Upload
pei-jin
View
24
Download
0
Embed Size (px)
DESCRIPTION
Lecture 09 Post Construction
Citation preview
LECTURE 08 compiled & presented by Prof. Madya Ar Meor Mohammad Fared 21 May 2013 ARC 4710 Architectural Practice 2nd Semester 2012/ 2013
POST CONSTRUCTION
ARC4710-2nd Semester 2012/2013 2
Project Completion
Certificate of Practical Completion (CPC) issued:-
Project has been completed
End of Interim Certificate
Defects Liability Period (DLP) commences
End of Contractors insurances coverage
Release of of retention sum
Building handed over to Client
Final measurement & Valuation begins
ARC4710-2nd Semester 2012/2013 3
Project Completion
Handing Over to Client:-
As-Built dwgs to be prepared by Consultants and submitted to Client:
- basis for Final Measurement
- record of what have been built
O&M Manual normally compiled by M&E contractor and supervise by M&E Engr.
Training for Clients personnel
Keys
ARC4710-2nd Semester 2012/2013 4
Project Completion
Application for Certificate of Fitness for Occupation (CFO):-
Apply CFO vide Borang E to LA
C&S and M&E Engr. to endorse on Borang E
Client cannot occupy building without CFO
LA will visit site for CFO inspection
As-Built Drawings to be submitted to LA before inspection
ARC4710-2nd Semester 2012/2013 5
Project Completion
CFO will only be issued by LA when :-
Building is considered safe for occupation
Water and Electricity is available
Support Letter from various authorities Bomba, TNB, Syabas, Telekom, JPS, JKR etc received by LA
ARC4710-2nd Semester 2012/2013 6
Reasons For Change? To remove bureaucracy To expedite the process of occupying new bldgs To give better protection to house buyers
CFO vs CCC
CFO Issued by Local Authority
After April 2007 CFO had been replaced with Cert. Of Completion & Compliance (CCC)
CCC Issued by PSP Arch/ Engr/ Bldg Draftsman
ARC4710-2nd Semester 2012/2013 7
Certificate of Completion & Compliance
Salient features of CCC:- Bldg plans are still required to be submitted by Principal Submitting Person (PSP) to Local Authority (LA) and approved by the LA. The new system is an effort towards self-certification and self-regulation approach in the construction industry CFO will be replaced by CCC PSP will issue CCC vide Form F and Partial CCC vide Form F1 The issuance of CCC is restricted to only tech. issues concerning health, safety and essential services. Other non-tech. issues will be resolved between Developer and LA
ARC4710-2nd Semester 2012/2013 8
Certificate of Completion & Compliance
CCC to be issued by Principal Submitting Person (PSP) i.e Prof. Arch, Prof. Engr. and Bldg. Draftsman CCC can only be issued by PSP after: All 21 forms G1 to G21 have been endorsed and submitted to LA Clearances from TNB, Water Authority, Sewerage Dept (JPP), Bomba and other authorities
CCC to be issued vide Form F in 4 copies (i)to Owner or Developer, (ii)PSPs copy, (iii) Local Authority and (iv) LAM.
ARC4710-2nd Semester 2012/2013 9
Acts/ Laws that were amended Architects Act 1967 (Act 113) - Architects Rules 1986 Street, Drainage & Building Act 1974 (Act 133) - UBBL 1984 Housing Developers Act 1966 Strata Title Act 1985 Engineers Act and many more.
CFO vs CCC
ARC4710-2nd Semester 2012/2013 10
ASMFR2010 - Rule 7: Basic Services
Rule 12. Final Completion Phase -
issuing a Certificate of Completion and Compliance (CCC) for building after being satisfied that the building is fit and safe for occupancy
certifying As-Built Drawings and submitting maintenance manuals together with all warranties to the Client
Issuing a Certificate of Making Good Defects (CMGD) after being satisfied that all defects to the building have been rectified
Preparing Final Accounts for the contract and issuing a Final Certificate of payment to the contractor
ARC4710-2nd Semester 2012/2013 11
Project Completion
Defects Liability Period (DLP):- a period of time where by any defects (bounded by the contract) during this period (as agreed in the contract document) on the building shall be rectified by the contractor at his own cost.
Duration of DLP - as per Appendix 1. DLP for Housing projects has been extended to 24 months after April 2007
Clients representative to provide list of defects & Contractor to rectify.
Within 14 days of DLP Architect to issue Schedule of Defects to Contractor for rectification works
ARC4710-2nd Semester 2012/2013 12
Project Completion
Cert. Of Making Good Defects (CMGD):-
will be issued once all defects have been rectified by the Contractor
release of the balance of retention sum.
ARC4710-2nd Semester 2012/2013 13
END OF DLP
CERTIFICATE OF MAKING GOOD DEFECTS
CONTRACTOR MAKE GOOD DEFECTS
ANY DEFECT?
SCHEDULE OF DEFECTS
DEFECTS LIABILITY PERIOD
CONTRACTOR MAKE GOOD DEFECTS
ISSUE INSTRUCTIONS
YES
NO CPC
ARC4710-2nd Semester 2012/2013 14
Project Completion
Final Certificate (FC) QS statement of final account for the work which take into account:
the variations to the work as ordered from time to time
PC sums
EOT
LAD
Etc
It will be presented through the Architect to the Client as a statement agreed with the Contractor.
The issuance of a Final Certificate assumes that everything is acceptable. Signed copies of the account to be issued to both the Client and Contractor.
ARC4710-2nd Semester 2012/2013 15
Commencement Date
Site Possession Mtg
Borang B
Performance Bond
Contractors All Risk
Workmans Compensation
Borang C Setting Out
Borang D Excavation for
Foundations Works Completed
Site Meeting
Valuation
Interim Certificates
Co
ntr
act
Pe
rio
d
ARC4710-2nd Semester 2012/2013 16
Original Date of Completion
CPC Issued
Release of Retention Sum
Interim Certificate Ends
End of DLP
Architects Power to Issue A.I. Ends
Contractors Insurances of Works End
Building Handed Over to Client
DLP Commences
Within 14 Days Arch to Issue Schedule of
Defects
De
fects
Lia
bil
ity P
eri
od
Penultimate Certificate
ARC4710-2nd Semester 2012/2013 17
Original Date of Completion
EOT Issued
Contractor Entitles for Loss & Profit Claim
Adjusted Date of Completion
End of DLP
CPC Issued
Within 14 Days Arch to Issue Schedule of
Defects
ARC4710-2nd Semester 2012/2013 18
Original Date of Completion
CNC Issued
Liquidated Ascertained & Damages (LAD) Begins
Works Completed
End of DLP
CPC Issued
Within 14 Days Arch to Issue Schedule of
Defects
LAD Ends
ARC4710-2nd Semester 2012/2013 19
Rectification Works Completed
Certificate of Making Good Defects (CMGD)
Release of Balance of Retention Sum
No Later Than 3 Months After DLP
No Later Than 3 Months After CMGD
No Later Than 3 Months After
Receiving All Info From Contractor
Final Certificate
Final Payment