Upload
cristina-cojocea
View
6
Download
0
Embed Size (px)
DESCRIPTION
Prezentare
Citation preview
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 1/82
The Star
Design and construction of
The Star Performing Arts Centre / Star Vista
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 2/82
Presentation Outline
• Project Team
• Project Site Location• Project Brief
• Structural Design
Challenges
• Steel Composite Design• Offsite Fabrication &
Logistic
• Construction Methodology
• Progress Photos
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 3/82
Project Team
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 4/82
Project Team
Client Rock Production Pte Ltd
Architect Aedas Pte Ltd
C&S Engineer Parsons Brinckerhoff Pte Ltd
M&E Engineer Mott MacDonald Pte Ltd
Contractor Hexacon Construction Pte Ltd
Project Manager
CapitaLand Retail Project
Management Pte Ltd
Quantity Surveyor Langdon & Seah Singapore
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 5/82
Project Site Location
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 6/82
Project site location
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 7/82
Project Brief
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 8/82
Project Data Sheet
Total GFA 62,000m2
Commercial 24,000m2
Institutional & Others 38,000m2
Total Car park lots 810
B2 269
B3 263
B4 278
Total auditorium seats 5142
Main floor 1903
1st Tier 1808
2nd Tier 1431
Amphitheatre 55m x 20m
Building height 85.70m
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 9/82
Building function
Cultural use
Retail
Car parking
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 10/82
Building function
HIGH OPEN ATRIUM SPACE
AND RETAILS
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 11/82
Building function
Auditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 12/82
Building function
The Star Terrace
Outdoor Amphitheatre
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 13/82
Building function
The Star Gallery
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 14/82
Building function
The Star Loft
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 15/82
Diaphragm WallBored Pile
RC Flat Slab
(Car park)
RC Beam & Slab
(Retail)
Composite Slab
(Offices /
auditorium)
Steel Trusses
(Auditorium)
RC Columns
Core Walls
Structural system
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 16/82
Structural Design Challenges
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 17/82
Structural Design Challenges
1. Deep excavation
adjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 18/82
Structural Design Challenges
1. Deep excavation
adjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 19/82
R o c h e s t e r D r i v
e
Vista Exchange Green
Deep excavation adjacent to railway protection zone
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 20/82
Deep excavation adjacent to railway protection zone
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 21/82
Monitoring Instrumentations
Tilt meter Inclinometer Water Stand PipeSettlement Marker Vibration meter
Deep excavation adjacent to railway protection zone
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 22/82
Deep excavation adjacent to railway protection zone
Diaphragm wall panelings
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 23/82
Control excavation sequence
Zone by Zone Excavation and Casting
Deep excavation adjacent to railway protection zone
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 24/82
`
2.7mm
6.7mm
7.3mm8.5mm
9.6mm
9.6mm
2.1mm
Final viaduct pier movement
Deep excavation adjacent to railway protection zone
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 25/82
Structural Design Challenges
1. Deep excavation
adjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 26/82
Excavation below MRT Viaduct
SECTION D-D
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 27/82
Excavation below MRT Viaduct
STEP 1 STEP 2 STEP 3
STEP 4 STEP 5 STEP 6
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 28/82
Excavation below MRT Viaduct
Deploy small excavator
Excavate down 1m
Expose Pilecap
Construct wall & further excavate
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 29/82
Excavation below MRT Viaduct
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 30/82
Structural Design Challenges
1. Deep excavation
adjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 31/82
Inclined Columns and Lateral Forces
Slender Inclined Columns
• Sizes range from 800ø to 2300ø• 22 numbers
• Inclined angles 5 to 20 degree
from vertical
C
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 32/82
Inclined Columns and Lateral Forces
3-D computer Modeling
TEKLA Model
ETABS Model
I li d C l d L t l F
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 33/82
Design loads
– Lateral forces due to Inclinedcolumn at random direction
– Disproportionate collapse load
– Horizontal and vertical load
B1
L5
1 s t M o d e
MODAL Analysis
2 n d
M o d e
3 r d M o d e
Inclined Columns and Lateral Forces
Elevation Plan view
I li d C l d L t l F
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 34/82
Triangular lateral t ie beams
L6 Main Auditorium Floor
L5 Auditorium Lobby Floor
Inclined Columns and Lateral Forces
I li d C l d L t l F
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 35/82
Column head and tie beams at B1
Inclined Columns and Lateral Forces
I li d C l d L t l F
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 36/82
Inclined Columns and Lateral Forces
Temporary Support and tie-back for inclined column
during construction
Tie-back and Props to main structure
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 37/82
Structural Design Challenges
1. Deep excavationadjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
C l C ti D t il
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 38/82
Column joint Detail
• External ring plate to receive incoming steel beams• Cast in shear stud / anchor rebars
• Slotted web plate in column for canti lever beam
Complex Connection Detail
Typical Tube
connection Detail
C l C ti D t il
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 39/82
L3 Long Cantilever connection
• FEM connection Analysis
Complex Connection Detail
Comple Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 40/82
L3 Long Cantilever connection
• FEM connection Analysis
Complex Connection Detail
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 41/82
L3 Long Cantilever connection
• FEM connection Analysis
• Strengthening :
– Enlarged external ring plate
– Add slot web plate within column
Complex Connection Detail
Without strengthening
With strengthening
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 42/82
L3 Cantilever box girder
Complex Connection Detail
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 43/82
Complex Connection Detail (C23)
• Enlarged column head• 3D detailing to reveal rebar arrangement
Complex Connection Detail
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 44/82
Complex Connection Detail
Double Roof Truss
• Column Inclined
• Truss in vertical plane
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 45/82
Complex Connection Detail
Auditorium Wall Truss
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 46/82
Complex Connection Detail
Raker Truss
Complex Connection Detail
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 47/82
Complex Connection Detail
Roof Truss
Structural Design Challenges
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 48/82
Structural Design Challenges
1. Deep excavationadjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge design
6. Vibration design ofauditorium
Sky Bridge Design
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 49/82
Pre-camber / deflect ion design
consideration
– Original design intent (3 supports)
– Temporary hoisting (2 supports)
– Construction sequence
• Precamber deflection• Hoisting deflection
• Preload Macalloy bar deflection
• Superimposed dead load
deflection
Sky Bridge Design
Sky Bridge Design
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 50/82
Sky bridge – Precamber magnitude
110mm
90mm
70mm
60mm
100mm
Original design intent
With Hoisting consideration
Support 1 Support 2
Support 3
L o c a t i o n 1
L o c a t i o n 2
Support 1 Support 2
Sky Bridge Design
Structural Design Challenges
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 51/82
Structural Design Challenges
1. Deep excavationadjacent RailwayProtection Zone
2. Excavation belowMRT viaduct
3. Inclined columnsand lateral forces
4. Complex connectiondetails
5. Sky bridge Design
6. Vibration design ofauditorium
Vibration Design of Auditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 52/82
Auditorium Vibration requirement
Vibration Design of Auditorium
Vibration Design of Auditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 53/82
Performance-based Approach
– BRE Digest 426 – 6.0Hz, with acceleration of 5%g
– Concrete encasement for 2 plate girders at main
floor and cantilever truss at 1st Tier balcony
Vibration Design of Auditorium
Vibration Design of Auditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 54/82
Vibration Test
Main Floor 1st Tier balcony 2nd Tier balcony
Vibration Design of Auditorium
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 55/82
Steel Composite Design
Steel Composite Design
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 56/82
Why composite system ?
Less structural self-weight
Minimize falsework / scaffolding
Fast construction
Better utilization of material strength
Steel Composite Design
Steel Composite Design
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 57/82
Steel Composite Design
Fastrak Model
Steel Composite Design
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 58/82
Steel Composite Design
Composite deck
Fireproofing
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 59/82
Offsite Fabrication & Logistic
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 60/82
Offsite Fabrication & Logistic
Storage Yard Tube with stiffener Shear stud in tube
Truss joints Cast-in plates Tube connection
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 61/82
Offsite Fabrication & Logistic
Double Roof Truss PPBW Preparation
Welding Preparation Flange join by weld
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 62/82
O s e ab ca o & og s c
Thick Steel Plate Welding preparation
Assemble Plate Girder Welding process
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 63/82
g
Roof Truss setting out Welding
Testing welds Ready for painting
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 64/82
g
Sky bridge trusses fabrication
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 65/82
g
Double trusses fabrication
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 66/82
g
Wall Trusses Fabrication
Offsite Fabrication & Logistic
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 67/82
g
Amphitheatre Column Tube & box girder assembly
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 68/82
Construction Methodology
Top down construction
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 69/82
p
Excavate, install D-wall & Pile with Plunge-in columns
Existing Ground Level
Top down construction
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 70/82
Concurrently construct basement and super-structure
Top down construction
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 71/82
Complete basement, continue super-structure
Top down construction
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 72/82
Rebar work for B1 beams Excavation after casting
Excavation to B2 level Rebar work for B2 beams
Top down construction
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 73/82
Column Casting
Amphitheatre column tube installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 74/82
Amphitheatre Column Tube Installation
Amphitheatre box girder installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 75/82
Amphitheatre box girder Erection
Wall Truss installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 76/82
Raker Truss Installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 77/82
Erect Temporary support
Erect 1st Tier
Erect 1st Tier
Finished 1st Tier
Erect 2nd Tier
Finished 2nd Tier
Double Roof Truss installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 78/82
Setting up of Jacking
Frame L i f t i n g u p
f r o m G
r o u n d
t o r o o f
Roof Truss installation
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 79/82
Erection on Temporary staging from auditorium main floor
Site welding on temporary working platform joining the truss modules
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 80/82
Progress Photos
Aug 09 Dec 09 May 10
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 81/82
Sep 10 Mar 11 Jun 11
Jan 12 Mar 12 Aug 12
7/18/2019 Lecture 1
http://slidepdf.com/reader/full/lecture-1-5692031e8854a 82/82
Thank You