ETC the remaining work)

    EAC = AC + Bottom-up ETC

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    33/36

    Control Costs T/Ts

    Forecasting EAC Forecast for ETC work performed at the budget rate

    It accepts the actual project performance todate as represented by theactual cost and predicts that all future ETC work will be accomplished atthe budgeted rate

    EAC = AC + (BAC EV)

    EAC Forecast for ETC work performed at the present CPI It assumes what the project has experienced todate can be accepted to

    continue in the future

    EAC = BAC/CPI

    EAC Forecast for ETC work considering both SPI and CPI factors In this the ETC work will be performed at an efficiency rate that

    considers both the cost and schedule performance indices

    EAC = AC + [(BAC EV)/(CPI x SPI)]

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    34/36

    Control Costs T/Ts

    To-Complete Performance Index (TCPI) It is a measure of the costperformance that is required to be achieved with the remaining resources in orderto meet a specified management goal, expressed as the ratio of the cost to finishthe outstanding work to the remaining budget

    TCPI = Work remaining (BAC EV)/Funds remaining (BAC AC) or (EAC AC)

    Performance Reviews

    Variance Analysis It is the explanation (cause, impact andcorrective actions) for

    Cost CV = EV AC

    Schedule SV = EV PV Variance at completion VAC = BAC EAC

    Trend Analysis It examine project performance overtime to determine ifperformance is improving or deteriorating. Graphical analysis techniques areused

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    35/36

    Control Costs T/Ts

    Performance Reviews

    Earned Value Performance It compares the performance measurementbaseline to actual schedule and cost performance. If EVM is not used thenthe analysis of the cost baseline against actual costs for the work performedis used for cost performance comparison

    Project Management Software

    Reserve Analysis

  • 7/30/2019 Lecture - 6 Pcm ( PMBOK)I

    36/36

    Control Costs O/Ps

    Work Performance Information CV, SV, CPI, SPI, TCPI, VAC Cost Forecasts EAC or a bottom-up EAC

    Change Requests

    Project Management Plan Updates

    Cost Baseline Cost Management Plan

    Project Documents Updates Cost estimates

    Basis of estimates

    Organizational Process Assets Updates Causes of variances

    Corrective action chosen and the reasons

    Financial data basis

    L ss s l