  • LECTURE 08 compiled & presented by Prof. Madya Ar Meor Mohammad Fared 21 May 2013 ARC 4710 Architectural Practice 2nd Semester 2012/ 2013

    POST CONSTRUCTION

  • ARC4710-2nd Semester 2012/2013 2

    Project Completion

    Certificate of Practical Completion (CPC) issued:-

    Project has been completed

    End of Interim Certificate

    Defects Liability Period (DLP) commences

    End of Contractors insurances coverage

    Release of of retention sum

    Building handed over to Client

    Final measurement & Valuation begins

  • ARC4710-2nd Semester 2012/2013 3

    Project Completion

    Handing Over to Client:-

    As-Built dwgs to be prepared by Consultants and submitted to Client:

    - basis for Final Measurement

    - record of what have been built

    O&M Manual normally compiled by M&E contractor and supervise by M&E Engr.

    Training for Clients personnel

    Keys

  • ARC4710-2nd Semester 2012/2013 4

    Project Completion

    Application for Certificate of Fitness for Occupation (CFO):-

    Apply CFO vide Borang E to LA

    C&S and M&E Engr. to endorse on Borang E

    Client cannot occupy building without CFO

    LA will visit site for CFO inspection

    As-Built Drawings to be submitted to LA before inspection

  • ARC4710-2nd Semester 2012/2013 5

    Project Completion

    CFO will only be issued by LA when :-

    Building is considered safe for occupation

    Water and Electricity is available

    Support Letter from various authorities Bomba, TNB, Syabas, Telekom, JPS, JKR etc received by LA

  • ARC4710-2nd Semester 2012/2013 6

    Reasons For Change? To remove bureaucracy To expedite the process of occupying new bldgs To give better protection to house buyers

    CFO vs CCC

    CFO Issued by Local Authority

    After April 2007 CFO had been replaced with Cert. Of Completion & Compliance (CCC)

    CCC Issued by PSP Arch/ Engr/ Bldg Draftsman

  • ARC4710-2nd Semester 2012/2013 7

    Certificate of Completion & Compliance

    Salient features of CCC:- Bldg plans are still required to be submitted by Principal Submitting Person (PSP) to Local Authority (LA) and approved by the LA. The new system is an effort towards self-certification and self-regulation approach in the construction industry CFO will be replaced by CCC PSP will issue CCC vide Form F and Partial CCC vide Form F1 The issuance of CCC is restricted to only tech. issues concerning health, safety and essential services. Other non-tech. issues will be resolved between Developer and LA

  • ARC4710-2nd Semester 2012/2013 8

    Certificate of Completion & Compliance

    CCC to be issued by Principal Submitting Person (PSP) i.e Prof. Arch, Prof. Engr. and Bldg. Draftsman CCC can only be issued by PSP after: All 21 forms G1 to G21 have been endorsed and submitted to LA Clearances from TNB, Water Authority, Sewerage Dept (JPP), Bomba and other authorities

    CCC to be issued vide Form F in 4 copies (i)to Owner or Developer, (ii)PSPs copy, (iii) Local Authority and (iv) LAM.

  • ARC4710-2nd Semester 2012/2013 9

    Acts/ Laws that were amended Architects Act 1967 (Act 113) - Architects Rules 1986 Street, Drainage & Building Act 1974 (Act 133) - UBBL 1984 Housing Developers Act 1966 Strata Title Act 1985 Engineers Act and many more.

    CFO vs CCC

  • ARC4710-2nd Semester 2012/2013 10

    ASMFR2010 - Rule 7: Basic Services

    Rule 12. Final Completion Phase -

    issuing a Certificate of Completion and Compliance (CCC) for building after being satisfied that the building is fit and safe for occupancy

    certifying As-Built Drawings and submitting maintenance manuals together with all warranties to the Client

    Issuing a Certificate of Making Good Defects (CMGD) after being satisfied that all defects to the building have been rectified

    Preparing Final Accounts for the contract and issuing a Final Certificate of payment to the contractor

  • ARC4710-2nd Semester 2012/2013 11

    Project Completion

    Defects Liability Period (DLP):- a period of time where by any defects (bounded by the contract) during this period (as agreed in the contract document) on the building shall be rectified by the contractor at his own cost.

    Duration of DLP - as per Appendix 1. DLP for Housing projects has been extended to 24 months after April 2007

    Clients representative to provide list of defects & Contractor to rectify.

    Within 14 days of DLP Architect to issue Schedule of Defects to Contractor for rectification works

  • ARC4710-2nd Semester 2012/2013 12

    Project Completion

    Cert. Of Making Good Defects (CMGD):-

    will be issued once all defects have been rectified by the Contractor

    release of the balance of retention sum.

  • ARC4710-2nd Semester 2012/2013 13

    END OF DLP

    CERTIFICATE OF MAKING GOOD DEFECTS

    CONTRACTOR MAKE GOOD DEFECTS

    ANY DEFECT?

    SCHEDULE OF DEFECTS

    DEFECTS LIABILITY PERIOD

    CONTRACTOR MAKE GOOD DEFECTS

    ISSUE INSTRUCTIONS

    YES

    NO CPC

  • ARC4710-2nd Semester 2012/2013 14

    Project Completion

    Final Certificate (FC) QS statement of final account for the work which take into account:

    the variations to the work as ordered from time to time

    PC sums

    EOT

    LAD

    Etc

    It will be presented through the Architect to the Client as a statement agreed with the Contractor.

    The issuance of a Final Certificate assumes that everything is acceptable. Signed copies of the account to be issued to both the Client and Contractor.

  • ARC4710-2nd Semester 2012/2013 15

    Commencement Date

    Site Possession Mtg

    Borang B

    Performance Bond

    Contractors All Risk

    Workmans Compensation

    Borang C Setting Out

    Borang D Excavation for

    Foundations Works Completed

    Site Meeting

    Valuation

    Interim Certificates

    Co

    ntr

    act

    Pe

    rio

    d

  • ARC4710-2nd Semester 2012/2013 16

    Original Date of Completion

    CPC Issued

    Release of Retention Sum

    Interim Certificate Ends

    End of DLP

    Architects Power to Issue A.I. Ends

    Contractors Insurances of Works End

    Building Handed Over to Client

    DLP Commences

    Within 14 Days Arch to Issue Schedule of

    Defects

    De

    fects

    Lia

    bil

    ity P

    eri

    od

    Penultimate Certificate

  • ARC4710-2nd Semester 2012/2013 17

    Original Date of Completion

    EOT Issued

    Contractor Entitles for Loss & Profit Claim

    Adjusted Date of Completion

    End of DLP

    CPC Issued

    Within 14 Days Arch to Issue Schedule of

    Defects

  • ARC4710-2nd Semester 2012/2013 18

    Original Date of Completion

    CNC Issued

    Liquidated Ascertained & Damages (LAD) Begins

    Works Completed

    End of DLP

    CPC Issued

    Within 14 Days Arch to Issue Schedule of

    Defects

    LAD Ends

  • ARC4710-2nd Semester 2012/2013 19

    Rectification Works Completed

    Certificate of Making Good Defects (CMGD)

    Release of Balance of Retention Sum

    No Later Than 3 Months After DLP

    No Later Than 3 Months After CMGD

    No Later Than 3 Months After

    Receiving All Info From Contractor

    Final Certificate

    Final Payment